Finance Committee Meeting on Capital Improvement Plan – August 13, 2025
Finance Committee Meeting on Capital Improvement Plan – August 13, 2025
The Delaware City Finance Committee met on August 13, 2025, at 2:30 PM in City Hall Council Chambers to discuss the 2026-2030 Capital Improvement Plan (CIP). Presentations were given by City Manager Paul J. Brake, Budget Director Alycia Ballone, Fire Chief Tim Pyle, and Parks Director Ted Miller. Key themes included significant funding gaps, equipment replacement challenges, and deferred maintenance. No public comments were received. The committee approved the motion summary from the August 5 meeting and will continue CIP discussions on August 19 and 25.
Consent Calendar
- Unanimous approval of the motion summary from the August 5, 2025 Finance Committee meeting.
Public Comments & Testimony
- No public comments were made.
Discussion Items
Capital Improvement Plan Overview (Paul Brake, Alycia Ballone)
- Ballone presented the CIP calendar, noting that the charter requires council adoption by October 15, and that the August 11 start allows completion before Christmas.
- Priority guidance: safety first, then outside funding, operational necessity, cost of deferral, and potential revenue generation.
- General fund summary: projected shortfall of $17 million by 2030, with an additional $31 million in unfunded projects (including Glen Road, local streets, and an engineering project).
- East Central project: $2.3 million in WARPSE funding secured, but a $4 million funding gap remains.
- Equipment challenges: $3.4 million in initial equipment requests for 2026 alone. Lead times (e.g., 48 months for fire trucks) require early purchase orders, leading to negative unencumbered balances.
- Facilities: space needs study underway; parking challenges for employees; deferred maintenance (roofs, masonry, HVAC) has been pushed out for years.
- Positive note: $2 million note issuance planned to address mid-sized projects like City Hall roof, Justice Center roof, Springfield Trail pier, and Oak Grove Cemetery grading.
- Councilmember Hoffman expressed concern about the $17+ million gap, noting it represents reasonable estimates of capital needs. Mayor Riggle emphasized that the city has an operating surplus but faces capital needs, comparing them to
Meeting Transcript
We ready to go? All right, good afternoon, everyone. It's 2 30, and we will call the order of the Delaware City Council or Delaware City Finance Committee meeting for August 13th, 2025. Roll call, please. Mr. Hoffman. Here. Mr. Sorry, Mayor Riggle. Yeah. And Chair Schaeffer. Here. Item two is approval of the motion summary. Approval of the motion summary from the finance committee meeting held on August 5th, 2025 is recorded and transcribed. Move for approval. Second. All in favor. Aye. And public comment. Anything in? I had nothing. All right. Well, we get to start talking about the capital improvement plan for the next few years. And I guess we're going to start Mr. Break and Felicia with you. She's over there. Yeah, you're going to be off. She's in a different spot. So as I brought up at Monday night's meeting, you know, this is the kickoff of the of the budget process. And so we hope that you found the plan and the document very informative. So again, I'd like to express my appreciation to Alicia and Rob and many others that the contribute and of course all the department directors. So this will be an important junction to figure out not only the upcoming year, but really to come up with a plan for following years as we have many unmet needs. So but uh I don't have any formal presentation, but I'll hand it over to Alicia if there's some overall comments that she would like to make. But thank you for this opportunity. Thank you. Um so I have just a quick presentation with some overview uh the guidance that was provided to the directors, the usual uh kind of stuff that we do at this first meeting. Um so the first part is it's advances. So this is just the calendar, and really this is just to show you that um we plan for this for months. We start working on the guidance and the packets in April and um distribute those to departments in May. Um the departments are absolutely great, they've met all of their time requirements and they're really good about getting everything back to us. But we are required by charter to get this resolution to council by August 15th of each year. If we do the first meeting in August, that allows us to have budget done before Christmas, which is the goal, so that's why you have it August 11th. Um and then council must adopt it by um October 15th of each year. All right, so this is the guidance that was given to city staff back at the beginning of May. And really priority for projects is always given to the safety first. So safety of residents, safeties of employees, safety of visitors. Um also we take into account whether or not a project has an outside funding source. Would we would we be turning down potential grant dollars? Um is this necessary to continue to and maintain operations. Uh would it cost significantly more to defer?