The City Commission held a workshop on October 22, 2025, to discuss the Septic-to-Sewer Master Plan, funding, and implementation. The workshop focused on the $2.5 billion water and wastewater program, with $1.3 billion allocated to the septic-to-sewer expansion for 17,000 properties. Commissioners discussed timelines, rate impacts, in-house construction, and enforcement of connection ordinances.
All right, good morning, everyone. Uh welcome to City Hall here in the city of Hollywood. Today is October 22nd, 2025. We are here, of course, for a city commission workshop on the subject of the city's septic to sewer program. Uh certainly a priority that the city commission and the administration have uh have been working on for many, many years. Uh and welcome some uh legislative action at the state level that we uh pursued and the initiative of the city commission administration to really uh start addressing this uh issue uh that's important environmentally and also benefits our property owners in many ways to help convert uh the city's legacy septic systems uh ultimately uh in the future to a full uh sewer and uh treated wastewater program. And so uh I know the city commission's uh very uh uh eager to get through this uh workshop and uh make some uh decisions uh and provide some direction so that ultimately we can have some items come to the city commission for uh for uh resolutions and um and action. And so with that, I'd like to invite our uh city manager to uh begin the workshop. Thank you. Thank you, Mayor Vice Mayor Commissioners and to all the members of the uh the public and staff in attendance. Well that that pretty much captures it uh literally for decades this issue has been in the making and uh has had uh efforts in the past to move forward, but now we're really moving forward. And so the uh the presentation and the information today um is is fairly extensive. We'll move it through as quickly as possible if it's possible to kind of get that in a chunk of information and its continuity um and save questions and answers for the end. Promise there'll be plenty of time for that. It's literally one of the driving forces along with the the whole stormwater issue, infrastructure, some of the city's finances, um those handful of issues are the issues that are turning the city around and driving it for the next generation. So this will be a major issue and of course um a big price tag attached to it as well. Um the benefits as you mentioned, Mayor, in terms of people with their property values, environmental issues, economic development, um the help with commercial corridors, um very, very important. So with that I'll turn it over to Vin and uh and then our um our consultants will be able to go through some of the details for you. Thank you. Good morning, Vin Morello Department of Utilities. Um thank you for this opportunity to present the material in this workshop. Uh I want to thank our partners that have worked so hard on the presentation, Hazen and Sawyer, Arcadis, Stantec, and Brizaga that have put a lot of work uh into this presentation. And uh the other day I had the opportunity to see the uh the CMED's uh time capsule. And I reflected that in many ways. Actually, the optimum way. The infrastructure we're contemplating today is the quintessential time capsule. This will be the foundation, as George said, for the next generation. And so very pleased to be part of that effort this day. The septic to source program is a subset of the overall water and wastewater master plan. And although we're focused on the septic to sewer program, the rates discussed today capture the entire water and wastewater master plan. We've had the opportunity with having both plans in hand to overlay all of the all of the infrastructure proposed infrastructure projects onto the GIS system in order to prioritize the septic to sour uh pro basins. And in doing so, we've been able to program out at a high level uh for your consideration a multi-phase approach over the next uh thirty years. Um principally it's a two and a half billion dollar water and wastewater program. Um 1.3 billion of that is the sanitary SOAR portion of the septic to SOAR program, and another uh 300 million or 200 million rather is in the water mains, which are so the whole program is also coordinated. Well, although stormwater is not shown on this table, is also coordinated with the stormwater program. The intent being that we would go into an area, handle all of the utilities at once so to minimize disruption and come out with a finished project and not having recurring excavations in the same area. We looked at not now knowing the cost of the programming, having updated it and we'll address that in the presentation. Uh we looked at uh stretching out the program over different periods of years. Fort Lauderdale back using Fort Lauderdale as a benchmark, they addressed 14,000 properties. Uh and they did their program between 2004 and 2011. They had no other competing projects, they didn't have a consent order, they didn't have any other master programs going on, so they were able to do it rat relatively aggressively. And back then, of course, at a much lower cost. So they were able to accomplish their 14,000 property program in seven years. We have 17,000 properties, and we looked at a 10-year, 20, 30-year, and 40-year program. And for the intensive analysis, we we did the financial analysis for 30 years and back. So uh so although this the rest of this pro um presentation will be kind of centered on a 30-year program because uh the evaluation looked like that was the least aggressive water and rate to impose on the public. We have a detailed analysis for the 20, we have a detailed analysis for the 25, 20, and 15 and 10 year programs, should this commission want to uh look into those in further detail. So the objectives of today, similar to how we structured the stormwater workshop, is uh we're going to try to reach a consensus or I'm I'm going to try to ascertain a consensus from the commission on uh to adopt the water and wastewater master plans. That's fairly straightforward. And the benefit of that is that from time to time we'll come to the commission with uh state revolving fund loan applications and a companion reserve with that will be to update the facilities plan by and we have to do that because we do not have an adopted water and wastewater master plan.