0:00Board of Public Works meeting.
0:01I am the board chair Todd Wilson, Director of Department of Public Works.
0:05I'd like to ask for our board members to introduce themselves, starting my left.
0:16I also like to introduce our board counsel, Benjamin Moracle behind me and our board coordinator, Jennifer Dominguez.
0:24The first item on our agenda today is to adopt the August 13th revised agenda, removing item 3B and adding a walk on item.
0:33Do I have a motion to adopt the agenda?
0:36So moved by Bob Perrin.
0:39Seconded by Leslie Schulte.
0:41All in favor, please signify by saying aye.
0:47Next item on agenda is to approve the amendments.
0:50Do I have a motion to approve the July 23rd minutes?
0:55So moved by Idris Redman.
0:58Seconded by uh Cordy.
1:03Uh all in favor, please signify by saying aye.
1:08Next item on agenda are resolutions.
1:11Uh Natalie, you have several.
1:14Good afternoon, everyone.
1:16I am Natalie Stevens, the DPW stormwater program manager.
1:19Uh the first resolution is number nine, uh, the encroachment into the right-of-way of the shilling regulated drain.
1:27DPW staff recommends the Board of Public Works approve and adopt resolution number nine, twenty twenty-five, granting a petition to Lenar Holmes of Indiana LLC for encroachment into the right-of-way of the shilling regulated drain as further detailed below.
1:42Lenar Holmes of Indiana has petitioned the board for approval of an encroachment into the right-of-way of the shilling regulated drain.
1:48The requested approval of encroachment would allow the construction of the Crescent Ridge subdivision and associated infrastructure.
1:54This construction would entail the installation of a culvert curbed width streets and a crossing for the culvert with sidewalk on each side.
2:01Storm sewer pipes and infrastructure as long as well as a sanitary force main crossing and asphalt path all within the regulated drain right-away of the property.
2:11DPW staff reviewed Lenar Homes of Indiana LLC's petition for encroachment into the shilling regulated drain right away, including proposed construction, and found that the submitted calculations and plans indicate the proposed improvements are acceptable for the expected flows of the regulated drain.
2:27The proposed encroachment will allow for continued unaffected operation of the regulated drain based on information as reviewed by DPW.
2:34As such, DPW staff recommend approval of the petition petition, which will allow for development of the site as planned.
2:41Happy to answer any questions associated with that.
2:45Are there any questions?
2:48CNN, do I have a motion to approve the resolution?
2:52So moved by Bob Perrin.
2:54Seconded by Leslie Schulte.
2:56All in favor, please signify by saying aye.
3:04Uh the next item is resolution number 11, which is the petition for the modification of the right-of-way of the Fowler House and regulated drain.
3:14DBW staff recommends the Board of Public Works approve and adopt resolution number 11, 2025, granting a petition by AeroGas, Inc.
3:22for the modification of the right-of-way for the Fowler Houston regulated drain as further detailed.
3:28AeroGas has petitioned the board for approval of the modification of the Fowler Houston regulated drain.
3:34The requested approval of the modification would allow the expansion of the existing detention basin required for site improvements.
3:41This construction would include the expansion of the detention basin and modifications of the regulated drain right-away to remove existing and future encroachments related to the proposed basin expansion.
3:52DPW staff reviewed AeroGas petition for modification of the regulated drain right-away, including proposed construction and found that submitted calculations and plans indicate the proposed improvements are acceptable for the expected flows of the regulated drain.
4:07The proposed modifications will allow for continued unaffected operation of the regulated drain based on information reviewed by DPW.
4:14As such, DPW staff recommend approval of the petition, which will allow for the development of the site as planned.
4:22Are there any questions?
4:24Seeing none, do I have a motion to approve the resolution?
4:28So moved by Idris Redman.
4:29Do I have a second as seconded by Susie Cordy?
4:35All in favor, please signify by saying aye.
4:43Um this is for board resolution number 12, petition for encroachment into the right-of-way of the Miller Ditch regulated drain.
4:49DPW staff recommends the Board of Public Works approve and adopt resolution 12 2025, granting a petition by Steve Jones for encroachment into and modification of the right-of-way of the Miller Ditch regulated drain.
5:02Steve Jones has petitioned the board for approval of an encroachment into the right-of-way of the regulated drain.
5:08The requested approval of encroachment would allow the development of a new tractor sales and service facility and related infrastructure.
5:15This construction would entail two outfall facilities, a box culvert, some additional pavement and security fencing within the regulated drain right-away.
5:23DPW staff reviewed the Steve Jones petition for encroachment into the Miller Ditch regulated drain, including proposed construction, and found that the submitted calculations and plans indicate the proposed improvements are acceptable for the expected flows of the regulated drain.
5:39The proposed encroachment and modification will allow for the continued unaffected operation of the regulated drain based on information as reviewed by DPW.
5:48As such, DPW staff recommend approval of the petition, which will allow for development of the site as planned.
5:56Are there any questions?
5:59Seeing none, do I have a motion to approve the resolution?
6:03So moved by Bob Perrin.
6:06Seconded by Aegis Redman.
6:07All in favor, please signify by saying aye.
6:11Seeing none motion carries.
6:13Next resolution, Natalie.
6:16This is for board resolution number 13.
6:18Petition for the modification of an encroachment into the right-of-way of the Smith Young regulated drain.
6:23DPW staff recommends the Board of Public Works approve and adopt resolution number 13, 2025, granting a petition by Indianapolis Public Transportation Corporation doing business as indigo for encroachment into and modification of the right-of-way of the Smith Young regulated drain.
6:40The Indianapolis Public Transportation Corporation has petitioned the board for approval of an encroachment into and modification of the right-of-way of the Smith Young regulated drain.
6:50The requested approval of encroachment and modification would allow the building of the Indigo Blue Line terminus.
6:56This construction would entail landscaping, a concrete curb and pavement for buses and staff vehicle movement and parking within the regulated drain right-of-way on their property, as well as a reduction in the width of the regulated drain right away to 20 feet to exclude new storm sewer and detention infrastructure owned by Indigo.
7:15DPW staff reviewed the Indianapolis Public Transportation Corporation petition for encroachment into and the modification of the Smith Young regulated drain right-away, including proposed construction, and found that the submitted calculations and plans indicate the proposed improvements are acceptable for the expected flows of the regulated drain.
7:35The proposed encroachment and modification will allow for the continued unaffected operation of the regulated drain based on the information reviewed by DPW.
7:43As such, DPW staff recommend approval of the petition, which will allow the development to continue as planned.
7:51Are there any questions?
7:53C and none, do I have a motion to approve the resolution?
7:57So moved by Leslie Schulte.
8:02Seconded by Bob Perrin.
8:03All favor, please signify by saying aye.
8:11Board resolution number 14, which is the petition for encroachment into the right-of-way of the Raborn regulated drain.
8:19DPW staff recommends the Board of Public Works approve and adopt resolution number 14, 2025, granting a petition by Lenar Holmes of Indiana LLC for encroachment into the right-of-way of the Raborn regulated drain as further detailed in the petition below.
8:35Lenar Holmes of Indiana LLC has petitioned the board for approval of an encroachment into the right-of-way of the Raborn regulated drain.
8:42The requested approval of encroachment would allow the construction of the Crescent Ridge subdivision and associated infrastructure.
8:48This construction would entail the installation of three storm sewer outfalls within the regulated drain right away on their property.
8:55DPW staff has reviewed the Lenar Homes of Indiana LLC petition for encroachment into the Raborn regulated drain right-away, including proposed construction, and found that submitted calculations and plans indicate the proposed improvements are acceptable for the expected flows of the regulated drain.
9:12The proposed encroachment will allow for the continued unaffected operation of the regulated drain based on the information reviewed by DPW.
9:18As such, DPW staff recommend the approval of the petition, which will allow the development of the site as planned.
9:26Are there any questions?
9:28Seeing none, do I have a motion to approve the resolution?
9:31So moved by Susie Cordy.
9:34Seconded by Edis Redman.
9:36All in favor, please signify by saying aye.
9:40Seeing none, that motion carries.
9:42Very good job, Natalie.
9:44Uh next on the agenda are change orders.
9:50Chair, members of the board.
9:51My name is Jason Watt.
9:52I'm the administrator of construction for DPW Engineering.
10:00The engineering division staff recommends the board of public works approve and authorize the director to execute change order number one to ST-22-092 thoroughfare structural rehabilitation area one with milestone contractors LP with no change to the agreement amount of $2,537,000 and zero cents and 200 days added to the substantial final completion dates.
10:14Change order number one will provide compensation and quantity adjustments for change order detail 1.1, which is summarized below.
10:21COD 1.1 adds an intermediate completion date.
10:24So this project does have a IDE construction stormwater general permit.
10:29Because of that permit, they cannot achieve substantial completion until the grass is fully grown.
10:36So we're preemptively extending this out to a more achievable goal for the contractor.
10:42We're looking to add these intermediate completion dates to all of our projects with completion dates in a similar time frame.
10:47So you may see more of these.
10:48I'd be happy to answer any questions you might have this time.
10:52Do we have any questions?
10:55Seeing none, do I have a motion to approve the change order?
10:59So moved by Bob Perrin.
11:02Seconded by Egypt Redman.
11:04All in favor, please signify by saying I.
11:08C and none the motion carries.
11:10Next change order, Jason.
11:12The engineering division staff recommends the Board of Public Works approve and authorized the director to execute change order number one to ST-24-114 concrete rehabilitation 2024 CCMG with Reath Riley Construction Company Inc.
11:25and the increased amount of $19,746 and 36 cents for a new total not to exceed contract amount of $1,807,746 and 36 cents with no change to substantial final completion dates.
11:38Change order number one provide compensation and quantity adjustments for WDCs one through four, which are summarized herein.
11:46We added in an aero board, uh additional detour route, adjusted uh some additional castings to grade, and then essentially a balance of overruns and underruns.
11:54Change order number one accounts for no change to substantial on final completion dates.
11:58I'd be happy to answer any questions you might have at this time.
12:02Do we have any questions?
12:05Seeing none, do I have a motion to approve the change order?
12:09So moved by Aegis Redman.
12:12Seconded by Susie Cordy.
12:15All uh all in favor, please signify by saying aye.
12:20Seeing none motion carries.
12:21Next change order, Jason.
12:23The engineering division staff recommends the board of public works approve and authorized director to execute change order number two to SD-19-073.
12:32AJ Brown, 30th Keystone drainage improvements with Eagle Valley Inc.
12:36in the increased amount of 467,899 and 65 cents for a new not to exceed amount of 5,991,9016 cents with 55 days added to substantial final completion dates.
12:51We did add in um change order number two will provide compensation and quantity adjustments for WDCs three through seven and COD COD 2.1, which was summarized herein.
13:01So WDC number three adds for on-site security.
13:05Uh number four and five uh add additional pavement reconstruction on 32nd, Hovey Arsenal and Baltimore, and then uh number six uh add some additional sidewalk to the project that was was previously not traversable and 88 compliant uh and then number seven is for some drainage improvements and then uh COD 2.1 is a quantity uh true up so change order number two accounts for 55 days added to substantial final completion dates.
13:35I'd be happy to try to answer any questions you might have at this time.
13:39Do we have any questions?
13:42Seeing none, do I have a uh motion to approve the change order?
13:48So moved by Legend Schulte.
13:52All second seconded by Bob Perrin.
13:54All in favor, please signify by saying aye.
13:59Jason, next change order, please.
14:01The engineering division staff recommends the board of public works approved and authorized director to execute change order number two to BM-24-113, Washington Street over Little Eagle Creek with Pontum Contractors Inc.
14:12and the increased amount of $3,066,142 and 76 cents for a new total not to exceed contract amount of six million one hundred and eighty-one thousand two hundred and thirty-seven dollars and sixty-five cents and 157 days added to substantial final completion dates.
14:27Uh change order number two will provide compensation and quantity adjustments for change order detail 2.1 and WDCs two and three, which are summarized here in WDC 2s for temporary fence, W D C number three is for some additional stormwater management, uh, law enforcement officer and test piling, and then COD 2.1 is for the full demolition and hard replacement.
14:48Change order number two accounts for 157 days added to substantial and final completion dates.
14:53Um the board may recall this structure was originally intended for a rehabilitation.
15:00It was determined in the field after several attempts to try to salvage the existing structure that that was not feasible.
15:06We had to attempt to replace the existing art structure in kind.
15:11And so we are replacing it with another art structure that's being assembled off-site.
15:16And that's part of the accelerated bridge construction of this project.
15:20And we expect to receive that structure starting in about a month.
15:26And then the project, once that happens, the project will come together fairly quickly, and we still hope to have this uh bridge open to traffic in the month of October or later this year.
15:37So with that, I'd be happy to answer any questions you might have this time.
15:44Jason, just uh one question to see your thinking on this.
15:48So this has gone from a two million dollar project to a six million dollar project.
15:52Um I understand why and all, but how do you judge the uh competitiveness of the additional work?
15:59I mean, do you do you look at the unit prices or how do you how do you judge that?
16:05Yeah, that's a great question.
16:07So when the team gets these proposals, um we review them against and historical bid data, and we try to find comparable um bid costs for price per linear foot or square yard or what have you.
16:21There's a lot of historical data.
16:22We also have some historical data at DPW that we use as well.
16:26Um and there was a little bit of a negotiation and back and forth on this, but um I did question the team on that too to make sure that we did those reviews and and those cost analysis, and they and they had and they found uh that this was an acceptable um dollar amount.
16:43It is always difficult when you're change ordering this much product or something into an existing contract.
16:49Uh that concerns always there about you know being competitive.
16:52But what I will say is Pontum has been an excellent partner for the city throughout all this and been fully transparent with everything.
16:59Um, and the um supplier of this precast has also accelerated voluntarily on the construction on site, the off-site um construction of this as well.
17:12So I think we're very fortunate to have this particular contractor working with us on this project.
17:17But uh and so they have been very cooperative and and transparent in their pricing.
17:25Any other questions?
17:29CNN, do I have a motion to approve the change order?
17:36I'll say seconded by Bob Perrin.
17:38All in favor, please signify by saying aye.
17:43Seeing none, that motion carries.
17:46Uh next change, or we're gonna move on to the next board items change orders final.
17:52The engineering division staff recommends the board of public works approve and authorized the director to execute change order number three, final and final acceptance for PA-25-003 Poges Run trail, phases two and three C project with Morphe Construction Inc.
18:08and the decreased amount of 49,264.01 cent for a final contract amount of three million six hundred and ten thousand six hundred and fifty-nine dollars and ninety-eight cents.
18:17Change order number three will provide quantity adjustments for WDC number nine and change order detail number three point two, which are summarized here in the board action is also for final acceptance of this project.
18:29So WDC number nine uh is for some relocation of some signs, uh WD and COD number three point two is a final quantity true up.
18:39Uh change order number three final and final acceptance accounts for 303 days added to the substantial and 303 days added to the final completion dates.
18:48Um I'd be happy to attempt to answer any questions you might have this time.
18:52I I do believe a lot of uh the days that were added were similar situation with the NOT.
18:57Um I'd have to dig in a little bit more to find out the full extent of those, but I'm happy to try to answer those questions if they do arise.
19:05Do we have any questions?
19:08CNN, do I have a motion to approve the final change order and final acceptance?
19:12So moved by Susie Cordy.
19:14Do you have a second?
19:16Seconded by Bob Perrin.
19:18All in favor, please signify by saying aye.
19:22C and none the motion carries.
19:26The engineering division staff recommends the Board of Public Works approve uh the director execute change order number one final for CL-16069 small structure replacement of asset number LEO 762 at 5030 North Molar Road with edge construction LLC and the decreased amount of 50,851 dollars and eighty-seven cents for a new total not to exceed amount of four hundred and forty thousand four hundred and forty-four thousand dollars uh four hundred and forty.
20:004445083 cents and no days added to substantial final completion dates.
20:04Uh change order number one final will provide compensation and quantity adjustments for COD 1.1 and WDC's one and two, which are summarized below.
20:12Final project true up additional cost for excessive uh concrete removal and a new cast in place head wall for the box culvert.
20:19Uh change order number one uh final accounts for zero days added substantial final completion dates and I apologize for my tongue tie there, but uh be happy to answer any questions you might have this time.
20:29I get tongue tied as well.
20:31Uh do we do we have any questions?
20:34C and then uh do we have a motion to approve the final change order?
20:38So move by Aegis Redman.
20:40Do we have a second?
20:43Seconded by Bob Perrin.
20:44All in favor, please signify by saying aye.
20:48C and none, the motion carries.
20:52The engineering division staff recommends the board of public works approve and authorized director to execute change order number three, final to ED-25-213, 16th and Monon Development Phase 2 with Wreath Raleigh Construction Company Inc.
21:05in the decreased amount of 158,187.10 cents for a new total not to exceed contract amount of two million seven hundred and ninety-three thousand one hundred and nine dollars and eight cents with no change to substantial final completion dates.
21:18Change order number three final will provide compensation quantity adjustments for COD 3.1 and COD 3.2, which are summarized here in uh partnering and escalation due to a late purchase order and then uh final overruns and underruns.
21:34Um change order number three final provides no change to substantial final completion dates.
21:40Um with that I'd be happy to answer any questions you might have this time.
21:45Do we have any questions regarding this change order?
21:49CNN, do I have a motion to approve the final change order?
21:54So moved by Aegis Redman.
21:57Seconded by Susie Cordy.
21:58All in favor, please signify by saying aye.
22:02That motion carries.
22:05All right, next on the agenda are professional services agreements.
22:10The engineering division staff recommends the Board of Public Works approve and authorize the director to execute ENG-25-004 on call residential reconstruction sectors one through four, a new professional service agreement for inspection with crossroad engineers PC, and then not to exceed total agreement amount of two million five hundred thousand dollars and zero cents within an agreement expiration date of December 31st, 2027.
22:34Uh projects ST-24-00077, ST-24-078, ST-24-079, and ST-24-080 is for resurfacing and reconstruction of residential streets in Marion County across sectors one through four.
22:54Uh crossroad engineer PC's uh XBE participation will include 10% to BE read, uh, 10% to 7NT Engineering LLC, 10% to resolution group, Inc.
23:06and 10% uh veterans engineering and technical services.
23:09Uh crossroad engineers PC was selected through RFQ 2025-01.
23:16Um so this will be uh ENG uh with on call assignments for each one of these specific projects.
23:23Uh we do anticipate with the current uh with the recent bids that we had on these projects that we will come in well underneath this estimate for the uh ENG.
23:32Um and we're currently negotiating those uh uh for requisition.
23:37Um that I'd be happy to answer any questions you might have at this time.
23:41Do we have any questions?
23:44CNN, do I have a motion to approve the services agreement?
23:49So moved by Bob Perrin.
23:50Do I have a second second by Aegis Redman?
23:54All in favor, please signify by saying aye.
23:59Seeing none, that motion carries.
24:03Next item on the agenda.
24:09John, chief engineer for the Department of Public Works.
24:12Uh, I have a professional service agreement for inspection services for BM-25-179A, fiscal year 2025 to 2028 pedestrian bridge inventory uh with Aegis BLN USA, formally known as Beam Longest and NEF LLC.
24:28Uh the engineering division staff recommends the Board of Public Works approve and authorize the director to execute BM-25-179A fiscal year 2025-2028, pedestrian bridge inventory, a new professional services agreement for inspection with Aegis BLN USA in the not to exceed total agreement amount of 288,200 with an agreement expiration date of August 31st, 2029.
24:54Project BR-25-179A is for the inventory inspections for the pedestrian bridges within Marion County.
25:01Substantial and final completion dates do not apply for this scope of work.
25:15There is no participation from VBE or DOBE subconsultants.
25:25Happy to answer any questions.
25:29Before we open up for questions, I'd like to uh tell the board that this is uh Mark's first board meeting as a chief engineer.
25:36Um so he's accepted that position, and we're very happy to have him on board um in that position.
25:42Um do we have any questions regarding this uh service agreement?
25:48Seeing none, do I have a motion to approve the service agreement?
25:51So moved by Susie Cordy.
25:55Seconded by Bob Perrin.
25:56All in favor, please signify by saying aye.
26:01Seeing none that motion carries.
26:02Mark net next uh item, please.
26:05So the next item is also for bridge inspection.
26:07It's a professional services agreement for BR-25-178H, Marion County Bridge Inspec inspections for fiscal year 2026 to 2029 with USI Consultants Incorporated.
26:19The engineering division staff recommends the Board of Public Works approve and authorize the director to execute BR-25-178H, Marion County Bridge Inspections Fiscal Year 2026 to 2029.
26:32A new professional services agreement for bridge inspections with USI Consultants Incorporated in the not to exceed total agreement amount of $2,452,244.15 cents with an expiration agreement date of May 30th, 2020.
26:48Project BR-25-178H is for state mandated inspections of all bridges in Marion County for 2026 to 2029.
26:58Has specified a 7% DBE subconsultant goal for this agreement.
27:02USI consultants uh DBE participation will include 7.15% to resolution group.
27:09Uh USI Consultants was selected through an INDOT RFP posted January 20th, 2025.
27:15Happy to answer any questions on this one as well.
27:18Are there any questions?
27:21Do I have a motion to approve the services agreement?
27:24So moved by Aegis Redman.
27:28Seconded by Susie Courty.
27:30All in favor, please signify by saying aye.
27:34Seeing none that motion carries.
27:37Uh next item on agenda are professional services amendments.
27:41Uh Jason Mmott, you're up.
27:44The engineering division staff recommends the Board of Public Works approved and authorized your director to execute amendment number two to BM-24-113, West Washington Street over Little Eagle Creek professional service agreement with Wolper Inc.
27:57in the increased amount of 236,236 and five cents for a new total not to exceed agreement amount of 727,059 dollars and ninety-five cents and no change to expiration date of December 31st, 2025.
28:11Amendment number two provides funding to complete additional respect requested inspection work.
28:16Um this will include project oversight throughout the revised duration of the project and the completion of the final construction records.
28:22Um there was uh original agreement of 249,999 and 88 cents.
28:30Amendment number one was for 240,824 and uh zero and two cents plus time, and then this amendment is for two hundred and thirty-six thousand uh two hundred and thirty-six dollars and five cents for a total uh agreement amount of seven hundred and twenty-seven thousand fifty-nine dollars and ninety-five cents.
28:52Um this is the same project we discussed earlier about having to add the additional money for the the pre-cash structure.
28:58Um be happy to answer any questions you might have this time.
29:02Do we have any questions?
29:05C and then do I have a motion to approve the uh professional services amendment.
29:11So moved by Leslie Schulte.
29:13Do we have a second?
29:14Seconded by Aegis Redman.
29:16All in favor, please signify by saying aye.
29:20Seeing none that motion carries.
29:22Jason Watt, next one, please.
29:25The engineering division staff recommends Board of Public Works approve and authorize the director to execute amendment number two to project number stree one-059, White River Innovation District Infrastructure Project Professional Service Agreement with Butler, Fairman, and Cypher Inc.
29:41in the increased amount of $909,851 and 74 cents for a new total amount not to exceed $3,328,106 and $510.
29:53This amendment will provide no change to the agreement expiration date.
30:00to project number stree one zero five nine white river innovation district infrastructure project professional service agreement with butler ferman and cipher inc in the increased amount of nine hundred and nine thousand eight hundred and fifty one dollars and seventy four cents for a new total amount not to exceed three million three hundred and twenty eight thousand one hundred and six dollars and fifty one cents this amendment will provide no change the agreement expiration date the agreement will provide the inspection services for the construction of new bridge over White River the extension of Henry Street from Harding Street to Kentucky Avenue also included is the rehabilitation of South White River Parkway drive from Washington Street and the construction of Division Street from Oliver Avenue to Henry Street so this project has three separate distinct phases the west side of the uh the bridge the bridge itself and then the east side infrastructure and BFNS has been doing the inspection on all three phases um so the amendment summary the original agreement was for 12928 dollars and seventeen cents amendment number one accounted for 2,288 plus rates and then amendment number two uh this amendment adds 90951 dollars and seventy four cents for a new total agreement amount of three million three hundred and twenty eight thousand one hundred and six dollars and fifty one cents with that I'd be happy to try to answer any questions you might have this time thank you Jason do we have any questions seeing none do I have a motion to approve the amendment so moved by Bob Perrin do I have a second seconded by Susie Cordy all in favor please signify by saying aye aye any opposed seeing none that motion carries next item on agenda our final acceptances and Jason you're still up thank you the engineering division staff recommends the Board of Public Works approved and authorized the director to execute final acceptance for WQ-22-010 Broad Ripple outfall rehabilitation with CE construction services inc for a total contract amount of $92989 and zero cents this board actions for final acceptance of this project I'd be happy to answer questions you might have this time thank you are there any questions seeing none do I have a motion to approve the final acceptance so move by Aegis Redman do I have a second seconded by Bob Perrin all in favor please signify by saying aye aye any opposed seeing none that motion carries last item Jason oh this is our walk on um so go ahead Jason thank you the engine engineering division staff recommends the board of public works approve and authorized the director to execute amendment number one to ENG-23-017 on call of transportation inspection services with VS Engineering Inc and the increased amount of 2000 dollars for a new total not to exceed agreement amount of 700 thousand dollars this amendment will provide no change to agreement expiration date of December 31st 2026 amendment number one provides additional funding to complete additionally requested inspection work uh this amendment will provide no change the agreement expiration of December 31st 2026 again the original contract was for half a million dollars this amendment's for 2000 a total of 700 thousand dollars and zero cents um vs engineering has been doing an uh an excellent job working on on the job order contracts for us um which enables us to get a lot of things done very nimbly here at the city and they they've also got a a bridge project that they were assigned on this ENG that they are working on finishing up as well so um that was the major need for the um additional funds here was to get us through the jock program for the remainder of the year with that I'd be happy to answer any questions you might have this time thank you do we have any questions seeing none do I have a motion to approve the amendment so moved by Bob Perrin and second second by Leslie Schulte all in favor please signify by saying aye aye any opposed motion carries uh other business there is no other business uh do I have a motion to adjourn so moved by Leslie oh sleep I'm so sorry so moved by Susie Cordy do we have a second second second by Edis Redman thank you this meeting is adjourned talk us so fast