0:53I'd like to call to uh the March 25th Board of Public Works meeting to order.
0:57I'm Adrice Redman, acting chairman of the board.
1:00Board members, would you please introduce yourself starting from the left?
1:14I would also like to introduce uh board counsel, uh Benjamin Moracle and Acting Board Coordinator, Colin Campbell Maher and the DPW staffed.
1:24Uh the first item on the agenda is to adopt the March 25th, 2026 agenda.
1:32Uh moved by Bob Perrin.
1:35Second by Sabako Jawanza.
1:37All in favor signify by saying aye.
1:43And next on the agenda is item number two, bid awards, Nathan Sheets.
1:47Good afternoon, Nathan Sheets, Deputy Director of our Engineering Division for DPW.
1:52Starting with uh justification for bid award for SD 22103, this is our 2022 Thoroughfare Drainage Improvements Area 4 with Calumet Civil Contractors Inc.
2:05The engineering division staff recommends the Board of Public Works approve and authorize the director to award SD 22103 Thoroughfare Drainage Improvements Area 4 to Calumet Civil Contractors Inc.
2:18in the total not to exceed amount of $5 million on the basis that they are the lowest responsive and responsible bidder.
2:26A bid alternate was included for pavement repairs in the Ridge Hill Trail neighborhood near West County Line Road and Morgantown Road.
2:34The bid alternate was not awarded due to the INEP partner withdrawing their project.
2:39Project SD 22103, 2022 thoroughfare drainage improvement project area four consists of drainage improvements and structural rehabilitation of Bluff Road from Wicker Road to just south of Thompson Road.
2:52Substantial completion is scheduled for May 17, 2027, with final completion scheduled for July twelfth, twenty twenty-seven.
3:51And if you have uh questions about that particular item, I'd be happy to try to answer them.
3:56Nathan, uh are there any questions?
3:58And Nathan, um just so we know what we're evaluating here.
4:02So as I understand from reading through some of this, that the after the engineer made his estimate that there was some significant uh changes and reducing conflicts with utilities and all that and that but he then he did not re-estimate based on that.
4:18Um I know I know you know when I talked about the um bid being sixty-three percent uh roughly less than the engineer's estimate.
4:27It's 36 percent, by the way.
4:29Uh so that's uh you know that tends to be a concern sometimes.
4:33Um we had our designer uh look at the uh bids and um if you look at uh I think in your packet, the the second or third page um shows what the other bidders were at, and um you know there was a decent spread there, but um based upon their unit prices that they provided, the uh low bidder, um in this case Calumet, a lot of their bids that are the lump sum bids, which are like MOB and DMOB, maintenance of traffic, those tended to be um quite lower than what what we anticipated, which I think goes to show that uh contractors are hungry out there and and so we're satisfied with um uh that that bid that was placed.
5:19But you are correct, I guess long story short.
5:21Um we had some conflicts with Citizens Energy Group.
5:25Um, and any time that there's a conflict uh that's part of a project, there's risk associated with that conflict.
5:32And so a lot of times contractors will build that risk in monetarily to their bids.
5:38And in this case, um after uh bids were received, we continue to work with citizens to minimize that that impact.
5:45And so um we suspect that that also plays a role in that very competitive bid um bid amount.
5:53Okay, and then one of the one of the things, yeah, looking at that, yeah, a lot of it's mobilization and whatever else, kind of labor.
5:58But uh the the one thing that stuck out as far as materials was the uh HMA type C that uh it was significantly less than what the engineer estimated, but it was quite frankly kind of close closer to what some of the other bidders bid.
6:12So in your mind, is that a reasonable yeah?
6:16I mean, uh obviously with HMA asphalt being a petroleum-based product, uh, you know, it's it's kind of a toss-up as far as what what um what we're gonna get from a pricing perspective.
6:28Yeah, and we've got plenty of experience with uh Calumet, all positives as I can remember.
6:36Should be a good project.
6:43Hearing none, do I have a motion to approve uh the bid abort?
6:48So moved by Bob Heron.
6:52Second by Sabako Jawanza.
6:55All in favor signify by saying aye.
7:02Next item on the agenda is item number three, which is change orders and uh Nathan Sheets here back up.
7:08Yeah, this is uh change order number four to GT 06001 nickel plate trail.
7:14This is with Calumet Civil Contractors Inc.
7:16The engineering division staff recommends the Board of Public Works approve and authorize the director to execute change order number four to GT 06001 nickel plate trail with Calumet Civil Contractors Inc.
7:28with no change to total agreement amount for a total not to exceed agreement amount of 11,882,938.63 cents, an additional 253 days added to the substantial and final completion dates.
7:43Change order number four will provide compensation and quantity adjustments for change order details, which are summarized in uh change order 4.1, and again, this is basically adding additional uh days for substantial and completion dates.
7:58Uh questions or concerns?
8:01Are there any questions?
8:02Yeah, what's driving the effectively adding another construction season to this project?
8:09Yeah, so um good question.
8:11Uh what we've been dealing with here recently is we have a notice of termination that uh that's issued um from Marion County Stormwater, um, and this is an IDEM permit requirement.
8:25And towards the end of a contract, uh we need to make sure that all disturbed areas have uh basically growth uh grass or turf that's been established.
8:38And from a timing perspective, we've run into a couple instances, and and this will be uh kind of a common theme for the next couple items where uh the project was supposed to finish towards the end of the year, and obviously when that happens, uh we don't have the ability to get that that growth down, and so we do have to extend um that project duration in order to make sure that we're compliant with that individual permit.
9:08Hear none, do I have a motion to approve the change order?
9:14So moved by Sebaco Jawanza.
9:17Second by Leslie Schulte.
9:19Um all in favor, signify by saying aye.
9:27Uh this is change order number three.
9:29This is for ST 45067.
9:32This is South County Line Road added travel lane uh project, and this is with Renaissance Inc.
9:38The engineering division staff recommends the Board of Public Works approve and authorize the director to execute change order number three to ST 45067, South County Line Road added travel lanes with Renaissance Inc.
9:50with no change to total agreement amount of 898,093 and 27 cents and 330 days added to substantial and final completion dates.
10:01Change order number three will provide days added, which are summarized in change order uh detail 3.1 again very similar to uh what you guys just approved um ensuring that uh we've met our notice of termination from the Indiana Department of Environmental Management uh contingent upon Marion County Soil and Water Conservation District.
10:24Um contract uh change order number three accounts for 330 additional days to substantial and final completion dates.
10:31Questions concerns thank you, Nathan.
10:37Hearing none, do I have a motion to approve the change order?
10:41Moved by Daniel Haig.
10:43Uh do I have a second?
10:45Second by Bob Perrin.
10:46All in favor, signify by saying aye.
10:51Nathan, you're back up for another change order.
10:54Yep this is uh change order number two for st 2552, Ralston Campus Infrastructure Improvements with Edward and Jones Concrete Inc.
11:04The engineering division staff recommends the Board of Public Works approve and authorize the director to execute change order number two to ST 2552, Ralston Campus Infrastructure Improvements with Edwardson Jones Concrete Inc.
11:18with no change to the total agreement amount of $1,482,038 and 42 cents and 330 days added to substantial and final completion dates.
11:29Change order number two will provide additional days uh for the details summarized below, which again is extension of the notice of termination.
11:38Contract change order number two accounts for 330 days added to substantial and final completion dates.
11:44It is important to note that in order to avoid this, we're actually looking at uh as we bid our projects what our true substantial final completion dates are.
11:55If we are in a situation where we are going to uh butt up against that fall timeline, um we're gonna extend those dates that way we don't have to continually come back to the board and ask for an extension.
12:09So contractually, we're gonna adjust those dates to uh take into consideration the uh need to get that uh that that grass uh growth.
12:21But then of course go ahead.
12:23Yeah, but then of course, how do you let the contractor know that they have been told so long to get the road open?
12:30But that is um there's probably some intermediate completion dates that we can kind of throw in in there just uh to make sure that that's in fact covered, but that is a good good point.
12:41Um it is a balancing act.
12:43You know, clearly we we want to give contractors enough time to construct uh the project, and uh you know, any time you you try to tighten that time frame up, you're gonna pay a premium for that, and um so it is uh somewhat of a balancing act.
13:01Yeah, any other questions?
13:03Hearing none, do I have a motion to approve the change order?
13:08Moved by Leslie Shelty.
13:12Second by Sabako Juwanza.
13:14Um all in favor, signify by saying aye.
13:21Nathan, you're up for item number four, change orders final.
13:25Uh this is change order number three final for ST 25095.
13:31Concrete pavement reconstruction on Heathrow Way from Decatur Boulevard to Kentucky Avenue.
13:36This is with milestone contractors LP.
13:39The engineering division staff recommends the Board of Public Works approve and authorize the director to execute change order number three final to ST 21095, concrete pavement reconstruction of Heathrow Way from Decatur Boulevard to Kentucky Avenue with milestone contractors LP in the decreased amount of 239,22022 for a new total not to exceed contract amount of 2,234,104 and 70 cents and 144 additional days added to substantial and final completion dates.
14:13Change order number three final provides for contract adjustments for COD 3.1 and work directives 11 through 13.
14:24Uh change order 3.1 was uh final quantity true up and uh work directives 11 through 13.
14:31Um there was some additional uh pipe and pavement removal that was uh necessary uh as we got out there.
14:37We identified a structure that needed um uh a bit of rehab.
14:42Um there's some additional pipe placement and pavement repair on Heathrowway and uh we uh again when we were out there we noticed that there was some pavement markings that uh needed to be refreshed and uh decided it to include that as part of this project as well.
15:00Um questions or concerns about change order number three.
15:07Hearing none, do I have a motion to approve the final change order?
15:11Moved by Bob Perrin.
15:14Second by Daniel Hake.
15:16Um all in favor, signify by saying aye.
15:19Any opposed motion carries.
15:24Uh this is change order number three, uh, another final for BM 24113.
15:30This is West Washington Street over Little Eagle Creek with Pontum Contractors Inc.
15:35The engineering division staff recommends the Board of Public Works approve and authorize director to ratify and execute change order number three final to BM 24113 West Washington Street over Little Eagle Creek with Pontum Contractors Inc.
15:49and an increased amount of 134,233 and 52 cents for a new total not to exceed contract amount of six million three hundred fifteen thousand four hundred and seventeen dollars and seventeen cents and ninety additional days added to substantial and final completions.
16:06Change order number three final will provide compensation and quantity adjustments.
16:11Uh those again were basically final quantity true-ups and uh uh work directive four added uh additional substructure items and time to relocate uh major utility lines, which uh I believe were AES lines that were in conflict with the project.
16:29Uh contract change order number three final accounts for 90 days added to substantial and final completion dates.
16:35And if you have questions about uh change order number three final, I'd be happy to try to answer them.
16:45Yeah, I have one question.
16:46This particular bridge project, the current contract amount is three times the original bid amount.
16:54What what happened there?
16:56Yeah, uh great question.
16:58Um there was there was quite a bit of uh coverage on the news about this particular uh project.
17:05Um as with many of our bridges, particularly the historic bridges that we have out there.
17:10Uh we got out there and the condition uh was a lot worse than what we anticipated.
17:16In fact, during the uh the rehab of the bridge, um, as the contractor was doing some demo work, uh one of the spandrel walls uh fell, and we basically went from a rehab uh project that we anticipated having to do to a total uh replacement.
17:34And so um yeah, it uh it it took quite some time in order to um change gears.
17:44You know, clearly when we went from uh a rehab to uh a full replacement, um quite a surprise for everyone.
17:52Also surprise for the uh residents and people that utilize that road every day.
17:57We the closure um was uh unfortunately pretty impactful, but good news is it's it's open, it's a brand new bridge, and hopefully we won't have to touch that with any uh within any of our lifetimes.
18:14Any other questions?
18:17Hearing none, do I have a motion to approve the final change order?
18:21So I move move by Sebaker Juwanza.
18:26Second by Leslie Schulty.
18:28All in favor say signify by saying aye.
18:37Move on to section number five, and Nathan, uh, looks like you're back up.
18:42This is uh thank you.
18:43This is amendment number three to ENG 20024.
18:47This is an on-call inspection services contract that we have with Christopher B.
18:51Burke Engineering LLC.
18:53The engineering division staff recommends the Board of Public Works approve and authorize the director to ratify and execute amendment number three to ENG 2002, on call inspection services, a professional services agreement with Christopher B.
19:08Burke Engineering LLC with no change to total agreement amount of $500,000.
19:14This amendment provides updated rates and will extend the agreement expiration date to December 31st, 2027.
19:21Amendment number three provides updated rates and time to complete additionally requested inspection work to projects under this current on-call.
19:28Expiration date will be extended to December 31st, 2027.
19:33Uh we currently have Burke working on uh a project uh known as uh Farley Top.
19:41Uh it's a drainage project, and then there's another project that we intend, assuming that this does in fact um get amended.
19:48Um they would be working on a uh project that we have over on 91st in Ream Creek.
20:00And so in order to uh allow them to finish these two particular projects, we're suggesting that the uh expiration date of the contract be extended to December 31st, 2027.
20:11Uh are there any questions?
20:15Do I have a motion to approve the amendment?
20:18Moved by Daniel Haig.
20:21Second by Sebaco Juwanza.
20:23All in favor, signify by saying aye.
20:28And Nathan, you can take a break and mark your up.
20:33John, Chief Engineer for the Department.
20:35Uh up first I have amendment number two to SD 48009 Southport and Five Points Road roundabout with Crossroad Engineers PC.
20:43The engineering division staff recommends the Board of Public Works approve and authorize the director to ratify and execute amendment number two to ST-48-009.
20:52Southport and five points road roundabout with Crossroad Engineers PC.
20:56This amendment provides an additional subconsultant with no change to the total agreement amount of 391,789 dollars.
21:03This amendment will also extend the agreement expiration date to December 31st, 2027.
21:08Amendment number two provides time and an additional subconsultant to request additionally requested design work.
21:13Actually, more specifically, it's one of their right-of-way buyers.
21:16It's a different right-of-way buyer that they're using.
21:18Um this will include a project time ex this will will include a project time extension through December 31st, 2027.
21:25Happy to answer any questions.
21:28Uh are there any questions?
21:31Do I have a motion to approve the amendment?
21:36Moved by Leslie Shelty.
21:40Second by Sebaker Juanza.
21:41All in favor, signify by saying aye.
21:48The next item is amendment number one to ST-17-052, 29th and 30th Streets two-way conversion with Hanum Waggle and Klein Engineering.
21:57Um, also known as doing business as HWC engineering.
22:00The engineering division staff recommends the Board of Public Works approve the approve and authorize the director to ratify and execute amendment number one to ST-17-052, 29th and 30th Streets two-way conversion with HWC engineering with no change total agreement amount of $1,180,585.28 cents.
22:21This amendment provides updated rates and extends the agreement expiration date to December 31st, 2027.
22:26Amendment number one provides updated rates and additional time to complete the project.
22:31Happy to answer any questions on this one, too.
22:35Are there any questions?
22:38Do I have a motion to approve the amendment?
22:40So moved by Bob Perrin.
22:44Second by Daniel Haig.
22:46All in favor, signify by saying aye.
22:52And looks like Brian Europe.
22:56Good afternoon, Brian Kavanaugh, General Counsel for the Department of Public Works.
23:00I have for the board's consideration today amendment number five to contract number two zero one eight one for temporary labor personnel services with keys to work.
23:10DPW staff recommends the Board of Public Works approve and authorize the director to execute amendment number five to contract number two zero one eight one, a services agreement with keys to work for temporary labor personnel services.
23:24This amendment will extend the agreement term for an additional year with an updated expiration date of March 16th, 2027.
23:31DPW holds a contract with keys to work for the provision of temporary labor personnel as needed by the department.
23:37This amendment renews uh DPW's agreement with keys to work for temporary labor personnel services for another year.
23:43So no new dollars here, just uh extending the expiration date.
23:51Are there any questions?
23:53Hearing none, do I have a motion to approve the amendment?
23:58So moved by Daniel Haig, do I have a second?
24:02Second by Sebac Juanza.
24:04All in favor signify by saying aye.
24:13This is uh final acceptance for BR 46088.
24:18This is Derbyshire Road over Derbyshire Creek with HIS Constructors Inc.
24:24The engineering division staff recommends the Board of Public Works approve and authorize the director to execute final acceptance of BR 46088 Derbyshire Road over Derbyshire Creek with HIS Constructors Inc.
24:38The final contract amount is 1,388,326 and 69 cents.
24:47This particular board action is is for final acceptance of the project.
24:51Questions or concerns?
24:55Are there any questions?
25:02Move by Spectre Wanza.
25:07All in favor, signify by saying aye.
25:13Next up is other business.
25:15And doesn't look like we have any other business.
25:17So I will ask for a motion to adjourn.
25:21So move by Daniel Eighth.
25:24Second by Spector Wanza.
25:27This meeting is now adjourned.