OPENPUBLICA · PUBLIC MEETING RECORD
Record of Proceedings

City Council Meeting Summary - November 18, 2025

City Council MeetingsTuesday, November 18, 2025
BodyTuscaloosa, Alabama
SessionCity Council Meetings
DateTuesday, November 18, 2025
StatusFILED
Video Record
0:00 / 27:00

Transcript — Verbatim
0:02

To approve.

0:02

So move.

0:03

Move.

0:04

Second in any discussion.

0:05

All in favor say aye.

0:06

Aye.

0:07

Minutes are approved.

0:09

Item number one is approval change order number two with Mark Johnson construction.

0:14

For the Fletcher phase two improvements project, the total is 943, 883, and an additional 304 days.

0:22

Brian, welcome.

0:23

Hey, good afternoon.

0:25

Good afternoon.

0:26

So I'm gonna walk through some of the history and how we got here.

0:31

Um as a reminder, this the phase two project at the Fletcher plant is to rehab the digesters and to rehab the aeration basis.

0:41

So the aeration basins are done, that's that's complete.

0:44

Uh the remaining scope is to replace the lids on digesters one and two.

0:50

Um the change order that we're asking for will add digester three back into the project.

0:55

And I'll explain that.

0:57

But so about this time last year, we took third digester out of the project to cover the cost of lid uh replacements for digesters one and two during construction.

1:09

Once we had the sludge removed from those digesters, we had in the constructor project to inspect the lids because we couldn't do it outside construction.

1:17

We did the inspection showed that the lids needed replacing.

1:20

So that time the decision was made to pull digester three out to help cover the cost of the lid replacement for digesters one and two.

1:28

You with me?

1:30

Okay.

1:31

So for reluctant for uh so there is an accompanying finance committee item for to transfer monies from the wastewater lagoon project to Commodore Changer.

1:46

Uh the this time last year, since then we've done a study for that project on the lagoons.

1:55

Um the intent of the city was to determine the scope for improvements and correct preliminary cost estimates.

2:02

Uh and it so a component of those improvements is restoring some of the lagoon capacity by sludge removal.

2:09

Um the study indicated we could restore eight to ten years of capacity within the proposed modified budget.

2:15

So, in other words, we take what we're proposing 943,000 dollars from the lagoon project.

2:21

We still can remove the amount of sludge we need to to restore 10 years worth of capacity and do the other components of that project we want to do.

2:31

Um and then another note is that the digesters and the lagoons are they're interconnected systems, so the lagoons basically serve as an overflow for sludge that can't be processed by the plant.

2:44

Um, or if the solids facilities overload it, so restoration of the third digester will help to reduce the transfer of sods to the lagoon and reduce the amount of capacity needed for the lagoon to be restored.

3:02

So any questions?

3:05

You understand all that?

3:06

I do that's good.

3:11

Remember how the athlete done went basically at the time when we established the review budget.

3:20

How much did they originally for the cost?

3:22

Yes.

3:23

Five million five the six million dollars of that budget through two sources.

3:28

So six million dollars is the answer to your question.

3:31

So at that time we didn't have this study.

3:32

We so now we're increasing that another million nine forty.

3:38

Uh I was talking about the legume project.

3:40

Okay.

3:40

That we're taking money from so for that project.

3:45

We had six million dollars.

3:47

Since then, we've done a study.

3:48

The study shows that we have enough money to remove sludge, restore it.

3:55

There's other components of that project we can do as well.

3:57

And so that's I guess that's the the bottom lines.

4:03

We're we we have plenty of money in that budget, so we're you want to use that extra money.

4:07

I'm just trying uh we're we're bumping something up 943,000.

4:13

Gotcha, okay.

4:14

And we're increasing it another 304 days.

4:17

Yes.

4:18

What was it original?

4:21

So originally all the lagoon repairs.

4:25

No, we're uh the uh the digest digest digest.

4:30

Original budget was 706-194.

Discussion Breakdown — Share of Meeting
Water And Wastewater Management█████████████████████████████████████37%
Facility Management██████████████████████████26%
Procedural████████████████████20%
Public Safety█████████████13%
Technology and Innovation████4%
Summary of Proceedings

City Council Meeting Summary - November 18, 2025

The Tuscaloosa City Council convened on November 18, 2025, to review and approve a wide range of municipal contracts, including construction change orders, professional services agreements, and property lease amendments. The meeting featured detailed presentations from city staff regarding capital improvements for the Fletcher Wastewater Treatment Plant, infrastructure upgrades, and safety initiatives for first responders. All items were discussed, with no public testimony or opposition recorded, and every motion passed unanimously.

Consent Calendar

  • Minutes: The minutes from the previous meeting were approved.
  • Item 1: Approved Change Order No. 2 with Mark Johnson Construction ($943,883) to add Digester 3 to the Fletcher Phase 2 project and extend the timeline by 304 days, funded by a transfer from the Wastewater Lagoon project budget.
  • Item 2: Approved deductive Change Order with Mark Johnson Construction ($1,265,605) for the Ed Love Raw Water Pump Station project, bringing the total contract cost down to approximately $18.4 million.
  • Item 3: Approved a professional services on-call contract with Jacobs Engineering (up to $50,000) for water distribution modeling and sewer software reporting.
  • Item 4: Approved a minor public works contract with Dixie Painting and Sandblasting ($28,761) for additional metal replacement and rehab work on the West End Tank.
  • Item 5: Approved Contract Amendment No. 1 with McGiffert Associates ($198,520) to advance the East Over Drainage Project into the acquisition and construction phases.
  • Item 6: Approved a professional services contract with Bullet Environmental ($7,500) for routine maintenance of the soil vapor extraction system at the Mercedes-Benz Amphitheatre.
  • Item 7: Approved a minor public works contract with Amison and Associates ($38,500) for repairing an overhead door and sidewall at Environmental Services, with insurance coverage anticipated for the loss.
  • Item 8: Approved a minor public works contract with Ryan Metal Works ($34,700) for security improvements at City Hall, including new handrails and fencing.
  • Item 9: Approved a minor public works contract with Fast Signs ($38,500 not explicitly stated but included in the item context) for city seal plaques on the new City Hall fencing.
  • Item 10: Approved a minor public works contract with Building Specialties ($2,670) for gate hardware and emergency egress systems at the City Hall parking lot.
  • Item 11: Approved a professional services contract with Appraisal and Consult Group ($20,000) for property appraisals regarding the Northern River Walk Project Phase 2.
  • Item 12: Approved a professional services contract with Southeast Appraisal ($10,400) for appraisals required to acquire easements for the East Over Drainage Project.
  • Item 13: Approved an amendment to the airport lease with Ascension FBO (Hawthorne Global) to remove a 1.25-acre parcel from their lease to facilitate future hangar development.
  • Item 14: Approved a 12-month contract with Vital Exam Special Services (up to $166,000) to provide physical wellness examinations, including cancer screenings and cardiovascular testing, for Fire Rescue firefighters.
  • Item 15: Approved a 36-month professional services contract with Sprout Social ($13,000) for social media management software to handle city-wide accounts across Facebook, X (Twitter), Instagram, and TikTok.

Public Comments & Testimony

  • No public comments or testimony were recorded during this meeting.

Discussion Items

  • Fletcher Wastewater Plant (Item 1): Staff explained that Digester 3 was initially removed from the Phase 2 scope to balance costs for lid replacements on Digesters 1 and 2. Following a study of the Wastewater Lagoon project, it was determined that the lagoon project budget remains sufficient to restore 10 years of capacity without the removed portion of the digester funds. Consequently, Council decided to reinvest the $943,883 into adding Digester 3 to the construction project to rehabilitate all three digesters as part of the solids handling process.
  • Security Improvements (Items 8-10): Staff detailed plans to enhance security and emergency egress at City Hall and the Annex parking lot. Discussion confirmed the necessity of installing a new gate with a crash bar and mesh to ensure public safety and proper egress for personnel exiting the building, addressing concerns about wandering individuals and security breaches.
  • Firefighter Wellness (Item 14): Fire Chief Dell presented data highlighting that firefighters face a cancer risk 1.5 to 2 times higher than the general population due to exposure to smoke and toxic inhalation. The proposed annual contract allows for comprehensive screenings (blood work, stress tests, ultrasounds) to detect issues early, with 165 firefighters participating in the previous year.

Key Outcomes

  • Unanimous Approval: All 15 action items passed with "Aye" votes.
  • Budget Adjustments:
    • The Fletcher Phase 2 contract total increased to approximately $14.2 million.
    • The Lagoon project will still proceed with full capacity restoration despite the $943,883 transfer.
    • The Raw Water Pump Station project will come in under budget, with the excess returning to the 2022B bond contingency.
  • Strategic Directives:
    • Initiate property acquisition for the Northern River Walk and East Over Drainage projects.
    • Release a 1.25-acre airport parcel from Ascension's lease to encourage new commercial hangar development.
    • Proceed with annual comprehensive health screening for all Fire Rescue personnel.
  • Next Meeting: Scheduled for Tuesday, December 9th.

Meeting Transcript

To approve. So move. Move. Second in any discussion. All in favor say aye. Aye. Minutes are approved. Item number one is approval change order number two with Mark Johnson construction. For the Fletcher phase two improvements project, the total is 943, 883, and an additional 304 days. Brian, welcome. Hey, good afternoon. Good afternoon. So I'm gonna walk through some of the history and how we got here. Um as a reminder, this the phase two project at the Fletcher plant is to rehab the digesters and to rehab the aeration basis. So the aeration basins are done, that's that's complete. Uh the remaining scope is to replace the lids on digesters one and two. Um the change order that we're asking for will add digester three back into the project. And I'll explain that. But so about this time last year, we took third digester out of the project to cover the cost of lid uh replacements for digesters one and two during construction. Once we had the sludge removed from those digesters, we had in the constructor project to inspect the lids because we couldn't do it outside construction. We did the inspection showed that the lids needed replacing. So that time the decision was made to pull digester three out to help cover the cost of the lid replacement for digesters one and two. You with me? Okay. So for reluctant for uh so there is an accompanying finance committee item for to transfer monies from the wastewater lagoon project to Commodore Changer. Uh the this time last year, since then we've done a study for that project on the lagoons. Um the intent of the city was to determine the scope for improvements and correct preliminary cost estimates. Uh and it so a component of those improvements is restoring some of the lagoon capacity by sludge removal. Um the study indicated we could restore eight to ten years of capacity within the proposed modified budget. So, in other words, we take what we're proposing 943,000 dollars from the lagoon project. We still can remove the amount of sludge we need to to restore 10 years worth of capacity and do the other components of that project we want to do. Um and then another note is that the digesters and the lagoons are they're interconnected systems, so the lagoons basically serve as an overflow for sludge that can't be processed by the plant. Um, or if the solids facilities overload it, so restoration of the third digester will help to reduce the transfer of sods to the lagoon and reduce the amount of capacity needed for the lagoon to be restored. So any questions? You understand all that? I do that's good. Remember how the athlete done went basically at the time when we established the review budget. How much did they originally for the cost? Yes. Five million five the six million dollars of that budget through two sources. So six million dollars is the answer to your question. So at that time we didn't have this study. We so now we're increasing that another million nine forty. Uh I was talking about the legume project. Okay. That we're taking money from so for that project. We had six million dollars. Since then, we've done a study. The study shows that we have enough money to remove sludge, restore it. There's other components of that project we can do as well.

SUMMARIZED BY OPENPUBLICA AI
TRANSCRIPT VIA PUBLIC VIDEO
openpublica.com