0:04Second in any discussion.
0:05All in favor say aye.
0:07Minutes are approved.
0:09Item number one is approval change order number two with Mark Johnson construction.
0:14For the Fletcher phase two improvements project, the total is 943, 883, and an additional 304 days.
0:26So I'm gonna walk through some of the history and how we got here.
0:31Um as a reminder, this the phase two project at the Fletcher plant is to rehab the digesters and to rehab the aeration basis.
0:41So the aeration basins are done, that's that's complete.
0:44Uh the remaining scope is to replace the lids on digesters one and two.
0:50Um the change order that we're asking for will add digester three back into the project.
0:55And I'll explain that.
0:57But so about this time last year, we took third digester out of the project to cover the cost of lid uh replacements for digesters one and two during construction.
1:09Once we had the sludge removed from those digesters, we had in the constructor project to inspect the lids because we couldn't do it outside construction.
1:17We did the inspection showed that the lids needed replacing.
1:20So that time the decision was made to pull digester three out to help cover the cost of the lid replacement for digesters one and two.
1:31So for reluctant for uh so there is an accompanying finance committee item for to transfer monies from the wastewater lagoon project to Commodore Changer.
1:46Uh the this time last year, since then we've done a study for that project on the lagoons.
1:55Um the intent of the city was to determine the scope for improvements and correct preliminary cost estimates.
2:02Uh and it so a component of those improvements is restoring some of the lagoon capacity by sludge removal.
2:09Um the study indicated we could restore eight to ten years of capacity within the proposed modified budget.
2:15So, in other words, we take what we're proposing 943,000 dollars from the lagoon project.
2:21We still can remove the amount of sludge we need to to restore 10 years worth of capacity and do the other components of that project we want to do.
2:31Um and then another note is that the digesters and the lagoons are they're interconnected systems, so the lagoons basically serve as an overflow for sludge that can't be processed by the plant.
2:44Um, or if the solids facilities overload it, so restoration of the third digester will help to reduce the transfer of sods to the lagoon and reduce the amount of capacity needed for the lagoon to be restored.
3:05You understand all that?
3:11Remember how the athlete done went basically at the time when we established the review budget.
3:20How much did they originally for the cost?
3:23Five million five the six million dollars of that budget through two sources.
3:28So six million dollars is the answer to your question.
3:31So at that time we didn't have this study.
3:32We so now we're increasing that another million nine forty.
3:38Uh I was talking about the legume project.
3:40That we're taking money from so for that project.
3:45We had six million dollars.
3:47Since then, we've done a study.
3:48The study shows that we have enough money to remove sludge, restore it.
3:55There's other components of that project we can do as well.
3:57And so that's I guess that's the the bottom lines.
4:03We're we we have plenty of money in that budget, so we're you want to use that extra money.
4:07I'm just trying uh we're we're bumping something up 943,000.
4:14And we're increasing it another 304 days.
4:18What was it original?
4:21So originally all the lagoon repairs.
4:25No, we're uh the uh the digest digest digest.
4:30Original budget was 706-194.
4:35No, is that not what you're saying?
4:38Yeah, originally we had right now if the with the proposal the budget will be 14.2 million.
4:46That'll be the contract amount for the constructor.
4:48So it would be approximately 13.3 million was the original contract.
4:54What is it we're creating 943,000?
5:00We're increasing 943,000.
5:01The phase two and what planet phase two originally.
5:07I don't know the okay.
5:11If you're looking for it by a line item, it's the just digestive mixing upgrades.
5:16Bowie, it was it was when we originally bid it, it was roughly 12 million dollars, 12.2.
5:21Then we did the lid the lid uh swap out, which increased it to 13.3 ish, and now we're at the 14 point uh two proposal and all right.
5:36I'm not gonna do that.
5:37And is that is that is that separate from the other proper we're taking money away.
5:43You guys with this deal keep it up, huh?
5:49No, there's the engineer's not here.
5:50Okay, well, but we're just taking away money from what was the other project you were talking about.
5:56The lagoon and proof.
5:57So are we still able to do the lagoon project?
6:03Yeah, that was the six million, correct?
6:06But but we're okay with taking this money away from that and putting it over here to do the number, whatever the other digester, correct?
6:16And that still leaves us enough money to complete that other project.
6:20That's what I was trying to walk through our yes.
6:24So we originally did this project.
6:26So we have three digesters.
6:27So the original project is only gonna do we're only gonna do two.
6:31We started out originally doing three, but we thought we were gonna be able to reuse the lids on them.
6:35And you can't really inspect the lids until you get everything out.
6:38So once we got everything out and did the inspections of it, we realized that we were gonna have to replace the lids.
6:44So instead of trying to reuse lids that didn't work, we opted to get two fully rehabbed, and we would come back at a later date and do the third.
6:50Now we've gotten a study back on the lagoon, and we realize that we don't have to have as much money as we thought we had, or that we have budgeted.
6:56So because the contractors still out there, we still have some components that we are that we had originally bid for the digester three.
7:04We're using some of that money that we don't need on the lagoon project and using it as an opportunity to go ahead and get all three digesters up and rehab.
7:11But at the end of the day, the digesters and the lagoons are both part of the solids handling process.
7:16So we're doing the front part of the solids handling process instead of the back part of it.
7:20Or we're still doing both of it, but that's where the money's coming.
7:23So it's still all part of the solids handling process that we're using money for.
7:27We believe that number is 943 883, which you will see a budget amendment and finance.
7:35Between yin and yang, that was a pretty followable explanation.
7:41Is that recorded over there when we play it back?
7:44We might need to play her back again.
7:49I don't have any other questions.
7:52Lonair, are you away?
7:55Would you like to explain it?
7:56Would you like to give me a summary of what we just talked about?
8:04That was motion and second.
8:09All in favor say aye.
8:12Item number one is approved.
8:15Item number two is approval.
8:16Balancing change order with Mark Johnson construction for the Ed Love Raw water pump station project, a deductive total of 1265605.
8:27We like deductive totals.
8:29This is more straightforward, yes, sir.
8:32This is uh the closeout change order for the raw water pump station project, the raw water pump stations uh just north of Ed Love water treatment plant.
8:43Uh we retrofitted the existing pumphouse building with four or five hundred horsepower pumps replacing the old 1976 pumps, and uh we've redone all the electrical components, added a new generator.
8:56So the project uh was originally contracted for 18.5 million.
9:01This puts it coming in at 18.4-ish.
9:05Um finished in August.
9:08The deductive amount, I believe, will go back to the funding was DWSRF and 2022 B bonding.
9:15So the remainder believe we'll go back to the 22 B bond contingency.
9:22So motion second, all in favor say aye.
9:25Item two is approved.
9:27Item three is approval of a professional services agreement with Jacobs Engineering for services related to water and wastewater total not to exceed 50,000.
9:37So this is uh on call contract.
9:39We had this for several years.
9:41Uh Jacobs will assist us with uh things like water distribution system modeling, uh water treatment planning assistance.
9:49Uh they'll assist us with uh screen software reporting, scream software is the software we use to uh when we do video inspection of our sewer collection system.
10:00Uh it helps us prioritize where we need to uh you know do preventive maintenance or do rehab or replacement.
10:07Um the project's funded through our operational budget water and zero and outside services.
10:14Frontiers up for the the remainder of the fiscal year, or is that for upcoming calendar year or what?
10:21It's for the a year from execution.
10:25Okay, and we'll execute as soon as it's approved.
10:36All in favor say aye.
10:37Item three is approved.
10:38Item four is approval of a minor public works contract with Dixie painting and sandblasting.
10:43Total is 28,761 dollars.
10:49Um, so Dixie was contracted to paint the west end tank, and while they were doing that, they discovered some areas that needed some more uh intensive rehab work, some metal replacement.
11:01So this is to cover that.
11:04Um the the project that's funded through the Ed Love Capital Repairs Improvement Operations budget should take 15 days to complete once it's approved.
11:19Is this the additional amount?
11:20Is that it's we're doing it in a separate contract.
11:27All in favor say aye.
11:29Item four is approved.
11:30Item five is approval of contract amendment number one with McGiffert Associates for the East Over Drainage Project.
11:42Uh so the East Over Drainage Project uh was funded uh about 18 months ago.
11:49I think I'm a number of time right.
11:51This is one of the drainage projects that we're tackling with the Noah's Ark 2.0 project.
11:57We initially budgeted uh $350,000 and engaged uh McGiffer to go into design services.
12:06Um we are wrapping up the design service, and this contract amendment is then to move forward with acquisition and both construction phase services.
12:16Their total contract amount addition uh is 1985.
12:23Um that puts us a little over the original 350.
12:28There'll be a corresponding finance amendment today as well.
12:34Um get this project ready and go to bid this summer.
12:38Uh, the estimated construction cost on this is around 2.1 questions that that account number in there.
12:50What account number is that?
12:51That's just general fund account.
12:55All right, I'm good.
12:57You got a motion second.
12:59Second, all in favor say aye.
13:01Item five is approved.
13:02Item six is approval.
13:04Professional services contract with bullet environmental for maintenance of the soil vapor extraction system at the Mercedes Benz AM.
13:17So this is funded by the River District uh improvement account for amp maintenance, and this is to perform just some routine inspections and um maintenance on the soil vapor extraction system that is on the amphitheater site.
13:35Uh consists of you know a series of vented pathways, blowers, and an exhaust system that exhausts everything on the west side of the property.
13:45What is a soil vapor extraction system?
13:49So um with the sound like something extracts vapor from the soil.
13:54Well, correct, but uh it uh with the nature of the site and previous uh garbage now.
14:01This is very common for sites that were formerly in that landfills or are currently landfills, yes sir.
14:06So any any gases or what have you that are in the ground residual from the past, it will extract those and safely get them off.
14:15And is there an ongoing process or is that something you do for a certain period and then it's done and you stop doing it?
14:21It is a continual process, yes, sir.
14:24So I mean this the system works continually, yes, sir.
14:28Will there come a time when you don't need it?
14:31I suppose there could come a time where with the right amount of um geotechnical investigations, you might be able to not have it anymore, but uh we would we would need to perform those investigations, and you're probably looking at at least a hundred years from the last time it was uh used as Tim.
14:51You said this was the river district one, yes, sir.
14:54Okay second motion is second, all in favor say aye.
15:00Item six is approved, item seven is approval, minor public works contract with Amison and associates for overhead door repair at environmental services for totals $38,500.
15:10So this is funded from the facilities maintenance outside services, and this is to repair a roll-up door and sidewall of the building that was damaged by um being hit accidentally by a driver on the side of PSD.
15:26Insurance, yes, sir.
15:27We have applied for insurance coverage, so that should be uh reimbursed reimbursed less than the $1,000 devotee.
15:37Motion motion and a second, all in favor say aye.
15:41Item seven is approved.
15:43Item eight is approved of a minor public works contract with Ryan Metal Works.
15:48The total is $34,700, Tim.
15:51So this item and the next two are all kind of a collective project.
15:56This is funded by the security improvements account, and this is to do several items.
16:02It's going to install a new handrail on the front of City Hall.
16:06It's going to install new fencing between City Hall and Chom.
16:10It's going to install new fencing at the Annex 1 parking lot where there's a yellow handrail right now, and it's going to install a new three swing gate at the entrance of that parking lot.
16:30All in favor say aye.
16:31Item eight is approved.
16:33Item nine is approval of a minor public works contract with fast signs for city city seal plaques for the gate between City Hall and Chom.
16:43This will install two plaques on the new fence between City Hall and Chom.
16:48These will be cast aluminum plaques.
16:51What are the plaques?
17:02All in favor say aye.
17:04Item nine is approved.
17:05Item 10 is approval of a minor public works contract with building specialties for gate hardware for new fencing between City Hall and Chom.
17:12The total is $2,670.
17:16So there will be a new man gate between City Hall and Chom, and this will be this work here will install the gate hardware, the emergency crash bar, hinges, uh closer, all the electronic devices associated with that gate.
17:41I think one of the things that we've looked at is just improved uh pedestrian uh entrance to the parking lot.
17:49Right now we have a lot of wanderers.
17:50We also want to make sure we've got a secure parking lot.
17:53Uh the gate itself right now is not conducive.
17:59Uh so it's not conducive to egress away from the building.
18:02We want to put a crash bar on that.
18:04They'll have mesh inside where you couldn't put your hand through and use that crash bar.
18:10Um, but right now, if we were to put gates up at the driveway and someone used the exits of the building outside, there's no egress out unless you happen to have your uh credential and have appropriate access, but we've got to get them to a public right-of-way if someone were to exit the building, so that's the purpose of this gate and doing the adjustments to the egress on it.
18:37Is this security driven or yes, sir?
18:42Motion motion is second, all in favor say aye.
18:46Item 10 is approved, item 11.
18:48Authorization for a professional services contract with the appraisal and consult a group to perform appraisals regarding the Northern River Walk Project Phase 2.
19:00Couldn't have said it better myself.
19:02That's what we're doing.
19:03We want to get ready to uh begin the request to be northern river.
19:08So you can start to go ahead and get the appraisals going.
19:12You have an estimated time.
19:19Uh with the appraiser, hopefully, we can get them not by the end of the year, but certainly by the first quarter.
19:30Motion second, all in favor say aye.
19:33Item 11 is approved.
19:34Item 12 is authorization for professional services contract with southeast appraisal to perform appraisals regarding the east over drainage project.
19:44This is in tandem with what Mr.
19:45Gardner presented, so this is to uh get the appraisals to require the right of way.
19:52I'm sorry, say it again, please.
19:55Get the appraisals to acquire the easements we need for.
20:01All in favor say aye.
20:03Item 12 is approved.
20:05Item 13 is authorization to amend the airport lease agreement with Ascension FBO at the Tuscaloosa National Airport.
20:15Well ascension is also known as Hawthorne Global.
20:18They're on the east side of the airport.
20:19We've seen a growing interest in development on the east side, in particular south of Hawthorne.
20:25That's the most likely way to initiate commercial or private development, and there's a 1.25 acre that kind of is in the way.
20:33We've been in talks with Ascension to remove that one parcel of 1.25 acres and like to move forward.
20:46And open for any further questions.
20:50Are we adding that onto their lease or taking that?
20:54We're taking it off.
20:56It started in 2013, Bama Air before Hawthorne, they had a Medivac of uh operation there.
21:02They uh closed their doors in 2018.
21:05And uh the property is just sitting there dormant.
21:10We're trying to uh encourage a local developer to build some more hangars right there.
21:20Motion second second, all in favor say aye.
21:24Item 13 is approved.
21:26Item 14 is authorization to enter.
21:28The 12-month contract with a vital exam special services, physical wellness examinations and tests and Tusclose fire rescue first responders.
21:37The total is not to exceed 166,000 dollars.
21:40Chief Dell, welcome.
21:42Good afternoon, council.
21:44This is the third year that we've been doing physicals, uh health evaluations for our firefighters.
21:48This is one of the one of the huge benefits, and I think recruitment tool that that somebody should look at the city of Tuscaloosa and say, you know what, this this might not be my paycheck, but this is going to get me to retirement.
21:59This is going to get me to enjoy retirement.
22:01Uh firefighters across the board, you look at every every cancer risk.
22:05I think everybody in here has probably dealt with cardiovascular issues and cancer risk in your own families.
22:14Every cancer category that you look at, firefighters are one and a half to two times higher risk than the normal population.
22:20That's not two percent, that's two times that.
22:23And so this is some of the stuff that that through ingestion, absorption, inhalation of some of the fires, some of the things that we run into, puts us at risk for that.
22:34And so what this does is allow my guys to get tested early.
22:37They do blood work, they do cardiovascular testing, cancer screenings, and hopefully we can catch some of these cancers uh, you know, early on in the process so that so that the treatment can be there and they can have that that long-lasting career and the retirement.
22:53Um final exam comes in, it's a company out of Florida, they come in, we're gonna start doing blood work in December, and this will go uh every firefighter that we have is eligible for this, and so over the years, you know, the first couple years, it's you know, you could tell there were some guys that that weren't really getting on board.
23:12Last year we had 165 guys uh actually step out and do this, and you know, no matter how old you are, how young you are, or how young you think you are, uh it's never too early to get tested for some of this stuff, and so I'm asking for your approval of this because this is a huge benefit and really firefighter safety issue for our guys.
23:33So, chief, is this just the blood work or no sir?
23:37They go through uh NFPA 1580 sets the standard for us, the fire protection uh sets the standard for for physicals and also the treatments there.
23:48So, what this does is they do blood work.
23:51So, so in December, these guys will get blood work, and it ranges from everything from a metabolic panel to tell them what their kidney, their liver, liver uh enzymes are doing, how their body's doing at that, uh a diabetes marker, hormone markers, prostate markers to figure out if they if they're higher risk for prostate cancer.
24:11They also look at everything BMI blood pressure O2, uh, 12 leads, stress test, all of those things are doing ultrasounding arteries all the way down.
24:23Uh is this contract annual biannual trying?
24:30I don't have any other questions.
24:33Motion second, all in favor say aye.
24:35Item 14 is approved, item 15 is approval to enter into a 36-month professional services contract with sprout social for social media management software of the total $13,000, $33.8.
24:49Good afternoon, counsel.
24:51So Sprout Social is a platform that we have been using for several years now to manage our dozens of social media platforms or accounts that the city of Tuscaloosa has.
25:02It allows us to schedule posts out in advance.
25:05It gives us analytics and it gives us the ability to set up workflows so that one person on my team can schedule and another person on my team can approve.
25:22What accounts do we have?
25:25So the city itself has several, you know, on all the different platforms.
25:30And then we have some uh departments and divisions that have their own.
25:35So the airport has their own Facebook, for example.
25:38The River Market has their own accounts.
25:40Um we have a couple of city events that have their own accounts too.
25:45And holidays on the plaza have their own accounts as well.
25:50This is just for social media, not yes.
25:54Instagram we have Instagram, uh Facebook, Twitter, formerly known as Twitter X.
26:07Um the mayor is on TikTok now.
26:09I don't know if y'all heard that or not.
26:14We're not we're not funding that all your turn with TikTok.
26:23You know, we're we're on all the platforms anywhere we can reach.
26:26Oh, that's worth $13,000.
26:29Motion motion second, all in favor say aye.
26:35Item 15 is approved.
26:36Is there any other business to be brought before this committee?
26:42Hearing none, our next committee meeting will be in three weeks because of the holiday.
26:47We will meet and reconvene again on Tuesday, December the 9th.
26:54Are we are we ready to give a motion to adjourn?
26:57We are motion motion or second.
26:59All in favor say aye.