OPENPUBLICA · PUBLIC MEETING RECORD
Record of Proceedings

Tuscaloosa City Council Meeting: March 24, 2026

City Council MeetingsTuesday, March 24, 2026
BodyTuscaloosa, Alabama
SessionCity Council Meetings
DateTuesday, March 24, 2026
StatusFILED
Video Record

STREAMING COPY IN PREPARATION — RECORDING AVAILABLE FROM THE ORIGINAL SOURCE

Transcript — Verbatim
0:00

Number one with price construction company for approval of Buddy Power Pavilion.

0:03

Tim.

0:04

Yes, sir.

0:05

Good afternoon.

0:05

Good afternoon.

0:07

So this is to balance the project with the Northridge pickleball price construction.

0:13

What we're asking to do is add additional funding into this contract so that we can do some additional paving at Buddy Powell Pavilion and re-stripe that parking lot.

0:30

You want to fresh a refresh us the amounts, Tim.

0:33

We went over them last week.

0:35

So the change order amount from price construction is 150,000.

0:39

We have $30,000 of underrun within the contract currently, and we still have $15,000 within the original budget.

0:47

So we're looking for right at $104,000 to execute this change order.

0:53

On the screen, you'll see the design.

0:55

We've got the existing asphalt on the right hand side of the screen is to have a new seal coat and restriping.

1:01

And then on the left hand side you'll see the new asphalt around the perimeter with also with new striping.

1:06

There's signage included and a few bollards included as well.

1:11

All right.

1:12

And that uh the differentials coming out of the tourism capital budget, Check.

1:16

Correct.

1:17

And Miss Standage, how much does that leave in there?

1:20

Um it will leave ballpark 400,000.

1:25

I'm good.

1:27

Most second.

1:27

All in favor.

1:28

Hi.

1:28

Motion passed.

1:29

Thanks, Tim.

1:31

Agenda item number two, approval minor public work contract with Red Oak Paint Company for paint service across city campus.

1:38

Yes, sir.

1:38

So this is to paint all the exterior exposed steel columns between this building and annex three.

1:45

Uh what holds up the sky bridges between uh Annex one and three, also going towards the parking deck.

1:52

It'll also paint all the exposed columns and steel at government plaza, the pavilion clock tower out there as well as the handrails.

2:02

And it's coming out of building that this is CFG's five-year facility plan.

2:09

Second, all in favor.

2:10

Aye, motion passed.

2:12

Agenda item number three, approval of minor publishing work contract, but Taylor Electrical Contractors for installational cabling and uh camera system.

2:18

I tell those tennis.

2:20

Yes, sir.

2:21

So this is for the infrastructure for the camera system that is for streaming tennis matches at the tennis center.

2:29

Um this includes all the underground raceway that has to be installed, raceway that will go to each individual court, both existing and new courts at the tennis center.

2:43

So this is the just the infrastructure, not the actual cameras.

2:47

Correct.

2:48

Uh has purchased the yeah, cameras have already been purchased.

2:52

Yeah, and I've got something of a lesson on this during the week.

2:56

Okay.

2:57

To feel better.

2:58

Why was it mispositioned for the game with to be completely frank, Mr.

3:05

Busby?

3:06

We had no knowledge of this desire during design uh or where these cameras would be placed.

3:12

We in design put raceway all over the property for future camera installations.

3:18

Um those installation locations are like like poles as we would typically do.

3:25

Um it was later brought to us that they would they desired to have these for streaming of the matches and that they need to be located center of the court.

3:36

Uh we didn't have this knowledge until about three or four months ago.

3:39

Okay.

3:41

So it's it's for streaming, it's not for public safety.

3:44

No, sir.

3:45

We we have we have installed public safety security cameras inside the facility already.

3:50

Um so that that has already been taken care of.

3:54

And the stream the streaming just said is one of the requirements they had to get the NCAA tournament there.

4:02

Yeah, what I was asking about was shine because I did get an extraction on the stream.

4:11

But apparently this is just the wiring so that that can take place, right?

4:17

Yes, sir.

4:18

Initially, it wasn't identified that there was going to need to be additional wiring to get to it.

4:26

That's what I'm saying.

4:27

Correct.

4:28

And just to kind of clarify, we have we have the raceway around the property.

4:32

This is going to take that raceway from uh quasi boxes, the the underground electrical boxes and light poles, extend that to center of the court on the fence line of each individual court.

4:45

So we've got to go into the landscaping on each court as well as put these throughout the indoor complex that is existing facility.

4:54

And excuse me, uh Taylor Electric, they did all the electrical work.

4:58

Yes, sir, that's correct.

5:00

Yes, sir.

5:02

Motion.

5:03

Second.

5:03

All in favor?

5:04

Motion passed.

5:06

Agenda item number four.

5:08

Approval and balance and change order number one with the construction contract with Snow Blaking for Linton Barbershop level.

5:14

Yes, sir.

5:15

So this is the balancing change order for snow blakening at Linton's barbershop.

5:19

Uh this project is still ongoing, however, snow blaking scope is at the wrap-up stages.

5:26

Uh we've still got some artistry work by Caleb O'Connor to be completed.

5:33

Um however, Snowflake is at a point where we would like to balance this contract, and that's an additional twelve thousand dollars.

5:43

Through the course of the project, we had several things we did not foresee or did not really anticipate.

5:50

There's some additional soding that we needed to do along the perimeter of the property.

5:54

Um also uh we we ended up replacing the sidewalk, it's about 150 feet of sidewalk along TY Rogers Avenue.

6:02

So those two items are what has put us slightly over the contract.

6:07

However, I I will say that this uh original bid came in our final cost estimation was 1.1 million, and this bid came in at 647,000 initially, and this puts us at 660 total motion, second, all in favor.

6:26

All right, agenda number five approval minor public work contract with RWC construction LLC to replace various ceilings across the city.

6:34

Oh, sir.

6:36

Uh this is funded by both facility renewal as well as water sewer facility renewal.

6:41

Uh this this covers two different items.

6:43

One is at Ed Low where we've had to repair and modify some HVAC duct work that was above a hard ceiling.

6:49

This is to repair that ceiling where we've corrected the ductwork.

6:52

Also out here at the drive up to this parking lot.

6:56

Um we've had to redo some power for the gates, new gates that have been installed, and this is to reinstall the ceiling in that location.

7:07

I don't have a question.

7:09

Most sir, all in favor.

7:10

All right, motion passed.

7:12

Thank you.

7:14

Agenda item number six, approval rewarded uh contract with GFC construction for the Greensboro Avenue Streetscape Project Bill.

7:24

Council.

7:26

So Mr.

7:26

Noel Linier said this is for award of the construction contract for the Greensboro Streetscape Project.

7:32

Uh and the award would be to GFC construction.

7:35

The amount is three million eight hundred fifty-two thousand eight hundred and sixty-two dollars and eighty-nine cents.

7:41

And for a reminder, this is uh Greensboro Ave between University Boulevard and Seventh Street, so a location up on the screen, and then uh a quick rendering uh top-down view of what we're looking to achieve here.

7:57

This is a true streetscape project, uh increasing sidewalk widths, uh freshening up the landscaping, and also some improvements that we made in the final stages of design, some dedicated um delivery zone and parking areas to accommodate some of the delivery challenges that was addressed with these business owners in the area.

8:19

What parts uh of the project would not be included?

8:23

Yes, it should include everything.

8:25

Not a freak, I hope they answered nothing but this covers everything.

8:28

Yes, sir.

8:29

What's the timeline on this?

8:31

Timeline is uh we want to go to construction beginning of May and finish construction before September.

8:41

I guess not to go too long.

8:42

We've been blocked blocked.

8:44

Go ahead.

8:45

This covers everything we know of.

8:47

This is this will be a challenging project.

8:49

Um the timeline's tight, uh, a lot of stakeholders, uh, but this covers everything we know of as a race.

8:55

I think GFC is the one that got us that's that stretch of university boulevard Queen City or Pinehurst up to about reach three squished into summer, so they they had their work cut out for them on that one.

9:11

How many bidders do we have?

9:13

We have five total five, sir.

9:21

All right, I don't have any other questions.

9:23

Motion second all in favor, aye.

9:25

Motion passed.

9:26

Item number seven approval contract amendment to the engineering service contract docking coker social.

9:32

I I did have one other question, and this it might be in here.

9:35

What breakdown of the money is from the bond versus the um sir?

9:44

So the total bond amount is uh six million applied to the project, and then the elevate amount is five hundred thousand.

9:51

So we'll probably expend um all of the elevate five hundred thousand and then whatever the um on which we did for the design work.

10:00

So we'll probably expend um all of the elevate five hundred thousand and then whatever the um which we did for the design work so six million dollars in the bond will be about two million and one and a half million, two million under budget for that.

10:09

And is that uh is that already site lined or something else?

10:13

No, not they're not as of right now.

10:15

Okay, that's all just we're there is the time lock and it's time line of the project, the unknowns of just being in downtown Tuscaloosa.

10:24

We just don't think at this point it's worth unencumbering that million and a half two million until we get you know through the project so all right.

10:36

So the next item this is for approval of an amendment for the engineering services contract with Duncan Coker for the Julia Tutweiler and Campus Drive Improvements Project.

10:47

Uh so a quick reminder about the location for this.

10:52

This is uh at the Julia Tutweiler intersection just off of McFarland Boulevard.

10:58

So this amendment, if you recall, we're getting a trip money for this project.

11:02

Uh with that comes the requirement to transition the design to a design that meets all the OL dot requirements.

11:08

So that's what this amendment largely accomplishes.

11:12

Uh so all the submittals and certifications and plan reformatting for the dot standards, as well as engineering services to go along with the right-of-way uh services during construction and the plan and prospective renderings that we want for this project.

11:25

So, similar to your question from before, this should take us all the way through uh the remainder of the project through construction for Dunkin' Coker for their services.

11:35

Is this is this involve the wraparound?

11:38

Yes, sir.

11:39

Okay.

11:40

So to the bottom of the screen, that purple outlined area.

11:44

That's the new interchange that we need to implement in order to accommodate traffic coming off of McFarland Boulevard and getting to Julia Tutweiler and all of the businesses in the school that's in that victim.

11:57

So you still won't be able to come out.

12:02

Correct, sir.

12:03

So this is off of McFarland only.

12:05

Uh we'll not be able to get from Tutweiler on to McFarlane.

12:12

Say that one more time, please, Bill.

12:16

I'm sorry.

12:17

So uh if you see the blue lines that are to the bottom left of the screen, so that's the OLBAT project.

12:23

Yeah, and to Mr.

12:24

Fail's point, what they are providing is an off-ramp only from McFarland.

12:29

Today you can come and go in the future, it'll be off of McFarland.

12:33

That's the one down at the bottom that's off-ramp only.

12:35

Yes, sir.

12:39

How did the A-trip money play into it?

12:41

It was something you couldn't do with that.

12:44

Yes, sir.

12:44

So um oversimplifying, but part of the requirement for oversimplifying big fine.

12:51

Part of the requirement for the A-trip is to display how it uh relates to a state route.

12:57

So the areas that are highlighted in purple are the areas that directly are connected to state routes, uh, and that's what got us qualified for the A-trip project.

13:07

Okay.

13:08

Motion second.

13:10

All in favor, motion passed.

13:12

Thanks, B.

13:13

Agenda item number eight, approval professional services agreement with TTL for Rice Mine Road Slope Repair Project.

13:20

My hello.

13:25

Okay, this is for a professional services agreement with TTL for consulting services for Rice Mine Road Slip Repair.

13:32

Um, so back in for a contract amount of 78,142.

13:38

Back in December, this was brought before council to have a study completed of the area.

13:42

Um, we're here on Rice Mine Road north of the river in between Indian Hills Drive and Overlook Road.

13:49

Here you can see some close-up photos of the slope failure.

13:52

Um the study's been completed.

13:54

We have a recommendation now.

13:56

This contract is for moving forward the design to repair the slope failure.

14:01

Yeah, okay.

14:03

Um are these separate sides of the road or is it no?

14:08

It's just two photos.

14:09

There's two failures that are kind of right next to each other on that north side of the road in this image.

14:14

So you can see picture one and picture two is identified.

14:17

I got to do that.

14:18

So you have picture one on the right, picture two on the left.

14:20

Right.

14:21

And what was this done?

14:22

Um 78,142.

14:25

How do we do that?

14:27

Um, it's gonna be a design to um the recommendation is for a riprap slope.

14:33

So if it stabilizes that slope there, so whenever groundwater is introduced, things of that nature, it's not causing that you know erosion condition.

14:43

All right, motion second, all in favor.

14:46

Motion pass agenda item number nine, approval professional service consulting services with uh Duncan Coker for fourth street and 23th and 23rd Avenue one-way project.

15:00

So this is for approval of professional services agreement with Duncan Coker for consulting services again.

15:05

Um and the contract amount of 142,796.

15:11

Um this project locations in this within this fourth and 23rd corridor.

15:15

Um and the goal of the project here is to increase pedestrian safety um and reduce traffic congestion.

15:20

Um conceptually, the idea here is to convert this to a one-way corridor with northbound traffic on 23rd Avenue being one way, eastbound traffic along fourth street in that one way, and then southbound traffic on 23rd Avenue.

15:34

Um, along with this, there is angled parking, bollards at 4th and 23rd, continental striping, um increased sidewalks along the Timerson Square block, things of that nature to again improve pedestrian safety and reduce congestion.

15:49

Cool.

15:50

Jimmy in here.

15:51

He is not yes, sir.

15:56

So this is just designing that area as one way, right?

16:01

Yes, sir.

16:02

And as Lane mentioned, along with the sidewalk modifications on the Timerson Square block, um, additional bollards restriping.

16:10

Are the bollards fixed?

16:12

Yes, sir.

16:14

So it'll be a total of I think we have six removable ones, and the rest of them are fixed, flanking the intersections.

16:25

The initial idea was to do all of this work this summer on both blocks.

16:30

So this first phase is basically the fourth and twenty-third intersection properything in front of Timerson Square, and then the 23rd Avenue.

16:41

23rd is north to south.

16:44

Yes, sir.

16:49

There's nothing going on around the east, north and west.

16:57

Not with this first phase, no, sir.

16:59

We're we're up against the wall to be able to bid this thing for the summer.

17:02

Um this came about pretty late in as far as the bid calendar goes.

17:08

So the low-hanging fruit, and I think the critical component of the safety improvement of this is the intersection at 4th and 23rd initially.

17:19

As y'all look at it, what are the what are the repercussions?

17:26

There's a concern over um impact to businesses.

17:33

Um, you know, losing the two-way condition.

17:35

Uh I you know, quite the other way.

17:38

Um, that you know, I think limiting the vehicular traffic to a one-way condition through there, you know, facilitates that ease of movement of the traffic through that area.

17:51

So increased circulation throughout the area um with the angled parking to facilitate that one way.

17:57

You don't have you know that counter-afflicting traffic for I'd allow asked a lot less questions than 128,000, not 400.

18:05

So that's this contract amount is for 142,000.

18:10

Um sorry, no, you're fine.

18:14

He takes his question, but as you know, we've been looking at this area now seven or eight years.

18:21

I mean, we've we've had issues within that entertainment area.

18:25

Um we had the most recent incident a few months ago after you know, we're continuously talking to TPD about this area about what we can do to make it safer for pedestrian traffic.

18:37

Um we've explored everything from closing the area and making it pedestrian.

18:42

Um we feel like this is probably the best option we have if we're going to have pedestrian safety in that area, control traffic flow, um, unless you wanted to close the streets, and I don't think that's an option.

18:57

No, I went out there with them on a couple of occasions.

19:00

There I see no easy answer.

19:05

So I agree.

19:07

So to allow this to I mean to support this.

19:11

And I will.

19:12

I I don't know.

19:14

We're gonna work to see if we can get the project included in my April 19th recommendation.

19:21

Um we would theoretically like to have this at the same condense time frame as Greensboro Avenue project.

19:29

Um I don't know if that's gonna be possible because my understanding this project it's um I guess it's where we are in life, but it's probably an 800,000 dollar construction project to do this, and so because you've got to it's my understanding, you've got to bump out medions, the ballards, all everything else that's included.

19:49

I I don't know if we're gonna have the budget capacity to put it into the 26.

19:55

It might have to flow into the 27th, but we'll you know, I I can't.

20:00

It might have to flow into the 27, but we'll you know I I can't my goal early on was to get this into the 26, but as you'll hear a little bit later when we talk go in finance and talk about RSA conversion, we need a little bit more in RSA conversion, so that's priority one.

20:14

So it is I don't know if I'm gonna be able to put this one into the fiscal 26 capital, but I would like to go ahead and get it design, have it in queue.

20:24

How many trying to get alpha vision?

20:28

I mean, to make uh this this work is relatively as sensitive to the university calendar as correct.

20:38

100% we wouldn't want to do this during football season or during the spring or anything like that.

20:44

We'd want to try to get it to limit their impact.

20:47

Yeah, but I don't have any other questions.

20:53

I'll make a motion.

20:53

I would like to talk about some concerns with that.

20:55

Okay.

20:57

Um my name's Jeremy Wyatt with Redman Bruce in downtown.

21:07

The only thing I really have a concern is if this is gonna hurt more than help as far as bottlenecking the traffic.

21:16

Because as I've been thinking about this past couple days, and the best thing I could really come up with is a little give and take.

21:23

Maybe you know, you talk to every business owner downtown, they're gonna say we want more parking, we want to increase the parking and increase the parking.

21:30

Well, obviously, we have an inflow of customers and it's getting busy, you know, the businesses are are bringing in more clientele, and it's a good thing, you know.

21:39

And I'm not opposed to any kind of um safety concerns with us, pedestrians.

21:45

We want to help all we can't all we can, but I think we have to add some parking somewhere to do this give and take type thing because I mean we're gonna be taking away how many of us about 29%.

21:59

So we're gonna be taking away some parking, and that's issue number one with everybody downtown, you know.

22:05

Um I think there's not gonna be a solid answer.

22:10

This is gonna work because I mean I don't think there's anywhere in Tuscaloosa that we've done this in a congested area that that we went to one way that's actually worked or um and if it has I I you know I'm not sure about it, but I just think bottlenecking all this traffic is gonna cause major concern with over spillage.

22:31

Now I'm sure the engineers are gonna do their due diligence and you know figure all that out.

22:35

But game days when we're shoving traffic down University to Lurlean, and then we're gonna be landlocked at that point.

22:43

Um I don't know, that's just all my concerns, and all the loading zones and stuff.

22:49

I mean, they say they're gonna implement loading zones and stuff like that.

22:51

I mean, Uber drop-offs, taxis, that's all gonna be fantastic.

22:55

Um but taking away parking before we add it somewhere else, I think is gonna is a major concern for me.

23:02

I mean, the parking deck has helped all those businesses right along beside five and all those businesses grow.

23:07

I mean, that's helped.

23:08

Um can they not park at like Parker Hall Park over there?

23:14

If they can, they would.

23:15

You know, that's why this is a problem.

23:16

Obviously, this is Parker Hall Park.

23:19

Oh, parker home, just our across down there.

23:23

There's uh free public parking, just one fetter just completely in the fair well over a hundred spaces.

23:30

So I have parking is probably not the biggest concern in the area.

23:33

I do want to make a quick note that the engineering team and Mr.

23:36

Duncan has done a masterful job, and then when they modify this area, that the bottlenecking won't happen because you'll have the ability to have a truck delivery and a truck to be able to pass around.

23:46

Currently you don't have that.

23:48

You have multiple conflicts of movements of both vehicle and pedestrians, so the vehicular movement will actually be a fairly smooth flow laws allowing for vehicles to pass.

23:57

So I don't see that as much of an issue on the bottom of that.

24:00

Yeah, well, there's you're losing two exits going into one exit.

24:03

That's what that's like.

24:04

That's the only concern I see.

24:05

And when you have you know multiple, multiple vehicles on a Friday and Saturday night trying to look for a park, but they're going in both directions.

24:12

And part of that's due to lack of time over.

24:15

Yes.

24:16

Well, if we had the parking spots, there wouldn't be a traffic jam.

24:23

What I would say on that is if it was meter parking, which is probably what it should be, the term would be there because a lot of its employees parking in there and they'll park for an extended period of time.

24:31

So you don't get to talk about after hours too.

24:34

Oh sorry, yeah, yeah, yeah.

24:36

Well, obviously, patrons are downtown, you want to turn them over every two hours.

24:41

I mean, somebody might want to go to a restaurant and go see some live music after, you know, we need that time frame.

24:46

Sure.

24:47

Or if they go to the amphitheater and you know, all this is shared parking.

24:50

Um just I just want to know for the businesses for the council.

24:53

One, every business center has been engaged in the area, two, council members have been engaged.

24:58

Three, uh Council Busby noted it.

25:00

It is there's not a one-shot solution to this.

25:02

In order to get vehicular and pedestrian safety in this area, it's probably the best you're gonna get with maintaining parking places.

25:08

And we keep stressing pedestrian, which is extremely important, but the HECO complex about 12 a.m.

25:13

as you know, very challenging in the area.

25:16

Very, very dangerous.

25:20

Well, like I said, I maybe it'll work, maybe it won't, but um I think it's gonna for me it's also the question the future, the outlook for the future of what's gonna happen with that area.

25:32

I mean, I'm the owner from the Ronald's German restaurant, and um I see the same concerns that if we have uh at the moment uh Uber and Lyft and so on, they just stop somewhere in the middle of the street, and if there are more people more uh more vehicles coming from from uh Reesville, that would just clock up the whole area.

25:51

The same as with uh with uh was the flow from going to uh 23rd street, it's the only exit people would have.

25:58

That's right, so with the people said with a few with the output for the future, has that been considered in the different scenarios.

26:09

I'm pretty sure you did at least three scenarios, and uh what is uh I talked already with a few people.

26:17

Why don't you come up here to like I said, my my name is Olaf Maya, I'm the owner from uh Rolls German restaurant, and um we enable us over there, and uh I've got a couple of couple of things uh where I have a concern with is um the scenarios we we got only the information that uh this concept one uh one way road is are there other concepts for example with the outlook for the future?

26:48

What can we what can we do in this whole area?

26:51

For example, um uh accommodating more festivities like uh like for example a Christmas market like Christmas in the Water or something, or having having uh different different things in that whole area, public viewing, name it.

27:06

And uh we block out this complete area, we lose a lot of parking lots, and uh from my experience in the in the uh time I'm there is it's really in the evening, not during the day, during the day we have basically enough parking lots.

27:23

But in the evening, all the parking lots are taken.

27:26

People that park in uh on the 4th Street, they go working, for example, on University Boulevard, and and this is this is kind of like a concept with uh with uh uh park meters that uh could could have been so could we uh could be solved, but not not necessarily.

27:41

Then it's also did you consider the future savings center?

27:46

Do they have an increase of the amount of parking lots?

27:49

I'm pretty sure they have and uh there's a nice place between the two hotels that could could be a nice area for a parking deck, which would solve kind of like all those problems.

28:01

And um Jeremy and I we talked already about it that um if we would kind of like turn this whole area into a pedestrian zone, just give it access to the bank and to the parking lot and one-way flow out of the 22nd street.

28:16

That would, and this the rest kind of like as a pedestrian zone, that would be a much, in my opinion, a much much smarter solution, and it will would be also uh beneficial for Tuscaloosa, just Tuscaloosa would due to the fact that we would get more more uh more guests, they would Tuscusa would uh get much much more sales taxes, which I think we should also look in both directions.

28:42

One site uh of uh from from the city of Tuscaloosa and also from the businesses if we get more business, more sales tax.

28:51

Yeah.

28:52

And we we uh um I do want you to know we've looked over the years, we've looked at the concept of the parking deck over there all below.

28:58

The city owns the lot below in DC Suites.

29:01

The problem is is that you have to go about 40 feet to Fed Rock to begin drilling piles to be able to support a parking deck, and you're talking about $70,000 of parking space to build a parking space and to build a parking deck there.

29:14

It's just it's just not an affordable we've even engaged the private sector about saying, you know, if the city were to even provide incentives, could you make a profit operating a parking deck here and it it's just wouldn't work?

29:28

Um we've had issues in this area for many many years.

29:32

I've met I know we we've been in meetings many times for many many years.

29:37

We have to find a safety solution for the nighttime hours of Thursday, Friday, and Saturday nights.

29:44

We we have to and if we close one street 22nd, which I do love the idea.

29:51

I'm with you actually on that one, but then we impact Jalapinos, diplomas.

29:57

Now all of a sudden they're saying you've taken our loading zone in our areas from us.

30:01

So what we're trying to do is find a solution that makes it safer.

30:06

And that so it's it's just hard to balance all those, all those different competing interests, and and what we have is a plan to do that.

30:14

And here's what I promise to you because I know the meeting's going long, Mr.

30:17

Lanier.

30:18

I can hear you with the gavel down there.

30:21

Is that allowing us to hire Mr.

30:23

Duncan today doesn't mean it's the end of discussion.

30:26

It really just means it's the beginning.

30:28

And I can promise you he's going to sit down when we have some ideas.

30:32

Our team is going to sit down and engage again to see, you know, from a practical standpoint every single day.

30:39

But we really want to get moving with this because what happened several months ago was disturbing.

30:44

I I get the warnings.

30:45

TPD advises us on these issues.

30:49

We're deeply concerned about the environment out there many nights.

30:53

And we have we're at the point we have to do something.

30:56

So we're we we will engage opportunities.

30:59

We want you, we're we want y'all to be so successful.

31:03

And we don't want people when they Google your business, something bad happening to be the first thing that comes up in the feed.

31:10

I I'm I'm promised you that's our goal, and we're gonna work with you.

31:13

This is won't be the end, it'll be the beginning, but I feel like we have to do something.

31:18

I mean, I'm I'm totally with you.

31:19

I totally understand that for me is in general, not just uh that we have kind of like all the things, uh pluses and minus for different concepts and not just like okay, we we found a solution now, we have to push it through, and then uh we have to uh wait another five years until we have the next decision.

31:39

I think it should be uh very very short-term dynamic that we can get this off.

31:45

And and one idea is having a parking deck over there.

31:48

The other idea would be having finding somewhere uh kind of like a lavelage spot where we can put some parking lots or a cop uh parking deck, but don't have to spend the 70,000 dollars per parking lot and having maybe a a shuttle, yeah.

32:04

Having maybe a shuttle because at the moment um the problem is that Mayor for the sake of time, I don't mean to cut you off, but we got a long agenda of a full schedule finance, so we could probably talk about it.

32:17

Okay, yeah, we'll and I'll I wish you would be invited to that.

32:23

That I'm sorry, that wouldn't be a Samurai make a motion.

32:27

Uh second.

32:29

Um I'm gonna support it.

32:31

It's it's a mixed bag, Jeremy Wolf.

32:33

Appreciate y'all coming in.

32:35

But okay.

32:37

All in favor.

32:38

All right.

32:38

All right, motion approved.

32:40

All right, very number 10.

32:45

Approved professional services agreement with Porter Higginsbot Engineering for engineering service related to Scottin Boulevard fiber uh good afternoon, council.

32:56

Good afternoon.

32:57

So this is a contract for professional services of Porter Higginsbotham for 28,000 five dollars.

33:03

This is for them to do survey and uh create the documents required for L dot permitting for IT to install fiber along the south side of Skyland Boulevard.

33:13

So this will roughly go from the like BMW Barkley dealerships over to uh firehouse number nine.

33:21

So we'll go to Woodland Forest and then go south.

33:24

Um the LDAP permit is required for them to be able to bore and put this fiber in.

33:30

Second, all in favor?

33:31

Uh motion passed.

33:33

Um approval warding contract with ST Boss Construction Company for the 2026 city wide resurfacing project.

33:42

Is that so this is our yearly resurfacing project?

33:45

We had two bidders, ST Bunn was a little bitter at just over 9.8 million.

33:50

Uh this did come in over budget due to kind of the uh fuel prices that we've seen, the uncertainty in that.

33:56

We think that's really what affected it.

33:57

So there will be an item on finance to go along with this to make up for that over budget amount.

34:03

Where's the extra mining camera?

34:05

Sir, do you know where's the extra mining?

34:07

We'll be pledging uh this year's Alabama gas tax funds.

34:11

Okay.

34:11

I'll make a motion.

34:12

Second.

34:13

All in favor.

34:14

Uh motion passed.

34:17

All right.

34:18

Agenda item number 12, approval professional service agreement with Show Engineering Company for engineering service for academy drive drainage project.

34:25

So this is one of the NOAA's R 2.0 drainage projects.

34:28

This is their proposal for design.

34:30

Uh this is the Academy Drift subdivision where we're having flooding on Stone River Road, where there's some undersized culverts and some other undersized pipes that we're gonna be addressing along that drainage.

34:40

So this is just north of the Indian Hills Country Club.

34:43

Okay.

34:46

This is what we discussed before, right?

34:48

What's the total again?

34:50

It is uh 292,612 and 50 cents.

34:54

And that takes us all the way to the bid phase.

34:58

Okay.

34:59

Make a motion.

35:00

Second.

35:01

All in favor.

35:03

Motion passed.

35:04

Thanks, number 13, approved professional service contract with Hughes Aerospace Corporation.

35:10

Yeah.

35:11

Afternoon.

35:13

The short version of this is that we're proposing the interim uh flight procedures uh during the runway extension project.

35:21

Uh it's a 495-day contract because we're displacing the runway.

35:25

Uh we're shortening the runway, it cancels the existing procedures by uh implementing these interim procedures allow operations to be less impacted to fly in and inclement weather, and also provides insurance on the back end that we have procedures ready to go once the full length.

35:40

Right now, the FA is advising that our uh the FA's procedures, the permanent procedures may be between June and September 30th, 2027.

35:49

Uh by using a third party, it prevents the athletic department to have a second fall season forgoing their charters.

35:57

Uh here's an example of what flight procedures look like.

36:01

Uh, this is what they'd be construction uh constructing on behalf of the FA.

36:05

Uh they were recommended.

36:07

Hughes Airspace was recommended to create a a flight procedure that would be initiated this fall during our busiest time of the year, and then once full length construction is available for full-length runway pavements available, they would amend this procedure to reflect the full 7600 feet.

36:24

Uh the contract is based off the option of uh doing the fall, and if we at by January, if we feel like the the FA schedule is not gonna be ready, we can tell this contractor to go ahead and initiate the full length procedure.

36:39

This reflects the displacement, 800 feet.

36:41

This will start in uh April, mid-April, and go all the way through next spring.

36:49

The uh red portion is is kind of uh a visual map of where that would be uh that's causing the cancellation of the existing procedures, and then here's their proposal option one for this fall would be 77,400.

37:05

If we uh elect option two, uh that would make a not to exceed of overall 140,000.

37:11

The funding for this is out of elevate.

37:13

We're asking to use the savings that we realize from the bid opening results with this project.

37:18

Uh we asked we saved over uh almost two million dollars.

37:22

We're asking to use 140,000 of that for this agreement.

37:27

That's a bad idea.

37:29

Oh I'll make a motion.

37:32

Yeah, what's the repercussion of the temporary procedure?

37:37

It's a benefit to have them.

37:39

Uh the risk is much more concerning to us if we do not have this if we rely solely on the FA's uh schedule.

37:47

We could go into late fall 2027, and the university would have to forego charters for a second year.

37:54

Second, all in favor.

37:56

Aye, motion passed.

37:58

Thank you.

38:05

Uh economic agreement.

38:09

Okay.

38:12

Okay, very much.

38:14

Thank you, sir.

38:15

Hello, good afternoon.

38:16

Thank you all.

38:17

I'm I'm gonna try and keep this brief.

38:18

I know we're running late.

38:20

Uh Michael Laney, the landing property group.

38:22

Yeah, counsel, thank you for uh hearing this.

38:25

So we came to finance committee.

38:27

I would say maybe two months ago, uh, had one review, then we had another one for this project Springbrook.

38:36

It was uh approved, and we went to council.

38:40

Uh we received a uh an agreement between the city and landing property group, and we we found some uh issues with the agreement, so we replied, and then this has been tabled, and so since then we've been kind of at a at a stalemate, so we're here today to hopefully maybe get this going in the right direction and and and start this process again uh and and talk with council.

39:05

We uh what y'all got here in front of you is is our six main bullet points for uh the agreement and if if I can just run through them real quick.

39:16

Um, like I said, I'll be brief.

39:18

Uh the the agreement we received is for uh a shopping center type development.

39:25

This is a subdivision of six parcels, it's going to be uh six separate facilities, and we can't give a square footage.

39:34

We can't do it's not gonna be one big shopping center where we can utilize like that.

39:39

So that was that was the first big thing, and so we're we're trying to change that.

39:42

And uh the second is the new to market business, it's kind of been a a buzzword for this agreement.

40:00

uh six separate facilities and we can't give a square footage we can't do it's not gonna be one big shopping center where we can utilize like that so that was that was the first big thing and so we're we're trying to change that and uh the second is the new to market business is kind of been a a buzzword for this agreement where we the agreement calls for six new to market businesses or we get no incentives without uh what for us what we've looked at and what we've what we had always considered is in the event that there uh we we couldn't bring a new to market tenant we would fill that hole with someone that was a suitable but we wouldn't get any incentives and so you know whether it be medical or or whatnot in our original proposal we we we had medical in there and other other not not all retail but we would not receive any incentives or or tax incentives in the event that that it was not a new to market and we define new to market as as uh you know someone that's not existing in in in the market or a new tenant in in that space where let's say if uh not armies I don't think that's a good example right now but uh uh if if if uh McDonald's wants to open a new store they don't close their existing store open a new store that would be a new to market so um and and those details can be worked out um payment period we've got 25 years we talked about trying to start that at uh the time we get our our third tenant which uh is is what we were had proposed was three new to market tenants uh so once we get the third tenant is when we would start the payment period um labor force construction materials there's several uh yeah like trying to come in and use city employees for something we don't control like if we do a ground lease and it's a national tenant uh they're they're gonna come in and bring in their own people whether it's union whether it's whatnot wherever they're from they're bringing their group with them we we have no control over that so we can't agree today to say this is what uh this is the uh we'll agree to work with the labor force union and and and whatnot in Tuscaloosa but we can't agree anything we do but work with site work uh you know especially material source of materials with uh locally within whatever parameters so I mean our objective and goal would be to work with local communities and right now we're working uh with uh jimmy duncan over there in his group so we're um I mean you know we're we're using local engineers and and and we'll continue continue to use those uh last was the employee guarantee um we had given a guideline and and then that ended up in the in the agreement uh I I've talked to staff about that there you know we're trying to work through that uh you know we could we could try to hit a a number and and and validate that at one time uh during the during the project and say this this number's here I mean us guaranteeing you know a big number of employees for the life of the project is which is a 17 18 year payout I mean hopefully if everything goes well then that's that's gonna be a tough ask for us to be able to guarantee that there's uh 200 plus employees on on payroll there the whole time but I you know I think there will be a point where there will be a number and and we'll we'll hit that number so uh you know the the big thing about this whole agreement is it it is a performance based agreement based on the tenants we bring in new to market and their sales and we don't get paid unless those sales numbers hit and so we're we're taking a big rest we're putting all the money up and we're we're hoping that these guys come to Tuscaloosa they thrive and and we're able to hit all of our rates and for our investors for ourselves and for everything else.

43:38

So it's it's not just as simple as uh we're trying to get tax incentives we're getting you know we're getting it based on the performance of them and we're splitting some with the city and it's it's all sales tax it's no ad valirum it's no uh use it's no none of that it's just sales tax so anyway I was trying to be quick so I apologize if y'all have any questions I mean I'll I'll feel free to ask or or y'all can hit me offline.

44:08

So you've got three new to market tenants already committed.

44:13

I mean are you you work yes okay and when we say committed I mean they're yeah ideally they're they're signed up they're they're ready to go but I mean something could happen that I it's outside of my control and so but we're still if one of them drops off it'd be a similar use something like that it would be similar to to that use would still fill the space right and it would need to be a new to market.

44:43

So I wanted to bring you here Mike I want anybody who had questions to ask you why you were here so you can present what you had and uh if the staff or anybody has something they could present what they had so we could all get on one accord I can get we can get all the information in one room so everybody can have the same understanding of this project so we can go ahead and vote and decide what we're going forward or not and uh so I'm open to the floor for that.

45:00

I can get we can get all the information in one room so everybody can have the same understanding of this project so we can go ahead and vote and decide whether we're going forward or not.

45:05

Um and uh so I'm I'm open to the floor for that.

45:10

Um I'm hoping that you could if anything you need to work out, you can work work it out with Brendan or whoever you work with uh with the city.

45:20

But my thing is I I want to be fair with you.

45:22

Uh if you can't get all the materials in Tuscaloous, then that's fine.

45:26

If we can't, you know, I'm I'm just being honest.

45:28

I'm sure everybody who developed here don't get everything from low the home depot, and I want to be fair with this development, you know what I mean.

45:35

If that's the case.

45:37

Um my whole thing is trying to bring something new to District 7.

45:42

And as far as the risk, I think you're taking a lot of the risk, but the city's not giving up everything because it's a percentage that we're splitting, right?

45:50

Right.

45:50

All right, so um I wanted you know what I mean.

45:54

I want the council to hear everything out in the open because uh I mean I mean these are the major points in the project that I just went through and I ran through the you know the the with the agreement where we were and I've I've sent this to staff and so they've had it, and and you know, we're we're we're I mean we're sitting on oh, you know, waiting on G.

46:17

I mean, we're we're we're ready for it.

46:18

We want to we want to do this project.

46:20

I I love Tuscaloosa.

46:22

I mean, my I've my I Hunt landed hours south here.

46:26

I lived here, you know.

46:27

I was here when when Walt ran for uh his first uh race.

46:32

I mean that was that was a minute ago.

46:34

But I I mean I've I lived here for five years and and uh in Kipp District, and I mean it's it's this I I like this town and I want to and we we do projects all over the state similar to this.

46:46

We're performers, uh we you know we're closers, we get things done, and most people are happy, and I mean we can you know we can get referrals and you know I think Brendan said that in the beginning, and and uh one of y'all's bigger developers gave us a recommendation here.

46:59

So I mean he knows who we are.

47:00

I mean, we're not just fly by the night.

47:02

The group that had this before was that kind of group, and I think that kind of you know may have may have muddy the waters a little bit, but but those days are over, and I mean we're here ready to push this thing forward.

47:14

So I have a question.

47:16

Will this go before the city council?

47:19

Yes, ma'am.

47:20

Well, if it passes fine.

47:23

Yeah, project.

47:24

Yeah, it will go for us again.

47:26

So and Scott, I wanted to know what so what do we need to do from here?

47:30

If I mean, I want to make sure the council is certified by because I want to get some on the table so we can I mean I know we tabled it in definitely, so what do we need to do for sure?

47:40

So and and I'll let Mr.

47:41

Mr.

47:41

Bobbit speak to this because he's been more more hands-on on with this one.

47:46

But what was what was redlined and came back to us was not what was presented and agreed on in here.

47:51

And so that's how we ended up with with the tabling.

47:54

And so depending on, and again, I'll let Mr.

47:56

Bobbitt speak with this.

47:58

If if council wants to move forward, or if the committee wants to move forward with what's been proposed here today, um, I'll let Mr.

48:08

Bobbitt speak to whether or not that is uh different than the terms that have been published in the 772 notice and whether or not we'll have to restart that process.

48:18

So Tom sorry.

48:24

What's been proposed, the two drafts that have come back are different than what the council approved in the 772 notice.

48:31

So yes, we gotta start the process over.

48:34

Well, what was different and what came back if you if you can talk to us a little bit about what what are the sticking points that were different.

48:43

You remember we showed you the red line draft.

48:45

Yeah.

48:46

Okay.

48:46

That was a lot of different things in there.

48:49

The difference this time is that gone from six to three, the agreement is only for three, not six lots now.

48:57

We haven't seen any new financials based upon the three.

49:01

So the thing about it is the two drafts that we have got are not what was approved by the city council.

49:09

Right.

49:10

So yes, we would have to start over that.

49:13

So the difference, Mr.

49:14

Laney, too, it's then uh I actually so now you all are asking for incentives after three.

49:20

And I think initially we were saying you you're asking for incentives after six.

49:25

And and maybe there was there was some confusion there, and it was and and in our presentation, uh, and then like I said, maybe I I was out of town, and then I'm not saying it without John I would have done anything different than John, but well we had always said, you know, we we if if we can't if we can't fill a lot with a new to new to market tenant, we've got to be able to sell that lot to a medical or someone like that, somebody that can come in to pay us to get us whole.

49:52

And we're not gonna get incentives on anybody over three if they're not new to market, and we're only gonna get incentives for the entire project if we bring in three new to market.

50:02

Uh and so that that's that was what we understood, and that I mean that's what we're where where we're trying to get now.

50:10

Now, if that's if that was misinterpreted, that's that's only my apologies.

50:14

And and if that's the agreement, then and we have to start over, then we're gonna have to start over because I can't agree for six new to market tenants, or we get nothing.

50:22

I mean, that's just I I can't, I mean, that's that's a deal killer for us.

50:29

Well, we want to bring six new to market tenants because we're only getting paid if we bring a new to market tenant.

50:34

Uh and Tom, all the financials that were in the first go around, the incentive amount was based on six new to market tenants.

50:42

Okay.

50:45

So I'd like to say something if I can, I'll get through.

50:50

I'll let you speak.

50:51

So I guess my question is, Tom, is when can we get uh Mike back in the ring with Brendan or who whoever the team is to get to refigure the number?

51:04

Yeah, let's get this thing back, you know, let's get it back rolling because I mean I I feel like we need to I don't how do the numbers change in?

51:11

Let me ask you this.

51:12

How do the numbers change?

51:14

If it could just feel not debating back forces to be mindful.

51:18

Mr.

51:19

Lanier, for council standpoint, it will require a full resubmission.

51:22

If the jobs do not meet the requirements on advertising, that's a full resubmission.

51:26

The tenants and categories were listed by sector in the application with the common uh score, excuse me, corresponding sales numbers that will all have to be re-run.

51:34

Materials will have to be redone.

51:36

So the full agreement that is up for vote will have to be resubmitted, redone, and repackaged.

51:41

So it's just starting over or going with what's available today.

51:44

Brandon, I got a question.

51:45

So you said the materials one of the requirements were was he buy all the materials he's building with local.

51:51

I don't think it's all the materials.

51:54

Okay, 50%.

51:55

And typically on that item, council and air, there are exceptions that um if provided by the developer or by the tenant that Mr.

52:03

Bobbett has worked on.

52:04

We've done this in a variety of, you know, tenant X buys their window systems or the roofing systems or XYZ or ABC from this preferred vendor because they do so many different deals with them.

52:15

That we've accommodated that on a handful of it.

52:17

So I see that as achievable.

52:19

Right.

52:19

Okay.

52:20

The job doesn't.

52:21

Okay, for if a national chain says, hey, we buy all our materials from this place.

52:25

Yeah, we've got the deal.

52:27

We we built something similar on Shops at Legacy Park, and you have nothing but national tenants.

52:30

And I want to know so would that be even possible?

52:32

Could you make that happen if 50% mine here is that with is that even possible?

52:37

Oh, with a with a with I mean if we're doing a ground lease, I I mean I don't control the right the construction.

52:43

Now for me, if I'm doing it's mo mostly site work and and clear, yeah, we can we can accommodate that or if we're we're doing a build of suit, we can work around that.

52:54

But I mean it's it makes it you know it's it's not it's not undoable, no.

52:59

I mean, but but I I guess the main thing I want to get at is is like these six points that we've been trying to get to the table to.

53:07

I mean, what what are what how can we you know just nail these down?

53:12

I mean it you know, we we said the new to market, if you're saying I'm I'm not gonna do six new tenants, we've got to rerun the numbers and start over, but I don't I don't really know why the numbers would change because our goal is to get six, but we don't want to lose the whole deal if we get only three.

53:30

I mean, and so that's I guess that that's the numbers would still be the same because our goal would be to get six, but we don't want to spend 20 15 million dollars of our money and ten million dollars of of tenant money or whatnot, and and then not get anything because on a deal that doesn't pencil unless we get the incentives.

53:52

So I I just you know we're just trying to figure out on our end what what we need to do.

53:58

And I'm sounds like you're trying to work at cash song.

54:01

Yeah, I mean I I and Mr.

54:04

Bobbitt can correct me.

54:06

Modifications to what has been tabled at council most of these sound substantial enough for that.

54:13

We'll just have to restart the process.

54:15

Okay.

54:16

I mean, just simply put, is that accurate topic?

54:19

And you can can we not, I mean, I and I know I don't know how long it takes for this on my field of expertise, but I don't want to drag it six months.

54:28

I mean, I'm I'm I'm anxious for something to happen in my district, right?

54:31

And if I'll be if I'll be up front, we would the city's not spending any upfront money, right?

54:39

We're not taking a risk, we don't have to go to the bond for this money or anything, right?

54:44

So it only happens if this big these businesses perform, right?

54:48

So I feel like we need to I I mean I'm willing to take a chance on that.

54:52

I mean, I'm I'm desperate for something to happen in my district, and so if if we could move expeditiously, I'd be really satisfied.

55:01

If there was a resubmission, that's what would have to happen.

55:03

You would actually have to as noted previously, the sector of tenants, and so we can call set out.

55:08

Uh typically we do it with identified tenants, which is easier to do an analysis run.

55:13

That's traditionally how we do it.

55:14

Sure.

55:14

So you've got that column there.

55:16

The alternative column would be if you don't bring six due to markets, where are you plugging in those holes?

55:20

Right?

55:20

Because the medical use, this use, this use, that can affect property tax.

55:24

That could affect obviously if there is no sales tax or their use taxes start changing our performance.

55:28

Yeah.

55:28

For our side.

55:29

Right, right, right.

55:30

So then all of a sudden, what we provided you from a financial standpoint would be inaccurate at this point.

55:35

So we would need to go back for so I mean that's completely up to you.

55:40

You have one today that's the terms as noted that you could vote on, or that could be resubmitted and we can run through the traps like we've done does a times in the last few years.

55:51

Okay.

55:53

So yeah, I just want to.

55:56

I do want to note it is a from a timing standpoint.

56:00

Uh it's I mean you're at minimum with advertising committee structure, review, submission.

56:05

It's not necessarily a super quick process.

56:08

It would just depend on how fast you could submit reviews could get done really quickly.

56:12

I mean we've got our submit all in a box over there.

56:15

We're ready to submit right now.

56:16

I think y'all still have a pending item at council.

56:19

So so what do we what do we need to do brand news for us?

56:22

So the item that was tabled indefinitely will be come back to the council under unfinished business from there.

56:28

That item will need to be officially withdrawn from the table.

56:32

I believe then the city attorney's office and branding's team can start working the what they need to for the 772 hearing.

56:38

Okay, so we can get that on council next.

56:41

Well, that's what that's what I'm that's what I need to do.

56:47

All right.

56:48

Okay, thank you.

56:49

Thank you, Tom, for clearing that up.

56:51

We have it.

56:53

We got two more committees.

56:54

Okay.

56:58

So we got time for that.

57:02

All right.

57:04

Any any more questions about the students?

57:07

Nothing else.

57:08

Uh we need to adjourn here.

57:12

Yeah, we're taking questions.

57:13

Yeah.

57:13

So we're 330-ish now.

57:22

That's fine.

57:22

We just need an adjournment.

57:24

This one you have five or ten minutes for that to be for her.

57:27

Can I get a motion?

57:29

Motion.

57:29

Second.

57:30

All in favor?

57:30

Hi.

Discussion Breakdown — Share of Meeting
Engineering And Infrastructure███████████████████████████████31%
Economic Development█████████████████████████25%
Transportation Safety████████████████████20%
Public Safety██████6%
Community Engagement██████6%
Procedural██████6%
Affordable Housing███3%
Public Engagement██2%
Technology and Innovation1%
Summary of Proceedings

Tuscaloosa City Council Meeting Summary - March 24, 2026

The Tuscaloosa City Council met on March 24, 2026, to consider 13 agenda items and an economic development agreement. All agenda items were approved unanimously, while the economic agreement was tabled pending resubmission due to substantial changes from the original proposal.

Public Comments & Testimony

  • Jeremy Wyatt (owner, Redman Bruce downtown) expressed concerns about the Fourth Street and 23rd Avenue one-way project, arguing it could bottleneck traffic, reduce parking (by about 29%), and create spillover issues, especially on game days. He urged adding parking elsewhere before proceeding.
  • Olaf (owner, Ronald's German Restaurant) echoed concerns about bottlenecking and parking shortages, especially in the evenings. He proposed exploring alternatives such as a pedestrian zone on 22nd Street or a parking deck, and asked for more dynamic, short-term solutions rather than a single rigid plan.
  • Michael Laney (Landing Property Group) presented six key points of disagreement with the city's proposed economic agreement for the Springbrook development, including the number of new-to-market tenants required (three vs. six), the definition of new-to-market, the 25-year payment period trigger, labor and material sourcing requirements, and employee guarantees. He noted the project is performance-based and the developer bears significant risk.

Discussion Items

  1. Buddy Powell Pavilion Change Order (Price Construction) – Approved a $104,000 change order for additional paving and restriping, funded from tourism capital budget ($30,000 underrun + $15,000 budget + request). Motion passed.
  2. Paint Services Across City Campus (Red Oak Paint Company) – Approved a minor public work contract to paint exposed steel columns and handrails at multiple buildings, funded by the CFG five-year facility plan. Motion passed.
  3. Tennis Center Camera Infrastructure (Taylor Electric) – Approved a contract for underground raceway and wiring to support streaming cameras for tennis matches, an NCAA tournament requirement. Cameras already purchased. Motion passed.
  4. Linton Barbershop Project Balancing Change Order (Snow Blaking) – Approved a $12,000 change order for additional sodding and sidewalk replacement along Hackberry Lane. Project originally bid at $647,000, now $660,000 total. Motion passed.
  5. Ceiling Replacements (RWC Construction) – Approved a contract to repair ceilings at Ed Low building and city drive-up parking lot, funded by facility renewal and water/sewer renewal. Motion passed.
  6. Greensboro Avenue Streetscape Project (GFC Construction) – Awarded construction contract for $3,852,862.89 for streetscape improvements between University Boulevard and 7th Street, including wider sidewalks, landscaping, and dedicated delivery zones. Five bids received; construction expected May through September 2026. Motion passed.
  7. Julia Tutweiler/Campus Drive Engineering Amendment (Duncan Coker) – Approved an amendment to transition the design to ATRIP (state route) standards, including right-of-way services and construction oversight. Project involves a new off-ramp from McFarland Boulevard. Motion passed.
  8. Rice Mine Road Slope Repair Design (TTL) – Approved a professional services agreement for $78,142 to design repairs for a slope failure north of the river between Indian Hills Drive and Overlook Road. Study completed; recommendation is riprap stabilization. Motion passed.
  9. Fourth Street & 23rd Avenue One-Way Project Design (Duncan Coker) – Approved a $142,796 contract to design conversion of the corridor to one-way traffic with angled parking, bollards, and pedestrian safety improvements, focusing on the intersection and Timerson Square block. Council members acknowledged public concerns but stressed the need for pedestrian safety after recent incidents. Motion passed.
  10. Skyland Boulevard Fiber Permitting (Porter & Higginsbotham) – Approved a $28,005 survey and permitting contract for IT fiber installation along south Skyland Boulevard from near the BMW dealership to Firehouse No. 9. Motion passed.
  11. 2026 Citywide Resurfacing Project (ST Boss Construction) – Awarded contract at $9.8 million, over budget due to fuel price uncertainty. Additional funding will come from this year's Alabama gas tax funds. Two bids received. Motion passed.
  12. Academy Drive Drainage Project Design (Show Engineering) – Approved a $292,612.50 design contract for flooding mitigation in the Academy Drive subdivision (Stone River Road area), addressing undersized culverts and pipes. Motion passed.
  13. Interim Flight Procedures for Airport Runway Extension (Hughes Airspace) – Approved a 495-day contract for $140,000 (with option for full-length procedure) to implement temporary flight procedures during the runway displacement project, avoiding disruption to fall athletic charters. Funded from construction savings. Motion passed.

Economic Development Agreement – Springbrook Project

  • Michael Laney (Landing Property Group) presented concerns about the city's proposed agreement, which required six new-to-market tenants for full incentives. The developer proposed a structure with three new-to-market tenants as the trigger, with no incentives for non-new-to-market tenants on the remaining three parcels. Other sticking points included labor/material sourcing and employee guarantees. Staff noted that the revised terms differed materially from the original 772 notice, requiring a full resubmission. Council members expressed interest in moving forward quickly to bring development to District 7. No vote was taken; the item remains tabled indefinitely and will need to be withdrawn and resubmitted.

Key Outcomes

  • All 13 agenda items (resolutions) were approved unanimously.
  • The Springbrook economic development agreement will be withdrawn from the table and resubmitted with revised terms, requiring a new 772 hearing and staff analysis.

Meeting Transcript

Number one with price construction company for approval of Buddy Power Pavilion. Tim. Yes, sir. Good afternoon. Good afternoon. So this is to balance the project with the Northridge pickleball price construction. What we're asking to do is add additional funding into this contract so that we can do some additional paving at Buddy Powell Pavilion and re-stripe that parking lot. You want to fresh a refresh us the amounts, Tim. We went over them last week. So the change order amount from price construction is 150,000. We have $30,000 of underrun within the contract currently, and we still have $15,000 within the original budget. So we're looking for right at $104,000 to execute this change order. On the screen, you'll see the design. We've got the existing asphalt on the right hand side of the screen is to have a new seal coat and restriping. And then on the left hand side you'll see the new asphalt around the perimeter with also with new striping. There's signage included and a few bollards included as well. All right. And that uh the differentials coming out of the tourism capital budget, Check. Correct. And Miss Standage, how much does that leave in there? Um it will leave ballpark 400,000. I'm good. Most second. All in favor. Hi. Motion passed. Thanks, Tim. Agenda item number two, approval minor public work contract with Red Oak Paint Company for paint service across city campus. Yes, sir. So this is to paint all the exterior exposed steel columns between this building and annex three. Uh what holds up the sky bridges between uh Annex one and three, also going towards the parking deck. It'll also paint all the exposed columns and steel at government plaza, the pavilion clock tower out there as well as the handrails. And it's coming out of building that this is CFG's five-year facility plan. Second, all in favor. Aye, motion passed. Agenda item number three, approval of minor publishing work contract, but Taylor Electrical Contractors for installational cabling and uh camera system. I tell those tennis. Yes, sir. So this is for the infrastructure for the camera system that is for streaming tennis matches at the tennis center. Um this includes all the underground raceway that has to be installed, raceway that will go to each individual court, both existing and new courts at the tennis center. So this is the just the infrastructure, not the actual cameras. Correct. Uh has purchased the yeah, cameras have already been purchased. Yeah, and I've got something of a lesson on this during the week. Okay. To feel better. Why was it mispositioned for the game with to be completely frank, Mr. Busby? We had no knowledge of this desire during design uh or where these cameras would be placed. We in design put raceway all over the property for future camera installations.

SUMMARIZED BY OPENPUBLICA AI
TRANSCRIPT VIA PUBLIC VIDEO
openpublica.com