CAPITAL IMPROVEMENTS ELEMENT

Introduction

Probably one of the most significant and far reaching provisions of the Local Government Comprehensive Planning and Land Development Regulation Act is the requirement that all local comprehensive plans contain a capital improvements element (CIE). The intent is to ensure that a community or governmental jurisdiction identify the public infrastructure and other facilities which projected growth requires, at given levels of service. Not only must new growth be considered, but efforts must be directed at correcting existing deficiencies.

Recognizing that there are major shortcomings in public facilities and services throughout the State of Florida, the new planning legislation adopted what is known as the "concurrency" principle. That is, as growth occurs, the facilities must be provided, thus assuring that the infrastructure situation will not deteriorate further. For those local governments having capital improvements programs, the capital improvements element will likely be more narrow in scope, since the functional areas covered are selective. Only the following items are concurrency public facility and services:

  • Transportation facilities
  • Sewerage
  • Water
  • Drainage/aquifer recharge
  • Solid waste disposal
  • Recreation/open space
  • Coastal management
  • Conservation
  • Educational/public school facilities

Notable for their absence are police, fire, health and criminal justice facilities, although infrastructure needs of health facilities are supposed to be considered.

The CIE should give attention to the total fiscal capability of the local governmental body to which it is applicable. This includes analysis of public expenditures, revenues, taxes and other funding sources, financial management, and capital programming and budgeting. Goals, objectives and policies related to these areas must be spelled out.

Since Miami-Dade County has a large and sophisticated Capital Budget and Multi-Year Capital Plan, it is not necessary for the CIE to contain detailed financial analysis. The capital improvements contained in the CIE are a subset of the County’s Capital Plan and the financial analysis contained therein is incorporated by reference in the CIE. Capital improvements associated with the construction of primary state highways, the turnpike and expressways are not addressed in the County’s Capital Budget and Multi-Year Capital Plan but rather are the responsibility of the Florida Department of Transportation and the Miami-Dade Expressway Authority. To address the financial feasibility of non-county roadways that are needed to meet LOS requirements, the most recent adopted Transportation Improvement Program for Fiscal Years 2013/2014 to 2019/2020 (TIP) of the Metropolitan Planning Organization for the Miami Urbanized Area (MPO), specifically the sections on Primary State Highways, Turnpike Enterprise and Miami-Dade Expressway Authority, are incorporated by reference into the CIE. Capital improvements associated with the construction of educational facilities are not addressed in the

County’s Capital Budget and Multi-Year Capital Plan but rather are the responsibility of the Miami-Dade County Public Schools. To address financial feasibility associated with school concurrency, the Miami-Dade County Public School Facilities Work Program for educational facilities is incorporated by reference into the CIE.

The Adopted Components of the CIE include the goal, objectives and policies, the level of service (LOS) standards, and the 6-Year Schedule of Improvements. Also, the requirements and suggestions for monitoring and evaluation are discussed.

GOAL

MIAMI-DADE COUNTY SHALL PLAN FOR AND MANAGE IN A FISCALLY PRUDENT MANNER, ITS FACILITIES AND INFRASTRUCTURE IN ORDER TO ADEQUATELY SERVE CURRENT AND NEW RESIDENTS WHILE EFFICIENTLY USING AND MAINTAINING EXISTING PUBLIC INVESTMENTS, AND MAKING TIMELY PROVISION OF REQUIRED NEW CAPITAL INVESTMENT.

Objective CIE-1

The CIE shall provide for necessary replacement of existing facilities, upgrading of facilities when necessary to maintain adopted level of service (LOS) standards, and for new facility investments which are needed and affordable in the future.

Policies

CIE-1A. Only capital expenditures, which address capacity or quality of life needs identified in the Comprehensive Development Master Plan (CDMP) and in excess of $50,000, are included in the Six-Year Schedule of Improvements of this Element.

CIE-1B. The Six-Year Schedule of Improvements shall contain a mix of capital expenditures which includes at least one-third allocated to upgrading and replacement and the remainder to new facilities which meet existing deficiencies or serve future needs.

CIE-1C. The County will continue to adopt an annual capital budget which contains the projects from the Six-Year Schedule of Improvements for the corresponding year.

CIE-1D. Miami-Dade County will manage its long-term general obligation debt in such a manner that the ratio of the debt service millage to the Countywide millage does not exceed 20 percent and the ratio of the outstanding capital indebtedness to the taxable property base does not exceed 2.5 percent.

CIE-1E. In planning for and implementing its infrastructure investments, Miami-Dade County will give explicit recognition to the requirements of new or expanded public educational and health facilities.

CIE-1F. County departments that have responsibilities for providing concurrency related capital improvements should continually seek to expand the funding sources which may be available to meet those requirements.

CIE-1G. The Miami-Dade County Public Schools and Miami-Dade County have the responsibility for providing school concurrency related capital improvements and

should continually seek to expand the funding sources available to meet those requirements.

CIE-1H. The Miami-Dade County Public Schools Facilities Work Program will be evaluated on an annual basis to ensure that the level of service standards will continue to be achieved and maintained throughout the planning period.

Objective CIE-2

Public infrastructure expenditures should be limited within the Coastal High Hazard Area.

Policies

CIE-2A. Public funds will not be used to subsidize increased overall density or intensity of urban development in coastal high hazard areas. However, public beach, shoreline access, resource restoration, port facilities or similar water-dependent projects may be constructed.

CIE-2B. Replacement or extension of infrastructure in coastal high hazard areas will be at or below existing service capacity except where such replacement or extension will improve hurricane evacuation time, mitigate storm damage, address an environmental hazard, or meet regulatory requirements.

CIE-2C. The Coastal High Hazard Area (CHHA) is defined as areas seaward of the elevation of the category 11 storm surge line, as established by a Sea, Lake and Overland Surges from Hurricanes (SLOSH) computerized storm surge model, as depicted on Figure 13 of the Land Use Element.

Objective CIE-3

CDMP land use decisions will be made in the context of available fiscal resources such that scheduling and providing capital facilities for new development will not degrade adopted service levels.

Policies

CIE-3A. The capital facilities and infrastructure implications of land use and development plans and implementation will be analyzed and set forth with attention to the following:

  1. Safety improvements and elimination of hazard.
  2. Providing the necessary capacity to maintain and/or improve levels of service and quality of life in areas designated for redevelopment, infill development, and/or higher residential densities in accordance with transit oriented development plans, smart growth initiatives, and other strategies to accommodate population growth in existing communities,
  3. Elimination of below-standard conditions and capacity deficits,
  4. Demonstrated linkage between projected growth and facility service area,
  5. Financial feasibility, including operating costs,
  6. Coordination with the capital programming of other public agencies,
  7. Contractual and/or mandated obligations.

Footnotes

  1. 1

CIE-3B. Service and facility impacts of new development must be identified and quantified so that sufficient public facilities will be planned and programmed to be available when needed. All development orders authorizing new, or significant expansion of existing urban land uses, shall be contingent upon the provision of services at levels which meet or exceed the adopted LOS standards except as otherwise provided in the "Concurrency Management Program" section of the CIE.

CIE-3C. The 6-Year Schedule of Improvements will incorporate the identified capital investments from each functional element and will be based on the following level of service standards:

Potable Water Supply

  1. The regional treatment system shall operate with a rated maximum daily capacity no less than 2 percent above the maximum day flow for the preceding year, and an average daily capacity 2 percent above the average daily per capita system demand for the preceding 5 years. The maximum daily flow shall be determined by calculating the average of the highest five single day flows for the previous 12 months.

  2. Water shall be delivered to users at a pressure no less than 20 pounds per square inch (psi) and no greater than 100 psi. Unless otherwise approved by the Miami-Dade Fire Rescue Department, minimum fire flow, based on the land use served, shall be maintained as follows:

Land UseMinimum Fire Flow Gallons per Minute
Single Family Residential Estate Density500
Single Family and Duplex Residential on Minimum lots of 7,500 sq. ft.750
Multi-family Residential, Semiprofessional Offices1,500
Hospitals, Schools2,000
Business and Industry3,000
  1. Water quality shall meet all federal, State, and County primary standards for potable water.

  2. Countywide storage capacity for finished water shall equal no less than 15 percent of the Countywide average daily demand.

Sanitary Sewer

  1. Regional wastewater treatment plants shall operate with physical capacity no less than the annual average daily sewage flow.

  2. Effluent discharged from wastewater treatment plants shall meet all federal, State, and County standards.

  1. The system shall collectively maintain the capacity to collect and dispose of 102 percent of the average daily sewage system demand for the preceding five years.

Solid Waste

The County Solid Waste Management System, which includes County-owned solid waste disposal facilities and those operated under contract with the County for disposal, shall, for a minimum of five (5) years, collectively maintain a solid waste disposal capacity sufficient to accommodate waste flows committed to the System through long-term interlocal agreements or contracts with municipalities and private waste haulers, and anticipated non-committed waste flows.

Traffic Circulation

The minimum acceptable peak period1 operating level of service (LOS)2 for all State and County roads in Miami-Dade County outside of the Urban Development Boundary (UDB) identified in the Land Use Element shall be LOS C. The minimum acceptable peak-period LOS for all State and County roads inside the UDB shall be the following:

  1. Within the Urban Infill Area (UIA)3 (a) Where no public mass transit service exists, roadways shall operate at or above LOS E; (b) Where mass transit service having headways of 20 minutes or less is provided within 1/2 mile distance, roadways shall operate at no greater than 120 percent of their capacity; (c) Where extraordinary transit service such as rapid transit (e.g., commuter rail, Metrorail and People Mover, or premium bus systems) exists, parallel roadways within 1/2 mile shall operate at no greater than 150 percent of their capacity.

  2. Between the UIA and the UDB (a) Roadways shall operate at no worse than LOS D (90 percent of their capacity) except that State urban minor arterials (SUMAs) may operate at LOS E (100 percent of their capacity); (b) Where public mass transit service exists having headways of 20 minutes or less within 1/2 mile distance, roadways shall operate at or above LOS E; (c) Where extraordinary transit service such as rapid transit (e.g., commuter rail, Metrorail and People Mover, or premium bus systems) exists, parallel roadways within 1/2 mile shall operate at no greater than 120 percent of roadway capacity.

Footnotes

  1. Peak period means the average of the two highest consecutive hours of traffic volume during a weekday.

  2. NOTE: LOS will be measured based on the latest edition of the Highway Capacity Manual.

  3. UIA is defined as that part of Miami-Dade County located east of, and including, SR 826 (Palmetto) Expressway and NW/SW 77 Avenue, excluding the area north of SR 826 and west of I-95.

  1. Notwithstanding the foregoing, the following standards are adopted by Miami-Dade County as its minimum LOS Standards for Florida Strategic Intermodal System (SIS) highway corridors in Miami-Dade County:

    (a) Outside the UDB

     (1) Limited access State Highways shall operate at LOS C or better;
    
     (2) Controlled access state highways shall operate at LOS C or better; and
    
     (3) Constrained[^p6-4] or backlogged[^p6-5] limited and controlled access State highways operating below LOS C, must be managed to not cause significant degradation.[^p6-6]
    

    (b) Inside the UDB

     (1) Limited access State highways shall operate at LOS D or better, except where exclusive through lanes exist roadways may operate at LOS E.
    
     (2) Controlled access highways shall operate at LOS D or better, except where such roadways are parallel to exclusive transit facilities or are located inside designated transportation concurrency management areas (TCMA's), roadways may operate at LOS E.
    
     (3) Constrained or backlogged limited and controlled access State Highways operating below the foregoing referenced minimum LOS standards must be managed to not cause significant deterioration.
    

Mass Transit

The minimum peak-hour mass transit level of service shall be that all areas within the Urban Development Boundary of the Land Use Plan (LUP) map which have a combined resident and work force population of more than 10,000 persons per square mile shall be provided with public transit service having 30-minute headways and an average route spacing of one mile provided that:

  1. The average combined population and employment density along the corridor between the existing transit network and the area of expansion exceeds 4,000 per square mile. The corridor is 0.5 miles on either side of any necessary new routes or route extensions to the area of expansion;

  2. It is estimated that there is sufficient demand to warrant service;

  3. The service is economically feasible; and

  1. The expansion of transit service into new areas is not provided at a detriment to existing or planned services in higher density areas with greater need.

Park and Recreation

Miami-Dade County's minimum level of service standard for the provision of recreational open space shall be the following: i.) 2.75 acres of local recreation space per 1,000 permanent residents in unincorporated areas; ii.) A County-provided, or an annexed or incorporated, local recreation open space of 5 acres or larger must exist within a 3-mile distance from the residential development; iii.) The acreage/population measure of the Level of Service Standard will be calculated for each Park Benefit District (PBD); iv.) For purposes of issuing residential development orders, the minimum LOS standard does not apply to rural and agricultural residences outside the Urban Development Boundary (UDB); and; v.) For purposes of issuing development orders, a PBD is considered below standard if the projected deficiency is greater than five acres. This does not relieve applicants for development orders of applicable requirements for contributions of impact fees.

Drainage

The Stormwater Management (Drainage) Level of Service (LOS) Standards for Miami-Dade County contains both a Flood Protection (FPLOS) and Water Quality (WQLOS) component. The minimum acceptable Flood Protection Level of Service (FPLOS) standards for Miami-Dade County shall be protection from the degree of flooding that would result for a duration of one day from a ten-year storm, with exceptions in previously developed canal basins as provided below, where additional development to this base standard would pose a risk to existing development. All structures shall be constructed at, or above, the minimum floor elevation specified in the federal Flood Insurance Rate Maps for Miami-Dade County, or as specified in chapter 11-C of the Miami-Dade County Code, whichever is higher.

  1. Basin-specific FPLOS standards shall be established through the adoption of a Stormwater Master Plan to be approved by the Miami-Dade County Board of County Commissions and the South Florida Water Management District. Until the approval of basin-specific FPLOS standards through this coordinated process, the following additional exceptions shall apply:

    a) Wherever Miami-Dade County has adopted cut and fill criteria pursuant to Chapter 24-58.3(F) of the County Code (November 30, 2004) including fill encroachment limitations necessary to prevent unsafe flood stages in special drainage basins, the minimum applicable FPLOS standard shall be the degree of protection provided by the applicable cut and fill criteria;

    b) Where cut and fill criteria have not been established north of S.W. 152 Street inside the Urban Development Boundary (UDB), the minimum acceptable FPLOS standard shall be protection from the degree of flooding that would result for a duration of one day from a ten-year storm;

    c) Exceptions may be granted on a case-by-case basis east of Levee-31 N, where physical characteristics of sites do not allow the ten-year one-day floodwater to be retained on site; and

d) West of Levee-31 N, there shall be no off-site drainage, all septic tank drainfields shall be elevated above the hundred-year flood elevation, and the extent of land filling shall be minimized as provided in applicable provisions of the Miami-Dade County East Everglades Zoning Overlay Ordinance. The County shall review these criteria when the water management facilities programmed in the N.E. Shark River Slough General Design Memorandum and the C-111 General Reconnaissance Review are fully operational.

  1. The Stormwater Management Water Quality Level of Service (WQLOS) component of the standard shall be met when the annual geometric mean for each of the following twelve priority NPDES pollutants does not exceed the following target criteria for each of those pollutants within a canal basin, or sub-basin, as determined in accordance with procedures established by Miami-Dade County DERM:
PollutantTarget Criterion
Biological Oxygen Demand (BOD)9 mg/l
Chemical Oxygen Demand (COD)65 mg/l
Total Suspended Solids (TSS)40 mg/l
Total Dissolved Solids (TDS)1,000 mg/l
Total Kjeldahl Nitrogen (Ammonia- Nitrogen and Organic Nitrogen)1.5 mg/l
Total Nitrate (NOx-N)0.68 mg/l
Total Phosphate (TPO₄)0.33 mg/l
Dissolved Phosphate (OPO₄)Not Available
Cadmium (Cd)0.0023 mg/l
Copper (Cu)0.0258 mg/l
Lead (Pb)0.0102 mg/l
Zinc (Zn)0.231 mg/l
  1. Applicants seeking development orders in canal basins, or sub-basins, that do not meet either the FPLOS or the WQLOS shall be required to conform to Best Management Practices (BMPs) as provided by Miami-Dade County Code. Owners of commercial or industrial properties where BMPs are required, shall, at a minimum, demonstrate that their on-site stormwater system is inspected two times per year and maintained and cleaned as required. Private residential developments in areas where BMPs are required shall demonstrate that their on-site stormwater systems are inspected two times per year and maintained and cleaned as required.

Public Schools

The County shall coordinate new residential development with the future availability of public school facilities1 consistent with the adopted level of service standards for public school concurrency, to ensure the inclusion of those projects necessary to address existing deficiencies in the 5-year schedule of capital improvements, and


Footnotes

  1. Level of Service standards for public school facilities apply to those traditional educational facilities, owned and operated by the Miami-Dade County Public Schools, that are required to serve the residential development within their established Concurrency Service Area. Levels of Service standards do not apply to charter schools. However the actual enrollment (October Full Time Equivalent (FTE)) of both charter and magnet schools as a percentage of the total district enrollment will be credited against the impact of development.

meet future needs based upon achieving and maintaining the adopted level of service standards throughout the planning period.

The adopted level of service (LOS) standard for all Miami-Dade County public school facilities is 100% utilization of Florida Inventory of School Houses (FISH) Capacity (With Relocatable Classrooms). This LOS standard, except for Magnet Schools, shall be applicable in each public school concurrency service area (CSA), defined as the public school attendance boundary established by the Miami-Dade County Public Schools.

The adopted LOS standard for Magnet Schools is 100% of FISH (With Relocatable Classrooms), which shall be calculated on a districtwide basis.

Objective CIE-4

Planning for further development will be done such that the level of service standards for those services listed in the CIE will be upgraded and maintained at adopted levels by vigorously pursuing adequate fiscal resources.

Policies

CIE-4A. Appropriate funding mechanisms will be adopted and applied by Miami-Dade County and the Miami-Dade County Public Schools in order to assure the fiscal resources to maintain acceptable levels of service. Such funding mechanisms may include special taxing districts, municipal taxing service units, local option taxes, user fees, local gas tax, general obligation bonds, impact fees, special purpose authorities, and others as appropriate and feasible.

CIE-4B. Particular attention will be given to the timely and full assessment of increased land and other property values resulting from public infrastructure investment, particularly where such land lies within the Urban Infill Area.

CIE-4C. Highway and transit planning activities of the County and the Metropolitan Planning Organization (MPO) of Miami-Dade County will give highest priority to the funding of necessary capacity improvements to roadways and transit services that would help to relieve congestion on Strategic Intermodal System (SIS) facilities as defined in Section 339.61, F.S., which are operating below their CDMP-adopted LOS standard.

CIE-4D. Where opportunities exist, consideration should be given to the application of unit charges for the use of public facilities especially what is known as "peak load pricing."

Objective CIE-5

Development approvals will strictly adhere to all adopted growth management and land development regulations and will include specific reference to the means by which public facilities and infrastructure will be provided.

Policies

CIE-5A. It is intended that previously approved development be properly served prior to new development approvals under the provisions of this Plan. First priority will be to serve the area within the Urban Infill Area and Transportation Concurrency Exception Areas. Second priority shall be given to serve the area between the Urban Infill Area and the Urban Development Boundary. And third priority for investments for services and facilities shall support the staged development of the Urban Expansion Area (UEA). Urban services and facilities which support or encourage urban development in Agriculture and Open Land areas shall be avoided, except for those improvements necessary to protect public health and safety and which service highly localized needs. Areas designated Environmental Protection shall be particularly avoided.

CIE-5B. Provision of infrastructure subject to LOS standards will be done through a process which integrates the CDMP, departmental and Miami-Dade County Public Schools functional plans, capital improvements programming, budgeting and financial planning.

CIE-5C. It is the policy of Miami-Dade County that the distribution of potable water from the proposed reverse osmosis water treatment plant located in proximity to the area encompassing Application No. 5 in the April 2005-2006 CDMP Cycle [area bounded by NW 154 Street on the south, NW 97 Avenue on the east, and the Homestead Extension of the Florida Turnpike (HEFT) on the northwest], using the Floridan Aquifer as its source, shall be dedicated first to satisfying the total potable water demand from development of the site of Application No. 5. In no event shall a Certificate of Occupancy (CO) for development in the area encompassed by Application No. 5 be issued until it is served by the proposed reverse osmosis water treatment plant or by another water supply source authorized under the County's Consumptive Use Permit from the South Florida Water Management District or as otherwise agreed upon with the District and incorporated into the County’s CIE Schedules of Improvements.

CIE-5D. Appropriate mechanisms will be developed by Miami-Dade County in order to assure that adequate water supplies are available to all water users of the Miami-Dade County Water and Sewer Department. Furthermore, the Miami-Dade Water and Sewer Department shall be responsible for monitoring the availability of water supplies for all water users of the Miami-Dade County Water and Sewer Department and for implementing a system that links water supplies to the permitting of new development.

Programs to Implement

Existing Programs

The following text, which is adopted as County policy, describes a number of existing programs and mechanisms regarding the provision of public facilities, the fiscal planning process, and the concurrency management program. Miami-Dade County has a number of programs and mechanisms in place which are effective in furthering the goals and objectives of the CIE. These are:

Comprehensive Development Master Plan. The goals, objectives and policies of the CDMP are collectively aimed at encouraging the provision of public facilities of sufficient quality and quantity to meet existing needs and future expansion. In addition, the Urban Development Boundary and the Population Distribution Map have major influence on the timing and location of public facilities and services.

Departmental Plans and Levels of Service. The County Departments having responsibility for the functional areas considered in this CIE usually have some type of formalized plan which they follow. However, the degree of formality, the scope of the plan, its time horizon and many other details vary among the operating agencies. Even so, the current practices ensure that the public facilities situation doesn't deteriorate to a state of dire inadequacy although in some cases bare minimums are being provided. CDMP policies affecting infrastructure provision must be adhered to and the population projections contained therein are to be utilized in capital planning.

Development Impact Committee. The Development Impact Committee (DIC) as mandated by ordinance shall: "Review all developments of County impact and prepare impact statements and recommend, where applicable, whether, and the extent to which:

  1. The development, as proposed, will efficiently use or unduly burden water, sewer, solid waste disposal, education, recreation, or other necessary public facilities which have been constructed or planned and budgeted for construction in the area.

  2. The development as proposed, will efficiently use or unduly burden or affect public transportation facilities including mass transit, public streets, roads and highways which have been planned and budgeted for construction in the area, and if the development is or will be accessible by private or public roads, streets or highways."

Thus, the DIC, at least for projects, which meet the required thresholds, is attempting to insure that adequate public infrastructure and services are available, or will be provided, before recommending development approval. Frequently, land dedications, cash contribution, or both are accepted from developers who are desirous of a favorable recommendation.

Capital Improvements Program. Since FY 1989/90, Miami-Dade County has produced an annual capital budget. FY 1989/90 is the first year of a six-year capital plan. The capital budget is adopted by the Board of County Commissioners each year along with the annual operating budget. Prior to that time, the County's Six-Year Capital Improvements Program was an informational document for the most part. Although the first year served as a guide to capital programming, it was not adopted as a capital budget. The information provided was useful in determining capital program priorities for the next fiscal year, potential future year priorities, and subsequent funding commitments necessary to begin, continue, or complete related projects.

However, since the document was not formally adopted as part of the budgetary process, it was unreliable as an indicator of what really was occurring in capital investment. Frequent changes were routine and a department’s actual capital program might have had little resemblance to what was shown in the program.

In contrast, the current Multi-Year Capital Plan (MYCP) is prepared pursuant to Chapter 163 F.S. and the Miami-Dade County Code. It is a true capital budget and program. It is systematically and carefully prepared by the Office of Management and Budget from information submitted by the operating departments as part of the formal budget process. The technical quality and reliability of the document are high and have improved each year.

The MYCP outlines expenditures and revenue schedules for current and new capital projects necessary to maintain, improve and expand public facilities and infrastructure to meet service needs of residents and visitors to Miami-Dade County. Capital reserves, debt service payments and capital purchases found in the operating budget (including mobile equipment, light and heavy equipment, computer hardware and electronic equipment) are not included in this MYCP.

The MYCP is divided into nine program areas: Policy Formulation, Public Safety, Transportation, Recreation and Culture, Neighborhood and Incorporated Area Municipal Services, Health and Human Services, Economic Development, and two groups of enabling strategies: Budget and Finance, and Government Operations. The specific information needed to prepare the CIE is a subset of this more inclusive information base and relevant details are extracted and incorporated into the CIE. This assures close correspondence between the CIE and the MYCP.

The CIE concentrates on projects which are capacity enhancing or help to fulfill some stated policy from one of the CDMP’s functional elements. The MYCP is more inclusive and lists major capital expenditures irrespective of their relationship to capacity.

Subdivision and Other Regulations. The Miami-Dade County Code imposes certain developmental requirements before land is platted. These relate to the provision of water and sewer facilities, local streets, sidewalks, drainage, and open space. Before use permits or certificates of occupancy can be issued Section 33-275 of the Miami-Dade County Code requires that adequate water, sewage and waste disposal facilities be provided.

Shoreline Review. The Shoreline Development Review Ordinance was adopted in 1985 and prescribes minimum standards for setbacks, visual corridors and, with its accompanying resolutions, sets out a flexible review process through which architectural interest, building orientation, landscaping, shoreline use compatibility, access, and other design related elements can be negotiated with the developers and enforced by the local governing jurisdiction.

Area Plan Report

Since 1998, Area Plan Reports have emerged as a preferred planning technique for community visioning and helping to find answers to fundamental planning questions. Included is the identification of local capital improvements and suggestions as to how they could be provided.

An Area Plan Report is a practical planning technique, which blends public participation, detailed planning, and the development of implementation tools. Its principal focus is the creation of planning products (instead of processes), hence its popularity as a tool for physical planning. Public participation is indispensable for a successful Area Plan Report. The overriding objective

is the creation of a detailed plan, which resolves areas of concern identified in the Area Plan Report study area; often these concerns involve capital improvements such as roads, sewers, sidewalks, parks and other community improvements. The Planning and Zoning Divisions of the Department of Regulatory and Economic Resources (DRER) implements the Area Plan Report process as a collective planning effort that develops a small area plan which incorporates the priorities of a community.

Beyond these existing procedures and processes, the CIE is obviously a key component in growth management and development planning. It provides the broad basis for meeting the public facilities needs of the existing and projected population of the area. However, unless it is being implemented, the CIE would quickly lose its effectiveness.

The central requirement for adequate implementation is close coordination among several agencies and departments in the County government. The following are involved: the Office of Management and Budget, Planning and Zoning Divisions of DRER, Finance Department, and operating departments. It is likely that the Capital Improvements Division of the Internal Services Department will become involved as time goes on. This office is charged with the implementation of projects contained in the $2.9 Billion General Obligation Bond Program.

The purpose is to achieve the following:

  1. The overall financial management of Miami-Dade County and comprehensive planning should be closely coordinated.
  2. Both capital and operating costs and existing and potential revenue sources need to be considered for both intermediate and long run.
  3. Planning guidelines and key indicators (such as population projections) must be utilized by operational agencies which in turn provide relevant input to the preparation of the CIE.
  4. Close agreement must be obtained from all participants in the development process concerning service standards and how their attainment is to be measured.

To a large extent, the existing process and procedures achieve these ends. However, demonstrated need exists for even more complete interconnection between the CDMP and the operating and capital budgets of the key County departments.

Concurrency Management Program

An essential requirement of the State's local government comprehensive planning law has been termed the service "concurrency" requirement. Paraphrasing Section 163.3202, Florida Statutes (F.S.), each county and municipality must amend its development regulations to incorporate specific and detailed provisions which shall provide that public facilities and services meet or exceed the LOS standards established in the Plan's Capital Improvements Element and are available when needed for the development, or that the development orders or permits are conditioned on the availability of these public facilities and services necessary to serve the proposed development. The term "development order" is defined in Chapter 163.3164, F.S., to include any zoning action, subdivision approval, certification, permit, or any other official action of local government having the effect of permitting the development of land. Miami-Dade County agencies and boards typically issue many different types of such development orders. These include zoning district boundary changes, variances, unusual use, and site plan approvals; environmental permits and certifications; tentative and final subdivision plat approvals; building

permits, and certificates of use and occupancy (COs). At progressive stages in the development planning and approval process, concurrency determinations can be made with greater certainty.

In order to effectuate the service concurrency requirements contemplated by Chapter 163, F.S, Miami-Dade County enacted, by ordinance, a concurrency management program which accomplishes the statutory requirements. Administration of the required program necessarily involves the establishment of methods and capabilities to monitor outstanding development commitments and the service demands posed by those commitments, plus the existing, programmed and projected capacities of all pertinent urban service facilities or systems.

In its concurrency management program, Miami-Dade County makes appropriate concurrency determinations in conjunction with the following development approval activities: 1) at the time of zoning actions, site plan approvals and subdivision approvals; 2) prior to the issuance of building permits; and 3) prior to the issuance of certificates of use and occupancy. Consideration will be given to effective measures which may be employed to mitigate traditional service impacts of developments. In general, no zoning action authorizing a new use or the expansion of an existing use and no subdivision plat or site plan shall be approved unless the facilities necessary to maintain level of service standards exist or are projected to exist when necessary to serve the development. Except [for] public schools facilities, zoning approvals shall be based on inclusion of necessary facilities in the applicable service Element of the Comprehensive Development Master Plan, in the adopted Capital Improvements Element of the CDMP, or in the plan or work program of the State agency having functional responsibility for provision of the facilities. Such findings shall be included in staff recommendations to the Board of County Commissioners, Community Zoning Appeals Board (CZAB), or other applicable board or agency. If the foregoing plans and programs indicate a low probability that concurrency will be met, but the necessary facilities are technically feasible, such rezoning action should be preceded by a CDMP amendment to add the necessary facilities. Alternatively, such zoning may be approved if the applicant executes a written agreement to provide the necessary facilities on a timely basis. Consistent with Education Element Policy EDU-1F and the provisions in the Interlocal Agreement for Public School Facility Planning between Miami-Dade County and Miami-Dade County Public Schools, a Schools Planning Level Review will be conducted for zoning actions containing residential units, but such reviews will not constitute a public school concurrency review. As described below, a principal concurrency determination for adequate public school facilities will be made prior to consideration of intermediate development order, including final subdivision plats or site plan approval, or the functional equivalent. All such development approvals prior to the "Principal Concurrency Determination" will contain a notice reserving the right of the County to make its principal concurrency determination prior to issuance of building permits.

An affirmative principal concurrency determination will be required before a prospective developer can obtain a subsequent development order. It is intended that at least one principal determination be made at an early stage in the development planning process prior to the point at which major expenses are incurred in reliance on development approval. Principal concurrency determinations will be made prior to the approval of subdivision plats or, in instances where plat approvals are not required or have predated the effective date of the concurrency requirement, a principal concurrency determination will be made at the building permit stage. A principal concurrency determination made at final plat approval will serve as the determination for requested building permits where said permits are issued within two years after the date of final plat approval. Where the applicant demonstrates that development has commenced on a timely basis and is continuing in good faith, this period may be extended but in no case shall this period exceed five years after final plat approval. Administrative procedures for demonstrating that development has

commenced on a timely basis and is continuing in good faith shall be established in the County's land development regulations.

  1. Except as provided in paragraphs 3, 4, 5, 6 and 7 below, in no instance shall a building permit be issued authorizing construction of a new building or expansion of an existing building unless the facilities necessary to maintain LOS standards are existing and available or are assured to be existing and available within the following timeframes relative to the date of issuance of a certificate of use and occupancy (CO):

    a) Necessary water, sewer, solid waste and drainage facilities must be in place and available at the time of issuance of a CO;

    b) Necessary parkland must be acquired or dedicated, or funds in the developer's fair share must be committed prior to the issuance of a CO if the development is located within the Urban Development Boundary (UDB)1; and

    c) Necessary transportation facilities must be contracted for construction no later than 36 months after issuance of a CO if the development is located within the UDB, and no later than the date of issuance of a CO if the development is located outside the UDB.

    d) Necessary public school facilities must be in place or under actual construction within three years after issuance of final subdivision or site plan approval, or the functional equivalent.

  2. Assurance that the facilities2 will be constructed or acquired and available within the timeframes established in foregoing paragraph 1b), 1c) and 1d) shall be provided by the following means:

    a) The necessary facilities are under construction at the time the building permit is issued;

    b) The necessary facilities and services are the subject of a binding executed contract for the construction of the facilities or the provision of services at the time the building permit is issued;

    c) The necessary facilities are funded and programmed in year one of the County's adopted capital budget or are programmed in the CIE for construction or acquisition; the necessary facilities shall not be deferred or deleted from the CIE work program or adopted one-year capital budget unless the dependent building permit expires or is rescinded prior to the issuance of a certificate of use and occupancy; the County and Miami-Dade County Public Schools will diligently strive to enter into construction contracts for necessary facilities within said time but shall retain the right to reject unsatisfactory bids; contracts shall provide that construction of the necessary facilities must proceed to completion with no unreasonable delay or interruption;

    d) The necessary facilities are programmed, in the five-year capital facility plan or work program of the Miami-Dade County Public Schools or State agency having operational responsibility for affected facilities, for construction or acquisition;

    e) The necessary facilities and services are guaranteed, in an enforceable development agreement, to be provided by the developer. An enforceable development agreement may include, but is not limited to, development agreements pursuant to Sections 163.3220-3243, Florida Statutes or an agreement or development order issued pursuant to Chapter 380, Florida Statutes; or

Footnotes

  1. The Urban Development Boundary is depicted on the Land Use Plan Map.

  2. The term facilities shall mean or shall include land, and the phrase construction of facilities shall mean acquisition of land, when applicable to a CDMP LOS standard.

f) Timely provision of the necessary facilities will be guaranteed by some other means or instrument providing substantially equivalent assurances.

g) In all instances where required park land is not dedicated or acquired prior to issuance of a CO, funds in the amount of the developer's fair share shall be committed prior to the issuance of a CO unless the developer has entered into a binding agreement to dedicate an improved park site within the time frame established in foregoing paragraph 1b). Where solid waste disposal facilities to be available for years 3 through 5 pursuant to the adopted LOS standard are not in place and available prior to the issuance of a CO, a commitment for that capacity to be in place and available to accommodate projected demand in those future years shall be made through the means provided in paragraphs 2a) through 2f), above, prior to issuance of a CO.

It is anticipated that after building permits are issued, determinations of concurrency prior to the issuance of COs may simply involve review and verification of compliance with terms of the conditions set forth in foregoing paragraphs 1 and 2.

  1. A proposed development will not be denied a concurrency approval for transportation facilities provided that the development is otherwise consistent with the adopted Comprehensive Development Master Plan and it meets the following criteria pursuant to Section 163.3180, Florida Statutes:

a) The proposed development located within the Urban Infill Area1; or

b) The proposed development is located in an existing urban service area2 within the UDB and is located in a Community Development Block Grant (CDBG)-eligible Area established pursuant to the Housing and Community Development Act of 1974, as amended, and CFR Part 570, or Chapter 163, Part 3, F.S., respectively, or in an Enterprise Zone established pursuant to Chapter 290, F.S.; or in a zoned Community Urban Center as depicted in CIE Figure 2; or

c) The proposed development is one which poses only special part-time demands3 on the transportation system pursuant to Section 163.3180, Florida Statutes, and is located in an existing urban service area inside the UDB; or

d) The proposed development is located inside the UDB, and directly and significantly promotes public transportation by incorporating within the development a Metrorail, Metromover or TriRail Station, or a Metrobus terminal4 for multiple Metrobus routes, or is an office, hotel or residential development located within one-quarter mile of a Metrorail, Metromover or TriRail station, or a Metrobus terminal for multiple Metrobus routes5; and

Footnotes

  1. Urban Infill area (UIA) is defined in Traffic Circulation Subelement Policy 1B and is depicted in CIE Figure 1.

  2. Existing urban service area means an area inside the UDB which is already built up and where public facilities and service such as sewage treatment systems, roads, schools, and recreation areas are already in place.

  3. A special part-time demand is defined as one that does not have more than 200 scheduled events during any calendar year and does not affect the 100 highest traffic volume hours.

  4. Metrobus terminals for multiple routes are those non-rail transit centers as mapped in the CDMP Mass Transit Subelement, which contain dedicated parking facilities or significant transit patron structures and amenities.

  5. Planned stations and terminals shall not serve as a basis to grant this concurrency exception if the station, associated rapid transit corridor segment, or terminal is identified in the Transportation Element as "not cost-feasible."

e) The proposed development is a public transit facility. For the purposes of this subparagraph, public transit facilities include transit stations and terminals; transit station parking; park-and-ride lots; intermodal public transit connection or transfer facilities; fixed bus, guideway and rail stations; and airport passenger terminals and concourses, air cargo facilities and hangars for the assembly, manufacture, maintenance, or storage of aircraft. The terms “terminals” and “transit facilities” do not include seaports or commercial or residential development constructed in conjunction with a public transit facility.

f) If the project would result in an increase in peak period traffic volume on an SIS roadway that is operating below the CDMP-adopted LOS standard or would operate below the LOS standard as a result of the project, and which increase would exceed 2 percent of the capacity of the roadway at the CDMP-adopted LOS standard, the County shall require the developer and successors to implement and maintain trip reduction measures to reduce travel by single-occupant vehicles so that the resultant increase in traffic volume does not exceed 2 percent.

Miami-Dade County shall include in its concurrency management program ordinance or administrative rules appropriate criteria and methodologies to implement the exceptions authorized in foregoing paragraphs 3a) through 3e), consistent with requirements of Chapter 163, Part 2, Florida Statutes.

  1. A proposed development that conforms to the criteria enumerated in Section 163.3180, F.S., and is located in an existing urban service area within the UDB where an affected transportation facility is operating below its adopted LOS standard is deemed to have a de minimis impact that, alone or in combination with other similar or lesser impacts, will not cause unacceptable degradation of the level of service on affected transportation facilities; however no impact will be a de minimis impact if it would exceed the adopted level of service standard of any affected designated evacuation route, as mapped in the Traffic Circulation Subelement. Miami-Dade County shall include in its concurrency management program ordinance or administrative rules appropriate methodologies for determining and monitoring de minimis impacts consistent with Chapters 163.3180 Florida Statutes, and any amendments thereto and successor legislation or rules.

  2. A proposed development that is located within the UDB may receive an extension of the 36-month limitation established in foregoing paragraph 1c), and receive transportation concurrency approval on this basis, when all the following factors are shown to exist:

    a) The CDMP is in compliance with State law;

    b) The proposed development would be consistent with the future land use designation for the specific property and with pertinent portions of the CDMP, as determined by the County;

    c) The CIE provides for transportation facilities adequate to serve the proposed development, and the County has not implemented that project;

    d) The landowner shall be assessed a fair share of the cost of providing the transportation facilities necessary to serve the proposed development; and

    e) The landowner has made a binding commitment to the County to pay the fair share of the cost of providing the transportation facilities to serve the proposed development. Miami-Dade County shall include in its concurrency management

program ordinance or administrative rules appropriate criteria and methodologies to implement this provision.

  1. Miami-Dade County shall, by ordinance, include proportionate share mitigation methodologies and options in its concurrency management program, consistent with the requirements of Chapter 163, Florida Statutes. The intent of these options is to provide for the mitigation of transportation impacts through mechanisms that might include, but are not limited to, private funds, public funds, contributions of land, and the construction or contribution of facilities. Transportation facilities or segments identified for improvement through the use of proportionate share mitigation options must be included in the Capital Improvements Element, or in the next regularly scheduled update of the Capital Improvements Element.

  2. The County in coordination with the Miami-Dade County Public Schools shall by ordinance, include proportionate share mitigation methodologies and options for public school facilities in its concurrency management program and adopted Interlocal Agreement for Public School Facility Planning consistent with the requirements of Chapter 163, Florida Statutes. The intent of these options is to provide for the mitigation of residential development impacts on public school facilities through mechanisms that might include, but are not limited to, one or more of the following: contribution of land; the construction, expansion, or payment for land acquisition or construction of a permanent public school facility; or, the creation of a mitigation bank based on the construction of a permanent public school facility in exchange for the right to sell capacity credits.

⬚ figure

![red dashed line]Urban Infill Area (UIA) Boundary
![solid black line]2020 URBAN DEVELOPMENT BOUNDARY
![black dashed line]2030 URBAN EXPANSION AREA BOUNDARY

SOURCE: MIAMI-DADE COUNTY DEPARTMENT OF REGULATORY AND ECONOMIC RESOURCES, 2013

Figure 1

URBAN INFILL AREA (UIA)

DEPARTMENT OF REGULATORY AND ECONOMIC RESOURCES, 2013

⬚ figure

Figure 2

REDEVELOPMENT CONCURRENCY EXCEPTION AREAS

DEPARTMENT OF REGULATORY AND ECONOMIC RESOURCES, 2013

Implementation Schedules of Improvements

The following pages deal with the implementation of the CIE. The capital projects forthcoming from each functional element are listed for the period 2012/2013-2017/2018 along with the cost, location, expected revenues and funding source. These are the latest schedules of projects, which have been derived from the County’s Proposed Budget and Multi-Year Capital Plan for fiscal year 2012-13. Additionally, those capital improvements for non-county roadways, as listed in the most recent adopted Transportation Improvement Program for Fiscal Years 2012/2013 to 2016/2017 (TIP) and approved by the Metropolitan Planning Organization (MPO) for the Miami Urbanized Area on May 17, 2012 are incorporated by reference into the CIE. Furthermore, those capital improvements for educational facilities, as listed in the Miami-Dade County Public Schools Facilities Work Program dated September 2012 and adopted by the Miami-Dade School Board, are incorporated by reference into the CIE.

Preceding a section containing the project listings is a section containing brief narratives which describe current local practices for the particular services, presents level of service standards, if any, and discusses how capital investments are prioritized. The relationship to the Land Use Element is indicated and operating cost implications are set forth, where applicable. In all instances, project and other cost figures originate with operational departments, which have direct responsibility for, and experience in, the functional area. The basis for their cost estimates range from actual bid prices to application of standard formulae for deriving such estimates.

The capital improvements identified herein are all derived from the functional elements and fall into three categories. First, there are those projects arising from the individual elements LOS standards. These are further subdivided into those meeting existing deficiencies, those accommodating growth, or simply replacement projects. A project meets existing deficiency in an area if it provides capacity improvements necessary to satisfy LOS requirements for the current population and/or service demands. A project addresses future growth in an area if it provides capacity improvements necessary to satisfy LOS requirements for the future based on growth assumptions regarding population and/or service demands. Often, a project is a combination of deficiency correction and future capacity addition. Another class of projects has their basis in the objectives and policies of a functional element and do not have definitive LOS standards. Finally, a few projects are included which are required to mitigate unsafe or hazardous conditions. In all instances, the schedules of improvements are consistent with the individual elements.

Aggregate Expenditures and Revenues

The aggregate values and phasing and categories of expenditures for all functional areas are shown in Table 1, reflecting the most current Schedules of Improvements for the CIE as of November 2012. Overall, the eleven functional areas include 412 active projects with a total cost of $21.96 billion. About a fourth of this, $5.73 billion, will be expended during the six-year programming period 2012/2013-2017/2018.

Aviation

The Miami-Dade Aviation Department (MDAD) has the responsibility for the development, maintenance and operation of the civil aviation facilities of the County. These facilities consist of Miami International Airport (MIA) and four general aviation and training airports: Opa-locka Executive Airport, Kendall-Tamiami Executive Airport, Homestead General Aviation Airport, and Dade-Collier Training and Transition Airport. The Airport System is considered the primary economic engine for Miami-Dade County as well as for South Florida.

The Aviation Department generates resources for the development, operation, and maintenance from aviation fees, property rentals, concessions, leases, and sales of services to tenants and from other miscellaneous revenues. The basic parameters of revenue and expenditures for Miami International Airport are set forth in the County's 1954 Trust Agreement as amended, and user agreements with the major airlines.

Funding for airport capital improvements is provided from bond and note proceeds, anticipated federal and state aviation grants, passenger facility charges (PFC's) revenue and interest income. Factors that may alter this proposed funding approach include, but are not limited to: differences in the actual amounts of federal and state grants; the risk of termination of PFC's; and the addition and deletion of projects. It is expected that Additional Bonds for the Capital Improvement Program (CIP) through future years will be issued pursuant to the Authorizations on a periodic, as-needed, basis. In addition, MDAD intends to continue its use of the Aviation Commercial Paper Notes to facilitate the construction of the CIP by means of short-term temporary financings pending longer-term refinancing through Airport Revenue Bonds.

Specific capital improvements needs are identified in the approved master plans for all airports. In the selection and scheduling of these needs priority is placed first on meeting existing deficiencies, next on renovating and maintaining existing facilities and then on addressing future growth needs. Appropriate planning and construction lead times are required in scheduling the last category of improvements.

The Aviation 2012/2013-2017/2018 Schedule of Improvements contains nine projects with planned expenditures at $259.042 million (See Table 2). The impacts of the planned projects on operating costs are mostly offset by the enhancement of revenue generation through expanded operations. As the program proceeds, funding will be generated as required through debt issues.

Coastal Management

The Beach Restoration and Preservation Program is Miami-Dade County's mechanism for initiating and coordinating federal and/or State projects essential to the protection and recreational viability of Miami-Dade's ocean shoreline. Local participation in the determination of activities pertaining to beach restoration and preservation is made through the program. The County has benefited from large federal and State funding contributions and the expertise obtained as a result of the program. Most notably, the Miami-Dade County Beach Restoration Project now provides hurricane and erosion control protection for upland property and a vast recreational resource for public use. This project replaced a seriously eroded shoreline sustained only by bulkheads and seawalls, which offered little protective or recreational value. Implementation of erosion control projects is based on the following criteria:

  1. Need for protection of public safety and property in areas threatened by coastal erosion.
  2. To provide enhanced beach-related recreational opportunities for both visitors and Miami-Dade County residents.
  3. To provide more effective and efficient long-term management of our natural and restored beach systems.

The Biscayne Bay Restoration and Enhancement Program objectives are to maintain or improve ecological, recreational, and aesthetic values of Biscayne Bay, its shoreline, and coastal wetlands. Projects include shoreline stabilization, mangrove and wetland habitat restoration, and

bay bottom community enhancement at parks and other public lands. These contribute to erosion control, water quality, and fisheries and wildlife resources.

Future capital expenditures will be directed primarily towards maintaining and enhancing durability of restored beaches and to environmental improvement on the Biscayne Bay ecosystem. All of these projects are developed and carried out based on the best scientific and technical information available to the agencies involved.

For the period 2012/2013-2017/2018, the two proposed projects would cost $56.235 million (See Table 3), with $22.119 million being expended during the six-year programming period.

Conservation

There are nine capital projects related to Conservation goals. One project includes the Environmentally Endangered Land Acquisition Program. This program focuses on preservation of ecologically significant land resources of the County, including wetlands and globally imperiled forest resources. The other projects listed are stormwater management projects identified within the Stormwater Management Master Plan, that focus on improving water quality and drainage infrastructure.

Biscayne Bay is a local natural resource of national significance. Improperly managed stormwater runoff can convey pollutants from urban areas to sensitive surface waters, such as the Bay or its tributaries. The Stormwater Management Master Plan is an essential step towards identifying and solving drainage-related water quality problems in the County. The Master Plan identifies and maps existing stormwater systems, estimates the effects of expositing and future land uses on flood protection and water quality, and develops “best management practices” (BMPs) and priority projects to reduce flooding and improve water quality.

The nine projects will require $54.836 million in expenditures over the 2012/2013-2017/2018 programming period, and sufficient funding is available (See Table 4). Total capital costs currently stand at $266.286 million. Operating cost impacts are not significant at present, but land management costs could be substantial in the future.

Drainage

Given the high and often sudden rainfall in Miami-Dade County coupled with its low elevations, drainage is a problem throughout the County. The most pressing problems are often found in older built-out areas, which have obsolete or sometimes substandard drainage systems. However, there are sound engineering solutions for drainage problems and continued implementation of the mitigation programs is gradually reducing the deficiencies.

The Division of Environmental Resources Management of the Department of Regulatory and Economic Resources (RER) is responsible for regulating and approving drainage programs, but the Public Works and Waste Management Department (PWWM) carries out drainage improvements projects on County maintained roadways. The County’s Stormwater Master Plan and citizen complaints are used to guide project implementation. Citizen complaints initiate a site inspection and ranking for prioritization. County arterial roads rank above residential collectors taking into consideration ponding which causes traffic lanes to become impassable or results in drivers deviating into adjacent lanes to avoid standing water.

The current program contains 32 active projects with expenditures to correct local drainage problems totaling $66.780 million over the 2012/2013-2017/2018 programming period. Primarily the Stormwater Utility funds the drainage programs. Mitigation of drainage problems is an ongoing effort in Miami-Dade County, and this is reflected in the Schedule of Improvements as completion dates are shown beyond the six-year programming period (See Table 5).

Park and Recreation

Local recreation open spaces are defined as open spaces, which serve the close-to-home recreation and open space needs of unincorporated residential areas. Population growth is the most important consideration guiding local park facilities investment decisions. The quantitative link used to translate population into local park needs is the adopted LOS standard of 2.75 acres of local recreation open space per 1,000 permanent residents.

Areawide recreation open spaces shall be provided and designed to meet the broad needs of all Miami-Dade County residents and tourists. They are developed to make important natural resources and major athletic activity complexes available to the public. Acquisition policy is oriented towards the addition of large properties with natural resources and good access to the park inventory.

In both cases, the primary determinant is supplemented by a number of additional considerations affecting the specific decision. Property characteristics, location, size, configuration and availability are critical variables. Access, proximity to the population in need, adjacent land uses and neighboring alternative recreation opportunities are also important criteria in facility investment decisions. The Parks, Recreation and Open Spaces Department also places special emphasis on the acquisition of environmentally and historically significant properties.

Policy ROS-5A: The County shall prioritize park capital improvement expenditures in accordance with the following criteria: 1) Acquire local parkland to maintain the adopted level-of-service standard for local recreation open space by correcting existing deficiencies and addressing future needs and acquire areawide parkland suitable for outdoor recreation while preserving natural, historical and cultural resources; 2) renovate and upgrade existing recreation open spaces and facilities, and; 3) develop new recreation open spaces and facilities within undeveloped or incomplete parks.

It has long been the policy of the Parks, Recreation and Open Spaces Department that the provision of all parks will be staged so that they are available to serve new development as it is completed. In addition, it is also department policy that unique natural features and historically significant properties to be given priority in parks acquisitions. Locational characteristics are also critical factors. Where possible, Public Local Recreation Open Space should be developed in conjunction with or near public schools and other compatible uses. They should also be located so as to be easily accessible; yet should not be degraded by excessive traffic.

Plans of State agencies providing public facilities are taken into consideration primarily in the context of State Department of Natural Resources (DNR) provision of State parks and recreation areas. The County’s Parks, Recreation and Open Spaces Department generally seeks to complement State facilities in terms of location and activities available at the site. In the Schedule of Improvements, there are 84 active projects, which total $212.149 million to be expended during the 2012/2013-2017/2018 programming period (See Table 6). Most of the projects are for the "quality of life" type facilities, which make up such a large component of its program. Funding has been identified mostly as the result of the Safe Neighborhood Parks

referendum approved in 1998, as well as the recent voter approved GOB program. Operating cost effects of Parks are often considerable and are frequently more of an impediment than construction funding.

Public Schools Facilities

Miami-Dade County shall coordinate with the Miami-Dade County Public Schools to annually update its Facilities Work Program to include existing and anticipated facilities for both the 5-year and long-term planning periods, and to ensure that the adopted level of service standard will continue to be achieved and maintained. Miami-Dade County, through its annual update to the Capital Improvements Schedule, will incorporate by reference the latest adopted Miami-Dade County Public Schools Facilities Work Program for educational facilities. Miami-Dade County and the Miami-Dade County Public Schools will coordinate their planning efforts prior to and during the Miami-Dade County Comprehensive Development Master Plan Amendment process and during updates to the Miami-Dade County Public Schools Facilities Work Program.

Seaport

PortMiami (PM) is among America’s busiest ports and recognized throughout the world with the dual distinction of being the Cruise Capital of the World and the Cargo Gateway of the Americas. The Port’s development has been guided by a series of master plans, the latest currently being completed is the 2035 Master Plan. This document updates the major expansion plans for the Port to ensure that the Port keeps pace with the demands of the cruise and shipping industries and maintains its beneficial impact on the South Florida economy, while responding to changing conditions in the market.

The Port pursues the following goal in conducting its operations and providing for its capital facilities needs: PortMiami shall provide for an effective and efficient maritime transportation facility and services, endeavor to retain its position as the top ranking cruise port of the world and as one of the leading cargo ports in the nation while minimizing any detrimental effects on the environment, the community and natural resources, and enhances the economy of the County, region and State. The Port has identified specific objectives and policies that must be met to implement this goal.

The Port’s projected cruise passenger volumes will reach approximately 3.85 million in FY 2011-12. Bookings are expected to increase by 4.5 million over the next five years. Also, the amount of cargo flowing through the Port is projected at 940,000 TEUs in FY 2012-13, a four percent increase over the previous year. This projected growth will be accommodated by the Port's current expansion plans, which concentrate on cargo, cruise and commercial real estate. Projects include: the Miami Harbor Dredge to -52’/-50’, which will accommodate deeper draft cargo vessels; the construction of the Port of Miami Tunnel, which will create a direct connection between the PortMiami and the interstate; the development of an off-island distribution center, along with private sector partners; the planning of two cruise terminals; and identifying potential real estate sites to complement cruise and cargo operations.

The Port is dedicated to cooperatively working with the cruise lines and cargo carriers to fulfill needed infrastructure improvements so that they can operate efficiently, thereby creating jobs and providing economic opportunities for residents of Miami-Dade County.

In light of the above considerations PortMiami is carrying out 18 projects for the 2012/2013-2017/2018 programming period totaling $510.552 million in expenditures over that time span.

About a third of the dollars are going to meet existing deficiencies the other two-thirds combine those needs with expansion for the future (See Table 7). Operating cost effects of these projects are likely to be significant, but are not known at this time. Total capital costs are close to $756.413 million.

Sewer and Water Facilities

The provision of countywide water and sewer services is the responsibility of the Miami-Dade Water and Sewer Department (WASD). The policy framework for WASD's activities was first established in the Water Quality Management Plan for Miami-Dade County (WQMP), which was adopted in 1983. The WQMP's advocacy of a countywide water and sewer system is embodied in Sec. 2-340 of the Code of Miami-Dade County which "declares it to be the policy of Miami-Dade County to establish, own, and operate a countywide sanitary sewage collection and disposal system and a water supply, treatment, and distribution system..."

Since its establishment in 1973, WASD has combined the water and sewer systems of the City of Miami and the County, acquired an additional 25 public and private utilities and incorporated them into the basic network. In addition to undertaking this monumental task, WASD meets the existing demand for water and sewer services. WASD facilities currently provide 87 percent of the potable water used in the County and treat and dispose of 99 percent of the sewage generated. At present, there are no private water or sewer utilities operating in the County, and most municipal systems provide only water distribution and sewage collection services. The cities of North Miami and North Miami Beach have a Water Treatment Plant and are currently wholesale customers to the WASD to provide water for a portion of their service area. Homestead and Florida City also have a Water Treatment Plant providing water service to their entire service area. Homestead buys water from the Miami-Dade WASD on an emergency basis. The city of Homestead also has a Wastewater Treatment Facility providing wastewater services to their service area.

As required by the County Code, WASD has closely coordinated the provision of these services with County plans and programs for growth and development. In accord with the land use policies of the Comprehensive Development Master Plan, water and sewer services are provided to the area within the Urban Development Boundary, and are not provided to areas designated for Agriculture or Open Land on the Future Land Use map.

Improvements to the water and sewer systems are based on the following general criteria:

  1. Improvements, which are necessary to protect the health, safety and environmental integrity of the community, and meet federal, State, and local regulatory requirements.
  2. Improvements, which are necessary to meet existing deficiencies in capacity or in performance. These include the retrofit of deteriorating facilities, which fail or threaten to fail to meet health, safety or environmental standards.
  3. Improvements which extend service to previously unserved developed areas.
  4. Improvements which have been identified in adopted functional plans and address system details which are beyond the scope of the comprehensive plan for wastewater facilities and potable water facilities and are consistent with the goals, objectives and policies of the comprehensive plan.
  5. Cost-effective improvements to expand capacity, maximize operational efficiency, and increase productivity.

In providing for improvements to the potable water supply system, the following additional criteria are also taken into account:

  1. Improvements associated with the protection of existing and planned potable water wellfields.
  2. Elimination of fire flow deficiencies, and otherwise improving system pressures.
  3. Interconnection of new South Miami Heights Water Treatment Plant to the countywide system; including upgrades to the Alexander Orr Water Treatment Plant.
  4. Water treatment upgrades for the Northwest Wellfield water to comply with surface water standards.
  5. Providing service to new development.
  6. Providing service to existing development and redevelopment.
  7. Development of alternative potable water sources.

In providing for improvements to the sanitary sewer collection system, the following additional criteria are also taken into account:

  1. Location within a public water supply wellfield protection zone.
  2. Potential for the disposal of wastes other than domestic waste.
  3. Designation on the Future Land Use Plan map for a use more intense than estate density residential.
  4. Potential for impacts on existing private wells.
  5. Areas with low land elevation in conjunction with high water table.
  6. Soil conditions.
  7. Proximity to open bodies of water.
  8. Proximity to existing sewer mains.

WASD actively plans for water and sewer facilities, which meet existing needs and will provide for future demand. In addition to the above criteria, specific plans for water facility improvements are contained in the WASD's Water Facilities Master Plan. The last version of the Water Facilities Master Plan was published in 2003. Specific plans for sewer facility improvements are contained in the Miami-Dade County Wastewater Facilities Plan Update (2007).

These facilities are programmed in accord with sound financial practices. WASD relies on the following bond programs: the State's General Obligation Pollution Control Bonds, and; bonds backed by the WASD's solid revenue base. Special Taxing Districts are established to provide new service areas that are already developed in accord with Chapter 18 of the County Code. Retrofitting of some deteriorating water distribution or sewage collection facilities are paid through the renewal and replacement funds, which WASD maintains for this purpose.

The developer and customer through connection charges pay for all improvements, which are required to meet the demands of new growth. In situations where the developer actually constructs the necessary water and sewer mains, WASD requires that the main be sufficiently large to meet the expected demand on the main. The developer is credited for the oversizing in accord with WASD's Rules and Regulations, and costs met through connection charges as new customers hook up to the systems.

In the Schedule of Improvements for Sewer Facilities, the 35 projects total close to $4.788 billion to be expended during the 2012/2013-2017/2018 period (See Table 8).

The Schedule of Improvements for Water Facilities lists 30 projects for 2012/2013-2017/2018 totaling $1.239 billion in expenditures (See Table 12). Adequate funding is available both for proposed water and sewer facilities. Operating cost effects of the water and sewer projects will be relatively modest, since most of the expenditures are directed at upgrades and improvements.

Solid Waste

The Miami-Dade County Public Works and Waste Management Department provides an integrated Solid Waste Collection and Disposal System with the principal responsibilities of collection, transfer and disposal of municipal solid waste and recycling of residential materials. Miami-Dade-County Department of Public Works and Waste Management Department (DPWWM) primarily provides solid waste services to account holders of single-family residential units and multifamily units in the unincorporated portions of the County, a small number of commercial accounts County-wide and 9 municipalities (Aventura, Cutler Bay, Doral, Miami Gardens, Miami Lakes, Palmetto Bay, Pinecrest, Sunny Isles Beach, Sweetwater). The Department holds long term interlocal agreements with 18 municipalities to provide solid waste disposal services and 11 municipalities for curbside recycling. The Department also ensures regulatory compliance in issues regarding solid waste through the Enforcement Division, which continues to be proactive in addressing and investigating occurrences of trash on the rights-of-way and illegal dumping.

The Department is currently developing a Solid Waste Management Master Plan that will meet the waste reduction, collection, recycling, transfer and disposal needs for Miami-Dade County for the next 50 years. The goal of this Plan is to identify and develop activities, programs, facilities, and technologies that will provide sustainability, resource conservation, source reduction, recycling, and diversion, disposal and collection options and ensure public health and environmental protection for the next generation of county residents.

The priority of solid waste facility projects are formulated in accordance with the following general criteria:

  1. Improvements, which are necessary to protect the health, safety and environmental integrity of the community, and meet federal, state, and local regulatory requirements.
  2. Improvements, which are necessary to exceed existing deficiencies in capacity or in performance. These include the retrofit of deteriorating facilities, which fail or threaten to fail to meet health, safety or environmental standards.
  3. Improvements, which extend services to previously not served developed areas.
  4. Improvements, which have been identified in adopted functional plans and the Solid Waste Master Plan, and are consistent with the goals, objectives and policies of the comprehensive plan.
  5. Cost-effective improvements to expand capacity, maximize operational efficiency, and increase productivity.

At the existing projected rate of demand for disposal services, the current program provides adequate capacity for more than the 5-year level of service required by Chapter 33G of the Miami-Dade County Code, Service Concurrency Management Program. To carry out this program, the decisions regarding placement and operation of transfer stations, processing facilities and disposal sites must consider, among other things, the land use implications and nuisance

perceptions. The principal concerns are environmental impacts, land use compatibility and cost effectiveness. For example, potential deleterious effects on groundwater must be avoided in development of disposal sites. Likewise, negative impacts of truck traffic, noise, emissions, odors, or unaesthetic views on residential neighborhoods must be mitigated or eliminated entirely. In general, facilities are located so as to create the least conflict with adjacent uses, thereby supporting policies concerning maintenance of compatibility among uses and cost effectiveness.

In the Schedule of Improvements for Solid Waste Management, for the 31 projects expenditures total $117.169 million during the 2012/2013-2017/2018 programming period (See Table 9). Total capital costs currently stand at $190.250 million. Operating costs effects of the projects are likely to be significant but are not available at this time. Capital funding has been programmed through an existing 2001 and 2005 revenue bond program, future solid waste disposal notes/bonds, and operating cash.

Traffic Circulation and Mass Transit

Planning transportation investments in the Miami-Dade County area for the ground transportation system is the primary responsibility of the County through the Metropolitan Planning Organization (MPO) for the Miami Urbanized Area, in conjunction with the Florida Department of Transportation (FDOT). In addition, the Miami-Dade Expressway Authority was created first by the County in 1994 and then adopted by the State legislature in 1996 to operate and maintain all toll roads in the County except for the Turnpike, and was given authority to expand existing facilities and construct new toll roads in the County which began in 1997. Regarding traffic circulation, the County has the responsibility to maintain development and improve those minor arterials and collectors on the County roadway system, with the exception of those facilities operated by the Miami-Dade Expressway Authority. The FDOT maintains, develops, and improves those freeways, expressways and arterials on the State highway system. The provision of Mass Transit services is solely the responsibility of Miami-Dade County.

Through the MPO and consistent with federal and State requirements, each urbanized area must have in place a continuing, cooperative and coordinated transportation planning process, also known as the "3-C" process, consistent with the planned development of the urbanized area. In Miami-Dade County's case this would mean consistency with the County's future growth and land use pattern reflected in the CDMP Land Use Element and Land Use Plan Map.

The "Miami-Dade 2035 Long Range Transportation Plan" (LRTP), as adopted and amended by the MPO Governing Board fulfills the "3-C" (Comprehensive, Continuing, and Cooperative) requirements. This Plan recommends a number of highway and transit capacity improvements considered necessary to effectively meet the transportation needs of the Miami-Dade County metropolitan area. A listing of projects contained in this document explicitly indicates the relative priority of the various highway and transit improvements. As indicated in the Traffic Circulation and Mass Transit Subelements of the Transportation Element, MPO Plans are used as the foundation for the future transportation network in the 2030 and 2040 CDMP. Priorities for highway and transit improvements were established in the MPO Long Range Transportation Plan according to four priorities with the first and highest priority responding to projects needed by the Year 2015 to remedy existing traffic capacity deficiencies; second in priority were those projects needed between 2016 and 2020; third in priority were those projects needed between 2021 and 2025; and finally projects responding to projected needs between 2026 and 2035.

Currently, based on the priorities established in the MPO Transportation Plan, projects are advanced for implementation to the MPO Five-Year Transportation Improvement Program (TIP)

for Miami-Dade County. The TIP is another required document of the MPO, which covers the current fiscal year and four subsequent years, and identifies all sources of funding (Federal, State and Local), which are known or anticipated to be available during the program period. Projects in the TIP include highway improvements on the State highway system (Primary, Intrastate and Turnpike) as well as those on the County highway system, which are identified as the Secondary Road Program, Impact Fee, and Gas Tax. Similarly, all programmed transit projects are included for the five-year period. The five-year work program of the Miami-Dade Expressway Authority is also identified in the TIP.

Drawing upon the various existing mechanisms described above for determining transportation investment decisions, this section addresses how transportation needs identified in the Traffic Circulation and Mass Transit Subelements are to be met in the six-year period and included as part of the Capital Improvements Element.

The Traffic Circulation and Mass Transit Subelements establish level-of-service (LOS) standards to ensure that adequate facility capacity will be provided for future development and for the purposes of issuing development orders. For traffic circulation, the minimum acceptable peak hour LOS standards for State and County road facilities are set forth in Policy TC-1B, and the transit minimum LOS standard is set in Policy MT-2A.

The ability to maintain this level of service standards becomes the primary determinant for addressing relative priority among the various transportation improvement needs. In conjunction with the LOS standards, priorities are established according to the following general criteria:

  1. Correction of existing capacity or service deficiencies;
  2. Repair/replacement of existing facilities; including hazard elimination projects;
  3. Maximize operating efficiency and productivity; and
  4. Meet future needs based on projected growth patterns and travel demand.

The timing and location of traffic circulation and mass transit improvements is driven by the ability to maintain the adopted LOS standards to serve new development consistent with the staging of future growth established in the goals, objectives and policies of the Land Use Element and the Land Use Plan map. For traffic circulation priority is to be given to the construction, maintenance, and reconstruction of roadways that serve the area within the Urban Development Boundary of the Land Use Plan map. Second in priority are those projects that support the staged development of the urbanizing portions of the County within the designated Urban Expansion Area. Concerning mass transit service, including routes and rapid transit corridors, priority will be to support the staging of development and to serve future ridership generators within the Urban Development Boundary with specific projects prioritized in the recently adopted 2012 Transit Development Plan.

Through the MPO process, the plans and programs of the FDOT are taken into consideration for improvements needed on the State highway system. The County seeks to coordinate the timing and location of these improvement projects with other County projects to maintain continuity in the transportation network.

In the Schedule of Improvements for Traffic Circulation, the 123 projects total $422.940 million, which will be expended during the 2012/2013-2017/2018 period (See Table 10). About one-third of the expenditures are for meeting existing deficiencies combined with future growth. The Mass Transit Schedule of Improvements contains 39 projects. Planned expenditures are $1.172 billion with the total cost of the program at $2.099 billion (See Table 11). Operating costs for Traffic are not significant, but will total several million dollars annually for Transit.

Schedules and Funding Sources

Following is the series of tables containing the adopted schedules of capital improvements and a list identifying the funding sources referenced in the tables. As explained in the previous pages, Table 1 summarizes the aggregate costs, phasing of expenditures, as well as available funding for each functional area, and it identifies the proportion of aggregate expenditures allocated to address past or future development requirements. Tables 2 through 12 each address specific functional programs. Tables 10-A and 11-A identify projects that are the responsibility of developers “to construct or cause the construction of” in order to address the traffic impacts created by privately initiated CDMP amendment projects.

In tables 2 through 12, the programmed expenditures for each of the six program years is listed for each project along with the total expenditures for the six-year interval, the total cost of the project, the total available funding, and the funding source(s). The "total" expenditures column reports the expenditures to occur during the posted six-year period, while the total cost column reports all expenditures to occur during all years including years before and after the posted six-year period. Similarly, "Available Funding" includes all funding available during the posted six-year period and prior years, and may include revenue anticipated for the project in future years from established revenue sources.

TABLE 1

CDMP CAPITAL IMPROVEMENTS SCHEDULE

ELEMENTPrior Years2012/132013/14Expenditures Revenues 2014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsNumber of Projects
(In Thousands of Dollars)
AVIATION
Existing Deficiency0000000000
0000000000
Future Growth6,250,214182,28663,60313,153000259,04206,509,256
6,421,37951,98429,5636,33000087,87706,509,256
Combined/Other0000000000
0000000000
TOTALS6,250,214182,28663,60313,153000259,04206,509,2569
6,421,37951,98429,5636,33000087,87706,509,256
COASTAL MANAGEMENT
Existing Deficiency1,1102,54062500003,16504,275
1,1102,54062500003,16504,275
Future Growth0000000000
0000000000
Combined/Other33,00613,7304002,4244002,000018,954051,960
33,00613,7304002,4244002,000018,954051,960
TOTALS34,11616,2701,0252,4244002,000022,119056,2352
34,11616,2701,0252,4244002,000022,119056,235
CONSERVATION
Existing Deficiency5,2061,6892,2051,0001,0006,1758,16020,2302,80528,241
5,3411,5542,2051,0001,0006,1758,16020,0952,80528,241
Future Growth0000000000
0000000000
Combined/Other145,9396,9003,7002,7002,70015,8062,80034,60657,500238,045
194,9953,40070095095014,3061,20021,50621,544238,045
TOTALS151,1458,5895,9053,7003,70021,98110,96054,83660,305266,2869
200,3364,9542,9051,9501,95020,4819,36041,60124,349266,286

TABLE 1

October 2012

CDMP CAPITAL IMPROVEMENTS SCHEDULE

ELEMENTPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsNumber of Projects
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
DRAINAGE
Existing Deficiency4,4558,2793,5192,5012,50624,98524,25366,04272971,226
7,0966,2792,8782,5012,50624,98524,25363,40172971,226
Future Growth0000000000
0000000000
Combined/Other4330738000073801,171
4330738000073801,171
TOTALS4,8888,2794,2572,5012,50624,98524,25366,78072972,397
7,5296,2793,6162,5012,50624,98524,25364,13972972,397
PARK and RECREATION
Existing Deficiency0000000000
0000000000
Future Growth1,8827316339152,9623,3885,30413,93312,96028,775
2,4422286338582,9623,3885,30413,37312,96028,775
Combined/Other110,75733,95635,44938,78518,93230,28940,805198,216112,912421,885
144,95917,69928,04032,43216,28228,75640,805164,014112,912421,885
TOTALS112,63934,68736,08239,70021,89433,67746,109212,149125,872450,660
147,40117,92728,67333,29019,24432,14446,109177,387125,872450,660
SEAPORT
Existing Deficiency60,31059,15737,72221,37722,5934,3693,000148,2180208,528
60,31059,15737,72221,37722,5934,3693,000148,2180208,528
Future Growth173,116165,974114,64625,59616,63312,0000334,8490507,965
173,116165,974114,64625,59616,63312,0000334,8490507,965
Combined/Other12,4357,8854,9004,9004,9004,900027,485039,920
12,4357,8854,9004,9004,9004,900027,485039,920
TOTALS245,861233,016157,26851,87344,12621,2693,000510,5520756,413
245,861233,016157,26851,87344,12621,2693,000510,5520756,413

TABLE 1

October 2012

CDMP CAPITAL IMPROVEMENTS SCHEDULE

ELEMENTPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsNumber of Projects
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
SEWER FACILITIES
Existing Deficiency45,40318,42424,77947,72354,208131,090231,636507,860471,5061,024,769
59,20015,30019,43343,32053,958130,790231,262494,063471,5061,024,769
Future Growth268,25820,5952,3981,1092,7641,8874,86233,61525,926327,799
290,9682,2771,0001097701,8874,86210,90525,926327,799
Combined/Other172,91795,403101,027151,034139,558245,286375,1331,107,4414,290,3215,570,679
253,32523,38193,448150,934139,258245,032374,9801,027,0334,290,3215,570,679
TOTALS486,578134,422128,204199,866196,530378,263611,6311,648,9164,787,7536,923,247
603,49340,958113,881194,363193,986377,709611,1041,532,0014,787,7536,923,247
SOLID WASTE MANAGEMENT
Existing Deficiency0000000000
0000000000
Future Growth0000000000
0000000000
Combined/Other47,56732,98427,26724,0163,9025,85523,145117,16925,514190,250
88,48610,01112,27223,9113,6925,75022,62878,26425,500192,250
TOTALS47,56732,98427,26724,0163,9025,85523,145117,16925,514190,250
88,48610,01112,27223,9113,6925,75022,62878,26425,500192,250
TRAFFIC CIRCULATION
Existing Deficiency49,63727,02548,03016,49021,43718,18310,221141,3860191,023
59,41422,30347,82418,23414,84418,18310,221131,6090191,023
Future Growth11,8248,4545,78050050050050016,234028,058
11,8248,4545,78050050050050016,234028,058
Combined/Other154,04493,39976,83431,60419,80427,56916,110265,3208,733428,097
162,75391,04975,07530,00416,80427,56916,110256,6118,733428,097
TOTALS215,505128,878130,64448,59441,74146,25226,831422,9408,733647,178
233,991121,806128,67948,73832,14846,25226,831404,4548,733647,178

TABLE 1

October 2012

CDMP CAPITAL IMPROVEMENTS SCHEDULE

ELEMENTPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsNumber of Projects
(In Thousands of Dollars)
MASS TRANSIT
Existing Deficiency31,77628,21615,87014,20712,98912,99412,99997,2750129,051
31,77628,21615,87014,20712,98912,99412,99997,2750129,051
Future Growth48,5828,434388300149009,271057,853
48,5838,433388300149009,270057,853
Combined/Other834,955211,516187,869188,255211,101161,322105,7831,065,84611,9501,912,751
836,211210,259187,870188,255211,101161,322105,7831,064,59011,9501,912,751
TOTALS915,313248,166204,127202,762224,239174,316118,7821,172,39211,9502,099,65539
916,570246,908204,128202,762224,239174,316118,7821,171,13511,9502,099,655
WATER FACILITIES
Existing Deficiency28,1567,9417,0007,0007,9947,0006,56943,504071,660
35,8605,8006,0006,0006,0006,0006,00035,800071,660
Future Growth0000000000
0000000000
Combined/Other212,60493,454126,617272,382220,454183,810299,2371,195,9542,508,6213,917,179
291,37715,998125,435272,332220,404183,775299,2371,117,1812,508,6213,917,179
TOTALS240,760101,395133,617279,382228,448190,810305,8061,239,4582,508,6213,988,83930
327,23721,798131,435278,332226,404189,775305,2371,152,9812,508,6213,988,839
ALL ELEMENTS
Existing Deficiency226,053153,271139,750110,298122,727204,796296,8381,027,680475,0401,728,773
260,107141,149132,557106,639113,890203,496295,895993,626475,0401,728,773
Future Growth6,753,876386,474187,44841,57323,00817,77510,666666,94438,8867,459,706
6,948,312237,350152,01033,69321,01417,77510,666472,50838,8867,459,706
Combined/Other1,724,657589,227564,801716,100621,751676,837863,0134,031,7297,015,55112,771,937
2,017,980393,412528,878706,142613,791673,410860,7433,776,3766,979,58112,773,937
GRAND TOTALS8,704,5861,128,972891,999867,971767,486899,4081,170,5175,726,3537,529,47721,960,416413
9,226,399771,911813,445846,474748,695894,6811,167,3045,242,5107,493,50721,962,416

Source: Tables 2 - 12

TABLE 2

AVIATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
1)MIA - North Terminal Development (NTD)2/20132,834,55787,6350000087,63502,922,192821, 917,
6339221Miami International Airport2,894,89227,3000000027,30002,922,1921145,3763, 3764
2)MIA - Support Facility Improvements2/2015884,15959,88838,38810,500000108,7760992,935124, 406,
6331290Miami International Airport978,8233,4927,1283,49200014,1120992,935821,1145, 1189,3763
3)MIA - Roadways and Parking2/2018154,74200000000154,742406, 821,
6331810Miami International Airport154,74200000000154,7423763
4)General Aviation Airports2/201558,699102102253000457059,156124, 821,
633693058,69945700000457059,1563763
5)MIA - Mover2/2013280,8983,735000003,7350284,633821, 3763,
6337230Miami International Airport284,63300000000284,6333764
6)MIA - Other Terminal Projects2/2013469,1455,4476,0732,40000013,9200483,065124, 406,
6337440Miami International Airport473,8081,6624,7572,8380009,2570483,065821, 3763
7)MIA - South Terminal Development2/20131,033,9012,15936000002,51901,036,420124, 406,
63310500Miami International Airport1,036,420000000001,036,420821, 1145, 3763
8)MIA - Airside Improvement Projects2/2014356,73621,82015,380000037,2000393,936124, 406,
6333310Miami International Airport361,38518,32314,228000032,5510393,936821, 3736
9)MIA - Cargo Development2/2014177,3771,5003,30000004,8000182,177124, 821,
6339990Miami International Airport177,9777503,45000004,2000182,1773736
TOTALS6,250,214182,28663,60313,153000259,04206,509,256
6,421,37951,98429,5636,33000087,87706,509,256

* 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Miami-Dade Aviation Department (MDAD) and Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

TABLE 3

COASTAL MANAGEMENT

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/13Expenditures Revenues 2013/14Expenditures Revenues 2014/15Expenditures Revenues 2015/16Expenditures Revenues 2016/17Expenditures Revenues 2017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
1)Biscayne Bay Restoration & Shoreline Stab.1/20131,1102,54062500003,16504,275470, 885
5555691Biscayne Bay and Tributaries1,1102,54062500003,16504,275
2)M-D County Beach Erosion & Renourishment3/-N/A33,00613,7304002,4244002,000018,954051,96011,13, 14,17,
552590Countywide33,00613,7304002,4244002,000018,954051,96018-25, 142,
834, 1043
TOTALS34,11616,2701,0252,4244002,000022,119056,235
34,11616,2701,0252,4244002,000022,119056,235
  • 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

TABLE 4

CONSERVATION

Expenditures
RevenuesSix YearFutureProject
PriorTotalsYearsTotals
Years2012/132013/142014/152015/162016/172017/18
ProjectProject NamePurpose* /Funding
Numberand LocationEstimated(In Thousands of Dollars)Source
Year of
Completion
1)Environmentally Endangered Lands Program3/-N/A145,9396,9003,7002,7002,70015,8062,80034,60657,500238,045
5555621Various Sites194,9953,40070095095014,3061,20021,50621,544238,045
2)Local Drainage Improvements for CRS Program1/201801,0001,0001,0001,0001,0001,0006,00006,000
5555631Various Sites01,0001,0001,0001,0001,0001,0006,00006,000
3)Drainage Improvements Within CD 011/20170000005,1295,12905,129
551100Commission District 10000005,1295,12905,129
4)Drainage Improvements NW 95 St.1/20170000050005000500
554450NW 95 St.-100 St. from NW 34 Ave.- 36 Ave0000050005000500
5)Drainage Improvements SW 127 Ave1/20170000075007500750
554720SW 127 Ave.- 128 Ave.from SW 58 St.- 65 St0000075007500750
6)Drainage Improvements Within CD 021/20170000001,5761,57601,576
555900Commission District 20000001,5761,57601,576
7)Drainage Improv. North Miami Beach Boulevard1/2017000001,50001,50001,500
5510070N Miami Beach Blvd from NE 17 Ave.to US-1000001,50001,50001,500
8)Drainage Improvements SW 157 Ave1/201419900001,30101,30101,500
559780SW 42 St. to SW 64 St. (SW 157 Ave Canal)19900001,30101,30101,500
9)Local Drainage Improvements1/20175,0076891,205001,1244553,4732,80511,285
602880Various Sites5,1425541,205001,1244553,3382,80511,285
TOTALS151,1458,5895,9053,7003,70021,98110,96054,83660,305266,286
200,3364,9542,9051,9501,95020,4819,36041,60124,349266,286
  • 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Public Works and Waste Management Department (PWWM) and Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

TABLE 5

DRAINAGE

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues (In Thousands of Dollars)Six Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
1)Roadway Drainage Improv. in the Uninc.Area1/201802,1251,0001,0001,0001,0001,0007,12507,125630
6031811Unincorporated Miami-Dade County02,1251,0001,0001,0001,0001,0007,12507,125
2)Drainage Impr.Caribbean Blvd@C-1NCanal Cr.1/20123842,00064100002,64103,025630
602900Carribean Blvd between FL Turnpike & Anchor Rd3,025000000003,025
3)Drainage Improvements Coral Way1/201700000750075007501188
553070to SW 21 St.from SW 67 Ave. to SW 72 Ave0000075007500750
4)Drainage Improvements SW 72 St1/2017000001,00001,00001,0001188
608820SW 72 St- SW 80 St from SW 52 Ave- SW 57 Ave000001,00001,00001,000
5)Drainage Improvements SW 92 Ave1/2017000001,25001,25001,2501188
558690SW 92 Ave from W Flagler St to SW 8 St000001,25001,25001,250
6)Drainage Improv. Within Comm. District 031/201700000135013501351188
551500Commission District 30000013501350135
7)Drainage Improv. Within Comm. District 041/201700000960096009601188
556540Commission District 40000096009600960
8)Drainage Improv. Within Comm. District 051/2017000001,00001,00001,0001188
556130Commission District 5000001,00001,00001,000
9)Drainage Improv. Within Comm. District 061/2017000004,89404,89404,8941188
555150Commission District 6000004,89404,89404,894
10)Drainage Improv. Within Comm. District 071/2017000001,27001,27001,2701188
558090Commission District 7000001,27001,27001,270
11)Drainage Improv. Within Comm. District 081/201700000529052905291188
558940Commission District 80000052905290529
12)Drainage Improv. Within Comm. District 101/201954500000007281,27313,14,17,
553020Commission District 1054500000007281,2731188
13)Drainage Improv. Within Comm. District 111/2018477000001,3811,38101,85811,13,14,

TABLE 5

DRAINAGE

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
551790Commission District 11477000001,3811,38101,8581188
14)Drainage Improv. Within Comm. District 121/20180000003,3153,31503,3151188
552880Commission District 120000003,3153,31503,315
15)Drainage Improv. Within Comm. District 131/201800000087487408741188
558620Commission District 130000008748740874
16)Master Plan Basinwide Drain.Impr.Com.Dist.011/2017000001,50001,50101,5011188
554180Commission District 1000001,50001,50101,501
17)Master Plan Basinwide Drain.Impr.Com.Dist.021/2017000002,00002,00102,0011188
554910Commission District 2000002,00002,00102,001
18)Master Plan Basinwide Drain.Impr.Com.Dist.041/2017000001,60001,60101,6011188
551430Commission District 4000001,60001,60101,601
19)Master Plan Basinwide Drain.Impr.Com.Dist.071/2017000001,37001,37101,3711188
559270Commission District 7000001,37001,37101,371
20)Master Plan Basinwide Drain.Impr.Com.Dist.081/2017000004,22704,22804,2281188
5510660Commission District 8000004,22704,22804,228
21)Master Plan Basinwide Drain.Impr.Com.Dist.101/2018542000005,0135,01305,55611, 1188
551710Commission District 10542000005,0135,01305,556
22)Master Plan Basinwide Drain.Impr.Com.Dist.111/20180000004,8754,87504,8761188
552540Commission District 110000004,8754,87504,876
23)Master Plan Basinwide Drain.Impr.Com.Dist.121/20180000004,6334,63304,6341188
559150Commission District 120000004,6334,63304,634
24)Master Plan Basinwide Drain.Impr.Com.Dist.131/20180000001,6381,63801,6391188
557510Commission District 130000001,6381,63801,639
25)Reserve for High Priority Drainage Projects1/201805005005005005005003,00003,000630
5553041Unincorporated Miami-Dade County05005005005005005003,00003,000

TABLE 5

DRAINAGE

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
26)Stormwater Pump Stations Telemetry1/20129652020000020201,16711,13,14,
555390Unincorporated Miami-Dade County9652020000020201,16717, 1188
27)Drainage Retrofit Of Arterial Roadways1/201801,0001,0001,0001,0001,0001,0006,00006,000630
607800Countywide01,0001,0001,0001,0001,0001,0006,00006,000
28)Drainage Impr.- NW 68 St and NW 32 Ave1/2018890000002222091213,14,17,
604480NW 68 St and NW 32 Ave89000000222209121188
29)San Sebastian Drainage Impr. Project3/20144330738000073801,17114,
609010Uninc. Miami-Dade County4330738000073801,171630,1188
30)Seaboard Acres Pump Station Retrofit1/20132851,997000001,99702,282630
9920Memorial Hwy & NE 131 St2851,997000001,99702,282
31)Drainage Impr.- NW 77 Ave to NW 78 Ct1/2012110123780000390050011,13,14,
552990NW 78 Ct to 77 Ave from NW 179 St to 186 St110123780000390050017, 1188
32)Stormwater Pump Stat/Control Struct.Upgrade1/2012257443000004430700630
608020Various257443000004430700
TOTALS4,8888,2794,2572,5012,50624,98524,25366,78072972,398
7,5296,2793,6162,5012,50624,98524,25364,13972972,398

* 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Public Works and Waste Management Department (PWWM) and Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

TABLE 6

PARK and RECREATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
1)Park Benefit District (PBD)No.1Local Park Dev3/20154,3532,293118749840020004,57808,931501
9340351Park Benefit District 18,1667650000076508,931
2)Park Benefit District (PBD)No.2Local Park Dev3/201510,7982,6383,1502,36615001233010,887021,685501
9340361Park Benefit District 220,94773800000738021,685
3)Park Benefit District (PBD)No.3Local Park Dev3/20155,180922120190115010003,27408,454501
9340281Park Benefit District 38,0234310000043108,454
4)Southridge Park - BBCBPN/20192,567200282011212,8004,2238107,60013,14,17,
93203019355 SW 114 Ave.2,587002820112128004,2038107,6001188
5)Boating Related Improvements3/20161,948330330300300001,26003,208840
9341501Countywide2,008300300300300001,20003,208
6)QNIP Phase II - Local Park Improv .N/20121,1541,863000001,86303,0171087
93410300Unincorporated Miami-Dade County3,017000000003,017
7)A.D. Barnes Park - BBCBP (Proj #24)N/20191,094000024345369622104,00011,13,14,
9311503401 SW 72 Ave.1,094000024345369622104,0001188
8)Beach Maintenance Facility - BBCBP3/201700000500050005001188
939730Vicinity of 76 St and Collins Ave0000050005000500
9)Biscayne Shores Park - BBCBP3/2018000003001,2001,50001,5001188
933730NE 116 St & NE 14 Ave0000030012001,50001,500
10)Chuck Pezoldt Park - BBCBP3/2019000004503,4153,8654854,3501188
936340SW 168 St & 157 Ave0000045034153,8654854,350
11)Colonial Drive Park - BBCBP3/20175360000789078901,32511, 13, 14,
93463010750 SW 156 Ter5360000789078901,3251188
12)Country Lake Park - BBCBP3/20190000004254252,0752,5001188
933480NW 195 St & NW 87 Ave00000042542520752,500
13)Domino Park-West Perrine - BBCBP3/20127014800000148021813, 14, 1188

TABLE 6

PARK and RECREATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures / Revenues 2012/13Expenditures / Revenues 2013/14Expenditures / Revenues 2014/15Expenditures / Revenues 2015/16Expenditures / Revenues 2016/17Expenditures / Revenues 2017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
936540SW 171 St & 104 Ave70148000001480218
14)Eden Lakes Park - BBCBP3/201251402866001000098601,50017, 1188
936230SW 162 Ave & 47 St51402866001000098601,500
15)Gloria Floyd Area - BBCBP3/201700000250025002501188
936910SW 126 St & 109 Ave0000025002500250
16)Homestead Bayfront Park - BBCBPN/20133,73300000004034,13611, 13, 14
9370209698 NW Canal Dr3,73300000004034,13617, 1188, 842
17)Ives Estates District Park - BBCBPN/20196392001875525140047114409,1515,21015,00011, 13, 14
936890NE 16 Ave & NE 209 St6392001875525140047114409,151521015,0001188
18)Jefferson Reaves Sr. Park - BBCBP3/20179400001060106020011, 1188
9352703100 NW 50 St94000010601060200
19)Lago Mar Park - BBCBP3/20183140000068668601,00011, 13, 14
934730SW 162 Ave & SW 80 St3140000068668601,00017, 1188
20)Leisure Lakes Park - BBCBP3/20135500062060001,22001,27513, 14, 1188
931084029305 Illinois Rd5500062060001,22001,275
21)Local Parks - Com.District 02 - BBCBP3/201927700002879811,2682001,74514
933490Various Sites27700002879811,2682001,7451188
22)Local Parks - Com.District 04 - BBCBP3/201710400002230223032711, 13, 1188
938550Various Sites104000022302230327
23)Local Parks - Com.District 10 - BBCBP3/2018785000009369362,2794,00011, 14, 1188
932050Various Sites7850000093693622794,000
24)Local Parks - Com.District 11- BBCBP3/20199420000101,2591,2691,2893,50011, 13, 14
937700Various Sites94200001012591,26912893,50017, 1188
25)Local Parks - Com.District 13 - BBCBP3/20186080000067567501,283
9310370Various Sites6080000067567501,2831188

TABLE 6

PARK and RECREATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/13Expenditures Revenues 2013/14Expenditures Revenues 2014/15Expenditures Revenues 2015/16Expenditures Revenues 2016/17Expenditures Revenues 2017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
26)Marva Bannerman Park - BBCBP3/201700000150015001501188
9310404830 NW 24 Ave.0000015001500150
27)Medsouth Park - BBCBP3/201700000700070007001188
935660SW 280 St. ans SW 130 Ave.0000070007000700
28)Naranja Park - BBCBP3/20122,11300000001602,27311, 13, 14,
93279014150 SW 264 St.2,11300000001602,27317, 1188
29)North Glade Park (Meadow Wood Prk)BBCBP3/201315600640604001,24401,40013, 14, 1188
93142017355 NW 52 Ave.15600640604001,24401,400
30)North Shorecrest & Military Trail Park- BBCBP3/201700000500050005001188
934640801 NE 88 St.0000050005000500
31)North Trail Park - BBCBP3/20136976982001640001,06201,75917, 1188
934610NW 8 St. and NW 127 Ave.6976982001640001,06201,759
32)Oak Grove Park - BBCBPN/201744300001750175061813, 14, 1188
935510690 NE 159 St.443000017501750618
33)Olympic Park - BBCBPN/2019129000009719715001,60011, 13, 1188
9360408601 SW 152 Ave.129000009719715001,600
34)Royal Colonial Park - BBCBPN/20172800001071,2651,37201,40014, 1188
935850SW 147 Ave. and SW 280 St.28000010712651,37201,400
35)Sergeant Joseph Delancy Park- BBCBPN/20172,0030000500050002,50311, 13, 14,
93834014450 Boggs Dr.2,0030000500050002,50317, 1188
36)Sharman Park - BBCBPN/2015000000006006001188
938680SW 219 St. and 123 Ave.00000000600600
37)South Dade Park - BBCBPN/2018463000025372,0004,53705,00011, 13, 14,
93139016350 SW 280 St.4630000253720004,53705,0001188

TABLE 6

PARK and RECREATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
38)West Perrine Park - BBCBPN/201911904353990456004,88105,00013, 14, 17,
93149017121 SW 104 Ave.11904353990456004,88105,0001188
39)Wild Lime Park - BBCBPN/20190000004004001,1001,5001188
93208011341 SW 147 Ave.00000040040011001,500
40)Amelia Earhart Park - BBCBP (Proj #45)2/20198463005605002,9627034,5299,55412,60023,00011, 13, 14,
931004011900 NW 42 Ave.1,080123560443296270345299,3201260023,00017, 1188
24
41)Arcola Lakes Park - BBCBP3/20131,1103,3601,83000005,19006,30011, 13, 14,
9388701301 NW 83 St.2,0912379183000004,20906,30017, 1188, 1216
42)Camp Matecumbe (Boystown) - BBCBPN/20194800500001201705,3506,00011, 13, 14,
937010SW 120 St. and SW 137 Ave.48005000012017053506,0001188
43)Camp Owaissa Bauer - BBCBPN/20177970000203020301,00011, 13, 14,
93486017001 SW 264 St.7970000203020301,0001188
44)Chapman Field Park - BBCBPN/20171,68600005501,3001,8501,4645,00013, 14
93353013601 Old Cutler Rd.1,686000055013001,85014645,0001188
45)Charles Deering Estate - BBCBPN/201991723320000906601,1832,9005,00013, 14, 17,
93758016701 SW 72 Ave.1,000350000906601,10029005,0001188
46)Crandon Park - BBCBPN/20197,7771,6572,70735720007,9367,28723,00011, 13, 14,
9390604000 Crandon Blvd.8,2041230270735720007,509728723,00017, 1188
25
47)Greynolds Park - BBCBPN/20195872659821104902706303,8632,5507,00013, 14, 17,
93660017530 W Dixie Hwy6232299821104902706303,82725507,0001188
48)Haulover Park - BBCBP3/20198,1491269239006051,4153,52811,32323,00011, 13, 14,
93274010801 Collins Ave.8,23112271990060514153,4461132323,00017, 1188
49)Homestead Air Reserve Park - BBCBPN/2019184534630011213,2144,85110,02215,05713, 14, 1188
933780SW 268 St. and SW 129 Ave.1845346300112132144,8511002215,05720, 23
50)Kendall Indian Hammocks Park - BBCBP3/20196000004131,9712,3843,5566,00011, 13, 1188

TABLE 6

PARK and RECREATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
93172011395 SW 79 St.60000041319712,38435566,000
51)Kendall Soccer Park - BBCBP3/20173,1500000850085004,00011, 13, 14,
936860SW 127 Ave. and 80 St.3,1500000850085004,0001188
52)Larry and Penny Thompson Park - BBCBPN/2019407000022102,2334,4431,7506,60011, 13, 1188
93712012451 SW 184 St.4070000221022334,44317506,600
53)Matheson Hammock Park - BBCBPN/20192,04200004771,3451,8222,1366,00011, 13, 14,
9321109610 Old Cutler Rd.2,042000047713451,82221366,0001188
54)Zoo Miami-Const.of PhV-FI Exhibit - BBCBPN/20193,3437511024916459118160039,275042,61811, 13, 14,
93365012400 SW 152 St.4,09401024916459118160038,524042,61817, 1188
25
55)Zoo Miami-Ph III-Impr. & Entry Way - BBCBP3/20157,2040000000479612,00011, 13, 14,
93601012400 SW 152 St.7,2040000000479612,00017, 1188
56)Redland Fruit & Spice Park - BBCBPN/20182,63800002521,1101,36204,00011, 13, 14,
93965024801SW 187 Ave.2,638000025211101,36204,0001188
57)Tamiami Park - BBCBPN/20191,238000004114116,3518,00011, 13, 14,
93500011201 SW 24 St.1,2380000041141163518,0001188
58)Trail Glades Range - BBCBPN/20194,7982,3586540004483,46010009,25811, 13, 14,
9310910SW 8 St. and 177 Ave.6,4509384220004481,80810009,25817, 1188
1216, 895
59)Tree Islands Park - BBCBPN/2019584000001461464,2705,00011, 13, 14,
9310720SW 24 St. and SW 142 Ave.5840000014614642705,00017, 1188
60)Tropical Park - BBCBPN/20192,44035163,3442001001,9451,74510,8501,71015,00011, 13, 14,
9370407900 SW 40 St.2,760319633442001001945174510,530171015,00017, 1188
61)West Kendall District Park - BBCBPN/201900000033133122,66923,0001188
931220SW 120 St. and 167 Ave.0000003313312266923,000
62)Greenways &Trails-CDist.01-BBCBP(Pr#51)N/20131,2722,5601,86800004,42805,70013,14,17,
932610Various Sites4,9190781000078105,7001188, 821

TABLE 6

PARK and RECREATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
63)Greenways &Trails-CDist.09-BBCBP(Pr#51)N/20157151601,3582,762996005,27605,99114, 17, 1188
937230Various Sites2,6208001358817396003,37105,991821
64)Greenways &Trails-CDist.08-BBCBP(Pr#51)N/20121,8902,0151,7506430004,40806,29813, 14, 1188
936760Various Sites4,205450164300002,09306,298821
65)Greenway Bridges ProjectN/201320555817500007330938821
933030Various Sites93800000000938
66)Marina Capital PlanN/20135,5563570000035705,913885, 3780
932660Various Sites5,913000000005,9131008,3766
67)Areawide & Local Parks - Park ImprovementsN/20120600000006000600650
937110Countywide0600000006000600
68)Goulds Park - BBCBP3/20171,073000036403641601,59711, 13, 14,
93110021805 SW 114 Ave1,073000036403641601,5971188
927
69)QNIP Phase V - Local Park Improv.N/20129845880000058801,5721184
938040Unincorporated Miami-Dade County1,572000000001,572
70)Haulover Beach Ocean Rescue - BBCBP3/20122,1511590000015902,31011, 13, 14,
939880Haulover Beach Park2,1531570000015702,31017, 1188, 650
1225
71)West Perrine Senior Citizen Center - BBCBP2/201412073415000488050014, 1188
936310SW 102 Ave and SW 172 St120734150004880500
72)Bikepath Improvements Along Canals-BBCBP2/201872203000072592801,00011, 14, 17,
934080Various Sites170105000072583001,0001188
73)Bikepath Imp On Snapper Creek Trail-BBCBP2/2018000004505050005001188
932040Along SW 117 Ave from SW 16 St to SW 79 St00000450505000500
74)Bikepath On Snake Creek Bridge - BBCBP2/2019140000050005003601,00013,14, 1188
936990I-95 at Snake Creek Canal140000050005003601,000

TABLE 6

PARK and RECREATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
75)Ludlam Bikepath - BBCBP2/2017812228000173501,96302,7751188, 821
939080FEC railroad from D-Land North to NW 12 St1,0400000173501,73502,775
76)New Haitian Comm. Center - BBCBPN/201934000010792,5903,6696,29710,00013, 14,
935350690 NE 159 St340000107925903,669629710,0001188
77)CDBG Park Capital ImprovementsN/20126001,520000001,52002,120190,191
931590Various1,0701050000001,05002,120
78)Miami River Greenway3/20171,1271,8001,8002,7730006,37307,50011,13,14,
6010960City of Miami1,1671760180027730006,33307,50017, 1188
79)Country Village Park - BBCBP3/20131,4030000017517501,57811,13,
9388406550 NW 188 Terr1,4030000017517501,57814, 1188
80)Briar Bay Park - BBCBP3/2012182000068068025013, 14, 1188
9310200SW 128 St amd SW 90 Ave1820000680680250
81)Continental Park - BBCBP3/2012275500000050032513,14, 17
9342901000 SW 82 Ave32500000000325
82)QNIP -Local Park ImprovementsN/20112836700000067009531217
931850Unincorporated Miami-Dade County95300000000953
83)Park Revenue Enhancement3/20125553450000034509003766
931080Various Sites90000000000900
84)Westchester Arts Center - BBCBPN/201794500004,0003,0557,05508,00011, 13,14,
9327307900 SW 40 St94500004,0003,0557,05508,00017, 1188
TOTALS112,63934,68736,08239,70021,89433,67746,109212,149125,872450,660
147,40117,92728,67333,29019,24432,14446,109177,387125,872450,660
  • 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Parks, Recreation, and Open Spaces Department and Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

TABLE 7

SEAPORT

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
1)Seaport Tunnel2/2014100,000055,000000055,0000155,00011, 1000
649870Dante B. Fascell Port of Miami-Dade100,000055,000000055,0000155,000
2)Dredge III2/20155,285129,05655,33310,5963,63300198,6180203,903142, 821,
649730Dante B. Fascell Port of Miami-Dade5,285129,05655,33310,5963,63300198,6180203,9031000
3)Infrastructure Improvements1/201710,87512,2807,3005,50012,0004,369041,449052,324821, 1000
645430Dante B. Fascell Port of Miami-Dade10,87512,2807,3005,50012,0004,369041,449052,324
4)Gantry Berth Reinforcements3/20131,6852,985000002,98504,6701000
643560Dante B. Fascell Port of Miami-Dade1,6852,985000002,98504,670
5)Container Yard Improvements - Seaboard1/201422,0991,8927,9567,17800017,026039,125821, 1000
644520Dante B. Fascell Port of Miami-Dade22,0991,8927,9567,17800017,026039,125
6)Cruise Terminals D & E Upgrds for New Serv.2/201313,7361,940000001,940015,676821, 1000
644710Dante B. Fascell Port of Miami-Dade13,7361,940000001,940015,676
7)Construction SupervisionN/201710,7504,9004,9004,9004,9004,900024,500035,2501000
6430061Dante B. Fascell Port of Miami-Dade10,7504,9004,9004,9004,9004,900024,500035,250
8)Dredge III Bulkhead Strengthening2/201441,90620,0003,913000023,913065,819821, 1000
647710Dante B. Fascell Port of Miami-Dade41,90620,0003,913000023,913065,819
9)Cargo Gateway Security Sustems1/20142502,0117242,7093,375008,81909,0691000
644010Dante B. Fascell Port of Miami-Dade2502,0117242,7093,375008,81909,069
10)Cargo Bulkhead Rehabilitation1/20151,0007,7038,4382,1475,4830023,771024,7711000
646300Dante B. Fascell Port of Miami-Dade1,0007,7038,4382,1475,4830023,771024,771
11)Terminal Bulkhead Future Repairs2/201700015,00013,00012,000040,000040,0001000
644300Dante B. Fascell Port of Miami-Dade00015,00013,00012,000040,000040,000
12)Terminal F & G Upgrades1/20147,4639,6025,000000014,602022,065917, 1000
645020Dante B. Fascell Port of Miami-Dade7,4639,6025,000000014,602022,065
13)Cruise Terminal J Improvements1/20182,85301,8000003,0004,80007,6531000

TABLE 7

SEAPORT

Expenditures
PriorRevenuesSix YearFutureProject
YearsTotalsYearsTotals
Purpose* /2012/132013/142014/152015/162016/172017/18
ProjectProject NameEstimatedFunding
Numberand LocationYear ofSource
Completion(In Thousands of Dollars)
642930Dante B. Fascell Port of Miami-Dade2,85301,8000003,0004,80007,653
14)Intermodal & Rail Reconstruction2/201412,18914,978400000015,378027,567
642780Dante B. Fascell Port of Miami-Dade12,18914,978400000015,378027,567
15)Mass Notification System1/20122,67250000005002,722
642390Dante B. Fascell Port of Miami-Dade2,67250000005002,722
16)Purchase 4 Add. Gantry Container Cranes1/201610,43625,4694,2942,5524440032,759043,195
6433531Dante B. Fascell Port of Miami-Dade10,43625,4694,2942,5524440032,759043,195
17)Cruise Terminal Bulkhead Repair1/20132,55250000005002,602
649890Dante B. Fascell Port of Miami-Dade2,55250000005002,602
18)Sewer Upgrades1/20161101002,2101,2911,291004,89205,002
647720Dante B. Fascell Port of Miami-Dade1101002,2101,2911,291004,89205,002
TOTALS245,861233,016157,26851,87344,12621,2693,000510,5520756,413
245,861233,016157,26851,87344,12621,2693,000510,5520756,413

* 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Port of Miami-Dade (POM) and Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

TABLE 8

SEWER FACILITIES

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
1)Central M-D W.W.Tr.Mains & Pump St. Impr.3/201847,37036,7379601,000002,98841,685290,217379,272
9650241W.W. System - Central District Area84,10709601,000002,9884,948290,217379,272
2)Gravity Sewer Renovations1/201815,097012,8007,0259,4035,4603,09537,783052,880
9650201Systemwide15,097012,8007,0259,4035,4603,09537,783052,880
3)Sanitary Sewer Improvements1/20171,9831,7664005005506006744,49006,473
9650221Systemwide4,6733003003003003003001,80006,473
4)W.W. General Maintenance & Office FacilitiesN/20191,55902,3008,85015,77510,70024,43362,05882,522146,139
9653201Systemwide1,55902,3008,85015,77510,70024,43362,05882,522146,139
5)W.W. Telemetering SystemN/20174,39651002,6262,4502,62208,208012,604
9652481Systemwide4,39651002,6262,4502,62208,208012,604
6)Lift Station Upgrades & Struct. Maint. Impr.3/20185,5241,5045,87610,25210,74111,7419,21349,327054,851
9650371Systemwide5,5241,5045,87610,25210,74111,7419,21349,327054,851
7)South District W.W.Tr. Mains&Pump St. Impr.3/20180001,290005,7347,02407,024
9651061W.W. System - South District Area0001,290005,7347,02407,024
8)Wastewater System Maint. & Upgrades3/201719,01112,01412,50015,00015,00015,00015,00084,514162,500266,025
9650361Systemwide19,01012,01512,50015,00015,00015,00015,00084,515162,500266,025
9)Pump Station Improvements Program3/201810,364003,0002,5005,00016,80027,300037,664
9651071Systemwide10,364003,0002,5005,00016,80027,300037,664
10)Corrosion Control Facilities Improvements1/201811,4871,32801,0001,5003,0002,0008,828020,315
9653381Systemwide12,815001,0001,5003,0002,0007,500020,315
11)Wastewater Engineering StudiesN/2012626373000003730999
9653241Systemwide99900000000999
12)Sanitary Sewer System Extension3/20199,89905,2591,8352,1132,1132,11313,433396,590419,922
9653281Systemwide9,89905,2591,8352,1132,1132,11313,433396,590419,922
13)Peak Flow Management Facilities1/201916,83615,33011,57939,19842,755122,030225,867456,759471,506945,101

TABLE 8

SEWER FACILITIES

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
9653371Systemwide26,61515,0006,33334,99542,755122,030225,867446,980471,506945,1011171,1266
14)W.W. Equipment & VehiclesN/201722,1055,6789,0009,0009,0009,0009,00050,67855,000127,783490,1266
9650301Systemwide26,1401,6439,0009,0009,0009,0009,00046,64355,000127,783
15)Central District Upgrades - W.W.T.P.3/20196,4581,4809,84616,1879,00030,53533,190100,2381,105,3491,212,045490,521,1170,
9653421Virginia Key8,51109,27316,1879,00030,53533,19098,1851,105,3491,212,0451171,1266
16)North District Upgrades - W.W.T.P.3/20184,6813,6138,65317,25613,59850,06829,454122,6420127,323490,1170,
96534112575 NE 151 St.9,70007,24717,25613,59850,06829,454117,6230127,3231171
17)South District Upgrades - W.W.T.P.3/20187,62316,87711,90715,858450029,45574,547568,824650,994521,1170,
96534018950 SW 232 St.30,00006,40715,858450029,45552,170568,824650,9941171,1266
18)W.W. Treatment Repl. & Renovation.3/201914,83811,9108,6809,2899,2899,2899,28857,74510,59883,181490,1171,
9653261Systemwide22,7174,0318,6809,2899,2899,2899,28849,86610,59883,1811266
19)Pump Station Generators & Misc. Upgrades3/20194366641,7859,62015,14016,34014,17057,7199,60067,7551170,1171
9652002Systemwide1,10001,7859,62015,14016,34014,17057,0559,60067,755
20)W.W.T.P. Automation Enhancements.N/20171,5091185003,5614,4822,577011,238012,747521,1171,
9652003Systemwide1,62705003,5614,4822,577011,120012,7471266
21)W.W.T.P. Miscellaneous Upgrades3/2017007003,1847,5563,778015,2187,50022,7181171, 1266
9652061Wastewater Treatment Plants007003,1847,5563,778015,2187,50022,718
22)North M-D W.W.Tr. Mains & Pump St. Improv.3/20180077000015,00015,77037,53853,3081171, 1266
9652101Wastewater System - North District Area0077000015,00015,77037,53853,308
23)South District W.W.T.P Expansion (Ph III)2/20191,48701,0001097701,8874,8628,62825,92636,041490,1170,
96554818950 SW 232 St.1,48701,0001097701,8874,8628,62825,92636,0411171
24)South District W.W.T.P.-High Level Disinfect.2/2014249,16318,454398000018,8520268,015521,1177,
965102408950 SW 232 St.265,7382,277000002,2770268,0151170,951,
25)Outfall Legislation3/2019004,1255,0009,53615,466123,457157,5841,459,1561,616,7401171, 1266
962670Systemwide004,1255,0009,53615,466123,457157,5841,459,1561,616,740

TABLE 8

SEWER FACILITIES

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior Years2012/132013/14Expenditures Revenues 2014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
26)Mun/WASD Projects - (GOB)3/2019000001,20013,72714,9274,96819,8951188
964490Various000001,20013,72714,9274,96819,895
27)Upgrade of Miami Spr.Pump St. -(GOB)3/20179500712000329060001,55014,17,1188
967730Various9500712000329060001,550
28)Needs Assessments Projects -(GOB)3/20181,1701458757982581,4801,4344,99106,16211,13,14,
964350Various (Wastewater 20%)1,1971198757982581,4801,4344,96506,1621188
29)NW 37 Ave Industrial Dev. Area -(GOB)3/20173122985001,6312,370004,79805,11011,13,14,
965520NW 37th Ave & NW 36 St (W.Water 50%)3122985001,6312,370004,79805,1101188
30)Perrine /Cutler Improv. -(GOB)3/20178,2353,3280002,89506,223014,45811,14,17,
969830Various (Wastewater 70%)8,3543,2090002,89506,104014,4581026,1188
31)System Enhancements -(GOB)3/20192,206551,096004,6153676,1314,95913,29611,14,17,
966370Various (Wastewater 50%)2,208531,096004,6153676,1294,95913,2961188
25
32)System Improvements Project -(GOB)3/20183,452000028,1169,53337,649041,10111,13,14,17,
962830Various (Wastewater 50%)3,452000028,1169,53337,649041,1011188
33)W.W. Pipes & Infrastructure Projects2/201717,6082,1411,0001,0001,994006,135023,743490
968750Various23,7430000000023,743
34)Miami Springs Construction Fund - WW3/20171931001001003002541531,00701,2001220
969110Miami Springs1,200000000001,200
35)W.W. Treatment Plants Effluent Reuse3/20190015,52515,49710,00022,16810,62473,81495,000168,8141171
965630Systemwide0015,52515,49710,00022,16810,62473,81495,000168,814
TOTALS486,578134,422128,204199,866196,530378,263611,6311,648,9164,787,7536,923,246
603,49340,958113,881194,363193,986377,709611,1041,532,0014,787,7536,923,246
  • 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable Source: Miami-Dade Water and Sewer Department

TABLE 9

SOLID WASTE MANAGEMENT

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues (In Thousands of Dollars)2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
1)Environmental Improvements3/20181001001001001001001006000700450
5050251Various Sites1001001001001001001006000700
2)South Dade Landfill Gr/water Remediation3/2018632502020120301425414900450,1027
505158024000 SW 97 Ave.63250202012030282680900
3)Trash & Recycling Center Improvements3/20180100100100100100100600100700451
5054061Various Sites0100100100100100100600100700
4)Collection Facility Improvements3/20180100100100100100100600100700451
5056840Various Sites0100100100100100100600100700
5)North Dade Landfill Gas Extr.Syst. - (Phase II)3/20181,0041051051052101055311,16102,1651027,1140
5051009121500 NW 47 Ave.2,165000000002,165
6)Disposal Facilities Improvements3/20180100100100100100100600100700450
5055760Countywide0100100100100100100600100700
7)North Dade Landfill Gr/water Remediation3/20180501,0001005050501,3002001,500450
505738021500 NW 47 Ave.0501,0001005050501,3002001,500
8)Central Transfer Station Compactor Repl.3/20124,14357000005704,200450,1027
50580001150 NW 20 St.4,14357000005704,200
9)West/Southwest Trash & Recycling Center3/2015263801651,50022001,76702,030451
505405128900 SW 202 Ave263801651,50022001,76702,030
10)Replacement of Scales at Disp. Facilities3/201810050505050505030050450450
5010750Various Sites10050505050505030050450
11)South Dade Landfill Cell 5 Closure3/202300000016,00016,000016,000965
50135024000 SW 97 Ave.00000016,00016,000016,000
12)Virginia Key Landfill Study and Closure GrantN/201532914,36814,02316,93000045,321045,650965,1140

TABLE 9

SOLID WASTE MANAGEMENT

Expenditures
RevenuesSix YearFutureProject
ProjectProject NamePurpose* /Prior2012/132013/142014/152015/162016/172017/18TotalsYearsTotals
Numberand LocationEstimatedYearsFunding
Year ofSource
Completion(In Thousands of Dollars)
503400Virginia Key28,285043516,93000017,365045,650
13)South Dade Landfill Cell 4 Closure3/20180001,0003,0005,0006,00015,000015,000
50437024000 SW 97 Ave.0001,0003,0005,0006,00015,000015,000
14)South Dade Landfill Cell 5 Construction3/20147,6673,2084,08500007,293014,960
50548024000 SW 97 Ave.7,6673,2084,08500007,293014,960
15)Scalehouse Expansion Project3/20134956050000060501,100
505670Various Sites4956050000060501,100
16)Resources Recovery Cell 20 Construction3/20134,1243760000037604,500
5093206990 NW 97 Ave.4,1243760000037604,500
17)North Dade Landfill East Cell Closure3/20180000000019,95019,950
50911021500 NW 47 Ave.0000000019,95019,950
18)Resources Recovery Ash Landfill Cell 19 Cl.N/201502501,0001,7500003,00003,000
5076906990 NW 97 Ave.02501,0001,7500003,00003,000
19)Home Chemical Collection Center Access Rd3/201396535000003501,000
5035308831 NW 58 St96535000003501,000
20)Disposal Facility Exit Scales3/20140505000001000100
502240Various Sites0505000001000100
21)Resources Recov. Ash Landfill Cell 20 Clos.3/2018000000005,0005,000
5032206990 NW 97 Ave000000005,0005,000
22)West Transfer Station Tipping Floor3/2013211110262670004390650
5014102900 SW 72 Ave211110262670004390650
23)58 Street Truckwash Facility3/20127495980000059801,347
5044508831 NW 58 St.7495980000059801,347

TABLE 9

SOLID WASTE MANAGEMENT

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
24)S Dade Landfill Cell 4 Gas Extr.&Odor Control3/201853050050505022010097001,500450
50928024000 NW 97 Ave53050050505022010097001,500
25)Resources Recovery - Cap.Improv.Proj.3/20132,1853,3271,7295440005,60007,785450
5086406990 NW 97 Ave2,1853,3271,7295440005,60007,785
26)Munisport Landfill Closure Grant3/201421,2258,5003,5931,50000013,593034,818450,1140
5010690NE 145 St and Biscayne Blvd31,02702,2911,5000003,791034,818
27)Disposal System Facilities Backup Power Gen.N/201250550000050510450
509270Various Sites50550000050510
28)NE Transfer Station Surge Pit Tipping Floor Roof3/201285010050000015001,000450
50910018701 NE 6 Ave85010050000015001,000
29)Old S.Dade Land Fill Recl. Water Force Main3/201406523500003000300450
60997023707 SW 97 Ave06523500003000300
30)Old S.Dade Land Stormwater Pump St. Mod.3/201408545000005350535450
60166023707 SW 97 Ave08545000005350535
31)Olinda Park Remediation3/20131,49010000001001,5003784
6033802101 NW 51 St1,49010000001001,500
TOTALS47,56732,98427,26724,0163,9025,85523,145117,16925,514190,250
86,48610,01112,27223,9113,6925,75022,62878,26425,500190,250

* 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Public Works and Waste Management Department (PWWM) and Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
1)Traffic Control Devices - Equip. & MaterialsN/202507507507507507507504,50004,500670
6033051Countywide07507507507507507504,50004,500
2)Causeway Toll System Upgrade3/20121,2002,500000002,50003,700440,3771
605220Rickenbacker & Venetian Causeway1,2002,500000002,50003,700
3)Railroad Improvements3/201605005005005005005003,00003,000670
6031831Countywide05005005005005005003,00003,000
4)Street Lighting MaintenanceN/202503,0003,0003,0003,0003,0003,00018,000018,000670,821
6031231Various Sites03,0003,0003,0003,0003,0003,00018,000018,000
5)Bridge Repair and PaintingN/201605005005005005005003,00003,000670
6050231Countywide05005005005005005003,00003,000
6)Maintenance of Roads & BridgesN/201605005005005005005003,00003,000670
6031221Countywide05005005005005005003,00003,000
7)Widen NW 87 Ave3/20142,4507,0757,0501,25700015,382017,8321107,1116
605840NW 87 Ave from NW 154 St.- 186 St.2,4507,0757,0501,25700015,382017,832
8)Widen NW 74 St1/201431,0596,0405,1063,00000014,146045,205821,1107,
6036590NW 74 St from HEFT to SR82631,0596,0405,1063,00000014,146045,2051116
9)Guardrail Safety Improvements1/202501001001001001001006000600670
6030281Countywide01001001001001001006000600
10)Beautification ImprovementsN/20255112,7002,7002,7002,7000010,800011,311670
6030091Countywide5112,7002,7002,7002,7000010,800011,311
11)People's Transp. Plan Neighborhood Improv.3/201412,85013,75013,864000027,614040,4641116
6037700Various Sites12,85013,75013,864000027,614040,464
12)Widen SW 328 St1/20172,4715,0162,5005005005001,89010,906013,377350,500
6036140SW 328 St from US-1 to SW 162 Ave7,4872,0005005005005001,8905,890013,377
13)Construction of NW 138 St Bridge1/20124,1405000000050004,640821,1107,

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
604860NW 138 St and the Miami River Canal4,1405000000050004,6401116
14)Advanced Traffic Management Syst.(ATMS)3/201340,15811,5007,090000018,590058,748500,821,1090,
608400Countywide40,15811,5007,090000018,590058,7481107,1116
15)Americans with Disabilities Act Hotline Proj.N/202505005005005005005003,00003,000670
609610Countywide05005005005005005003,00003,000
16)Infrastr. Improv. in the Uninc. Area - CD 01N/2019000007503751,1253751,5001188
601200To be Determined000007503751,1253751,500
17)Widen SW 27 Ave. from US-1 to Bayshore Dr.N/20132,7843,00067000003,67006,4541107,1116
601260SW 27 Ave. from US-1 to Bayshore Dr.2,7843,00067000003,67006,454
18)Widen SW 137 Ave. from HEFT to US-13/20259041,0004,4001,3020006,70207,6061107,1116
601910137 Ave from HEFT to US-19041,0004,4001,3020006,70207,606
19)Bike Path Constr. on Old Cutler RoadN/20122450000000024517,1188
602100From SW 184 St to SW 220 St1757000000700245
20)Infrastr. Improv. in the Uninc. Area - CD 12N/201800000094194109411188
602140To be Determined0000009419410941
21)Infrastr. Improv. in the Uninc. Area - CD 08N/201794900001,5001,5003,0001,5555,50413,14,17,
602730To be Determined94900001,5001,5003,0001,5555,5041187,1188
22)Infrastr. Improv. in the Uninc. Area - CD 07N/20171,87100001,4801,2502,7301,2505,8511187,13,14,
603330To be Determined1,87100001,4801,2502,7301,2505,8511188
23)Infrastr. Improv. in the Uninc. Area - CD 09N/20172,36700006335001,1335004,0001187,13,
603370To be Determined2,36700006335001,1335004,0001188
24)Refurbi.SW 296 St. Sonov.Bridge Over C-103C1/20126300003370337040011, 14, 18
603870SW 296 St. Sonovoid Bridge Over C-103630000337033704001187
25)Infrastr. Improv. in the Uninc. Area - CD 06N/20196100002,5821,2903,8721,2905,2231187,1188
604460To be Determined6100002,5821,2903,8721,2905,223

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues (In Thousands of Dollars)Six Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
26) 604960Infrastr. Improv. in the Uninc. Area - CD 13 To be DeterminedN/20180 00 00 00 00 00 0500 500500 5000 0500 5001188
27) 604990Widen SW 137 Ave. from US-1 to SW 184 St. SW 137 Ave. from US-1 to SW 184 St.3/20154,543 4,5436,565 6,5655,400 5,400434 4340 00 00 012,399 12,3990 016,942 16,9421107,1116
28) 605810Bikepaths Construction in District 10 To be DeterminedN/2017204 404200 00 00 00 0296 2960 0496 2960 0700 7001187,14, 1188
29) 605920Renovation of the Miami Ave. Bridge Miami Ave. over the Miami RiverN/20121,548 2,8473,052 1,7530 00 00 00 00 03,052 1,7530 04,600 4,60013,14,17, 18
30) 606190Widen NW 37 Ave.from N.River Dr. -NW 79 St. NW 37 Ave. from N. River Dr. to NW 79 St.3/20151,194 1,1942,050 2,0507,000 7,0007,000 7,0001,044 1,0440 00 017,094 17,0940 018,288 18,2881107,1116
31) 607020Infrastr. Improv. in the Uninc. Area - CD 03 To be DeterminedN/20190 00 00 00 00 0455 455228 228683 683227 227910 9101188
32) 607160Infrastr. Improv. in the Uninc. Area CD 05 To be DeterminedN/20190 00 00 00 00 0289 289144 144433 433144 144577 5771188
33) 607460Improv. on SW 176 St. from US-1 - SW 107 Ave. SW 176 St. from US-1 to SW 107 Ave.3/2015605 605500 5002,000 2,0001,941 1,9410 00 00 04,441 4,4410 05,046 5,0461107,1116
34) 603130Widen SW 312 St. from SW 177 Ave-187 Ave. SW 312 St. from SW 177 Ave.to SW 187 Ave.2/201311 11443 4435,280 5,2800 00 00 00 05,723 5,7230 05,734 5,7341107,1116
35) 607840Renovation of NW 22 Ave. Bascule Bridge NW 22 Ave. over the Miami RiverN/20170 00 00 00 00 01,000 1,0000 01,000 1,0000 01,000 1,00023
36) 607990Commodore Bike Trail Various SitesN/20121,518 2,125607 00 00 00 00 00 0607 00 02,125 2,125821, 500, 1187,13,14
37) 608000Infrastr. Improv. in the Uninc. Area-Com.D.11 To be DeterminedN/20183,089 3,0890 00 00 00 00 01,411 1,4111,411 1,4110 04,500 4,5001187,13,14, 1188

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
38)Infrastr. Improv. in the Uninc. Area-Com.D 04N/201747500004032026051701,2501187,13, 14,
608260To be Determined47500004032026051701,25017, 1188
39)Constr. of Old Cutler Rd Bridge Over C-100 C.N/201700000800080008001188
608290Old Cutler Rd and SW 173 St0000080008000800
40)Renovation of the Palmer Lake BridgeN/2017000003,00003,00003,00023
6083402600 S. River Dr.000003,00003,00003,000
41)School Speedzn Flashing Sign&Feedback Signs3/201311,0422,5911,16700003,758014,8001107,1116
608740Various Sites11,0422,5911,16700003,758014,800
42)Infrastr. Improv. in the Uninc. Area-Com.D.10N/201910,438234000002341,49712,1691187,13,14,
609220To be Determined10,438234000002341,49712,16925,17,1188
43)Renovation of the Tamiami Swing Bridge1/20173,474031,576000031,576035,05013,14,17,500,
6047902000 S River Dr.3,474031,576000031,576035,050821,1188
44)Constr.of SW 157 Ave. from SW 152 St.-184 St.3/20141,0894,0005,0001,26000010,260011,3491107,1116
609590SW 157 Ave. from SW 152 St. to SW 184 St.1,0894,0005,0001,26000010,260011,349
45)Rights-Of-Way Acquis. for Const. Proj.in CD 123/201210,28790000000900011,187500,821,
6010570To Be Determined10,28790000000900011,1871107,1116
46)Infrastr. Improv. in the Uninc. Area CD 02N/201954600008774391,3164382,3001187,1188
6010000To be Determined54600008774391,3164382,300
47)Bike Path Constr. on W Dixie HighwayN/201700000120012001201188
6010120W Dixie Hwy from Ives Dairy Rd & MG Dr0000012001200120
48)Sonovoid Bridge Improv. ProgramN/20193,5040140005,16905,3091,28710,1001187,13,14
6010380Countywide3,5040140005,16905,3091,28710,10017,1188
49)Improv.on SW 216 St.from the FT.-SW 127 Ave.3/20151,436502004,5005,000505010,255011,691500,1107,
6010390SW 216 St.from the Fl. Turnp.to SW 127 Ave.1,436502004,5005,000505010,255011,6911116
50)Improv.on SW 264 St. from US-1 to SW 137 Av.3/20146007852,7007000004,18504,7851107,1116

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
6010440SW 264 St. from US-1 to SW 137 Ave.6007852,7007000004,18504,785
51)Safety Lighting3/202505005005005005005003,00003,000670
6032191Countywide05005005005005005003,00003,000
52)Capitalization of Traffic Signals & Signs Crews1/201603,9933,9933,9933,9933,9933,99323,958023,958670
6036701Countywide3,4225713,9933,9933,9933,9933,99320,536023,958
53)Improvements on Arterial Roads3/201376250050000001,00001,7621107,1116
607940Countywide76250050000001,00001,762
54)Improvements to Intersections in RIF Distr.51/201603741241249752401,24301,243500
602780Road Impact Fee D503741241249752401,24301,243
55)Improvements to Intersections in RIF Distr.61/2016029913413413413408350835500
602130Road Impact Fee D6029913413413413408350835
56)Improvements to Intersections in RIF Distr.81/2016046621421421421401,32201,322500
608330Road Impact Fee D8046621421421421401,32201,322
57)Improv. to S Bayshore Dr from Darwin - MercyN/20174753903,0003,000006,03906,514500,1107,
601170S Bayshore Dr from Darwin St to Mercy Way4752,6392,0001,4000006,03906,5141116
58)Mast Arm Upgrades1/20133,0151,4261,4263,5890006,44109,456500, 670,
608510Countywide3,0151,4261,4263,5890006,44109,4561083
59)Resurface Arterial Streets - RIF Distr.51/201603741241249852401,24401,244500
609900Road Impact Fee D503741241249852401,24401,244
60)Resurface Arterial Streets - RIF Distr.61/2016030013413413413408360836500
603520Road Impact Fee D6030013413413413408360836
61)Resurface Arterial Streets - RIF Distr.81/2016046721421421421401,32301,323500
604810Road Impact Fee D8046721421421421401,32301,323
62)Special Taxing District Landsc.& MaintenanceN/201602802802802802802801,68001,680670
607910Countywide02802802802802802801,68001,680

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
63)Traffic Control Devices - Signalization RIF D51/201603741241249752401,24301,243500
601530Road Impact Fee D503741241249752401,24301,243
64)Traffic Control Devices - Signalization RIF D61/2016029913513513513508390839500
606280Road Impact Fee D6029913513513513508390839
65)Traffic Control Devices - Signalization RIF D81/2016046621421421421401,32201,322500
603230Road Impact Fee D8046621421421421401,32201,322
66)Rickenbacker/WM Powell Bridge Str.Repairs1/2012400400000004000800440,3771
604250Rickenbacker Causeway400400000004000800
67)Traffic Signal Loop Repairs2/201605005005005005005003,00003,000670
6010780Various Sites05005005005005005003,00003,000
68)Traffic Signal Materials3/202506006006006006006003,60003,600670
605680Countywide06006006006006006003,60003,600
69)Venetian Bridge Planning and Design1/20172,015004811,9001,15403,53505,550440,500,1090,
607640Venetian Causeway2,015004811,9001,15403,53505,5503771,3780
70)Capital Infrastr.Improv. on Causeway System3/20126935002002002002002001,50002,193440
603890Rickenbacker Cswy6935002002002002002001,50002,193
71)Improvements on Old Cutler Road from2/20135,4502,436000002,43607,8861116
603050SW 87 Ave to SW 97 Ave on Old Cutler Rd5,4502,436000002,43607,886
72)Road & Bridge Emerg.Bridge Rep/Impr/Paint.1/201702002002002002002001,20001,200670
607680Countywide02002002002002002001,20001,200
73)Rickenbacker C/Way Hobie N Side Barrier1/201800001501,85002,00002,000440
608560Rickenbacker Causeway00001501,85002,00002,000
74)Improv. on Ponce De Leon Blvd1/201700002,200002,20002,200500
604320Ponce De Leon Blvrd from Salamanca Ave-Antiquera Ave551,03054454427002,14502,200

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
75)Widen Caribbean Blvd:Coral Sea Rd.SW 87 Ave.2/20126,1885,000000005,000011,1881116
608480Caribean Blvd. From Coral Sea Rd. to SW 87 Ave.6,1885,000000005,000011,188
76)Causeway Bicycle Safety Projects1/20181,1871,0008029109209299385,49906,686440
603900Rickenbacker Cswy and Crandon Blvd1,1871,0008029109209299385,49906,686
77)Rights-of-way Acq. for constr.Of proj. in CD 123/20129,1092,000000002,000011,109500,821,
6010570Various Sites9,1092,000000002,000011,1091107,1116
78)East Venetian Bridge Electrical Repairs1/2012181182000001820363440
601680Venetian Cswy181182000001820363
79)Improvements to Cocoplum Circle1/20121851000000100195500
608730Lejeune Rd, Sunset Dr. Granada Blvd & Old Cutler Rd19500000000195
80)Improv. to Intersections in RIF D21/2016021214734745981301,97801,978500
604470Road Impact Fee District 2021214734745981301,97801,978
81)Improv. to Intersections in RIF D91/2016030718018018018001,02701,027500
6010670Road Impact Fee District 9030718018018018001,02701,027
82)Metrorail Bike Path (M-Path)1/201433296210600001,06801,40014, 1188
673150Existing Metrorail Guideway Right-of-Way700540160000070001,400
83)NW 107 Ave/NW122 St Flyover Ramp1/2012300683000006830983500
605952NW 107 Ave/NW 122 St98300000000983
84)Resurface Arterial St. - RIF D 21/2016021214734746081301,97901,979500
608100Road Impact Fee District 2021214734746081301,97901,979
85)Resurface Arterial St. - RIF D 91/2016030718018018018001,02701,027500
605570Road Impact Fee District 9030718018018018001,02701,027
86)South Miami Avenue Area Study1/201240100000010050500
604970City of Miami500000000050
87)Traffic Control Devices- Signalization RIF D 21/2016021214634645981401,97701,977500

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures RevenuesSix Year TotalsFuture YearsProject TotalsFunding Source
2012/132013/142014/152015/162016/172017/18
(In Thousands of Dollars)
609080Road Impact Fee District 2021214634645981401,97701,977
88)Traffic Control Devices- Signalization RIF D 93/2016030618018018018001,02601,026500
602330Road Impact Fee District 9030618018018018001,02601,026
89)West Avenue Bridge over the Collins CanalN/20147777623,95200004,71405,491350,500,
606880West Avenue4,2241,07419300001,26705,491821
90)Improv. to Coral Way and Anderson Rd.3/20170000020002000200500
607350Coral Way and Anderson Road0000020002000200
91)Improvements to Intersections in RIF D 11/20140000023402340234500
6050261Road Impact Fee District 10000023402340234
92)Improvements to Intersections in RIF D 31/2014000014026504050405500
606740Road Impact Fee District 3000014026504050405
93)Improvements to Intersections in RIF D 71/2014000017211502870287500
605870Road Impact Fee District 7000017211502870287
94)Improv.to NE 16 Ave.from NE 123 ST.-NE 135 St.1/201600003509003,1004,35004,350670
607530NE 16 Ave from NE 123 St to NE 135 St00003509003,1004,35004,350
95)Improv.to NE 2 Ave. rom NE 103 ST. -NE 115 St.1/20160000512005120512500
4530NE 2 ave from NE 103 St to Ne 115 St0000512005120512
96)Improv.to S Miami Ave.from SE 5 ST.-SE 15 Rd.1/201700090090090002,70002,700670
1640S Miami Ave from SE 5 St to SE 15 Rd00090090090002,70002,700
97)Intersect. Improv.at SW 122 Ave.and SW 104 St.1/20130171400001750175500
601800SW 122 Ave and SW 104 St0175000001750175
98)Intersect. Improv.at SW 127 Ave.and SW 72 St.1/20130150000001500150500
607420SW 127 Ave and SW 72 St0150000001500150
99)Intersect. Improv.at SW 137 Ave.and SW 72 St.1/20130400000004000400500
601230SW 137 Ave and SW 72 St0400000004000400

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
100)Intersect. Improv.at SW 147 Ave.and SW 72 St.1/20130300000003000300500
608710SW 147 Ave and SW 72 St0300000003000300
101)Resurface Arterial Streets - RIF D11/20140000026402640264500
6030081Road Impact Fee District 10000026402640264
102)Resurface Arterial Streets - RIF D31/2017000014026604060406500
603610Road Impact Fee District 3000014026604060406
103)Resurface Arterial Streets - RIF D71/2014000017211402860286500
608680Road Impact Fee District 7000017211402860286
104)Resurface Miami Ave. from N 87 St. to N 105 St.3/20160000550005500550500
608500North Miami ave from N 87 St to N 105 St0000550005500550
105)Resurf.at NE 12 Ave.from NE 125 St.-NE 135 St.1/20130135000001350135500
605940Ne 12 Ave from NE 125 St and NE 135 St0135000001350135
106)Resurf. at NE 16 Ave. near NE 131 St. (RXR)1/20130224000002240224500
606980NE 16 Ave near NE 131 St0224000002240224
107)Southcom Bridge Relocation2/20131757500000750250670
6057803511 NW 91 Ave1757500000750250
108)CDBG Infrastructure Improvements Countywide3/20130492000004920492190
606720Countywide0492000004920492
109)Const.SW 147 Ave.from SW 10 St.- SW 22 Ter.3/20132,3002,095000002,09504,395500, 670
604690SW 147 Ave from SW 10 St to SW 22 Terr2,3002,095000002,09504,395
110)Improv.On NE 2 Ave.from NE 20 St.- WLR Canal3/20137,19910,0004,127000014,127021,3261116, 1107
601110NE 2 Ave from NW 20 St to West Little River7,19910,0004,127000014,127021,326
111)QNIP Infrastr. Improv. in the Unincorporated areaN/201703,226000003,22603,2261087, 1131,
609630UMSA3,226000000003,2261184,1217

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
112)Rights-of-way Acq. for Con.Projects in CD 23/20121,0257000000070001,7251116
606990Commission District 21,0257000000070001,725
113)Rights-of-way Acq. for Con.Projects in CD 83/20133,87457581200001,38705,2611116, 1107
607930Commission District 83,87457581200001,38705,261
114)Rights-of-way Acq. for Con.Projects in CD 93/20123,8921,72555200002,27706,1691116, 1107
6010490Commission District 93,8921,72555200002,27706,169
115)Widen SW 152 St.from SW 157 Av.-SW 147 Av.1/2012150213005,700005,91306,0631116
605990SW 152 St from 157 Ave to SW 147 ave3632,0201,2001,2001,280005,70006,063
116)Illuminated Street SignsN/20135,4702900000029005,7601116, 1107
603970Various Sites5,4702900000029005,760
117)Traffic Control Devices- Signalization RIF D 11/20170000026502650265500
606460Road Impact Fee District 10000026502650265
118)Traffic Control Devices- Signalization RIF D 31/2017000014026504050405500
603120Road Impact Fee District 3000014026504050405
119)Traffic Control Devices- Signalization RIF D 71/2017000017311502880288500
601470Road Impact Fee District 7000017311502880288
120)Traffic Signal at Alton Rd. and 2 St.1/20131702400000240194500
605500Alton Rd and 2 St1702400000240194
121)Traffic Signal at Dickens Ave. and 72 St.1/201385120000012097500
604940Dickens Ave and 72 St85120000012097
122)Traffic Signal at Main Hwy and Commodore Plz1/201315160000001600175500
601020Main Hwy and Commodore Plaza15160000001600175
123)Traffic Signal at SW 112 Ave. and SW 236 St.1/20131752500000250200500
606330SW 112 Ave and 236 St1752500000250200
124)Traffic Signal at SW 37 Ave. and SW 17 St.1/20131802000000200200500

TABLE 10

TRAFFIC CIRCULATION

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
606520SW 37 Ave and SW 17 St1802000000200200
TOTALS215,505128,878130,64448,59441,74146,25226,831422,9408,733647,178
233,991121,806128,67948,73832,14846,25226,831404,4548,733647,178

* 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Public Works and Waste Management Department (PWWM) and Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

TABLE 10-A

TRAFFIC CIRCULATION Projects with Developer Responsibility to Construct or Cause to Construct

Project NumberProject Name and LocationPurpose* / Year of CompletionPrior YearsExpenditures Revenues (In Thousands of Dollars) 2018/192019/202020/20212021/20222022/20232023/2024Six Year TotalsFuture YearsProject TotalsFunding Source
1Widen Miami Gardens Drive 6 lanes from I-75 to NW 77 Ave (Including intersection improvements)2/2023 & 204019,200507.1
2Widen Miami Gardens Drive 6 to 8 lanes from NW 87 Ave to NW 82 Ave1 (Including intersection improvements)20404,800507.1
3AConstruct 4 lane Frontage Road from NW 180th St to ADM Delivery Entrance (Including intersection improvements)Feb-232,447507.1
3BConstruct 6 lane Frontage Road from ADM Delivery Entrance to I-75 Eastern Ramp (Including intersection improvements)Feb-234,727507.1
4Construct 4 lane NW 180th St from I-75 Off-ramp to Frontage Road (Including intersection improvements)Feb-234,763507.1
5Construct 6 lane NW 170th St from HEFT to NW 97 Ave (Including Intersection Improvements and potential Golden Glades canal relocation)Feb-408,583507.1
6Construct 6 lane NW 97th Ave from NW 170th St to NW 180th St (Including intersection improvements)Feb-234,120507.1
7Construct 4/6 lane NW 102nd Ave from NW 170th St to NW 180th St (Including intersection improvements)Feb-234,734507.1
8Construct 4 lane NW 176th St from NW 180th St to NW 102 Ave (Including intersection improvements)Feb-231,468507.1
9Widen NW 87th Ave to 6 lanes from NW 170th St to Miami Gardens Dr[^1, 2] (Including intersection improvements)Feb-234,491507.1
10New Interchange at HEFT and NW 170th StFeb-2360,000507.1
11New Partial Interchange at I-75 and NW 180th StFeb-2315,000507.1
12Interchange Modifications at I-75 and Miami Gardens Dr2Feb-2385,000507.1
13Okeechobee Road Intersection Improvements3Feb-23442507.1

* 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not Applicable

Source: Information provided by the applicant of the CDMP Amendment and reviewed by the County.

Notes; Details of Intersection improvements to be determined and/or addressed at the time of zoning through the development agreement.

Footnotes

  1. Appears to be constrained due to lack of sufficient right-of-way. In lieu of construction, other alternative mitigation may be considered per Developer Agreement.

  2. Includes improvements to I-75 at HEFT interchange.

  3. ADM Responsibility unless otherwise proven and approved at the time of platting.

TABLE 10-A (cont...)

TRAFFIC CIRCULATION Projects with Developer Responsibility to Construct or Cause to Construct

Project NumberProject Name and LocationPurpose* / Year of CompletionPrior YearsExpenditures Revenues 2018/192019/202020/20212021/20222022/20232023/2024Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
14Construction of 3-lane NW 170 St from NW 97 Ave to 102 Ave (including Intersection Improvements and potential Golden Glades canal relocation)2/2023 & 20402,251507.2
15Construction of 3-lane NW 170 St from NW 102 Ave to HEFT (including Intersection Improvements and potential Golden Glades canal relocation)20401,820507.2
16Construction of 4-lane 97 Ave from NW 170 St to NW 174 St (including Intersection Improvements)Feb-231,652507.2
17Construction of 4-lane NW 97 Ave from NW 174 St to NW 180 St (including Intersection Improvements)Feb-232,166507.2
18Construction of 2-lane NW 180 St from NW 97 Ave to western extent of Property (including Intersection Improvements)Feb-23966507.2
19Construction of 4-lane NW 102 Ave from NW 170 St to 180 St4,387507.2
  • 1=Existing Deficiency; 2=Future Growth;3=Combined/Other; N=Not Applicable

Source: Information provided by the applicant of the CDMP Amendment and reviewed by the County.

Notes; Details of Intersection improvements to be determined and/or addressed at the time of zoning through the development agreement. ¹ Appears to be constrained due to lack of sufficient right-of-way. In lieu of construction, other alternative mitigation may be considered per Developer Agreement.

TABLE 11

MASS TRANSIT

Expenditures
PriorRevenuesSix YearFutureProject
Purpose* /YearsTotalsYearsTotals
ProjectProject NameEstimated2012/132013/142014/152015/162016/172017/18Funding
Numberand LocationYear ofSource
Completion(In Thousands of Dollars)
1)Bus Enhancements3/2017022,14021,7401,9046802,8502,04051,354051,354
6730101Coutywide022,14021,7401,9046802,8502,04051,354051,354
2)Central Control Overhaul1/201414,54011,7400000011,740026,280
6733181111 NW 1st St.14,54011,7400000011,740026,280
3)Security & Safety EquipmentN/20186061,9385716006306616615,06105,667
6730551Countywide6061,9385716006306616615,06105,667
4)Rail Vehicle ReplacementN/201959,17625,88139,55275,986106,03356,510698304,66011,950375,786
6733001Countywide59,17625,88139,55275,986106,03356,510698304,66011,950375,786
5)ADA Improvements & Equipment3/20172522652782923073073071,75602,008
679510Countywide2522652782923073073071,75602,008
6)Passenger Amenities &Transit Enhanc/ents1/20175454754794844894944992,92003,465
6730531Countywide5454754794844894944992,92003,465
7)Facility and Equipment Rehabilitation3/20172522652782923073073071,75602,008
674190Countywide2522652782923073073071,75602,008
8)Fare Collection Equipment3/201359,1541,494000001,494060,648
6730051Countywide59,1541,494000001,494060,648
9)Capitalization of Preventative MaintenanceN/201774,33377,29878,07178,85179,64080,44281,240475,5420549,875
6634160Various75,59276,03978,07178,85179,64080,44281,240474,2830549,875
10)Earlington Heights (EH)/MIC Connector3/2013503,7762,753000002,7530506,529
6733210Earlington Heights Rail Station to MIA503,7762,753000002,7530506,529
11)NW 7 Ave & NW 62 St Passeng. Act. Center2/20147,6961,850300300149002,599010,295
6734671NW 7 Ave and 62 St7,6971,849300300149002,598010,295
12)Lehman Center Test Track for Metrorail1/20147,6147,9592,714000010,673018,287
6782206601 NW 72 Ave7,6147,9592,714000010,673018,287

TABLE 11

MASS TRANSIT

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
13)Palmetto Station Traction Power SubstationN/20139,3037,500000007,500016,803123, 1116
678280Countywide9,3037,500000007,500016,803
14)Earlington Heights (EH)/MIC Bus Plaza2/201330,47322100000221030,694125, 688,
6710190Earlington Heights Rail Station to MIA30,47322100000221030,694821
15)Mover Vehicle Replacement Ph. II (17 Cars)3/201337,33312900000129037,4621116
675590Various Sites37,33312900000129037,462
16)Park and Ride Lot Kendall Dr2/20133222,438000002,43802,760688, 821
6731191Kendall and SW 127 Ave3222,438000002,43802,7601116
17)Park and Ride Lot at SW 344 St3/20148,0732,6439100002,734010,807123, 821,
671610S-Miami Dade Busway & SW 344 St8,0712,6459100002,736010,8071116
18)Track & Guideway RehabilitationN/201625,2857,4305,9105,5491,5250020,414045,6991116
6710900Countywide25,2847,4305,9115,5491,5250020,415045,699
19)Bus and Bus Facilities3/20152,4081,7572,0021070003,86606,274125
6715603300 NW 32 Ave2,4081,7572,0021070003,86606,274
20)Busway ADA Improvements3/20138362,33264600002,97803,814123, 688,
672310SW 200th St & SW 88th St8362,33264600002,97803,814821, 1008
21)Graphics and Signage Upgrade3/20145,5121,450000001,45006,962123
678800Throughout Miami-Dade County5,5121,450000001,45006,962
22)Infrastructure Renewal Plan (IRP)1/201807,50012,50012,50012,50012,50012,50070,000070,0001116
677200Various Sites07,50012,50012,50012,50012,50012,50070,000070,000
23)Kendall Enhanced Bus Service3/20152,0232,5906781,3180004,58606,6091116
675550Kendall Dr2,0232,5906781,3180004,58606,609
24)Lehman Yard Rehab. & Expansion Ph. 13/20134,8196,4661,23200007,698012,5171116
6745606601 NW 72 Ave4,8196,4661,23200007,698012,517

TABLE 11

MASS TRANSIT

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
25)Metromover Bicentennial Park Station Ref.3/20131,8124880000048802,300123, 688,
6710860Bicentennial Park Station1,8124880000048802,3001116
26)Metromover Station Canopies & Escal. Repl.1/20136,7643860000038607,150123
672360Various6,7643860000038607,150
27)Transit Operations System (TOS) Repl. Proj.3/20146823,5341,98400005,51806,200123
671460111 NMW 1st St6823,5341,98400005,51806,200
28)Bus Tracker & AVLS Upgrade (CAD/AVL)3/20142,6008,3316,179000014,510017,1101116
672830111 NW First Street2,6008,3316,179000014,510017,110
29)Park & Ride Facility @ Quail Roost Dr.1/20132,3131561771,2230001,55603,869123, 507
671620SW 184th St & Busway2,3131561771,2230001,55603,869
30)Municipal Alloc. of ARRA Funding2/20148,9351,322000001,322010,257123
679870Various8,9351,322000001,322010,257
31)Mover Fiber Replacement3/20132,234524441000096503,199123
676250Various2,234524441000096503,199
32)Pedestrian Overpass @ University US 1N/20142,3173,0661,24500004,31106,628123, 821,
674220US 1 and Mariposa Ave.2,3173,0661,24500004,31106,6281116
33)Bus Replacement3/2018020,00020,00020,00020,00020,00020,000120,0000120,000908
673800Countywide020,00020,00020,00020,00020,00020,000120,0000120,000
34)Capital Expansion Reserve3/201829,3876,8464,8473,3561,97924553017,803047,1901116
675860Various Sites29,3876,8464,8473,3561,97924553017,803047,190
35)Northeast Transit Hub Enhancements3/20145621,3901,33200002,72203,284821, 1116
679230163rd Street Mall & Aventura Mall5621,3901,33200002,72203,284
36)Electronic Signage InfoSys (ESIS) & WIFI Impl2/20131,1562,6038800002,69103,847123, 688,
676590Various Sites1,1562,6038800002,69103,847821, 1008

TABLE 11

MASS TRANSIT

Expenditures
PriorRevenuesSix YearFutureProject
YearsTotalsYearsTotals
ProjectProject NamePurpose* /2012/132013/142014/152015/162016/172017/18Funding
Numberand LocationEstimatedSource
Year of
Completion(In Thousands of Dollars)
37)Fire Alarm Installation at Rail Stations3/20141,5001,500000001,50003,000
673050Various1,5001,500000001,50003,000
38)Mover Video Project3/20144881149600002100698
677520Various4881149600002100698
39)Kendall Dr SignalizationN/20142321,39269600002,08802,320
679060Dadeland North Metrorail Station2321,39269600002,08802,320
TOTALS915,313248,166204,127202,762224,239174,316118,7821,172,39211,9502,099,655
916,570246,908204,128202,762224,239174,316118,7821,171,13511,9502,099,655
  • 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Miami-Dade Transit (MDT) and Department of Regulatory and Economic Department (RER). Data provided by the Office of Management and Budget (OMB).

THIS PAGE INTENTIONALLY LEFT BLANK

TABLE 11-A

MASS TRANSIT Projects with Developer Responsibility to Construct or Cause to Construct

Project NumberProject Name and LocationPurpose* / Year of CompletionPrior Years2018/192019/20Expenditures Revenues 2020/20212021/20222022/20232023/2024Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
111 standard 40' buses for the extension and improvement of Metrobus Routes 54, 73, 95, 99 and 183 to the American Dream Mall (ADM) site12/20235,900507.1
2Metrobus Terminal/Transit Center within ADM with 10 bus bays made available to DTPW and 3 bus bays made available to Broward County Transit.12/202310,000507.1

Footnotes

  1. The specific details to be determined at the time of zoning through the development agreement. 2

TABLE 12

WATER FACILITIES

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
1)South M-D Water Trans. Mains Improv.3/20170005,9006,5001,100013,5004,50018,0001170,1171
9650021South Miami-Dade County0005,9006,5001,100013,5004,50018,000
2)Water T. Plant - Alexander Orr,Jr. Expansion3/20188,0896,69415,06025,30927,91413,5786,51595,070331,395434,554495,1170,
96500316800 S.W. 87 Ave.14,783015,06025,30927,91413,5786,51588,376331,395434,5541171,1266
3)Water T.Plant - Hialeah/Preston Improv.3/20172,7841002,30117,13927,06910,9901,62559,2249,97571,983495,1171,
9650041700 W. 2 Ave./1100 W. 2 Ave.2,88402,30117,13927,06910,9901,62559,1249,97571,9831170,1178
4)Wellfield Improvements3/201400500000050005001171
9650051Systemwide0050000005000500
5)Water Main - Extensions1/20172,2761,0001,0001,0001,0002,0001,5697,56909,845496
9651051Systemwide3,8451,0001,0001,0001,0001,0001,0006,00009,845
6)Central M-D Water Trans. Mains Improv.3/201910,5062,9190001,1212,6526,69216,08033,2781170,1171
9654041Central Miami-Dade County Area13,42500001,1212,6523,77316,08033,278
7)North M-D Water Trans. Main Improv.3/20172,5001,7756914,7382,8101,335011,349013,8491170,1171
9654031North Miami-Dade County Area4,27506914,7382,8101,33509,574013,849
8)W.T.P. Replacement & Renovations3/20188,9481,8741,7007,0776,7005,2493,24525,8453,04537,838495,1171
9650161Water Treatment Plants10,0517711,7007,0776,7005,2493,24524,7423,04537,838
9)Water System Maintenance & Upgrades3/201737,58718,49017,50020,00020,00020,00020,000115,990162,500316,077495,1171
9650181Systemwide46,5519,52617,50020,00020,00020,00020,000107,026162,500316,077
10)Water Distribution System Extension Enhanc.3/201912,4333,91511,69340,44930,99826,51841,807155,3801,528,0441,695,857495,952,
9653311Systemwide16,348011,69340,44930,99826,51841,807151,4651,528,0441,695,8571026,1170,
1171,1266
11)Water Equipment & VehiclesN/201718,3136,6777,5007,5007,5007,5007,00043,67755,000116,990495,1266
9650141Systemwide24,99007,5007,5007,5007,5007,00037,00055,000116,990
12)Water General Maintenance & Office FacilitiesN/201900011,30311,9604,8323,83331,92842,32974,2571171,1266
9650271Systemwide00011,30311,9604,8323,83331,92842,32974,257
13)Water System Fire Hydrant Installation1/201711,8964,8005,0005,0005,0005,0005,00029,800041,696403

TABLE 12

WATER FACILITIES

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
9653461Systemwide11,8964,8005,0005,0005,0005,0005,00029,800041,696
14) 9652001Water Engineering Studies SystemwideN/2014225 2250 025 250 00 00 00 025 250 0250 2501170,1171
15) 9654061Safe Drink Water Act Mod-SWT Rule&D-DBP Systemwide3/201914,249 20,3845,003 02,244 1,11276,965 76,96558,489 58,48944,642 44,642184,339 184,339371,682 365,547285,694 285,694671,625 671,6251171,1180
16) 9652821South Miami Heights W.T.P. & Wellfield 11800 SW 208 St.3/201636,867 53,97917,112 046,200 46,20043,801 43,8015,197 5,1970 00 0112,310 95,19863,600 63,600212,777 212,777403,520, 1170,1171, 1178,1266
17) 9656780Water Telemetering System Enhancements SystemwideN/20180 00 0433 433433 433433 433433 433433 4332,165 2,1650 02,165 2,1651171
18) 9610960W.T.P. Miscellaneous Upgrades Water Treatment Plants3/20196,312 7,9061,594 010,100 10,1004,796 4,7963,500 3,5002,500 2,5002,000 2,00024,490 22,8961,500 1,50032,302 32,3021170,1171, 1178
19) 963110Automation of Water Treatment Plants SystemwideN/2016929 1,529600 0750 750750 750550 5500 00 02,650 2,0500 03,579 3,579520,1170 1171
20) 96391087 Ave Water Main (Medley) - (GOB) Various3/2017640 6400 00 00 00 00 02,760 2,7602,760 2,7600 03,400 3,40011,13,14, 1188
21) 964520Florida Aquifer W.T.P. (Hialeah)-(GOB) Various3/20179,500 9,500500 5000 00 00 00 00 0500 5000 010,000 10,00011,1188
22) 964350Needs Assessments Projects -(GOB) Various (Water 80%)3/20184,682 4,788582 4763,499 3,4993,194 3,1941,031 1,0315,922 5,9215,738 5,73819,965 19,8580 024,646 24,64611,13,14, 1188
23) 965520NW 37 Ave Industrial Dev. Area -(GOB) NW 37th Ave and NW 36 St (Water 50%)3/2017312 312298 298500 5001,631 1,6312,370 2,3700 00 04,798 4,7980 05,110 5,11011,13,14, 1188
24) 969080NW Wellfield Land Buffer Acq. -(GOB) Various3/20182,708 2,7080 00 00 00 00 01,292 1,2921,292 1,2920 04,000 4,00011,13,14, 1188
25) 969830Perrine /Cutler Improv. -(GOB) Various (Water 30%)3/20173,529 3,5801,426 1,3750 00 00 01,241 1,2410 02,667 2,6160 06,196 6,19611,14,17, 1026,1188

TABLE 12

WATER FACILITIES

Project NumberProject Name and LocationPurpose* / Estimated Year of CompletionPrior YearsExpenditures Revenues 2012/132013/142014/152015/162016/172017/18Six Year TotalsFuture YearsProject TotalsFunding Source
(In Thousands of Dollars)
26) 966370System Enhancements -(GOB) Various (Water 50%)3/20192,206 2,20855 531,096 1,0960 00 04,615 4,615367 3676,131 6,1294,959 4,95913,296 13,2961026 11,14,17, 1188
27) 962830System Improvements Project -(GOB) Various (Water 50%)3/20183,452 3,4520 00 00 00 028,116 28,1169,533 9,53337,649 37,6490 041,101 41,10124,25 11,13,14,17, 1188
28) 967190Water Pipes & Infrastructure Projects Countywide1/201713,984 20,1192,141 01,000 01,000 01,994 00 00 06,135 00 020,119 20,119495
29) 965450Miami Springs Construction Fund - Water Miami Springs3/2017453 68750 050 050 050 034 00 0234 00 0687 6871219
30) 966620WaterTP - Floridian Reverse Osmosis 700 W 2nd Ave3/201825,381 46,17223,791 3,0004,775 4,7751,348 1,3487,383 7,3834,085 4,0856,099 6,09947,481 26,6900 072,862 72,862520,1267 1171
TOTALS240,760101,395133,617279,382228,448190,810305,8061,239,4582,508,6213,988,839
327,23721,798131,435278,332226,404189,775305,2371,152,9812,508,6213,988,839

* 1=Existing Deficiency; 2=Future Growth; 3=Combined/Other; N=Not-Applicable

Source: Miami-Dade Water and Sewer Department (WASD) and Department of Regulatory and Economic Resources (RER). Data provided by the Office of Management and Budget (OMB).

CAPITAL IMPROVEMENTS ELEMENT

LIST OF FUNDING SOURCES

CodeFederal Government
123FTA Section 5307/5309 Formula Grant
124Federal Aviation Administration
125FTA Section 5309 Discretionary Grant
142Army Corps of Engineers
150Federal Transportation Grant
190Comm. Dev. Block Grant
191CDBG Reimbursements
198FEMA Reimbursements
1026EPA Grant
1141US Department of Homeland Security
1145Transportation Security Administration Funds
1189Improvement Fund

 

Local Governments (Non-Miami-Dade County)

350Municipal Contribution
1106Private Donations

 

State of Florida

821Florida DOT Funds
834State Beach Erosion Control Funds
840Florida Boating Improvement Fund
842Recreation Development Assist. Prog.
885Florida Inland Navigational District
1082Florida Department of Environmental Protection
1083Florida Department of Economic Opportunity
1090FDOT - County Incentive Grant Program
1180Rock Mining Mitigation Fees

 

County Proprietary Operations

403Fire Hydrant Fund
406Aviation Passenger Facility Charge
440Causeway Toll Revenue
450Waste Disposal Operating Fund
451Waste Collection Operating Fund
470Biscayne Bay Envir. Trust Fund
490Wastewater Renewal Fund
495Water Renewal & Replacement Fund
497Wastewater Special Construction Fund

1177 HLD Special Construction Fund 1178 Water Construction Fund 3769 WASD Project Fund

Impact Fees/Exactions

500 Road Impact Fees 501 Park Impact Fees 507 Developer Fees/Donation 507.1 Developer Fees/Donation Responsibility/Construct or Cause to Construct - American Dream Miami (May 2016 CDMP Amendment Application No. 5) 507.2 Developer Fees/Donation Responsibility / Construct or Cause to Construct - May 2016 CDMP Amendment Application No. 6 Property Owners 520 Water Connection Charges 521 Wastewater Connection Charges

County Bonds/Debt

11 BBC GOB Series 2005A 13 BBC GOB Series 2008B 14 BBC GOB Series 2008B-1 17 BBC GOB Series 2010B 18-25 BBC GOB Future Series Base 908 Lease Financing – County Bonds/Debt 914 Wastewater Revenue Bonds Series 1997 917 Tenant Financing 927 Safe Neigh. Parks (SNP) Proceeds 951 State Revolving Loan Wastewater Program 952 State Revolving Loan Water Program 965 Future Solid Waste Disp. Notes/Bonds 1000 Seaport Bonds/Loans (County Bonds/Debt) 1027 Solid Waste System Rev. Bond 2001 (County Bonds/Debt) 1087 QNIP Phase II UMSA Bond Proceeds 1116 People's Transportation Plan Bond Program 1131 QNIP Phase IV UMSA Bond Proceeds 1140 Solid Waste System Revenue Bonds, Series 2005 1170 WASD Revenue Bonds Sold 1171 Future WASD Revenue Bonds 1184 QNIP Phase V UMSA Bond Proceeds 1187 Building Better Communities 2005 Series A GOB Bond 1188 Building Better Communities Future Series GOB Bond 1216 Building Better Communities GOB Interest 1217 QNIP Interest 1225 Capital Asset Series 2002 Bond Proceeds 1267 Hialeah Reverse Osmosis Plant Construction Fund 3763 Aviation Revenue Bonds 3764 Double – Barreled GO Bonds 3766 Capital Asset Series 2009A Bonds 3771 Capital Asset Series 2010 Bonds 3780 Sunshine State Financing

Other County Sources

620 Departmental Trust Funds 630 Stormwater Utility 640 Interest Earnings 650 Capital Outlay Reserve 660 Endangered Lands Voted Millage 670 Secondary Gas Tax 688 Capital Improvements Local Option Gas Tax 1008 Operating Revenue 1043 Future Financing 1107 Chapter County Transit System Surtax 1219 Miami Springs Water Construction Fund 1220 Miami Springs Wastewater Construction Fund 1266 WASD Future Funding 3782 1995 Sports Facility Bond Proceeds 3783 1995 Sports Facility Bond Interest 3784 Utility Service Fee

Monitoring Program

In order to enable the preparation of a periodic Evaluation and Appraisal of the comprehensive plan (EAR) as required by Section 163.3191, Florida Statutes (F.S.), which requires that local comprehensive plans must contain adopted procedures for monitoring and evaluating the Plan and its implementation. In addition, successful implementation of level of service standards, and requirements that services be available at the time of development, also require the establishment or enhancement of monitoring and reporting programs.

This section of the Element outlines the substantive aspects of Miami-Dade County's monitoring program pertinent to the objectives, policies and parameters referenced in this Element. It should be understood that the proposed programs or program improvements are continuously refined over time. Undoubtedly, by the time that the next Evaluation and Appraisal Report (EAR) is prepared, the measures and procedures outlined here may have been modified to reflect practical experience.

To successfully function in its central role in growth management, the CIE must be periodically evaluated and revised to meet changing conditions. With the capital planning process as outlined in previous sections in place, the monitoring and adjustment of the CIE is essentially automatic and ongoing.

In essence, the County's present Capital Budget and Multi-Year Capital Plan is the basis for the CIE. The annual preparation of the CIP/CIE includes those changes in cost, revenue sources, timing or other allowable modifications. Except under special circumstances, the CIE is amended only at the time of the CDMP biennial or other authorized amendment period. At that time and within that process, the following is accomplished:

  • Updating estimates and projections of growth indicators (population, housing, employment, land use, etc.)
  • Assessment of existing and projected service levels versus standards.
  • Status report on CIE projects (existing, programmed, planned), and assessment of capabilities.
  • Determine new or expanded facilities needs.
  • Review of fiscal conditions and preparation of updated analyses and forecasts.
  • Determine financial needs for unmet facilities and services.
  • Determine sources for additional financial support, modify standards to reduce financial obligation, or reduce growth potential.
  • Amend CIE as necessary.

A component of the monitoring program is a special review and assessment of the development status and plans for public school and health facilities. Attention is given to this aspect of capital improvements programming in order to determine if there are any unique potential impacts on public infrastructure. Problems should be minimal as Miami-Dade County agencies routinely use projections and other growth indicators which reflect these facilities in terms of location, employment, trip generation and other parameters.

Objective CIE-1

Objective CIE-1 will be evaluated through the use of information compiled in the annual CIE Summary Table.

Objective CIE-2

Objective CIE-2 will be monitored by checking development records of all areas within the coastal high hazard area.

Objective CIE-3

Concurrency records will be utilized to monitor and evaluate Objective CIE-3.

Objective CIE-4

For each CIE category, the dollar ratio of unfunded projects to the total of both funded and unfunded projects will be tracked and will serve to measure progress on Objective CIE-4.

Objective CIE-5

Objective CIE-5 is basically a regulation, which is controlled by certain processes. These processes consist of the master functional plans from operational departments, the CDMP amendments cycles, the Development Impact Committee reviews, and the preparation of the Capital Improvement Element. Future monitoring of this objective will continue to rely on results of these activities.