EISENHOWER WEST
SMALL AREA PLAN
Adopted December 12, 2015 - Ordinance No. 4980; Amended 4/13/19, Ord. 5219
Amended 12/16/2023, Ordinance 5514 Amended 5/18/2024, Ordinance 5537 Amended 1/25/2025, Ordinance 5569
SMITHGROUP JJR
⬚ figure
Adopted December 12, 2015 - Ordinance No. 4980; Amended 4/13/19, Ord. 5219
Amended 12/16/2023, Ordinance 5514 Amended 5/18/2024, Ordinance 5537 Amended 1/25/2025, Ordinance 5569
SMITHGROUP JJR
AMENDMENTS TO EISENHOWER WEST SMALL AREA PLAN - as of 1/25/2025
| Master Plan Amendment # | Ordinance # | Passage Date | Description/Address | Small Area Plan | Land Use Change |
|---|---|---|---|---|---|
| MPA2018-0006 | 5219 | 4/13/2019 | 880 and 890 S Pickett St, and 620 Burnside Pl | Eisenhower West | Amend Land Use map to allow self-storage on applicable parcel; Amend Neighborhood 1 Land Use diagram to allow self-storage on the applicable parcel; Revise definition of PWR uses on page 32 to exclude storage/warehouse uses |
| MPA2023-00005 | 5514 | 12/16/2023 | All Master Plan Chapters | 1. Amending the following sentence in the City's Master Plan wherever it occurs, as follows: "Areas of the city currently zoned residential should remain zoned for residential use at no higher than their current density." 2. References to low density will continue to refer to development configuration that limits overall building height and lot coverage compatible with the existing neighborhood. 3. Ensure race and social equity is "incorporated and centered in all planning" per City Council's Resolution 2974 including, but not limited to, all references to preserving and protecting neighborhoods and character. | |
| MPA2023-00007 | 5537 | 5/18/2024 | 701 S Van Dorn St and 698 Burnside Pl | Eisenhower West | Amend Figure 4.26 - Building heights diagram to change the height limit for the southern portion of the property from Medium-High to Medium |
| MPA2023-00004 | 5569 | 1/25/2025 | 4999 & 5001 Eisenhower Ave | Eisenhower West | Amend Figure 4.1 - land use from office/institutional to mixed use |
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Adopted November 14, 2015
Acknowledgements.........................................................................................................................5
Plan Overview................................................................................................................................7
1.1 Site and Context................................................................................................................10 1.2 Purpose of the Plan...........................................................................................................10 1.3 Economic Development....................................................................................................10
3.1 Small Area Plan Concept...................................................................................................21 3.2 Framework Plan................................................................................................................21
4.1 Land Use...........................................................................................................................26 4.2 Transportation and Connectivity......................................................................................34 4.3 Parks and Open Space......................................................................................................44 4.4 Urban Form and Building Character................................................................................51 4.5 Environmental Sustainability............................................................................................54 Summary of Plan-wide Elements...........................................................................................63
5.1 Neighborhood 1 - Van Dorn Innovation District...............................................................72 5.2 Neighborhood 2 - Backlick Run........................................................................................76 5.3 Neighborhood 3 - South Pickett.......................................................................................80 5.4 Neighborhood 4 - Van Dorn Metro Center......................................................................84 5.5 Neighborhood 5 - Bush Hill..............................................................................................88 5.6 Neighborhood 6 - Clermont Exchange.............................................................................92
6.1 Implementation Strategies................................................................................................98 6.2 Infrastructure Investments...............................................................................................102 6.3 Infrastructure Funding.....................................................................................................102 6.4 Incentives and Support.....................................................................................................102 6.5 Next Steps and Action Items............................................................................................102
For Appendices, please visit project website: www.alexandriava.gov/EisenhowerWest
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
CITY COUNCIL Mayor William D. Euille Vice Mayor Allison Silberberg John T. Chapman Timothy B. Lovain Redella S. Pepper Paul C. Smedberg Justin M. Wilson
PLANNING COMMISSION David Brown H. Stewart Dunn, Jr. Stephen Koenig Mindy Lyle Mary Lyman, Chair Nathan Macek Maria Wasowski
STEERING COMMITTEE Michael Adams, Community Representative Agnès Artemel, Business Representative Judy Coleman, Vice Chair, Park and Recreation Commission Jim Durham, Community Representative Mary Catherine Gibbs, Business Representative David Heiden, Business Representative Arthur Impastato, Community Representative Mindy Lyle, Chair, Planning Commission Member Tyler Orton, Environmental Policy Commission Charles Sumpter, Community Representative Maria Wasowski, Transportation Commission Ken Wire, Landowner Group Representative Don Buch, Former Community Representative
DEPARTMENT OF PLANNING AND ZONING Karl Moritz, Director Jeffrey Farner, Deputy Director Susan Eddy, Former Deputy Director Carrie Beach, Division Chief Radhika Mohan, Principal Planner and Project Manager Katherine Carraway, Urban Planner Brandi Collins, Urban Planner Nathan Imm, Urban Planner Ryan Price, Urban Planner Pat Mann, Urban Planner
DEPARTMENT OF TRANSPORTATION AND ENVIRONMENTAL SERVICES Yon Lambert, Director Sandra Marks, Former Deputy Director Carrie Sanders, Acting Deputy Director Steve Sindiong, Acting Division Chief William Skrabak, Deputy Director Jesse Maines, Watershed Management Planner
DEPARTMENT OF RECREATION, PARKS, AND CULTURAL ACTIVITIES Jim Spangler, Director Laura Durham, Open Space Coordinator Dana Wedeles, Planner
OFFICE OF HOUSING Helen McIlvaine, Acting Director Eric Keeler, Division Chief Tamara Jovovic, Housing Analyst
CITY MANAGER’S OFFICE Mark Jinks, City Manager Emily Baker, Deputy City Manager
CONSULTANT TEAM SmithGroupJJR Urban Design, Planning, Architecture, Sustainable Design, Community Engagement Merrill St. Leger Demian Valerie Berstene Don Posson Sven Shockey Kris Lucius Stacey Libra
HR&A Advisors Market Economics Caroline McCarthy Anthony Guma Kate Coburn Shuprotim Bhaumik Aaron Kurtz
Greening Urban Civil Engineering Chris Earley Nick Fudala Gary Woolsey
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
On May 29, 2013 the Alexandria City Council identified Eisenhower West as the area of a major planning effort to begin in 2014. The City’s Department of Planning and Zoning (P&Z) began the small area planning process in early 2014.
The purpose of the Eisenhower West Small Area Plan is to provide a framework to guide the development of the 620-acre plan area over the next 25 years. The Plan was developed through a community and stakeholder engagement process supported by analysis of major elements including urban design, land use, transportation, parks and open space, energy, environment, and market economics.
EISENHOWER WEST Small Area Plan | 7
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Eisenhower West Small Area Plan area consists of approximately 620 acres of land located in the southwestern corner of the City of Alexandria, Virginia, bordering Fairfax County (See Fig. 1.1). The plan area contains commercial, industrial and residential uses (Fig. 1.2) and is bounded by the Blue Line Metrorail and Amtrak rail tracks to the south (including the Van Dorn Metrorail Station); the Alexandria/Fairfax County border to the west, S. Pickett Street and Duke Street to the north, and Holmes Run and Cameron Run to the east. The plan area is bisected by Backlick Run, the Norfolk-Southern railway lines, and contains several large parks and four residential developments (See Fig. 1.3). See Appendix for more information.
The purpose of the Eisenhower West Small Area Plan is to provide a framework to guide the development of the plan area over the next 25 years. The Plan was developed through a community and stakeholder engagement process supported by analysis of major elements including urban design, land use, transportation, parks and open space, energy, environment, and market economics.
With the exception of Cameron Station, local parks, and Backlick Run, the Eisenhower West plan area lacks a strong character, sense of place, or cohesive identity. The area consists mostly of an eclectic mix of large footprint, low-rise, light-industrial or warehouse buildings; islands of residential development; some heavy industrial uses, and surface parking (See Fig. 1.4). The culturally, economically, and generationally diverse community in and around the area came together to help define a future character for the area through the Small Area Plan.
The market analysis of the Eisenhower West plan area provides a baseline assessment of current and projected market conditions in order to inform the development of the Small Area Plan, and considers:
⬚ figure
Fig 1.1 - Location map
⬚ figure
Fig 1.2 - Existing zoning diagram
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 1.3 - Eisenhower West Existing Site Plan
EISENHOWER WEST Small Area Plan | 11
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Eisenhower West Demographics
Fig. 1.4 - Eisenhower West Plan Area
RESIDENTIAL
RETAIL
OFFICE
HOTEL
INDUSTRIAL
SHORT TERM (0-7 YEARS)
MEDIUM TERM (7-15 YEARS)
LONG TERM (15-30 YEARS)
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 2.1 - Eisenhower West Vision graphic
The goals for Eisenhower West focus on creating a vibrant, sustainable, connected, transit-oriented community that contributes to the City’s economic development goals while providing opportunities for living, working, learning, and recreating.
⬚ figure
Eisenhower West will be an integral part of the City’s Eisenhower Valley economic engine in which economic development and employment opportunities are maintained and promoted by capitalizing on the Van Dorn Metrorail Station, proximity to the Capital Beltway, and the opportunity provided by the presence of large land holdings.
Eisenhower West will have a vibrant mix of uses achieved through phased implementation, including a mix of residential and employment opportunities, and the new mix of uses are able to co-exist with industrial uses remaining in the area long term.
Eisenhower West will be a transit-oriented community, with density focused around transit nodes and corridors.
⬚ figure
Eisenhower West will have safe, efficient, and linked pedestrian, bicycle, transit, and vehicular mobility thereby providing better access locally and citywide to the future amenities of the area.
Eisenhower West will be pedestrian-friendly by humanizing Van Dorn Street, S. Pickett Street, and Eisenhower Avenue so that they become safer for pedestrians and more attractive to residents and shoppers.
Eisenhower West will have a connected, accessible, and identifiable park and open space system that serves local and citywide recreational needs.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 3.1 - Concept Diagram
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Eisenhower West Small Area Plan is a development framework to guide the long term redevelopment of the plan area. This Plan was developed through a community-based process which began with the identification of nodes, connections and green connections.
The Plan is intended to transform what is now mostly large, disconnected parcels with low density single-use predominantly light industrial, office and warehouse buildings into a mixed-use, higher density, green, sustainable, connected place. People will be able to walk, bike, take transit or drive to homes, workplaces, shops, restaurants, parks and recreational opportunities. (See Fig. 3.1.)
The Plan recommends incorporation of the following as part of redevelopment:
Nodes are public spaces which encourage activity. Nodes can be public plazas around which mixed uses are located. They offer opportunities to hold activities such as festivals, farmers markets, as well as seating for restaurants and cafés. Other nodes include important parks and green spaces which bring people together for passive recreation and activities.
Several nodes of activity currently exist within the plan area. These include the existing parks, Armistead Boothe, Ben Brenman, and Hensley, and the mixed use neighborhood retail/residential along Brenman Park Drive in Cameron Station. A future node of activity is anticipated north of the plan area, as part of the Landmark Van Dorn Corridor Plan. Future nodes in the plan area identified through the planning process will serve different parts of the neighborhood. These include:
⬚ figure
Mixed-use node, Reston, VA
⬚ figure
Green node, Hensley Park, Alexandria, VA
⬚ figure
Green node, Portland, OR
⬚ figure
Mixed-use node and farmers market, Alexandria, VA
EISENHOWER WEST Small Area Plan | 21
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Small Area Plan establishes a new connected, walkable, pedestrian-scale network of streets and blocks that supports driving, transit, bicycling, and walking within the Plan area, to adjacent neighborhoods, and to the Van Dorn Metrorail Station. The new street grid builds on existing primary streets and creates better connectivity and more choices for local mobility. The urban street grid will be created over time as properties are redeveloped.
⬚ figure
Pedestrian-friendly street, Alexandria, VA
⬚ figure
Pedestrian and bicycle facilities, Portland, OR
⬚ figure
Pedestrian-friendly street, Portland, OR
⬚ figure
Transit, Alexandria, VA
In addition to connections, the Plan integrates green connections, knitting the existing parks with new parks and open spaces. This will be accomplished through the revitalization of Backlick Run, the introduction of new park spaces in each neighborhood, new trails, green streets, and green connections that serve to increase tree cover and vegetation throughout the plan area while contributing to stormwater management through green and low-impact strategies.
⬚ figure
Pedestrian/bike trail, Alexandria, VA
⬚ figure
Neighborhood Park, Portland, OR
⬚ figure
Green connection, O Street Market, Washington DC
⬚ figure
Tree lined street, Portland, OR
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Small Area Plan - Illustrative Plan Redevelopment is expected to take place over a timeframe of 25-30 years, depending on market conditions and funding for infrastructure improvements. The illustrative plan shows one potential way in which the plan area could redevelop. The Plan does not require building locations, footprints, parks and open spaces to be designed or developed as shown, so long as the vision for redevelopment expressed by the community, the principles contained in this document, and the City of Alexandria’s standards for redevelopment are met.
⬚ figure
Artist's rendering of the Backlick Run greenway Fig. 3.2 - Illustrative Plan
Artist's rendering looking west along Eisenhower Avenue
Artist's rendering of Eisenhower West future redevelopment
EISENHOWER WEST Small Area Plan | 23
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
SMALL AREA PLAN
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
The Eisenhower West Small Area Plan envisions a series of distinctive neighborhoods with a rich mix of uses that allow residents, employees, and visitors to live, work, shop, play, learn, and recreate in a cohesive and sustainable environment. While the predominant land use is residential, a high-density mix of predominantly office and retail is envisioned for the area around and near the Van Dorn Metrorail Station. Lower density mixed use is envisioned for other neighborhoods in the plan area.
PLAN AREA LAND USES
Amended 4/13/19, Ord. 5219 Amended 1/25/25, Ord. 5569
⬚ figure
Ord. 5219 Allow self-storage use
Ord. 5569 Allow Mixed Use
Fig. 4.1 - Land use
Note: The Plan depicts general land uses for each area. The specific land use requirements will be addressed in the future rezoning.
EISENHOWER WEST Small Area Plan | 27
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Commercial includes office, hotel, and institutional uses. Institutional uses include medical, educational, and arts facilities.
⬚ figure
Medium rise office building, Alexandria, VA
⬚ figure
Urban hotel proposal, Washington DC
⬚ figure
High-rise office building, Arlington, VA
⬚ figure
Low-rise office/institutional building, Alexandria, VA
Retail uses include neighborhood shops, large format (or “big box”) stores, grocery stores, restaurants and cafés.
⬚ figure
Neighborhood retail, King Street, Alexandria, VA
⬚ figure
Multi-story urban big box retail, Mosaic District, Fairfax, VA
⬚ figure
Mixed use with retail at the ground level, Reston, VA
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 4.2 - Required and recommended retail frontages
Note: Retail frontages shown as required, in this diagram, will be required as part of redevelopment. Retail frontages shown as recommended, in this diagram, are strongly encouraged. The specific uses and requirements will be established as part of the future rezoning.
Residential uses include townhome, mutifamily residential buildings, and senior living facilities.
The growing unmet demand for affordable housing - caused by stagnant wages, rising rents (resulting in the loss of market-affordable units), and the decline in federal and state housing funding - poses potential critical challenges to the city’s livability, economic competitiveness, social service network, and transportation system. Less than one fifth of the Landmark/Van Dorn area’s rental housing stock is currently affordable to residents earning up to 60% of the Area Median Income determined by the federal Department of Housing and Urban Development to be $45,900 for a one-person and $65,520 for a four-person household in 2015.
Consistent with the City’s Housing Master Plan (2013) recommendation to focus affordable housing efforts in areas with the greatest potential for increased density and mixed-use development - in particular the Eisenhower Valley and Landmark/Van Dorn areas - this plan area will include a range of high-quality housing options that are affordable and accessible to households of different income levels, ages, abilities, and sizes and offer convenient access to transportation and services.
| Area | Market Affordable Units as a percent of total assisted units and rental units in buildings with 10 or more units | Assisted Affordable Units as a percent of total assisted units and rental units in buildings with 10 or more units | Number of affordable ownership units with current resale restrictions |
|---|---|---|---|
| Landmark/Van Dorn Area | 7% | 13% (including ARHA properties) | 61 |
| Eisenhower West Small Area Plan | 0% | 0% | 7 (The Residences at Cameron Station) |
Source: Office of Housing, 2015 The affordable housing inventory in Eisenhower West is extremely limited. The area has no assisted or market affordable rental units—units that are affordable due to their age, location, and amenities—and only seven affordable ownership units.
⬚ figure
In 2007, seven affordable set-aside condominium units were delivered at the Residences at Cameron Station. The one and two-bedroom units—pledged by the developer through the City’s voluntary contribution policy for affordable housing—are indistinguishable from their market-rate neighbors within the building. The units have long-term affordability restrictions that ensure they can only be resold to other low- or moderate-income homebuyers at discounted prices for a period of 30 years.
⬚ figure
The Station at Potomac Yard—a mixed-use project combining a state-of-the-art fire station, ground-floor retail, and 64 affordable and workforce rental units—is the product of an innovative collaboration between the City, the Alexandria Housing Development Corporation, and national home builder, Pulte Homes. This creative public-private-nonprofit partnership succeeded in constructing the first new city fire station in more than 30 years and generating affordable housing while leveraging more than $11 for every $1 of city funding.
⬚ figure
Completed by the Arlington Partnership for Affordable Housing (APAH) in 2014, Arlington Mill Residences is the first new affordable housing development of the Columbia Pike corridor revitalization effort and has dramatically increased housing for low-income households in the County; the 122-unit complex includes 98 two- and three-bedroom units to support larger families and 13 units designated for formerly homeless individuals and families. By co-locating the Residences with the Arlington Mill Community and Senior Center on public land with a shared underground garage and shared infrastructure costs, the project creatively leveraged public funding and saved nearly $9 million.
Community facilities include a school and recreation center that is an identified need, and is compatible with adjacent plan area goals, including the Landmark/Van Dorn Corridor Plan. The City of Alexandria Recreation, Parks & Cultural Activities Strategic Master Plan prioritizes recreation programming space that supports a multi-generational indoor recreation center and specifically proposes one additional neighborhood center in the western portion of the City, where density levels are high. The Landmark/Van Dorn Corridor Plan called for one in that area. The Citywide Parks Improvement Plan identifies Ben Brenman Park as a location for a multigenerational center. A neighborhood recreation center could be co-located with a school or even be located in an office building, particularly in one of the areas designated for institutional use. More work will be needed to identify the location for this recreation center somewhere in the West End.
⬚ figure
⬚ figure
⬚ figure
The 2015 Long Range Educational Facilities Plan (LREFP), developed in a joint effort between Alexandria City Public Schools and the City of Alexandria, offers a range of options for providing educational facilities in Alexandria that meet the needs of increasing enrollment and that accommodate 21st century learning environments. In the Eisenhower West planning area, the LREFP recommends reserving a new elementary school site and considering a second in or near the plan area if growth continues to increase. Enrollment projections in the LREFP coupled with student generation projections for the Eisenhower West plan area support this recommendation. The LREFP also suggests considering co-locating new schools in a mixed-use building or retrofitting an existing commercial building.
Program
Size and Outdoor Space
Location and Circulation
Production, Wholesale, Repair (PWR) is a term that covers a wide variety of businesses that are traditionally located in light-industrial or warehouse-type spaces because of the low cost of leasing compared with prominent retail locations. These businesses are an important source of employment and include light industrial uses, spaces for start-up companies, technology companies, innovation and “maker” businesses. Examples also include pet services, catering/food services, sports facilities, and contractor offices. These businesses sometimes have a showroom or retail component.
⬚ figure
⬚ figure
The Eisenhower West Small Area Plan contains four heavy industrial uses, some of which have potential conflicts with nearby residential and school uses. The 2009 City of Alexandria Industrial Use Study explored the costs and benefits of redevelopment for those uses (Vulcan Materials, Virginia Paving, Covanta Energy from Waste, and Norfolk Southern Railroad and Transloading Facility). The study sites, primarily located around the intersection of South Van Dorn Street and Eisenhower Avenue, are part of a larger industrial corridor along Eisenhower Avenue to the east and Farrington Avenue to the west. Other industrial uses along the corridor are generally lighter industrial, such as warehouse and flex space, with considerably less potential impact on the redevelopment of nearby parcels.
Vulcan Materials Vulcan Materials, an aggregate material producer, has been operating under an amended 1996 Special Use Permit (SUP). In 2013, the owners of Vulcan Materials were signatories on a letter to the City urging action on the Eisenhower West SAP, and the company has since decreased its active operations. The Vulcan property should be redeveloped as a residential and mixed use area under the SAP recommendations.
Virginia Paving The asphalt plant at 5601 Courtney Ave has been in operation since April 1960. Virginia Paving took over the plant in 2001, and applied for a new SUP (#2005-0042) in 2005, which was subsequently amended in 2010. According to the SUP condition #75, if City Council determines that Virginia Paving’s operations are inconsistent with the Eisenhower West SAP, the company must cease operations no sooner than seven years after SAP adoption and no longer than the applicable amortization period (Zoning Ordinance Section 12-214). While currently an important source of asphalt for the City of Alexandria, a site so close to a Metrorail station should be redeveloped in the future into a more compatible use.
Covanta Energy from Waste The Covanta facility has been operating since 1988, under a 1998 Special Use Permit, and with $45 million in air pollution controls in 2001. Redevelopment of the Covanta site is not foreseen for this Plan because of existing contractual commitments to Covanta, joint decision making with Arlington County, significant public investment in the operation, the lack of attractive alternatives to the City’s waste disposal needs, and the facility’s compatibility with the City’s sustainability objectives. The current City agreement with Covanta will keep the facility in place until 2038. Activities associated with operating the plant, including truck traffic, need to be taken into account when planning for the future.
Norfolk Southern Railroad Ethanol Transloading Facility The Van Dorn Railyard has been in operation for over 100 years. However, the Norfolk Southern Transloading Facility began operation in April 2008. It does not require a special use permit, and its facility and truck operations are exempt from City regulations. The City is holding ongoing meetings with Norfolk Southern regarding proposed capacity expansion and enhancements for the site, as well as the proposed multimodal bridge over their property.
Redevelopment could bring long term financial benefits to the City with more mixed-use, pedestrian and transit-oriented development of the sites and better utilization of the Van Dorn Metrorail station. New development must be sensitive to required remediation and environmental analyses, floodplain restrictions, and the existing topography to help situate service areas. More guidance can be provided at a later time through the Development Special Use Permit (DSUP) and SUP permitting processes as sites are ready to redevelop.
Issues and Opportunities:
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 4.3 - Key plan of existing heavy industrial uses in Eisenhower West
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Artist's rendering looking west along Eisenhower Avenue
The Plan implements improved multimodal connectivity throughout the Eisenhower West plan area and adjoining neighborhoods. The City conducted a transportation study for an area encompassing, but larger than, the Eisenhower West plan area. The Transportation Study assessed the transportation implications of future development in the area and the potential location, alignment, and impact of a new multimodal bridge between Eisenhower Avenue and South Pickett Street. The bridge would provide additional multimodal connectivity between Eisenhower Avenue and the Van Dorn Metrorail station to the south and roadways and neighborhoods to the north. Outreach was conducted with all of the affected property owners, including the Norfolk Southern Railroad. During this outreach process, the City learned that the bridge alignment options could affect the railroad's long term plan for expanding its Thoroughbred Bulk Transfer Facility. The City will continue to work with Norfolk Southern, and will conduct additional engineering analyses to help determine a preferred bridge alignment.
The new grid of complete streets and blocks accommodates multiple modes of transportation, building on existing primary streets and providing improved mobility. Eisenhower Avenue is an important existing primary street, traversing much of the City of Alexandria east to west. The Plan envisions Eisenhower Avenue as a "Great Street" - an inviting multimodal complete street that accommodates pedestrians, cars, a raised cycletrack for bicycles, and transit. It will have activating land uses and streetscape that create a desirable street with an attractive and comfortable pedestrian environment. The curve at the western end of Eisenhower Avenue is proposed to be straightened to create a new mixed-use destination around a redeveloped Van Dorn Metrorail Station. The new multimodal bridge will connect the Landmark-Van Dorn area north of the Norfolk Southern tracks to the Van Dorn Metrorail Station. In addition, a new street connection between Farrington Avenue and Edsall Road will provide additional north-south connectivity. Other existing streets will be enhanced to create a more inviting pedestrian environment.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The future street grid in Eisenhower West will consist of existing and new streets, implemented as development occurs. This section identifies streets that are existing, required, and recommended. It describes the street hierarchy, improvements to existing streets, and expectations for new streets.
The network of streets and blocks in Eisenhower West will be created over time as new development and redevelopment takes place. The grid will connect to and build on existing streets.
Eisenhower West will have streets of varying importance. Fig. 4.5 shows the hierarchy of the future street grid for Eisenhower West. The City has a strong preference for all new streets to be public streets. The City will consider private streets if the property owner demonstrates a need for parking under sidewalks or streets based on site constraints, topography, or block size, during the development review process.
PLAN AREA STREETS
⬚ figure
Fig. 4.4 - Required and recommended streets (Exact alignment of Farrington-Edsall connector through Fairfax County to be further defined)
| Streets - Required & Recommended | |
|---|---|
| Existing | |
| Multi-Modal Bridge Options | |
| Farrington Bridge | |
| Planned - Required | |
| Planned - Recommended | |
| Pedestrian Connection Only |
EISENHOWER WEST Small Area Plan | 35
"A" streets are the existing primary streets that traverse the plan area and provide major vehicular, transit, pedestrian, and bicycle access and mobility. They include Eisenhower Avenue, Van Dorn Street, and South Pickett Street. These existing streets will be improved to enhance mobility options and to become important addresses for future development.
See Figures 4.6, 4.7 and 4.8 for cross sections showing improvements to Eisenhower Avenue, Van Dorn Street and South Pickett Street.
Eisenhower Avenue Eisenhower Avenue becomes a "Great Street" that includes new mixed use development, and accommodates pedestrian activity, bicycling, transit, and driving. See Fig. 4.6 for the Eisenhower Avenue cross section within the plan area.
Straightening of Eisenhower Avenue A portion of Eisenhower Avenue between the Covanta facility and Metro Road is proposed to be straightened. This new alignment will create an important terminus at a new mixed-use node centered on the Van Dorn Metrorail Station. It would
⬚ figure
Fig. 4.5 - Street hierarchy
be constructed in conjunction with redevelopment of the WMATA property and adjacent sites. It offers the opportunity to consolidate Metro’s facilities which are currently bisected by Eisenhower Avenue, while clarifying wayfinding and access to the station. (See Figures 4.15 and 4.16.)
The Eisenhower West Small Area Plan builds on the Landmark Van Dorn Corridor Plan’s vision for a redesigned Van Dorn Street, reconstructed as an attractive green boulevard with dedicated transit lanes for the West End Transitway and new pedestrian and bicycle facilities. The Plan recommends improvements to Van Dorn Street along its southernmost stretch. See Fig. 4.7 for the Van Dorn Street cross section.
Van Dorn Street is critical to providing access to the West End Transitway, and Van Dorn Metrorail Station. Currently, the pedestrian realm along Van Dorn Street is very uninviting, especially as it bridges across Backlick Run and the railroad right-of-way. In that location, sidewalks are in disrepair or missing entirely, discouraging people from walking to the Metrorail Station. WMATA conducted a Pedestrian and Bicycle Station Access Study for this station. Recommendations from that study to improve connectivity and access to the station should be implemented in the interim before redevelopment of the station.
⬚ figure
Fig. 4.6 - Cross section showing improvements to Eisenhower Avenue - “A” street
South Pickett Street is an important existing connector from Duke Street through Eisenhower West to Fairfax County. The Plan requires enhancements to South Pickett Street to become a complete street that accommodates pedestrians, bicycles, and cars. See Fig. 4.8 for the South Pickett Street Cross Section.
“B” Streets will be new secondary streets in Eisenhower West. Where these streets serve nodes of mixed use development, they are active, vibrant streets with shops, restaurants and cafés with outdoor seating at the ground level, as well as public spaces and plazas. These streets will include tree-lined sidewalks, high-quality streetscape, paving, furnishings, lighting, and landscape. See Figure 4.9 and 4.10 for the typical cross section.
⬚ figure
Fig. 4.7 - Cross section showing improvements to Van Dorn Street - “A” street
These streets are located in mixed-use and residential areas within Eisenhower West. They will be pleasant places to walk and will include tree-lined sidewalks, high-quality streetscape, paving, furnishings, lighting, and landscape. See Figures 4.11 and 4.12 for the typical cross section.
⬚ figure
Fig. 4.8 - Cross section showing improvements to South Pickett Street - “A” street
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 4.9 - Cross section through typical "B" street with bike lanes
⬚ figure
Fig. 4.10 - Cross section through typical "B" street without bike lanes
⬚ figure
Fig. 4.11 - Cross section through typical "C" street with bike lanes and green connections
⬚ figure
Fig. 4.12 - Cross section through typical "C" street without bike lanes or green connections
⬚ figure
Fig. 4.13 - Cross section through typical "P" street with park frontage
⬚ figure
Fig. 4.14 - Cross section through typical "P" street with railway frontage
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
"P" Streets "P" streets, are typically one-sided streets, with buildings on one side, and either a park or vegetated buffer to a railway on the other side. P streets that front parks or significant green spaces include those along Backlick Run, the Clermont Natural Park and the forested areas to its west. These streets may include a cycle track. P streets that front railways include those along the Norfolk-Southern, WMATA, and CSX rights-of-way. (See Figure 4.14.)
Other Street Improvements Straightening of Farrington Avenue Straighten Farrington Avenue between Van Dorn Street and the City of Alexandria/Fairfax County line to provide additional connections within and adjacent to the plan area. Planning and analysis to determine the feasibility and preferred alignment will require further collaboration with Fairfax County and the Virginia Department of Transportation.
Farrington-Edsall Connector In order to provide additional north-south connectivity and mobility on the west side of the plan area, a new street connecting Farrington Avenue with Edsall Road is recommended. The street would bridge the Norfolk-Southern railroad right-of-way and Backlick Run, providing new access to areas along the City of Alexandria/Fairfax County border, and discouraging cut through traffic through local neighborhoods. This street will be developed in two phases. 1) Farrington Avenue to South Pickett Street, and 2) South Pickett Street to Edsall Road. To avoid existing uses that are not proposed for redevelopment, the street would need to be built as two different components along the city’s western boundary with Fairfax County.
The street will include adequate facilities for pedestrians and bicyclists. The Plan depicts one potential location. The ultimate design, alignment, and location of the Connector will be determined in future design and planning efforts, as well as in coordination with Fairfax County and Norfolk Southern.
Blocks Eisenhower West’s network of streets and blocks will enable the development of compact, walkable neighborhoods. Block size and design are primary components that will enable a successful walkable community. Long blocks with uninteresting or non-existent streetscape discourage walking while small blocks with a variety of buildings, vegetation, high quality streetscape and interesting things to look at encourage walking. Fig. 4.17 illustrates a general pattern of blocks for the Eisenhower West that works in conjunction with the street hierarchy described above.
As redevelopment matures, transit will be enhanced throughout the plan area. New transit stops will be provided along all primary streets and at appropriate locations as needed along secondary streets. Enhanced transit, particularly as recommended along Eisenhower Avenue, could also include greater passenger capacity, including larger buses and more frequent service and greater reliability in service, including improved shelters, real-time information, and on-time service through signal priority and off-board fare collection. Refer to the Eisenhower West Transportation Study for details. (See Fig. 4.19.)
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The plan envisions a multimodal bridge to connect the Van Dorn Metrorail Station to South Pickett Street, as initially recommended in the Landmark Van Dorn Corridor Plan (2009). The bridge will serve as a future alignment for the West End Transitway, providing dedicated transit lanes between the station and South Pickett Street, and connecting buses to South Van Dorn Street. In addition, the bridge will include ample width for pedestrians and bicycles, improving multimodal connectivity between the station and existing and future development areas to the north. The construction of the bridge is necessary to support the full build out of land use as proposed in this plan.
The bridge should accommodate two general purpose lanes (one lane each direction), two transit lanes (one lane each direction), a separated cycle track, and sidewalks on both sides. During the small area planning process, a number of alignment options for the bridge were studied (See Figure 4.18):
⬚ figure
PLAN AREA BLOCKS
⬚ figure
Fig. 4.17 - Blocks
Note: Blocks depicted are for illustrative purposes. The actual block configuration will be based on the plan and all future requirements.
MULTIMODAL BRIDGE OPTIONS
⬚ figure
Fig. 4.18 - Multimodal bridge options
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Option 3a – From Eisenhower Avenue east of the Covanta Energy facility to the western edge of the Armistead Boothe park using the existing right-of-way set aide, and ending on the north side at South Pickett Street just west of Cameron Station Boulevard. Should this option be selected, the Alexandria Police Firing Range at 5261 Eisenhower Avenue will need to be relocated. Site acquisition and construction of a similar facility is estimated to be $15.2 million in 2015 dollars (excluding operating costs and demo/remediation of the existing site).
Option 3b – Similar to Option 3a but ends further east, at the Cameron Station Boulevard / Edsall Road intersection (similar to Option 2b). During the planning process, the alignment options went through an evaluation process to help inform the decision on the preferred alignment for the multimodal bridge. All of the bridge options will have some impact to various properties. Outreach was conducted with all of the affected property owners, including the Norfolk Southern railroad. During this outreach process, the City learned that the bridge alignment options could affect the railroad’s long term plan for expanding its Thoroughbred Bulk Transfer facility. The City will continue to work with Norfolk Southern and impacted property owners, and will conduct additional detailed engineering to help determine a preferred bridge alignment. The Eisenhower West Small Area Plan does not identify a specific preferred alignment, and all alignment options, as well as other potential solutions will be analyzed as part of the implementation of the plan in coordination with Norfolk Southern and impacted property owners. If the multimodal bridge cannot be constructed due to impacts to Norfolk Southern, Van Dorn Street between Eisenhower Avenue and South Pickett Street would need to be widened in order to accommodate the West End Transitway, wider sidewalks, and bicycle facilities.
⬚ figure
As development occurs, Eisenhower West will benefit from increased bicycling opportunities. Enhanced bicycle corridors, trails, and Capital Bikeshare stations will be implemented over time. See Figure 4.20 for locations of bicycling facilities.
EISENHOWER WEST Small Area Plan | 41
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The gradual redevelopment of Eisenhower West will include enhanced facilities to encourage pedestrian activity. Figure 4.21 shows the future pedestrian network. Components include:
Primary Sidewalks - These sidewalks are located in high-pedestrian activity areas including mixed-use nodes and developments.
Secondary Sidewalks - These sidewalks are located in low-pedestrian activity areas including residential portions of the Eisenhower West.
Multi-use Off-Street Trails - Also referred to as shared-use paths, these trails are usually paved and should be a minimum of 10-feet wide. Path widths of 12, 14, and even 16 feet are appropriate in high-use urban situations and areas with a significant mix of pedestrian and bicycle traffic.
Unpaved Off-street Trails - These paths provide places for walkers, hikers, runners and bicyclists to mix and explore. Sufficient width and surface quality must be maintained on these pathways.
Guidelines for Pedestrian Environment include:
⬚ figure
Fig. 4.20 - Bicycle facilities
⬚ figure
Fig. 4.21 - Pedestrian network
A comprehensive transportation study was undertaken in the development of the Eisenhower West Small Area Plan to examine the transportation impacts within the defined plan area, as well as the surrounding area. The transportation study extended well beyond the Plan boundaries and included approximately 86 intersections (in the Build Scenarios) that were studied during both the AM and PM peak hours.
The transportation analysis performed for the Plan is a planning level study that evaluates the impacts associated with the Plan. The study assumed a 25 year buildout period (year 2040) and assumes changes in regional traffic patterns over that period. All future redevelopment applications associated with the Plan will require additional traffic studies to analyze specific plans for each site and will include additional transportation data available at that time and more refined development information. The studies will also update the traffic impacts associated with the specific development and refine the recommended improvements to transportation.
The proposed redevelopment within the plan area assumed a horizon year of 2040 for purposes of the transportation analysis. Three general scenarios were analyzed:
In addition, a 2040 build scenario without the Multimodal bridge was also analyzed. This analysis was conducted due to the uncertainty of the bridge location at the time of analysis. This scenario assumes that Van Dorn Street (between Eisenhower Avenue and S. Pickett Street) would need to be widened to accommodate the West End Transitway, which otherwise uses the Multimodal bridge.
The analysis assumes increases in traffic attributed to regional growth, including approved development in the Plan area and planned development in neighboring jurisdictions for future 2040 scenarios. The Plan provides new roadway and pedestrian / bicycle connectivity and enhanced transit facilities in and through the Plan area which provides travel choices in terms of route and mode. The 2040 Build scenario included a net increase of 9.3 million square feet within the Plan area. The analysis of the 2040 Build scenarios (with and without the bridge) identified a number of additional intersection and transit improvements to be considered as mitigation, and compared to the 2040 Baseline scenario. These improvements included:
If the multimodal bridge were not constructed under the 2040 Build scenario, it would require significant widening of Van Dorn Street to accommodate the intersection improvements identified above, in addition to dedicated transit lanes and an improved pedestrian and bicycle connection between South Pickett Street and Eisenhower Avenue. The resultant significant width of Van Dorn Street would be contrary to the urban and pedestrianized character that is envisioned within the plan area. In addition, a widening of Van Dorn Street still does not achieve improved multimodal connectivity to the extent that the multimodal bridge does and may not support the full 9.3 million square feet of proposed new development.
The traffic analysis showed that under the 2040 Build scenario (with the Multimodal bridge), there is an increase in the number of intersections that fail, as compared with the 2040 Baseline scenario, due to the significant increase in associated traffic. However, if the proposed mitigation is implemented, including intersection and transit improvements identified above, the number of failing intersections is significantly reduced, both within the Small Area Plan boundary and overall transportation study boundary. The analysis also showed that without the Multimodal Bridge, there are a greater number of failing intersections than with the bridge, due to the increased level of connectivity and alternative routes to using Van Dorn Street. The 2040 Build scenario without the Multimodal bridge was also analyzed with the proposed added mitigation (previously discussed). The mitigation also helped to significantly reduce the number of failing intersections under this scenario.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Artist’s rendering looking west along the Backlick Run greenway toward Neighborhood 1 - Van Dorn Innovation District
Parks and open space are a vital component of sustainable and healthy communities. Parks offer opportunities for improving health through exercise and recreation, and are places for respite and reconnection to nature. In addition, they contribute to naturally managing stormwater while enhancing value by making a community visually pleasing.
Eisenhower West is home to a number of high quality parks and green spaces including Armistead Boothe Park, Ben Brenman Park, and Hensley Park which serve citywide recreational needs. Future redevelopment of properties in Eisenhower West will bring new residents and workers to this area, requiring the addition of new parks and open spaces. All portions of the Eisenhower West area will be within a five to ten minute walk of accessible open space. Accessible open space will include neighborhood parks which are multi-use spaces oriented to the surrounding neighborhood.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
PLAN AREA PUBLIC PARKS AND OPEN SPACE
⬚ figure
Fig. 4.22 – Public parks and open space
Note: The locations of the proposed parks are for illustrative purposes. The final design and configuration of the parks will be subject to compliance with this plan and future zoning.
This graphic does not depict an anticipated park on 550 South Pickett Street.
EISENHOWER WEST Small Area Plan | 45
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Eisenhower West Area includes several significant City parks including Ben Brenman Park, Armistead Boothe Park, Hensley Park and the Clermont Natural Area. However, the projected increase in population in the area will place far greater demands on these parks. This plan therefore advocates enhancing existing parks. Enhancements could include features such as lighting, drainage, irrigation, fencing, turf fields and picnic shelters, per approved City plans.
Enhancing existing parks also includes providing greater access to the parks, particularly access over the rail lines. Two bike/pedestrian bridges are shown on the Concept Land Use Plan connecting Ben Brenman Park to Neighborhoods 5 and 6, Bush Hill and Clermont Exchange, south of the rail line. Given the cost of bridge construction, only one bridge is likely, and more work will be needed to determine its optimal location.
The property west of the Clermont Natural Area, owned by Norfolk-Southern, is a priority open space site identified in the Alexandria Open Space Master Plan. If acquired or placed in a conservation easement, it would provide additional passive open space in the plan area and could potentially include stormwater management features.
⬚ figure
Armistead Boothe Park
⬚ figure
Hensley Park
⬚ figure
Ben Brenman Park
The Plan envisions the creation of new parks in each of the six neighborhoods in the plan area. While the parks will vary in each neighborhood, they should be designed to be visible, inviting, accessible, and to accommodate all ages and abilities. A variety of active and passive spaces is encouraged in each park, as are high-quality trees, vegetation and plantings.
⬚ figure
Areas for play with amenities such as fountains attract activity, Jamison Park, Portland, OR
⬚ figure
Well designed and maintained trees and vegetation create a high-quality park environment, Yards Park, Washington DC
⬚ figure
Passive spaces and grassy areas encourage picnics and relaxation, Crispus Attucks Park, Washington, DC
⬚ figure
Shady places with seating invite gathering and interaction, Jamison Park, Portland, OR
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
As part of the Plan, the inaccessible and degraded stretch of Backlick Run located between the City of Alexandria/Fairfax County line and Cameron Station will be revitalized into an active greenway, a key open space feature of the plan.
Revitalization of this greenway will include stream restoration, the removal of structures from the Resource Protection Areas (RPAs) the removal of invasive species and replacement with native vegetation. Existing buildings and other non-pervious surfaces will be removed from the RPA concurrent with development of the sites on which they are located. This natural area will include a multi-use trail and passive open space. Some benches and picnic areas will also be provided. The open space may include stormwater management features.
See Section 5.5.2 for stream revitalization strategies.
⬚ figure
Backlick Run existing condition
⬚ figure
Accessible stream edge, Alanson, MI
⬚ figure
Revitalized and stabilized stream. Sylvania, OH
Connecting to the Backlick Run greenway will be a number of safe green connections which include stream valleys and other environmentally sensitive areas. One example is the small stream that connects to Backlick Run in the vicinity of 731 S. Pickett Street. Additional green connections linking to Backlick Run will be identified and planned through the development process and provided as development occurs.
⬚ figure
Through-block pocket park forming a green connection linking two parallel streets, Portland, OR
⬚ figure
Green conection within an urban mixed-use development, O Street Market, Washington DC
⬚ figure
Green connection linking two streets, National Mall, Washington DC
⬚ figure
Green connection created via vegetated streetscape elements along a park path, Portland, OR
The Eisenhower West area will contain a linked pedestrian, bicycle and trail system within the parks and open spaces. In addition, many of the streets in Eisenhower West will be complete streets that accommodate different modes of transit. Sidewalks will be provided on each street and many will include bicycle accommodations. (See Figures 4.20 and 4.21.)
⬚ figure
Pedestrian/ bike trail, Alexandria, VA
⬚ figure
Mt. Vernon Trail, Alexandria, VA
STREETSCAPE - The City has an active program to plant street trees. This plan seeks to maximize opportunities to enhance tree coverage with easy to maintain street trees. This will help to meet the overall City goal to achieve 40% tree canopy coverage by 2020. Two locations have been identified for streetscape enhancement as part of the City goal to create welcoming gateways to the area including the City-owned property in the area of the Eisenhower Avenue collector (Clermont interchange) and the City-owned property at the intersection of Eisenhower Avenue and S. Van Dorn Street. The proposed enhancements could include special planting, lighting, paving. The City will work with WMATA to jointly enhance WMATA’s property on South Van Dorn Street. The City’s adopted Wayfinding Program has identified the need for gateway signs at the two gateway locations and also identified the need for vehicular directional signs on Eisenhower Avenue and Van Dorn Street.
BUFFERS - Vegetated buffers or screening will be located adjacent to the rail lines to mitigate visual and noise impacts from these uses. This vegetative screen would be planned and planted as part of the development of adjacent properties.
GATEWAYS - Gateways are elements in a plan that introduce a neighborhood and provide identity to a community. These locations contain architectural, public art and placemaking elements that describe and highlight the Eisenhower West plan area and its neighborhoods, and serve as visual markers of major entries and exits, crossing points, and neighborhood transitions.
PUBLIC ART - Special places can be celebrated and marked through creative and innovative public art. Public art will be integrated into public spaces at nodes and gateways such as the Van Dorn Metrorail station, and along public paths and trails.
HISTORIC CHARACTER - Knowledge of the history of the planning area can create special places through enabling connections to the past. The history of the planning area provides opportunities to elucidate and interpret the early landscape of the area and its probable use by Native Americans, late 18th and early 19th-century settlement by Europeans and the activities at several plantations and estates, railroad history, and the military activities that took place during World War II. Historical markers as well as other design elements in open space will be used to accomplish these goals.
⬚ figure
Streetscape, Portland, OR
⬚ figure
Public art, Seattle, WA
⬚ figure
Example of a vegetated buffer, Portland, OR
⬚ figure
Gateway building, Arlington, VA
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 4.23 - Placemaking opportunities diagram
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
See Fig. 4.23 for locations.
(See Fig. 4.23.)
As new development is proposed and open space is planned, the City will work with developers to determine the optimal form of ownership and maintenance of the new publicly accessible open spaces. Open spaces that only benefit immediate residents should be owned, operated and maintained by private entities, such as a homeowners association. Public access easements may be required as part of the development review process for open spaces to be accessible to the public and privately maintained. Open spaces that serve a wider community are likely best owned by the City, although funding for maintenance may be sought from those future residents or businesses that will benefit the most. This will be determined as part of the development review process.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Artist's rendering of buildings in Eisenhower West, looking east
The character, image, and marketability of Eisenhower West will be shaped in large part by the quality of buildings and public spaces. Building designs should promote the character of each neighborhood and further the overall placemaking goals of the Plan. While no specific architectural style is mandated, buildings and structures in Eisenhower West will be contemporary, innovative, and high quality in design and materials.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
As part of future zoning and/or CDD approvals, more detailed design standards and guidelines will be approved to supplement the requirements of the plan.
Depending on the structural system, a typical floor plate (floor to floor) for residential is 10-12', office is 13-15', and commercial is 15-18'.
⬚ figure
Fig.4.24- Neighborhoods key plan
⬚ figure
Fig.4.25- Stages 1 and 2 potential development summary
| Neighborhood | Site Area | Building Heights | Land Uses | Total |
|---|---|---|---|---|
| 1 - Van Dorn Innovation District | 79.6 acres | 5-15 floors | ||
| 2 - Backlick Run | 26.5 acres | 5-15 floors | ||
| 3 - South Pickett | 29 acres | 3-7 floors | ||
| 4 - Van Dorn Metro Center | 34.2 acres | 10 - 20 floors | ||
| 5 - Bush Hill | 48.3 acres | 5-15 floors | ||
| 6 - Clermont Exchange | 25.9 acres | 5-8 floors | ||
| TOTAL | 244 acres | 9.3 M GFA |
Development density does not include existing buildings, nor planned approved projects with the exception of the existing Victory Center building Note:
See Fig. 4.23 for all potential locations
⬚ figure
Fig. 4.27 - Parking tucked into grade
⬚ figure
Fig. 4.26 - Building heights diagram
Ord. 5537, allow Medium
Amended 5/18/24, Ord. 5537
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
⬚ figure
Sustainability means meeting our community's present needs while ensuring the ability of future generations to meet their own. It involves balancing and integrating environmental, economic, health and social issues so as to maximize the quality of life for all Alexandria residents. It also requires us to consider the impacts of our decisions and actions beyond the City of Alexandria and seek the continuous evolution of policies and programs.
In an effort to achieve the overall goals of the 2008 City of Alexandria Eco-City Charter, the plan recommends a series of sustainability measures as it relates to the overall energy systems and environmental requirements within the development area. The foundational goals of the Eco-City Charter are to envision Alexandria as a city that:
The City of Alexandria’s Environmental Action Plan 2030 (EAP), which was adopted in 2009, serves as the broad road map for city leaders, staff, and citizens to implement the sustainability visions set forth in Alexandria's Eco-City Charter. It sets out principles, goals, targets and actions that explain how Alexandria can lead the new Green economy, address the challenges of climate change, and continue its high quality of life while decreasing the city's carbon and ecological footprints.
The City's draft Energy & Climate Action Plan 2012-2020 builds on the work done in developing the EAP by providing information on policies and measures that the City is already undertaking, as well as possible new measures under consideration, to achieve the City's climate change goals.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The City of Alexandria signed an agreement to meet or exceed the Kyoto Protocol greenhouse gas reduction targets through the use of local land planning, urban reforestation, public outreach, and other greenhouse gas (GHG) reduction strategies. The draft Energy and Climate Change Action Plan 2012 – 2020 provides information on policies and energy measures that the City is already undertaking, as well as possible new short-term and medium-term measures to achieve the EAPs greenhouse gas emission reduction targets, which include:
Two primary outside energy companies serve the Eisenhower West area - Dominion Virginia Power Company (DVP) and the Washington Gas Light Company (Washington Gas). The plan area also has a significant on-site energy asset, the Covanta Resource Recovery Facility (Covanta), a waste-to-energy plant providing electricity.
Dominion Virginia Power Company is a regulated electric utility that transmits, and distributes electricity from its power plants in Virginia, North Carolina, Connecticut, and West Virginia to customers in Virginia and specifically to Eisenhower West. Dominion Virginia Power encourages the growth of renewable energy in the Commonwealth, and is committed to providing customers with program options to support customer interest and needs in renewable technologies.
Headquartered in Washington, DC, Washington Gas delivers natural gas to more than one million residential, commercial and industrial customers throughout Washington, DC, and the surrounding region. Washington Gas is a regulated subsidiary of WGL Holdings, Inc., a public utility holding company. The unregulated affiliates of WGL Holdings are in energy-related businesses, selling natural gas and electricity in competitive markets, and providing heating, ventilating and air-conditioning products and services.
The Covanta Resource Recovery Facility began commercial operation in February 1988 and serves about 300,000 residents of the County of Arlington and the City of Alexandria, which jointly own the site. The facility’s three, 325 ton-per-day furnaces process 975 tons of solid waste, generating up to 23 megawatts of renewable energy that is sold to Dominion Virginia Power Company. Covanta has developed a facility-wide Environmental Management System based on applicable federal regulations and good management practices to ensure:
Figure 4.28 indicates the location within Eisenhower West of the Covanta Resource Recovery Facility along with the primary infrastructure for both electric power and natural gas.
The current energy resources, electric power from Dominion Virginia Power (DVP) and natural gas from Washington Gas Company, can adequately supply energy to Eisenhower West for the near term; however, infrastructure upgrades will be required to distribution networks for both systems in order to support the full development buildout in the long term.
⬚ figure
Fig. 4.28 - Existing Energy Infrastructure
⬚ figure
Fig. 4.29 - Projected Future Energy Usage
The Eisenhower West area is served by DVP from two separate high voltage power substations utilizing a combination of overhead and underground distribution systems. Per DVP, these two substations are sized to accommodate approximately 25-30% of the projected future growth prior to requiring significant upgrades.
Separate power circuits have been provided along Eisenhower Avenue in the area around the Van Dorn Metrorail station to serve the power requirements for Metrorail equipment. Because of the high density of power circuits around the Metrorail station, any developments in and around the station, or any large single load addition, will require careful coordination with DVP and adequate planning time to accommodate possible infrastructure upgrades.
DVP has indicated that district energy systems, combined heat/power systems and net-metered photovoltaic systems are all possible and can be connected to the DVP distribution system; however, analysis must be done and coordinated with DVP on how to connect this new generation to DVPs infrastructure.
Washington Gas’ natural gas piping infrastructure in Eisenhower West is at or near capacity and any large single load additions to their system may require an upgrade to the primary infrastructure. The natural gas main piping running through the Eisenhower West area ranges in size from 2” to 16” in size and is designed to optimally operate below 20 pounds per square inch gauge gas pressure.
Covanta, one of the most sustainable energy assets within Eisenhower West, currently generates a maximum 23 megawatts of renewable energy that is sold to DVP to supply users within Alexandria. This accounts for less than 20% of the total peak electric power utilized within the Eisenhower West plan area. As the future development progresses to full buildout this will reduce to less than 15%. Therefore, in order to meet the City’s goal for clean renewable sources, additional renewable energy sources will be required to be deployed along with future development.
Figure 4.29 indicates the projected future full-development energy usage, calculated utilizing benchmarked square footage energy criteria. The areas outlined in red indicate the future development areas with the largest density of future energy usage and areas highlighted in yellow represent the lowest density of future energy usage.
In order to extend the usage of the existing energy resources currently serving Eisenhower West and meet the energy reduction goals set out by the City of Alexandria, strategies are recommended to be incorporated and/or studied in all future developments. On the individual building scale energy conservation strategies can be implemented to reduce the overall project greenhouse gas emissions. Where a large scale development is planned, the opportunities should be studied, coordinating with the City and applicable local utilities for environmental and regulatory requirements, in order to incorporate community scale energy solutions that can take advantage of larger and more diversified energy loads. (See p. 57.)
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
District Energy Systems (DES) District energy systems deliver hot water, steam or chilled water from a central plant(s) to multiple buildings via a network of pipes to meet thermal end uses. These systems can use a wide variety of energy sources including CHP, and may incorporate microgrids.
Combined Heat and Power (CHP) CHP systems use the same energy source to simultaneously produce useful thermal energy and electricity. A CHP opportunity that currently exists within Eisenhower West is the Covanta Resource Recovery Facility. Although the facility is currently only setup to deliver electricity, Covanta has studied and is prepared to modify its facility to add heat exchangers to provide a CHP that can deliver thermal energy to local developments adjacent to the plant. Figure 4.30 indicates the estimated future heating loads in the development neighborhoods with projected high, medium and low opportunity zones indicated for extending heating piping from Covanta to these heating loads.
Microgrids Microgrids are small-scale electricity distribution systems that link and coordinate multiple distributed energy resources into a network serving some or all of the energy needs of one or more users located in close proximity. It can operate connected to the traditional centralized electric grid or autonomously from it, in an intentional island mode.
Integrated Community Waste Energy Solutions Sources of surplus heat from municipal and commercial processes at Eisenhower West that can be tapped include building sewage that can be sufficient for heating buildings. A highly efficient hot water district heating system was installed for heating the Olympic Village for the 2010 Winter Olympics in Vancouver, Canada, extracting heat from sewage. This system is now being expanded to complete a district scale waste energy plant for Vancouver. Locally, DC Water is currently planning to install sewage waste heat recovery systems throughout Washington DC that can be utilized for both heat extraction and heat rejection.
⬚ figure
Daylighting Natural daylight is the most efficient lighting strategy. New buildings should be constructed to maximize daylight exposure in both private and common areas. Lighting control should respond to human occupancy to ensure that artificial lighting is used only when needed.
Exterior Lighting Exterior lighting is the most overlooked energy savings opportunity. Exterior lighting uses high efficiency fixtures such as light emitting diodes (LED) and should implement energy-efficient control technologies. It should also incorporate the “Dark Skies” principles for fixture selection.
Energy Efficient Envelopes Reduce energy usage as much as practical and economical through energy-efficient envelope design for all new buildings.
Electrical Vehicle Infrastructure Provide infrastructure on-site for accommodating electrical vehicles, which are anticipated to increase over time.
Renewable Energy Apply renewable energy technologies on-site including solar electric photovoltaics (PV) and active solar heating for energy systems, utilizing available incentives from DVP and Washington Gas. Alternatively, participate in the Dominion Green Power® program, which is certified by Green-e® Energy, for 100% of electric power usage. Utilizing planned future roof areas for roof-mounted PV and planned parking areas for overhead mounted PV on-site, Diagram X indicates the projected peak solar electric peak power generation possible for each neighborhood area. (See Figure 4.31.)
Ground Source Heat Pump Where site area is available for a ground source well field, energy efficient ground source heat pump systems can be installed to tap the relatively consistent temperature of the ground for heating and cooling. For commercial and large residential projects that would typically utilize a cooling tower, this has the additional benefit of significantly reducing overall water consumption for mechanical system makeup.
⬚ figure ⬚ figure ⬚ figure
EISENHOWER WEST Small Area Plan | 57
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Holmes Run and Cameron Run are considered impaired by the Virginia Department of Environmental Quality for exceeding the bacteria water quality standard. These streams and tributaries are surrounded by 100-foot Resource Protection Area (RPA) buffers which were adopted by the City of Alexandria in 1992 in response to the Chesapeake Bay Preservation Act of 1988. (Intermittent streams area protected by 50-foot buffers.) The creation of these protected areas ensures that sensitive environmental corridors are preserved in a natural condition. Backlick Run, Holmes Run, Cameron Run, their tributaries and their designated RPAs must remain through and following this project with measures to be implemented to further their protection. The open space along the Backlick Run stream corridor is intended to be functional by addressing stormwater, stream improvements and restoration/ stabilization of the RPA.
The Plan recommends stream revitalization strategies be implemented to restore the health of existing streams and contribute to the creation of the Backlick Run greenway. The stream system will be the focal environmental element within the plan area. As such, the Plan recommends a Backlick Run Restoration Master Plan be pursued as a next step.
Redevelopment that capitalizes on Resource Protection Areas (RPAs) buffer restoration/ stabilization with possible natural stream improvements of Backlick Run and small tributaries, and the environmental features existing in Clermont Cove, will enable enjoyment for the community, more diverse animal habitat, and greater functionality to the stream system. Consideration for siting green infrastructure stormwater Best Management Practices (BMPs) in the RPA will be given to redevelopment projects adjacent to Backlick Run and other tributaries that remove existing encroachments. Following removal of the existing encroachment, the BMP can be placed in the footprint of the previous encroachment. This will benefit the stream and increase the buildable area outside of the RPA. Replanting of the stream buffer will provide open space, treat stormwater and create natural habitat.
⬚ figure
Fig. 4.32 - Existing conditions - surface environment
⬚ figure
Photos of Backlick Run today
⬚ figure
Fig. 4.33 - Existing Resource Protection Areas
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Resource Protection Areas (RPA) Maintain the 100-foot RPA buffer area along streams in the plan area. Current encroachments within the first 50 feet of the buffer may be supplanted with green infrastructure practices that provide water quality benefits for the fronting parcels to maximize buildable area outside of the RPA.
Stream Restoration/Stabilization This practice varies but can include: grading of stream bank, realignment, native plant installation, rock structures, naturalization, bank reconstruction and stabilization, matting, utility relocations, and outfall repairs, among others.
Stream Daylighting Stream daylighting includes the removal of natural streams from artificial pipes and culverts to restore a natural stream. Stream daylighting restores habitat, promotes infiltration, helps reduce pollutant loads and can provide better runoff attenuation because it increases the storage size of the natural system. A few small tributaries could benefit from this practice.
Trails and Pathways Trails and pathways are described throughout the Plan as a way to connect amenities and resources.
Plantings Planting new native trees, shrubs and groundcover within the RPA buffer of a stream is considered as a desired method of restoring natural landscape for riparian areas. Plantings must follow manuals and guidelines from the Virginia Department of Environmental Quality.
Constructed Wetlands Stormwater runoff flows through the wetland, allowing for pollutant removal through the settling and biological uptake within the practice. Wetlands are among the most effective stormwater practices in terms of pollutant removal, and they also offer aesthetic and habitat value.
⬚ figure
⬚ figure
The plan covers a drainage area of over 600 acres, with most properties within the plan area having low-scale buildings and/or surface parking constructed before stormwater quality and quantity requirements were in place. This, along with topography, and a large upstream drainage, contributes to the periodic flooding and untreated stormwater runoff that are a problem in the plan area.
Low impact development (LID) or Green Infrastructure (GI) stormwater management strategies are recommended to be implemented with redevelopment in the plan area to minimize stormwater runoff and reduce water pollution, while creating a greener and healthier environment, and providing ancillary benefits such as habitat areas for wildlife, reducing the heat island effect and providing opportunities for connection to nature.
The gradual redevelopment of the plan area over time offers the opportunity to significantly improve stormwater management and reduce pollutant runoff throughout the plan area while enhancing the health of existing streams and tributaries.
The plan encourages the installation of permeable pavers in sidewalks and parallel parking areas. In addition, tree wells – or urban bioretention – will be designed to treat stormwater runoff for new or redeveloped roadways per the Complete Streets Guidelines.
Consideration for siting green infrastructure stormwater BMPs in the RPA will be given to redevelopment projects adjacent to Backlick Run and other tributaries that remove existing encroachments. Following removal of the existing encroachment, the BMP can be placed in the footprint of the previous encroachment. This will benefit the stream and increase the buildable area outside of the RPA. Replanting of the stream buffer will provide open space, treat stormwater and create natural habitat.
The Plan recommends a Stormwater Master Plan to decrease stormwater runoff, and improve water quality. The Plan also recommends the installation of low flow or ultra low flow water features such as toilets, lavatory sinks, and showers in new units, encouraging retrofits in the existing older units and buildings as buildings are renovated. Rainwater capture and reuse and grey water reuse can provide stormwater benefits and reduce use of potable water for non-potable uses.
EISENHOWER WEST Small Area Plan | 59
⬚ figure
Bioretention Areas Landscaping features adapted to provide on-site treatment of stormwater runoff, bioretention areas are generally applied to smaller sites in urbanized settings. Surface runoff is directed into shallow, landscaped depressions that incorporate pollutant removal mechanisms such as runoff filters through a mulch layer and soil mix is taken up by plantings.
⬚ figure
Permeable Pavers These manufactured concrete units are designed with small openings between permeable joints filled with highly permeable, small-sized aggregates allowing stormwater to enter a crushed stone aggregate bedding layer and base that supports the pavers. They can replace traditional impervious pavement for most pedestrian and vehicular applications except high-volume/high-speed roadways.
Pervious Concrete Pervious concrete is made with reduced sand or fines that allows water to drain through the surface to the aggregate storage layer below. It can replace traditional impervious pavement for most pedestrian and vehicular applications except high-volume/high-speed roadways.
Cisterns Cisterns are designed to intercept and store runoff from rooftops to allow for its reuse, reducing volume and overall water quality impairment.
⬚ figure
Tree Well BMPs/Urban Bioretention Tree well BMPs, per the Green Sidewalks Guidelines, perform the same functions that other infiltration practices perform but in addition provide an increased tree canopy.
Planter Box These containers, located either above or below ground, are planted with vegetation that captures stormwater within the structure itself rather than allowing it to drain directly into nearby storm drains. Planter boxes must be located reasonably close to downspouts or structures generating runoff.
Bioswale As stormwater runoff flows along these planted open channels, it is treated through vegetation slowing the water to allow sedimentation, filtering through a subsoil matrix, and/or infiltrating into the underlying soils.
Green Roofs Green roofs absorb, store, and evapotranspire initial precipitation and reduce the discharge of pollutants such as nitrogen and phosphorus to a storm sewer system as a result of soil microbial processes and plant uptake.
Infiltration Trench These rock-filled trenches allow stormwater runoff to pass through a combination of pretreatment measures, such as a swale and detention basin, and into the trench. There, runoff is stored in the void space between the stones and infiltrates through the bottom into the soil.
⬚ figure
⬚ figure
The Plan area falls within the Holmes Run Sanitary Sewershed and the Alexandria Renew Enterprises (AlexRenew) service area. Currently, 80,000 feet of sanitary sewers exist in the plan area, mostly small collector sewers (10-12”) owned and maintained by the City. (See Fig. 4.34.) Small collector sewers discharge to three trunk sewers owned by Fairfax County, which are then conveyed to the AlexRenew Holmes Run Trunk Sewer and conveyed to their treatment facility.
With new development and redevelopment envisioned over the next 20-25 years, portions of the existing sewer system will need to be upgraded as development happens:
A variety of strategies to conserve water and reduce flow into the sanitary sewer system - such as low-flow toilets, rainwater harvesting, etc. listed on the following page - will reduce the need for upgrades, and are recommended to be implemented as new development occurs throughout the plan area.
⬚ figure
Fig. 4.34 - Existing sanitary sewer system
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Reclaimed Water Reduction of overall domestic water usage across the City of Alexandria is a major goal in moving towards Alexandria’s environmental priority of increasing water conservation. One of the ways this can happen is to use reclaimed water across the city as much as possible in order to reduce overall dependency of clean domestic water.
This reclaimed water system is more widely known as a “Purple Pipe” water system as it is typically colored purple to clearly indicate to building occupants or building maintenance that it is a non-potable water system and different from the domestic systems in the building. Reclaimed water is water that has received a level of treatment appropriate for non-potable uses. It is produced by using physical, biological, and chemical processes to remove harmful material from wastewater that flows into our plant. Treating wastewater so that it can be classified as “reclaimed” includes two stages of ultraviolet disinfection prior to distribution.
The City wastewater reclamation facility located in Old Town Alexandria is operated by AlexRenew. The AlexRenew facility serves about 320,000 people in the City of Alexandria and parts of Fairfax County, processing an average of 13 billion gallons of wastewater every year. While most of AlexRenew’s cleaned water is returned back to the environment, AlexRenew has recently embarked upon installation of a reclaimed water system (Purple Pipe System) to make use of the high quality water for non-potable uses. AlexRenew is currently planning to utilize the purple pipe reclaimed water in the new AlexRenew Headquarters and in other buildings in the Carlyle development. They have expectations for expansion of this buried Purple Pipe system up Eisenhower Avenue.
Reclaimed water has been gaining acceptance nationwide, and is used in almost all 50 states. In the National Capital Region, Loudoun Water and Fairfax Water have reclaimed water systems. Since 2000, AlexRenew has used about 1.5 billion gallons of reclaimed water annually for on-site heating, cooling, and equipment cleaning. Beginning in 2016, they will make reclaimed water available to customers.
Reclaimed water is water which has received a level of treatment appropriate for non-potable uses. It can be used for :
Rainwater should be captured on-site from roof surfaces and reused for irrigation, and indoor plumbing needs. This reduces the demand for potable water and has associated energy and cost savings.
More than 4.8 billion gallons of water is flushed down toilets each day in the United States as conventional toilets use 3.5 to 5 gallons of water per flush. Low-flush toilets use only 1.6 gallons of water or less.
Showers account for about 20 percent of total indoor water use. By replacing standard 4.5-gallon-per-minute showerheads with 2.5 gallon-per-minute heads, a family of four can save approximately 20,000 gallons of water per year.
Faucet aerators break the flowing water into fine droplets and entrain air while maintaining wetting effectiveness. They can reduce water use at faucets by as much as 60 percent while still maintaining a strong flow.
The maximum water flow from a fixture can be reduced if the water pressure is reduced. For example, a reduction in pressure from 100 psi to 50 psi at an outlet can result in a water flow reduction of about one-third.
⬚ figure
Reclaimed water
⬚ figure
Reclaimed water
⬚ figure
Rainwater harvesting
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Required and Recommended Streets
PRIMARY OR “A” STREETS
SECONDARY OR “B” STREETS
TERTIARY OR “C” STREETS
“P” STREETS
BLOCKS
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
PEDESTRIAN ENVIRONMENT
EXISTING PARKS
NEW PARKS AND GREEN SPACES
BACKLICK RUN GREENWAY
GREEN CONNECTIONS
PUBLIC SPACES AND PLAZAS
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
5.1 NEIGHBORHOOD 1 - VAN DORN INNOVATION DISTRICT 5.2 NEIGHBORHOOD 2 - BACKLICK RUN 5.3 NEIGHBORHOOD 3 - SOUTH PICKETT 5.4 NEIGHBORHOOD 4 - VAN DORN METRO CENTER 5.5 NEIGHBORHOOD 5 - BUSH HILL 5.6 NEIGHBORHOOD 6 - CLERMONT EXCHANGE
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
This chapter describes elements of the six neighborhoods within the Eisenhower West Small Area Plan.
⬚ figure
Fig. 5.1 Neighborhoods key plan
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 5.2 - Neighborhood 1 key plan
| Site Area | Building Heights | Land Uses |
|---|---|---|
| 79.6 acres | 5-15 floors |
Fig.5.3 - Neighborhood 1- Land uses
⬚ figure
Neighborhood 1 is envisioned as Eisenhower West’s Innovation District. Over time, the area will redevelop from existing low density warehouse spaces to a vertical and horizontal mix of residential and commercial development fronting on to a new Backlick Run greenway. The permitted mix of commercial uses is intentionally broad and diverse, and can include retail, office, and Production, Wholesale and Repair (PWR). Specific uses could include creative services, maker space, start-ups, craft manufacturing, sporting/exercise businesses, and catering companies, among many others.
This diversity strengthens the area’s employment base by encouraging innovation, maintaining and integrating existing light industrial, and promoting neighborhood-serving uses. It will also create a distinct character to the residential development, a fresh take on urban industrial that has evolved into residential mixed use neighborhoods. Residents’ quality of life will be enhanced by proximity to high quality natural amenities, retail services, and transit.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
LAND USE
⬚ figure
Fig. 5.4 - Neighborhood 1 - Land use diagram
⬚ figure
Fig. 5.5 - Neighborhood 1 - Street hierarchy
⬚ figure
Fig. 5.6 - Neighborhood 1 - Required and recommended streets
EISENHOWER WEST Small Area Plan | 73
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Artist's rendering looking west along the Backlick Run greenway toward Neighborhood 1 - the Van Dorn Innovation District
⬚ figure
Fig. 5.7 - Neighborhood 1 - Parks and open space
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Protect and enhance the Resource Protection Area (RPA) along the Backlick Run stream corridor and its associated stream tributaries by maintaining the minimum 100’ buffer from the stream that is required by law, with the first 50’ being the most critical. Removing development from at least the first 50’ of the buffer is a priority with removal of all encroachments and full RPA restoration being the overall goal. In no case will new development extend into the RPA beyond existing developed areas.
Predominantly residential developments will provide 30% open space. 15% of the open space on site will be publicly accessible at-grade open space. The remaining 15% may be provided off-site or by contribution in lieu to new neighborhood parks or the creation of the Backlick Run greenway.
Predominantly commercial development projects will provide 10% publicly accessible at-grade open space.
A new off-street pedestrian and bike trail will be created along Backlick Run.
Green connections along streets will be implemented in the general locations approximate to those shown in Figs. 5.7 and 5.8.
Open space at the intersection of the tributary stream with Backlick Run provides an opportunity to interpret Native American activity that could have occurred thousands of years ago on the terraces overlooking the creek. Similarly, green space along the railroad line could include interpretation of the Orange & Alexandria, the earliest railroad in the city.
⬚ figure
Fig. 5.8 - Neighborhood 1 - Summary of plan elements
Redevelopment is expected to take place over a timeframe of 25-30 years, depending on market conditions and funding for infrastructure improvements. The illustrative plan shows one potential way in which the plan area could redevelop. The plan does not require building locations, footprints, parks and open spaces to be designed or developed as shown, so long as the vision for redevelopment expressed by the community, the principles contained in this document, and the City of Alexandria’s standards for redevelopment are met.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig.5.9 - Neighborhood 2 - Key plan
| Site Area | Building Heights | Land Uses |
|---|---|---|
| 26.5 acres | 5-15 floors |
Fig.5.10 - Neighborhood 2 - Land uses
⬚ figure
Neighborhood 2, Backlick Run, is envisioned as primarily residential with some mixed use along Van Dorn Street and Backlick Run, and, in the future, along the Virginia Paving site, that includes retail and services with commercial and/or residential above. Neighborhood retail would be located at the ground levels of buildings along South Pickett Street and Van Dorn Street. This neighborhood will also revitalize and connect to a new greenway along Backlick Run. New residents and workers will be able to connect to and enjoy Backlick Run as a new environmental area and linear park.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Redevelopment is expected to take place over a timeframe of 25-30 years, depending on market conditions and funding for infrastructure improvements. The illustrative plan shows one potential way in which the plan area could redevelop. The plan does not require building locations, footprints, parks and open spaces to be designed or developed as shown, so long as the vision for redevelopment expressed by the community, the principles contained in this document, and the City of Alexandria's standards for redevelopment are met.
Street grid and building locations may change depending on final selection of multimodal bridge alignment.
Fig. 5.15 - Neighborhood 1 - Illustrative plan
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 5.16 - Neighborhood 3 key plan
| Site Area | Building Heights | Land Uses |
|---|---|---|
| 29 acres | 3-7 floors |
Fig.5.17- Neighborhood 3 - Land uses
⬚ figure
Neighborhood 3, South Pickett, is envisioned as primarily residential with some mixed use areas that include maintaining existing neighborhood-serving retail with small office and/or residential above. Neighborhood retail would be located at the ground level of buildings along South Pickett Street and in the mixed-use neighborhood node to be created with future redevelopment of the Trade Center site.
The major character-defining element of the neighborhood is Cameron Station. New development along South Pickett Street has the opportunity to extend the grid, character and scale of Cameron Station.
The existing Trade Center strip shopping center in Neighborhood 3 contains neighborhood small businesses reflecting the diversity of residents in the area. To the extent possible, future development should preserve these businesses and business types by integrating them in new space on the ground levels of new buildings.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 5.18 - Neighborhood 3 - Land use diagram
⬚ figure
Fig. 5.19 - Neighborhood 3 - Street hierarchy
⬚ figure
Fig. 5.20 - Neighborhood 3 - Required and recommended streets
EISENHOWER WEST Small Area Plan | 81
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
BUILDING HEIGHT
⬚ figure
Fig. 5.21 - Neighborhood 3 - Parks and open space This graphic does not depict an anticipated park on 550 South Pickett Street.
PARKING
PARKS AND OPEN SPACE
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Redevelopment is expected to take place over a timeframe of 25-30 years, depending on market conditions and funding for infrastructure improvements. The illustrative plan shows one potential way in which the plan area could redevelop. The plan does not require building locations, footprints, parks and open spaces to be designed or developed as shown, so long as the vision for redevelopment expressed by the community, the principles contained in this document, and the City of Alexandria's standards for redevelopment are met.
Fig. 5.22 - Neighborhood 3 - Illustrative plan
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 5.23 - Neighborhood 2 key plan
Neighborhood 4, Van Dorn Metro Center, is envisioned as an active and vibrant high density, transit-oriented mixed use neighborhood. It will include retail at the ground level and commercial and/or residential uses above. Destination retail would be located at the ground levels of buildings along primary and secondary streets. This neighborhood is where the largest concentration of office space would be located in Eisenhower West, leveraging proximity to the Van Dorn Metrorail Station. A new urban plaza provides an animated place for gathering and interaction. A new park will provide recreational opportunities and reconnection to nature.
The main character-defining elements of Neighborhood 4 are the Van Dorn Metrorail Station and the Covanta Waste-to-Energy Plant. Currently, Eisenhower Avenue curves between the WMATA and UPS properties and Metro Road as one travels past Summers Grove. This curve splits the Metrorail Station in two sections, with the park-and-ride lot to the north of Eisenhower Avenue and the bus and shuttle zone on the south side.
⬚ figure
| Site Area | Building Heights | Land Uses |
|---|---|---|
| 34.2 acres | 10 - 20 floors |
Fig. 5.24- Neighborhood 4 - Land uses
LAND USE
TRANSPORTATION AND CONNECTIVITY
BUILDING FORM AND CHARACTER
⬚ figure
Fig. 5.25 - Neighborhood 4 - Land use diagram
⬚ figure
Fig. 5.26 - Neighborhood 4 - Street hierarchy diagram
⬚ figure
Fig. 5.27 - Neighborhood 4 - Required and recommended streets
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Redevelopment is expected to take place over a timeframe of 25-30 years, depending on market conditions and funding for infrastructure improvements. The illustrative plan shows one potential way in which the plan area could redevelop. The plan does not require building locations, footprints, parks and open spaces to be designed or developed as shown, so long as the vision for redevelopment expressed by the community, the principles contained in this document, and the City of Alexandria's standards for redevelopment are met.
Fig. 5.29 - Neighborhood 4 - Illustrative plan
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 5.30- Neighborhood 5 - Potential development density
| Site Area | Building Heights | Land Uses |
|---|---|---|
| 48.3 acres | 5-15 floors |
Fig. 5.31- Neighborhood 5 - Land uses
Neighborhood 5, Bush Hill, takes its name from the Bush Hill Plantation, a house and 354-acre estate dating back to the 1790s whose foundation remains within a hidden wooded area at what is now 4720 Eisenhower Avenue. The eastern half of this neighborhood will be predominantly residential with more commercial uses on its west end closer to the Van Dorn Metrorail Station. As redevelopment matures, retail could be incorporated at the ground level of buildings along Eisenhower Avenue to provide services to residents and to strengthen the idea of Eisenhower Avenue as a Great Street.
The main character-defining element of Neighborhood 5 is the wooded area at 4720 Eisenhower Avenue, a parcel of land shared with the FedEx facility and located east of the Exchange residential development. This stand of trees west of the FedEx building is hidden from view by the property at 4750 Eisenhower Avenue. It contains a stream with a Resource Protection Area, and, as mentioned above, the remains of the foundation of the Bush Hill Plantation.
LAND USE
TRANSPORTATION AND CONNECTIVITY
⬚ figure
⬚ figure
⬚ figure
BUILDING FORM AND CHARACTER
BUILDING HEIGHT
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Buildings located beyond a 1/2 mile of the Van Dorn Metrorail Station in this neighborhood will be 5 stories with some buildings up to 10 stories to provide variety in height along Eisenhower Avenue.
Buildings located between 1/4 and 1/2 a mile of the Van Dorn Metrorail Station in this neighborhood will be a minimum of 10 stories and a maximum of 15 stories.
Building heights will respect adjacent land uses. Buildings will incorporate shoulders, or step down in height, to be compatible in height and setback with the adjacent developments such as Summers Grove and The Reserve.
Building heights should maximize sun and shade for pedestrians.
New buildings will be configured to be parallel to the adjoining street and define the adjoining street and open spaces by establishing an urban street wall.
areas.
Predominantly residential developments will provide 30% open space. 15% of the open space on site will be publicly accessible at-grade open space. The remaining 15% may be provided off-site or by contribution in lieu to new neighborhood parks.
Predominantly commercial development projects are encouraged to provide 10% publicly accessible at-grade open space.
Create at least one children's play space in either Neighborhood 5 or 6 both.
Residential developments on the Victory Center site are encouraged to provide a unified publicly accessible open space along with a green connection behind the development.
Integrate an off-street pedestrian and bike trail in the wooded area north of Neighborhood 5.
This plan encourages a new passive park in the vicinity of the Bush Hill Estate ruins, where the opportunity exists for interpretation of a late 18th-century plantation as well as Native American settlement in Alexandria. This area is also heavily wooded, includes a stream, and is a Resource Protection Area (RPA). This potential new Bush Hill Park, could be created as part of the future redevelopment of this neighborhood. This new park would be a combination of a new publicly accessible green space on 4720 Eisenhower Avenue and the existing wooded area, stream and RPA at 4750 Eisenhower Avenue.
Protect and enhance the RPA along the stream tributaries to Cameron Run by maintaining the minimum 100' buffer from the stream that is required by law, with the first 50' being the most critical. Removing development from at least the first 50' of the buffer is a priority with removal of all encroachments and full RPA restoration being the overall goal. In no case will new development extend into the RPA beyond existing developed
⬚ figure
Fig. 5.35 - Neighborhood 5 - Parks and open space
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Redevelopment is expected to take place over a timeframe of 25-30 years, depending on market conditions and funding for infrastructure improvements. The illustrative plan shows one potential way in which the plan area could redevelop. The plan does not require building locations, footprints, parks and open spaces to be designed or developed as shown, so long as the vision for redevelopment expressed by the community, the principles contained in this document, and the City of Alexandria's standards for redevelopment are met.
Fig. 5.36 - Neighborhood 5 - Illustrative plan
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. 5.37 - Neighborhood 6 key plan
| Site Area | Building Heights | Land Uses |
|---|---|---|
| 25.9 acres | 5-8 floors |
Fig. 5.38- Neighborhood 6 - Land uses
Neighborhood 6, Clermont Exchange is the easternmost neighborhood of Eisenhower West. Located along Eisenhower Avenue, this neighborhood is also accessed from Clermont Avenue, and therefore has good vehicular connectivity to the Beltway and to Eisenhower East. As future redevelopment occurs over time, this neighborhood will consist primarily of mixed use with residential areas that include neighborhood-serving retail/services with office and/or residential above. Ground level retail and other active or destination uses will be important to strengthen the idea of Eisenhower Avenue as a Great Street. This neighborhood also has the potential to absorb additional car-oriented uses, such as large format retail, on an interim basis until the market for mixed use development is mature. Future redevelopment of this neighborhood will also mean that more people will need access to the parks and recreational amenities surrounding it. Enhancements to Hensley Park and Holmes Run/Cameron Run could be phased in with future redevelopment.
Neighborhood 6 is not only characterized by its proximity to the Beltway and Eisenhower East, but also by its proximity to natural and recreational amenities including Hensley Park and Holmes Run/ Cameron Run. Although it is also very close to Ben Brenman Park, it is physically cut off from that park by the railroad right-of-way.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
As new development is phased-in over time, ensure that it respects and co-exists with existing development and businesses.
Buildings should have their primary frontages, and entrances/lobbies on “A” and “B” streets, or facing parks or major green spaces. This encourages safety and helps provide “eyes on the park” and “eyes on the park.”
Buildings should be designed to accommodate retail or restaurant/café space at the ground levels of buildings along Eisenhower and Clermont Avenues.
Compact multi-story buildings are highly encouraged for large format retail if located in this neighborhood as an interim use.
Use distinctive architecture, high-quality materials, excellent public space design, special landscaping, wayfinding signage, streetscape furnishings, lighting, and public art to highlight buildings at gateways, nodes, parks, and public spaces. Specific locations in Neighborhood 6 include buildings at the intersection of Clermont and Eisenhower Avenues, and buildings fronting parks and public spaces within the neighborhood.
Use distinctive architecture, landscaping and streetscape design to reinforce Eisenhower Avenue as a Great Street.
New buildings will be configured to be parallel to the adjoining street and define the adjoining street and open spaces by establishing an urban street wall.
⬚ figure
Fig. 5.39 - Neighborhood 6 - Land use diagram
⬚ figure
Fig. 5.40 - Neighborhood 6 - Street hierarchy diagram
⬚ figure
Fig. 5.41 - Neighborhood 6 - Required and recommended streets
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Enhance the Clermont Natural Area to become a passive and well-utilized park for neighborhood residents.
Protect and enhance the Resource Protection Area (RPA) along the Backlick Run stream corridor and its associated stream tributaries by maintaining the minimum 100' buffer from the stream that is required by law, with the first 50' being the most critical. Removing development from at least the first 50' of the buffer is a priority with removal of all encroachments and full RPA restoration being the overall goal. In no case will new development extend into the RPA beyond existing developed areas.
Acquire, or protect in perpetuity, property owned by Norfolk Southern west of the Clermont Natural Area to provide additional passive open space in this neighborhood.
Create a new neighborhood park and or plaza within the mixed-use development in Neighborhood 6, north of Eisenhower Avenue.
Create at least one children’s play space in either Neighborhood 5 or 6 or both.
Predominantly residential developments will provide 30% open space. 15% of the open space will be publicly accessible at-grade open space. The remaining 15% may be provided off-site or by contribution in lieu to new neighborhood parks.
Predominantly commercial development projects are encouraged to provide 10% publicly accessible at-grade open space.
Integrate an off-street pedestrian and bike trail in the wooded area north of Neighborhood 6 and in the Clermont Natural Park.
Improve Hensley Park to enhance active recreational opportunities pending fulfillment of open space requirements in the plan area.
Opportunities exist to interpret a former embankment that appears on a Civil War map in addition to Alexandria’s early railroad history.
⬚ figure
Fig. 4.42 - Neighborhood 6 - Parks and open space
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Redevelopment is expected to take place over a timeframe of 25-30 years, depending on market conditions and funding for infrastructure improvements. The illustrative plan shows one potential way in which the plan area could redevelop. The plan does not require building locations, footprints, parks and open spaces to be designed or developed as shown, so long as the vision for redevelopment expressed by the community, the principles contained in this document, and the City of Alexandria's standards for redevelopment are met.
Fig. 5.43 - Neighborhood 6 - Illustrative plan
EISENHOWER WEST Small Area Plan | 95
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
An overarching goal of this Plan is to provide flexible recommendations in order to catalyze and support redevelopment. The purpose of this chapter is to describe a set of implementation strategies for the long term land use, infrastructure, public space, and placemaking goals envisioned in the Eisenhower West Small Area Plan. The implementation considerations incorporate current and expected future market demand, including the recent announcement of the Transportation Safety Administration (TSA) relocation to Victory Center, for the intended real estate product types, planning level cost estimates for infrastructure improvements, and the potential for developer contributions.
Realizing the vision of a vibrant mix of uses across the planning area will depend on the capacity for current and future market conditions to support a range of residential and commercial uses. The Plan recommends a series of potential strategies to advance the implementation of the plan. The following implementation strategies are both practical with respect to current market forces, and targeted approaches that will establish the foundation for the realization of the plan.
Strategy 1: Use near term residential development to build on the current levels of demand, begin establishing the character of the Plan, and to begin providing amenities. The residential uses, amenities and population will help attract future retail and commercial uses.
In the near term, the Eisenhower West submarket presents stronger opportunities for residential development than commercial, and the market analysis reveals several strengths in the residential market, particularly:
Residential market fundamentals in the area are exhibiting low vacancy and growing rents, driving a reaction from developers and a pipeline of over 500 units of rental and condo product. This activity is currently centered on the intersection of South Van Dorn Street and South Pickett Street, adjacent to the Van Dorn Innovation District and Backlick Run neighborhoods. In addition to projects in the development pipeline, JBG Cos. acquired the three buildings comprising the Pickett Industrial Park (841-881, 883-885, 901-929 South Pickett Street), sited on 10.8 acres of land in June 2015. Property owners who are actively looking to redevelop in the near term will likely be primarily interested in residential projects.
Mid-rise residential developments, of which Modera Tempo is an example, present near term market feasible opportunities that are aligned with the plan recommendations for parcels located more than one half mile from the Van Dorn Metro Station. Projects like these contribute to the critical mass of activity in the planning area, support current and planned retail, and will potentially support developer contributions to fund infrastructure and public amenities.
High-rise residential development in the Van Dorn Innovation District and Van Dorn Metro Center areas is consistent with the neighborhood principles, and there is a current market for residential development. However, average market rents do not currently support the higher construction cost of high-rise development so it may be some time before high-rise residential development is constructed. For example, the current market will support a five-story wood-frame development in the Bush Hill neighborhood, but a 15 story steel or concrete frame project in the Van Dorn Innovation District will requires higher rents, which will likely come as the area matures as a residential location.
Strategy 2: Continue to strengthen the area’s appeal to commercial development, leveraging the TSA headquarters announcement as well as the fact that residential development will help support amenities that establish the area as an attractive place to live and work.
A guiding principle of the Plan is to create an area that balances residential and commercial development, supporting employment and forming a mixed-use district. Under current market conditions, office development presents a challenge. The recent announcement of the location of the Transportation Safety Administration headquarters in the Victory Center will stimulate interest in Eisenhower West for office and it is important for this Plan to facilitate any office development that might occur as a result. Recognizing that general market conditions are such that many areas are competing for commercial development (especially office), activities that continually improve the appeal of Eisenhower West for commercial uses should be pursued. In locations other than those designated for commercial development, residential development will improve the appeal of the area and support the retail, open space, and other amenities sought by office tenants. Sites within the planning area that present the greatest opportunity for office development include:
Strategy 3: Encouraging mixed-use light industrial and innovation uses will create a diverse economic and employment foundation.
Eisenhower West is historically an industrial district, supporting a local manufacturing employment base. Residential and office development has started to transform the area into a mixed-use neighborhood. This plan encourages the retention of a broad mix of uses, including flex/PWR (defined in Section 4.1), because these uses support an innovation economy and provide services needed by residents and businesses alike. To maintain a portion of the historic job market as warehouse and manufacturing sites are converted to other uses, Neighborhood 1, the Van Dorn Innovation District, is planned to leverage its existing physical and economic assets such as transportation access, a burgeoning mix of commercial and residential uses, and diverse job employment base to transform the predominantly warehouse and industrial land uses into a mixed-use district combining
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
residential, PWR (Production, Wholesale, Repair), craft manufacturing, and retail uses. This approach is intended to retain an employment base in related industries, but occupy new higher density construction, as the existing building stock offers limited reuse opportunities.
Potential creative uses could include:
Partnerships between the City and non-profits, businesses, and other organizations to create incubator programs will encourage the arrival of innovation uses. This may include rent subsidy for leasing ground floor spaces at rates comparable to existing industrial rents. Temporary rent subsidies will reduce the startup cost for innovative businesses, to establish self-sufficient operations, to later convert to long term market leases.
Placemaking will be accelerated through a comprehensive open space strategy across the planning area. Development projects will occur along different timelines, which will require an open space strategy that must be defined in advance and flexible enough to be implemented in a phased approach. To support this effort, the Plan encourages 20% of residential land be combined within neighborhoods in a manner that enhances real estate value, and provides a larger public amenity, in addition to private community green spaces. The locations of desired public open spaces are clearly defined in the Plan and include Bush Hill Park and Backlick Run.
In developing a comprehensive open space strategy the City should:
Through redevelopment of blocks within these neighborhoods, the 20% ground level open space contribution may be pooled and applied to these identified parcels in order to achieve these preferred neighborhood parks. This allows properties sited at a distance from intended open spaces to contribute to a larger public amenity. For land on which the preferred open space is located, property owners will provide the land, and will be compensated, through the remaining neighborhood open space contributions, for dedicated open space beyond the required amount. The Plan recommends that when developers are not providing a total of 30% ground level open space on site within the Eisenhower West area (either individually or as part of an open space pool), they will contribute a fee in lieu of this.
See open space principles and guidelines in Chapter 4 of this report.
To support and initiate redevelopment activity across the planning area, interim projects could help to create a node that would attract a critical mass of activity, and spur complementary development in adjacent areas. Interim uses can range from “pop up” container stores on vacant parcels to big box retail uses. Food trucks can immediately increase the range of dining options for office workers, especially in the Eisenhower West corridor, and should be encouraged.
Long-term interim retail uses will require an owner/developer with a commitment to the future vision. Interim projects, in use for a 10-15 year time frame, can be strategic anchors within the plan to generate activity and new visitors to the area. The time frame that interim uses are permitted must be defined as part of city approval.
As part of interim use approval, the city should consider elements such as future phasing and leasing. In addition, new buildings should be designed and constructed to the extent possible to not preclude implementation of the required streets and open space. New interim buildings will be required to be located adjacent to the street with the parking behind the building.
Potential interim catalyst uses include:
In efforts to encourage the development of catalyst uses, the City may:
Preparation of the Eisenhower West Small Area Plan involved planning-level analysis of the need and options for transportation infrastructure and other
EISENHOWER WEST Small Area Plan | 99
public facilities necessary to support the future development. This level of analysis is sufficient to justify the general vision and framework of this plan; however, more detailed engineering, phasing and funding will be required to ensure that the pace of development and the provision of infrastructure are timed so that (a) new and existing residents and workers are well-served and (b) the cost of the infrastructure can be supported by anticipated revenue sources. The analysis demonstrated that the construction of the multimodal bridge significantly mitigates traffic congestion, and that all development in the greater plan area will benefit from this key piece of infrastructure and will be expected to contribute to its funding. Depending on the timing and location of development, different contribution amounts may be appropriate. If the construction of the multimodal bridge is not feasible, an alternative option of widening the Van Dorn Street bridge will need to be explored, including revised development thresholds.
The Infrastructure and Funding Plan will address not only the Eisenhower West Small Area Plan but also the Landmark/Van Dorn Corridor Plan, for which a detailed implementation plan has not yet been completed. These two plan areas overlap and share dependency on planned infrastructure, such as the multimodal bridge and the elementary school. Looking at the phasing and funding of both plans in concert will provide the coordination needed between these two plans.
The Infrastructure and Funding Plan will be guided by the concept of three phases of growth: catalyst, choice location/limited connectivity, and implementing the long term vision. These are consistent with the phases of growth in the Landmark/Van Dorn Corridor Plan.
Catalyst projects are early projects, and/or projects that are ready to begin the permitting process upon adoption of this Plan, that help create a
critical mass of redevelopment activity. Catalyst projects may include "interim redevelopment" or development that is wholly consistent with the long-term vision of this Plan. The catalyst phase is characterized by limited expectations for developer contributions to mitigate off-site impacts of their development on infrastructure and public amenities such as a lower developer contribution in addition to standard contributions. A suggested developer contribution for this phase should take into account market conditions, project economics, and financial feasibility. It may also be characterized by a streamlined regulatory process, primarily by substituting a limited set of design and use guidelines in place of the Special Use Permit (SUP) process.
The amount of development that is included in the "catalyst" category will be limited by three criteria:
During the catalyst phase, approved Development Special Use Permits (DSUPs) will likely favor land uses that reflect current market conditions. This is acceptable as long as the Plan’s ultimate required land use mix is still achievable, both neighborhood-wide and site-by-site. If a DSUP reaches the end of its approval time (36 months) without beginning substantial construction and another landowner in the neighborhood would like to
move to approval, the Planning Commission and City Council may take that into account when considering whether to approve an extension of the original DSUP. It will be in the interest of all landowners that development capacity (density) be allocated to projects that are ready to move to construction.
The Infrastructure and Funding Plan may or may not set a dollar-per-square-foot rate for development to contribute to infrastructure that will mitigate their off-site impacts. Development proposed in the catalyst phase and prior to the completion of the Infrastructure and Funding Plan will be evaluated for the potential to contribute to mitigating their off-site impacts balancing the need for that infrastructure with economic development and other plan goals.
This phase is entered when a critical mass of catalyst development is approved and/or under way, indicating that Eisenhower West has become a choice location for new development in the region. It consists of redevelopment consistent with the long term vision of the Plan and will likely be characterized by a greater proportion of non-residential development and denser office, commercial, and residential development at the Metro node. Increased requirements for developer contributions toward off-site impacts on infrastructure and transportation (connectivity, open space, schools, etc.) will be considered.
This phase limits the total amount of redevelopment to that which can be supported by a limited set of transportation improvements shown in Figure 6.1. This phase will have an implementation plan calculating infrastructure funding needs and assigning shares to the public and private sources of funds. The difference between Choice Location/Limited Connectivity and Implementing the Long Term Vision is based on what the transportation network can support. This
phase is complete when approximately 7.1 million square feet of net new development is achieved.
This phase is characterized by completion of the planned connectivity network and the other public facilities needed to support build out of planned development in Eisenhower West. The Plan will set the amount of additional square footage that will be available for development approvals during this phase, which will reflect the amount of development supportable by planned transportation improvements, including transit infrastructure and service improvements, and pedestrian and bicycle facilities. This phase will also be characterized by completion of all non-transportation public facilities, including public space, education, and other facilities, recommended by the Plan that were not completed during earlier phases. This phase will have an implementation plan calculating infrastructure funding needs and assigning shares to the public and private sources of funds, which may be independent of, or a continuation of, the previous phase in the implementation plan.
The Infrastructure and Funding Plan will confirm development ceilings for each phase of development (Catalyst, Choice Location/Limited Connectivity, and Implementing the Long Term Vision) consistent with the table below. The amount of development permitted in each phase will be limited by the capacity of the transportation network at that time.
The Infrastructure and Funding Plan may also preliminarily allocate portions of the overall development potential of the Plan to each neighborhood. It is anticipated that through the zoning and DSUP process, individual landowners will draw from the development ceiling for their neighborhood. This may occur through a CDD for each neighborhood or other zoning
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
tool. Landowners will lay claim to this shared development capacity through the DSUP process and will be allocated on a first-come, first-served basis.
In the event that the supply of development capacity in any neighborhood is exhausted by DSUP approvals and other landowners are seeking development approval prior to moving to the next phase, reallocation of development capacity (transfer of development rights) may be accomplished in the following way:
Strategy 7: Explore a range of potential zoning options, from existing zoning categories to new zones, for parcels in Eisenhower West that will occur at the time of redevelopment.
A key tool for implementing the Plan’s vision will be zoning that expresses the desired mix of land uses in the Plan. Properties would apply for a rezoning at the time of redevelopment, taking into account that in zoning for some properties already allows densities consistent with the Plan’s objectives. Future rezonings will balance the desire for incentivizing redevelopment with paying for the cost of infrastructure to support that development. Rezonings could include the following:
| Staging | Projected Development | Needed Improvements | Cost (2015) |
|---|---|---|---|
| Stage 1 | Total: 7.1M SF (includes TSA site) | Initial Spot Improvements (For Planned / Approved) | $1 Million |
| Allocation of this amount of development to the “Catalyst” phase and the “Choice Location/Limited Connectivity” phase will occur in the Implementation Phasing and Funding Plan to follow. | • Van Dorn/Eisenhower<br>• Van Dorn/Main<br>• Van Dorn/Edsall<br>• Van Dorn/Pickett<br>• Pickett/Edsall | $450,000<br>$630,000<br>Minimal<br>Minimal<br>Minimal | |
| Major Improvements<br>• Enhanced transit service<br>• Farrington Ave. Connector Bridges (Alexandria)<br>• Multimodal Bridge or Widening Van Dorn St.<br>• Van Dorn / Courtney<br>• Pedestrian Bridge (Clermont to Ben Brenman Park)<br>• Community Facility<br>• Housing*<br>• Open Space Acquisition<br>• Clermont Cove Acquisition<br>• Mitigation of Impacts to the Waste-to-Energy Facility<br>• School<br>• Construction<br>• Land Acquisition | $400,000 +<br>$44 Million<br>$51 Million<br>Minimal<br>$14,300,000<br>$19,000,000<br>$5,250,000<br>$8,200,000<br>TBD<br>TBD<br><br>$45,000,000<br>TBD | ||
| *Estimated potential City investments to acheive affordable housing or mixed-income assisted living co-located with community facility | $188 Million + | ||
| Stage 2 | 2.2 Million SF | • Rebuild Metro Rd. NB ramp; Remove SB loop ramp<br>• Farrington Ave. Connector (Fairfax responsibility) | $2.8 Million<br>$15M plus ROW |
| Following Phase: Implementing the Long Term Vision | 2.8 Million + | ||
| Stage 3 | To be determined | Additional infrastructure could provide additional development capacity to be determined by future studies. | To be determined |
⬚ figure
Figure 6.1 Infrastructure Costs
Additional Implementation Strategies The City will explore additional implementation mechanisms that include:
To assess the potential for developer contributions toward funding infrastructure improvements in the planning area, the total infrastructure cost is considered with respect to potential new development in the planning area. The total infrastructure cost is estimated at $191 million based on data provided by the City, with individual costs described in Figure 6.1. The Plan recognizes that the City may need to make early investments to create infrastructure improvements prior to additional demand. Particularly, the City should consider near-term, interim improvements to accommodate TSA. North-south connections should be prioritized in future analysis.
The total new development is approximately 9.3 million square feet. However, development should not exceed 7.1 million square feet until Stage 1 transportation improvements have been completed. Allocation of the 7.1 million square feet of development to the “Catalyst” phase and the “Choice Location/Limited Connectivity” phase will occur in the Implementation Phasing and Funding Plan to follow, which will also provide greater detail regarding the pacing of development and infrastructure within Stage 1.
Developers are required to build on-site and adjacent improvements such as new streets, adjacent infrastructure (including sewers), and some key open space features such as the proposed Backlick greenway and stream restoration and the plaza near Metro. In addition, the City requires a developer contribution to support larger off-site infrastructure improvements that will be necessary with increased development.
The Plan envisions that there will be developer contributions to accommodate future infrastructure needs that are comparable to other recent small area plans. The City’s initial analysis assumes that at least fifty percent of the cost of planned infrastructure would be provided through developer contributions. The actual developer contribution rates will be determined during a subsequent and more detailed study. That study will recognize that this plan’s goal is to calibrate developer contributions so as to build and sustain redevelopment momentum created by the TSA Headquarters announcement and this plan as well as to fund infrastructure. The Infrastructure and Funding Plan will determine how contributions should be phased in over time and will look at varying contributions by neighborhood and land use such as to encourage office.
During the period that the Infrastructure and Funding Plan is under development, contributions will be evaluated on a case-by-case basis taking into account the financial feasibility of each project and its status as a catalyst project. The Infrastructure and Funding Plan will also confirm the list and timing of infrastructure improvements and public facilities called for by the small area plans and determine funding sources for each. Funding sources will likely vary by category of infrastructure or facility. Contributions to affordable housing will follow the City’s guidelines at all phases of implementation.
Annual net tax revenue from full development of the plan area is expected to yield $21.3 million per year of which a portion will be used to fund improvements in the plan area. Along with this revenue, resources from the general fund and other grants can be used to build the improvements listed in the table above.
The City may wish to provide incentives or encouragement for desired development. Incentives should be focused on these areas:
Regulatory, financial or programmatic incentives or support the City could explore:
In order to achieve the vision for Eisenhower West, a number of action items have been identified to begin implementation:
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
EISENHOWER WEST SMALL AREA PLAN
Adopted November 14, 2015
A EXISTING CONDITIONS B SUMMARY OF ISSUES AND OPPORTUNITIES C MARKET ANALYSIS D COMMUNITY ENGAGEMENT E CASE STUDIES
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
This report provides an analysis of existing physical conditions in the Eisenhower West Small Area Plan area. This analysis defines the physical situation “on the ground” in the study area, and identifies issues to be addressed, and opportunities to be explored. This understanding forms the basis upon which conceptual options will be developed in later phases of the process. This analysis will also become part of the Final Report which will be completed at the end of the planning process.
The early history of Eisenhower West planning area goes back approximately 8,500 years. The two existing streams - Holmes Run and Backlick Run - were natural resources likely to have been used by early hunter-gathers and Native Americans living and roaming throughout the area. Use of the streams could have included the plants and animals, but also the collection of cobbles, primarily quartz and quartzite, which would have been used to manufacture stone tools. In 1649, the land was granted to supporters of King Charles II, and, by the end of the 17th century, came under the control of Lord Fairfax who issued grants for large tracts of land. During the 17th and 18th centuries, plantations were established, on which African Americans worked as slaves. The foundations of the house at Bush Hill, a 354 acre estate, still exist at approximately 5000 Eisenhower Avenue. Several grist mills operated in the area. Portions of Cloud’s Millrace are preserved in place along Holmes Run.
In the early 19th century, Little River Turnpike (Duke Street) was established as a toll road. The Orange and Alexandria Railroad was established in the 1850s, parallel to Duke Street. During the Civil War, a Union camp was set up near the planning area and observation balloons were launched to observe the movements of confederate troops. The area was annexed to Alexandria in 1952. In recent years, the Eisenhower West planning area developed rapidly primarily with light industrial and warehouse uses, taking advantage of proximity to the railroad, but also with office buildings, and some residences. The Van Dorn Metrorail Station opened in 1991, on the Blue Line. In 1992, the Cameron Station neighborhood was developed, replacing the Cameron Station military installation.
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Eisenhower West Small Area Plan area consists of approximately 620 acres of land located in the southwestern corner of the City of Alexandria along its border with Fairfax County. The plan area is bounded by the Blue Line Metrorail and Amtrak rail tracks to the South (including the Van Dorn Metrorail Station); the Alexandria/ Fairfax County border along to the West, McConnell Avenue/ S. Pickett Street/ Duke Street to the North, and Holmes Run and Cameron Run to the East. The plan area is bisected by Backlick Run, and the CSX/ Norfolk-Southern railway lines, and contains several large parks.
⬚ figure
Refer to Market Analysis for additional demographics
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
With the exception of Cameron Station and Summers Grove, local parks, and Backlick Run, the Eisenhower West plan area has no specific character, sense of place, or sense of identity. It is mostly comprised of an eclectic mix of large, low-rise, light-industrial or warehouse buildings; islands of residential townhomes; some heavy industrial uses and ample surface parking. However, the culturally, economically, and generationally diverse community in and around the area offers opportunities to define a future character for the area.
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The “figure-ground” is a type of analytical urban design diagram that goes back several centuries. It is used to understand patterns of urban form by looking at the relationship of solids (built form, shown in black), to voids (everything else). In this diagram, the collection of solids reveal the generally haphazard nature of urban development in the plan area. The large void in the middle of the area represents the gap in the urban fabric created by the railway right-of-way and the natural resources and park areas that are a key characteristic of the area. The notable exception to this is the strong urban fabric of Cameron Station, where the buildings, open spaces, and street network are well-defined.
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The zoning map for Eisenhower West shows that the area is comprised primarily of large swaths of commercial, industrial and office/ warehouse space, three Coordinated Development Districts (CDD), and a significant Utility/Transportation corridor. However, the map does not provide the complete picture of uses in the area, because there are residential enclaves within the office areas and a mix of uses within the CDDs.
Prior zoning had higher FAR limits. The downzoning which took place after adoption of the 1992 master plan slowed redevelopment of the area. Residential projects exist along Eisenhower Avenue because the previous zoning code allowed them by right. This suggests an opportunity to rethink future potential uses in the area, and to move from segregated uses to a mix of uses, including light and/or green industry and more affordable and workforce housing choices.
⬚ figure
Appendix A - Existing Conditions
EISENHOWER WEST Small Area Plan | 7
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
This diagram shows the actual uses building-by-building, and the layouts/ arrangements of the buildings relative to one another. Most commercial and industrial/ warehouse buildings are surrounded, or fronted, by surface parking, thereby not fully leveraging the land they are on. Residential along Eisenhower Avenue is squeezed tightly into islands and fenced off or otherwise separated from surrounding uses.
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Most of the industrial/ warehouse buildings on the western portion of the plan area were built in the 1960s, while commercial and industrial/ warehouse buildings along Eisenhower date from the 1970s and 1980s. With a few exceptions, including the Trade Center along South Pickett Street, the majority of recent buildings in Eisenhower West- constructed in the 1990s and 2000s - are residential, signaling the strong market for residential development.
⬚ figure
⬚ figure
Appendix A - Existing Conditions EISENHOWER WEST Small Area Plan | 9
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Most of the land in Eisenhower West is privately owned with the exception of WMATA-owned land around the Van Dorn Metro Station, City parks and some municipal properties along Eisenhower Avenue. Aside from the tight-knit residential developments in the plan area, land is very underutilized due to large-footprint, low-rise buildings and surface parking. Opportunities exist to densify and leverage land resources and create a more lively urban realm with new plazas, parks and public spaces.
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The presence of numerous east to west oriented barriers and the resulting lack of good north-south connectivity is a major defining characteristic of the Eisenhower West study area. Van Dorn Street is high-speed, high-traffic, and not designed with the pedestrian in mind, particularly in the area bridging the train tracks. Eisenhower Avenue has the potential to be a more pedestrian-friendly and pedestrian-scaled roadway. The train tracks north and south of Eisenhower Avenue remain the major barrier to creating a connected and cohesive urban realm.
⬚ figure
⬚ figure
Appendix A - Existing Conditions EISENHOWER WEST Small Area Plan | 11
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Eisenhower West is generally well-served by transit including the Van Dorn Metrorail Station and bus lines along Eisenhower Avenue, Van Dorn Street and South Pickett Street. This diagram shows that half of the Eisenhower West area- and part of Fairfax County to the south- is within a 1/2 mile (10 minute walk) radius, of the Van Dorn Station, yet the station continues to be one of the most underutilized stations on the Blue Line in terms of ridership. The true 10-minute walking shed from the metro highlights how insufficient connectivity and physical barriers, limit the pedestrian, in contrast to the overlaid 1/2 mile radius.
Eisenhower West is also well-served by bus lines. The diagram shows the extent of walkability to local bus stops. The yellow shading represents a combination of 1/4 mile (5 minute walk) radii from local bus stops, and indicates where walkability is impeded due to a physical barrier such as train tracks. As a result, despite the area being well-served by transit, physical barriers continue to significantly reduce the pedestrian’s ability to access
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Eisenhower West area is home to several parks which together provide approximately 105 acres of green space in the plan area:
Ben Brenman Park, Hensley Park, and Boothe Park all have approved plans in the Citywide Park Plan.
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The large footprints of light industrial/ commercial/ warehouse buildings, extensive surface parking areas, roadways, residential development, and heavy industrial sites combine to a very impervious environment in Eisenhower West. These elements contribute to the heat island effect, stormwater runoff, low water quality, and a lack of tree-cover in the built-up areas and have negative impacts on the environment. The parks and green spaces in Eisenhower West do provide some relief from these conditions but future redevelopment should prioritize reducing impervious area, improving the resource protection area adjacent to streams and increasing the tree cover to improve the overall environment.
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The topography of the west end of Alexandria varies considerably with elevations from approximately 30 feet up to 250 feet. Eisenhower West is in a low point in the topography of the area, the lowest points generally being along Backlick, Holmes and Cameron Runs. It will be important to understand the area's drainage patterns in order to determine a strategy for future development that reduces flooding and associated stream and property impacts and also evaluates potential locations for local and/or regional stormwater management facilities.
⬚ figure
Appendix A - Existing Conditions EISENHOWER WEST Small Area Plan | 15
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Flooding risk generally follows the significant length of Backlick Run and the portions of Holmes Run and Cameron Run in the plan area. The 100-year floodplain area covers a significant portion of the Virginia Paving site, as well as other industrial sites presenting challenges and opportunities to be considered.
A comprehensive stormwater management (SWM) plan for the plan area involves determining how to integrate multiple types of Low Impact Development elements, and water reuse technologies over highly diverse land use types and ownerships with hardscape and impediments to connectivity. The existence of streams, parks, and large industrial sites offer potential opportunities to connect to these disparate land uses.
A SWM plan will also identify and evaluate regional stormwater facility opportunities to meet the stormwater pollution reduction requirements of the MS4 permit. These facilities would be capable of treating large drainage areas and could capture areas not scheduled for redevelopment or areas outside the boundaries of Eisenhower West that are connected hydraulically. These cost effective larger facilities could incorporate amenities that the community can utilize.
⬚ figure
16 | EISENHOWER WEST Small Area Plan Appendix A - Existing Conditions
The Virginia General Assembly enacted the Chesapeake Bay Preservation Act in 1988 to protect and restore the Chesapeake Bay’s ecosystem. The State mandates that all City streams with perennial flow must be protected by a 100-foot Resource Protection Area (RPA) buffer. All land uses and structures within the RPA that existed at the time of ordinance adoption may continue as “nonconforming” uses. Property owners may engage in passive recreational activities such as fishing, bird watching, hiking, boating, and canoeing within the RPA. Except under very specific circumstances, new development in the RPA is limited to those that are considered “water-dependent uses.” All land disturbing activities proposed in the RPA must first be approved by the City.
Properties adjacent to RPAs may be redeveloped as long as there is no additional encroachment into the RPA and no increase in pollution. The redevelopment must also be found compatible with the City’s Master Plan. The ordinance contains specific provisions to handle cases where applying the RPA would mean the loss of buildable area. For lots that existed before March 2002, the ordinance allows an encroachment into the first 50 feet of the RPA only if it is found that there is no other reasonable alternative and measures are taken to mitigate the impacts on water quality. Any encroachment greater than 50 feet must go through an exceptions process.
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Eisenhower West Small Area Plan (SAP) will likely result in significantly more wastewater than what is currently generated. There are a total of approximately 80,000 feet of sanitary sewer within the plan area. The majority of these sewers are small diameter (10-12 inches) collector sewers, which are owned by the City of Alexandria (City). The small diameter collector sewers convey the wastewater to larger interceptor sanitary sewers owned and operated by Fairfax County, which ultimately discharges into the Holmes Run Trunk Sewer (across Cameron Run) and conveyed to the wastewater treatment facility, both owned and operated by Alexandria Renew Enterprises (AlexRenew).
The City maintains a hydraulic model of its collection system, which identifies where sanitary sewer infrastructure upgrades are required in order to accommodate growth. For instance, where sanitary sewer hydraulic capacity is exceeded due to growth, the developer is required to provide for these infrastructure improvements. These improvements can typically be accomplished by replacing the existing sanitary sewer with a larger pipe. For the Eisenhower West SAP, several infrastructure upgrades to the existing City-owned collector sewers are anticipated to serve proposed development/redevelopment. Based on previous planning forecasts and current modeled results, a total of 5,000-7,000 feet of sanitary sewer pipe will need to be upsized in the future.
Fairfax County maintains a hydraulic model of its own collection system. When development/redevelopment occurs in portions of the City impacting the sewer system, it is required of the developer to contact Fairfax County early in the development process to ensure sufficient sanitary sewer capacity is available.
The Holmes Run Trunk Sewer, owned by AlexRenew, serves both the City and Fairfax County. Currently, all three parties are involved in a joint study to develop and implement a plan to provide for additional capacity in order to reduce wet weather surcharging in the sewer due to flows from both the City and County. As development occurs in areas served by the Holmes Run Trunk Sewer, developers are required to acknowledge that future investments to reduce wet weather surcharging of this trunk sewer may be required. These investments will be based on equal and proportionate participation and, if required, must be made prior to the release of the Final Site Plan.
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Alexandria/Arlington Resource Recovery Facility operated by Covanta began commercial operation in 1988 and serves residents of Arlington County and the City of Alexandria, which jointly own the site. The facility has 45 full time employees. Three, 325 ton-per-day furnaces process nearly 1000 tons of solid waste per day, generating up to 23 megawatts of renewable energy that is sold to Dominion Virginia Power Company. It receives and processes 350,000 tons of Municipal Solid Waste annually. This powers up to 20,000 homes continuously. The plant runs on approximately 50,000 to 70,000 tons of waste annually, 30% of that contributed from Alexandria. The facility is currently being operated under a User’s Agreement between Covanta and the City of Alexandria through 2038.
⬚ figure
Sustainability Opportunities for Consideration:
Convert Facility to Combined Heat & Power (CHP) plant. This would require having Covanta design and install additional heat exchangers that would convert the waste heat currently being discharged to the facilities cooling towers to heating hot water or steam. This waste heat could then be utilized by industrial or commercial users in the Eisenhower West Development. This will require an assessment during the planning process of potential users in the future development for this waste heat, and a strategy for how to get the piping to the future users.
Extend Non-Potable Water from Alexandria Renew for Cooling Tower Make-Up. Under a potential agreement between the City of Alexandria and Alexandria Renew Enterprises (AlexRenew), the city’s wastewater treatment facility, AlexRenew would provide a non-potable water source and piping system from the Alexandria treatment facility to the Covanta site for use by Covanta as make-up water for its cooling towers. Since Covanta is the largest potable water user in the City, this would significantly reduce the potable water usage for the development. This will require an assessment during the planning process of other potential users, in addition to Covanta, for the non-potable water in the future Eisenhower West development. The more users that can be found the more economically viable the proposal will be for AlexRenew.
Extend Non-Potable Water from Alexandria Renew for Heat Rejection. Under a similar agreement between the City of Alexandria and AlexRenew as indicated above, piping would be provided to and from the Covanta site for use as a heat rejection system in-lieu-of utilizing the cooling towers on-site.
⬚ figure
Appendix A - Existing Conditions EISENHOWER WEST Small Area Plan | 19
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. B.1 - Existing conditions - building use
⬚ figure
Fig. B.2- Existing conditions - transportation and connectivity
LAND USE
TRANSPORTATION AND CONNECTIVITY
PARKS AND OPEN SPACE
BUILDINGS AND ARCHITECTURE
INFRASTRUCTURE AND ENVIRONMENT
LAND USE
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Fig. B.3 - Existing conditions - parks and open space
⬚ figure
Fig. B.4 - Existing conditions - surface environment
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
HR&A, under contract to SmithGroupJJR, completed a real estate market analysis to inform the development of a Small Area Plan (“SAP”) for the Eisenhower West area of Alexandria, Virginia. The following is an overview of HR&A’s key findings and recommendations.
HR&A’s analysis provides a baseline assessment of current and projected market conditions. The goal of this work is to inform the development of the Small Area Plan, which will consider:
⬚ figure
22 | EISENHOWER WEST Small Area Plan | Appendix C - Market Analysis
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Summary of Opportunities and Challenges HR&A recommends that the area wide development plan consider strategic opportunities around key nodes and be flexible to current and future market conditions.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Eisenhower West Small Area Plan plan area ("Plan Area") consists of roughly one square mile located on the southwestern corner of the City bordering Fairfax County. It is bounded by the Yellow Line Metro in the South, the McConnell Avenue to S. Pickett Street in the North, and Holmes Run Trail to the East.
Eisenhower West has undergone a significant transition in uses, and the last Small Area Plan was completed in 1992. Formerly consisting solely of commercial uses, including light and heavy industrial activities, the area has seen new residential and mixed-use developments which have introduced nearly 5,000 new residents to the area since the first developments were delivered in 1999.
In light of this rapidly changing environment, the City of Alexandria identified the Eisenhower West area as a candidate for a Small Area Plan. The City retained SmithGroupJJR to assist with the plan, who in turn solicited HR&A Advisors, Inc. ("HR&A") to perform a market scan of residential, retail, office, and industrial real estate to determine the future possibilities for Eisenhower West.
HR&A's analysis seeks to inform components of the Small Area Plan, including:
HR&A's analysis, contains a summary of the real estate inventory in Eisenhower West, how this inventory has changed over time, and how regional demographic, economic, and real estate market dynamics may affect real estate development in the future.
⬚ figure
Figure 1: Eisenhower West Plan Area
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Plan Area’s population has grown significantly since 2000 due to extensive new residential development.
Households in Eisenhower West earn higher incomes than households in the City and the Washington MSA overall.
| Year | Eisenhower West | Alexandria | Washington MSA |
|---|---|---|---|
| 2000 | 1,235 | 128,283 | 4,837,430 |
| 2010 | 4,832 | 139,966 | 5,636,232 |
| 2014* | 4,907 | 144,869 | 5,874,437 |
Figure 2: Total Population *2014 population estimated by ESRI. Does not include new residents in the recently completed Modera Tempo (formerly “Landmark Gateway”), which began leasing these units in July, 2014, and opening them for occupancy in October, 2014. Source: City of Alexandria; ESRI Business Analyst
⬚ figure
Figure 3: Percentage Change, Population, 2000-2014 Source: City of Alexandria; ESRI Business Analyst
| Eisenhower West | Alexandria | Washington MSA | |
|---|---|---|---|
| Median Household Income | $125,984 | $83,054 | $90,415 |
Figure 4: Median Household Income Source: ESRI Business Analyst
⬚ figure
Figure 5: Distribution of Household Income, 2014 Source: ESRI Business Analyst
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Households in Eisenhower West tend to be younger and without children.
⬚ figure
Figure 6: Percentage of Households by Age of Householder, 2014 Source: City of Alexandria, ESRI Business Analyst
⬚ figure
Figure 7: Percentage of Households by Composition, 2014 Source: City of Alexandria, ESRI Business Analyst
Regional and citywide unemployment rates have remained lower than national unemployment rates prior to and during the recent recession.
⬚ figure
Figure 8: Annual Unemployment Rate, 2000-2013 Source: Bureau of Labor Statistics
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Despite its heavily commercial character, Eisenhower West represents only a small portion of the City’s total employment.
⬚ figure
Figure 9: Percentage of Alexandria Employment within Eisenhower West Source: ESRI Business Analyst
Administrative, support, and waste management industries make up the majority of all jobs in Eisenhower West.
⬚ figure
Figure 10: Total Employment by Industry, Eisenhower West, 2014 Source: ESRI Business Analyst
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Citywide, many of the industry sectors which make up the majority of Eisenhower West’s employment base have declined since 2002.
⬚ figure
Figure 11: Percentage Change in Employment by Industry, 2002-2011 Source: US Census Bureau; Center for Economic Studies, LEHD
| In the context of a region experiencing overall population growth, the population in Eisenhower West has grown substantially as the result of new housing development, mainly Cameron Station. | ⇨ | With projected continued regional growth, demand for housing and related amenities is likely to increase. New housing development will also drive demand for retail and other amenities in Eisenhower West. |
| Jobs in Eisenhower West are mainly concentrated in industries, such as warehousing and wholesale trade, that have declined regionally. | ⇨ | While it may be challenging for Eisenhower West to continue to retain these jobs given regional market conditions, it provides an opportunity for the area to attract new job-generating sectors. |
| Administrative, Support, and Waste Management industries comprise most of the Plan Area’s jobs, and remained stable between 2002 and 2011. | ⇨ | These sectors benefit from Eisenhower West’s location and affordability. In the near term, they are likely to remain stable. |
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
HR&A assessed the market for the already eclectic mix of residential, retail, office, and industrial properties located within Eisenhower West.
| Land Use | Gross Square Feet/Units | Median Year Built |
|---|---|---|
| Office | 735,515 SF | 1979 |
| Industrial* | 3,430,134 SF | 1975 |
| Retail | 739,194 SF | 1977 |
| Total Commercial | 4,904,843 SF | |
| Residential** | 2,727 Units | 2001 |
Figure 12: Land Use by Gross Square Feet/ Units Source: CoStar; City of Alexandria
*Includes all warehouse and flex; excludes Virginia Paving and Vulcan Materials **Includes all rental and for-sale multifamily and single family dwelling units in the Plan Area
In addition to comparing Eisenhower West to the region, HR&A analyzed the local market for each product type, the boundaries of which differ slightly depending on industry-accepted definitions of local submarkets.
⬚ figure
| Product Type | Market Analysis Area | Notes |
|---|---|---|
| Multifamily Rental | “West Alexandria”: N Quaker Lane to the east City limits to the north, south, and west | West Alexandria is the industry-defined market for multifamily rental product comparable to projects in Eisenhower West |
| Multifamily For-Sale (Condo) | City of Alexandria | The City of Alexandria as a whole is the industry-defined submarket for comparable condos, single-family houses, and townhouses |
| Single-family/ Townhouse | ||
| Retail | One- and three-mile radii from the center of the plan area | Retail areas account for the “draw” of potential consumers based on product type and distance |
| Office | City of Alexandria | The City of Alexandria as a whole is the industry-defined submarket commercial real estate uses |
| Industrial |
Figure 13: Market Analysis Product Types
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Residential development in Eisenhower West is relatively new, and several developments are scattered amongst commercial uses.
Residential product within Eisenhower West consists of a split between single-family1 and multifamily developments.
⬚ figure
Figure 14: Residential Developments in Eisenhower West Source: Zillow; HR&A Advisors, Inc. *This property will eventually consist of 492 units. 161 units have been completed and are available for lease as of this report. Mill Creek will deliver an additional 199 apartments as a part of its first phase, and an additional 132 units in it second phase; both phases are schedule for completion in July/August of 2015.
⬚ figure
Figure 15: Distribution of Units by Units in Structure, 2014 Source: ESRI Business Analyst
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Residential product within Eisenhower West is largely owner-occupied.
In contrast to Eisenhower West, rental buildings within the West Alexandria submarket are much older, with few deliveries in recent years.
⬚ figure
Figure 16: Housing Tenure, All Housing Units, 2014 Source: ESRI Business Analyst
⬚ figure
Figure 17: Percentage of Multifamily Units by Decade of Construction, West Alexandria Source: CoStar
⬚ figure
Figure 18: Total Multifamily Rental Inventory (units), West Alexandria, 1995-2014* *2014 year-to-date, or 2nd quarter as of this report Source: CoStar
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
| Landmark Gateway (now Modera Tempo) | |
| Developer: Mill Creek Residential | |
| Residential | 492 Rental Units |
| Unit Size | Range from studios (530 SF) to 2-bedroom, 2-bathroom with dens (1,384 SF) |
| Average Monthly | $1,977/unit |
| Asking Rent | $2.72/SF |
| Retail | 15,000 SF |
Residential: Multifamily Rental With 161 units leasing and another 331 scheduled for completion in July/August 2015, Modera Tempo, (formerly "Landmark Gateway") is the first residential development in Eisenhower West since 2007.
Source: Mill Creek Residential Trust
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The multifamily rental market appears to be recovering post-recession.
The local and regional for-sale housing market is improving.
⬚ figure
Figure 19: Deliveries, Absorption, and Vacancy, West Alexandria, 2000-2014* ¹2014 year-to-date, or 2nd quarter as of this report Source: REIS
⬚ figure
Figure 21: Average Number of Days on Market, 2000-2014* *2014 year-to-date, or 2nd quarter as of this report Source: Zillow.com
⬚ figure
Figure 20: Effective Rent per Unit, 2000-2014* ¹2014 year-to-date, or 2nd quarter as of this report Source: REIS
⬚ figure
Figure 22: For-Sale Inventory, All Units, Alexandria, 2010-2014* *2014 year-to-date, or 2nd quarter as of this report Source: Zillow.com
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Median home values for all housing types in Alexandria have trailed those in Arlington and Fairfax, but Alexandria remains fairly competitive.
A dramatic increase in new building permits demonstrates positive developer response to strong demand for residential rental and for-sale development.
⬚ figure
Figure 23: Median Home Value, Single-Family*, 2005-2014** * Includes all residential structures designed as one dwelling, including townhouses ** 2014 year-to-date, or 2nd quarter as of this report. Source: Zillow.com
⬚ figure
Figure 25: Building Permits Issued, City of Alexandria, 2007-2013
| Residential | Type | Other Uses | |
|---|---|---|---|
| Cameron Park | 457 Units | Multifamily Condo/Rental, Townhouse | 36,000 SF Retail |
| Landmark Gateway | 331 Units | Multifamily (Remaining Phases 1, and Phase 2) | |
| Pickett's Place | 48 Units | Townhouse /Stacked Townhouse | |
| Eisenhower West Total | 505 Units |
Figure 26: Eisenhower West Residential Pipeline
⬚ figure
Figure 24: Median Home Value, Condo, 2005-2014** ** 2014 year-to-date, or 2nd quarter as of this report Source: Zillow.com
| Residential | Type | Other Uses | |
|---|---|---|---|
| Landmark Mall | 370-400 | Multifamily Rental | 250,000 – 320,000 SF Retail |
| Stevenson Ave Condos | 121 Units | Multifamily Condo | 80,000 SF Office |
| Washington Suites | 219 Units | Multifamily Rental | |
| Choi Site | 300,000 SF | Unknown | 500,000 SF Office, 10,000 SF Retail |
| Van Dorn Plaza | 550,000 SF | Unknown | 100,000 SF Retail |
| Millennium/Saul Centers | 445,000 SF | Unknown | 700,000 SF Office, 125,000 SF Retail |
Figure 27: Nearby Residential Pipeline Source: HUD SOCDS Building Permit Database; CoStar; City of Alexandria; HR&A Advisors
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The current supply of housing in Eisenhower West was built since 1999.
⬚ figure
Several indicators suggest a recovered market for multifamily rental housing, including decreased vacancy, positive net absorption, and a spike in building permits.
⬚ figure
Modera Tempo (formerly “Landmark Gateway”) is comparable to the type of multifamily housing in demand throughout the region.
⬚ figure
Eisenhower West has a new and evolving identify as a residential area.
⬚ figure
Sites in Eisenhower West could be well situated for transit-oriented multifamily developments to capture additional demand due to their location near the Metro and Beltway.
⬚ figure
Eisenhower West could support additional, highly amenitized multifamily rental product which appeals to a younger demographic seeking locations inside the Beltway, priced competitively with newer projects elsewhere.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
HR&A analyzed the sales volume and demand for retail goods within a one-mile and three-mile radius of Eisenhower West.
Retail clusters in the vicinity of Eisenhower West consist of a diverse mix of locally-serving and regionally-serving shopping centers and other businesses.
⬚ figure
Figure 28: Retail Analysis Trade Areas Source: HR&A Advisors, Inc.
| Comparison Goods |
|---|
| 1 mile (Convenience Goods) |
| Grocery |
| Personal Care |
| Miscellaneous |
| 3 miles (Comparison Goods) |
| Home Furnishing |
| Electronics |
| Apparel |
| Hobby, Books, Music, Sports |
| General Merchandise |
| Building Materials |
| Dining |
Figure 29: Convenience and Comparison Goods
⬚ figure
Figure 30: Local Retail Clusters Source: ESRI Business Analyst, CoStar
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Regionally-serving retail within Eisenhower West competes with a number of major shopping centers within the three-mile trade area.
The Plan Area has a only a few entertainment, sports, and other recreational venues.
| Shopping Center | Type* | GLA** |
|---|---|---|
| 1. Landmark Mall | Super-Regional Mall | 969,000 |
| 2. Plaza at Landmark | Regional Mall | 443,000 |
| 3. Beacon Center | Community Center | 365,115 |
| 4. Crossroads Place | Community Center | 336,248 |
| 5. Village at Shirlington | Community Center | 261,000 |
| 6. Kingstowne Towne Center*** | Community Center | 227,359 |
| 7. The Trade Center | Community Center | 205,837 |
| 8. Kings Crossing | Community Center | 135,000 |
| Total | 2,807,559 |
Figure 31: Area Shopping Centers
⬚ figure
⬚ figure
Figure 32: Local Entertainment Establishments Source: ESRI Business Analyst, HR&A Advisors, Inc.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The 2009 Landmark/Van Dorn Corridor Plan (“LVDCP”) estimates that parcels near Eisenhower West can support a total of 1.4 million square feet of retail in town centers and mixed-use development.
Currently, the Landmark/Van Dorn Corridor contains approximately 1.5 million square feet of retail space, located primarily in the Landmark Mall and other various neighborhood centers and freestanding retail buildings.1 The City envisions that much of this retail space will be replaced with denser, more urban retail in town center-style and mixed-use developments.
The City envisions properties within the “West End Town Center” as encouraging “regional scale development at this prominent entry into Alexandria,” proposing that these properties in total be redeveloped with, at minimum, 1 million SF of retail mainly within town-center style developments. These future developments will absorb much of the demand for regional retail destinations in the area, likely precluding the potential for regional retail destinations in Eisenhower West.
The City envisions properties within “Pickett Place” as encouraging “a strong community retail center and convenience centers for adjacent residential areas,” proposing a minimum of 359,000 SF of retail be developed on these properties in total. These areas, which the LVDCP proposes should contain more neighborhood-oriented retail uses, are located closer to and in some cases within Eisenhower West.
Near-term development activity may absorb much of this demand, though there still may be some opportunities for a variety of types of retail in Eisenhower West.
Approved redevelopment plans for the Landmark Mall will replace 640,000 SF of existing retail space with 250,000 to 320,000 SF of retail in a town center-style development. The Macy’s and Sears will remain, and as a result, the new Landmark Mall will contain 510,000 to 580,000 SF of retail—though this will be less than the 800,000 SF suggested by the LVDCP.
Two developments—one completed (Modera Tempo - (formerly “Landmark Gateway”), and one approved (Cameron Park)—are located within the Eisenhower West plan area. Though Cameron Park will offer more retail than the minimum proposed, the Modera Tempo is only delivering 15,000 SF of retail—though less than the 250,000 SF of retail suggested by the LVDCP.
The capacity for Eisenhower West depends on the timing of future developments in the Landmark/Van Dorn Corridor and other submarkets which compete with Eisenhower West for retail spending.
| Development Block | Land Use | Minimum Retail SF Proposed |
|---|---|---|
| West End Town Center | ||
| 1. Landmark Mall | Regional Town Center | 800,000 |
| 2. Choi | Regional Town Center | 10,000 |
| 3. Millennium/Sal Centers | Regional Town Center | 125,000 |
| 4. Van Dorn Plaza | Residential/Office Mixed-Use | 100,000 |
| Subtotal | 1,035,000 | |
| Pickett Place | ||
| 5. Edsall/Van Dorn North (part) | Residential Mixed-Use | 25,000 |
| 6. Koons Collision | Residential Mixed-Use | 60,000 |
| 7. Edsall/Pickett/Van Dorn | Mixed-Use Community Retail Center | 250,000 |
| 8. Auto Dealer | Residential Mixed-Use | 12,000 |
| 9. Gateway II Pickett | Residential Mixed-Use | 12,000 |
| Subtotal | 359,000 | |
| Total | 1,394,000 |
⬚ figure
Figure 33: LVDCP Development Blocks Source: City of Alexandria
| Development Block (LVDCP) | Land Use (LVDCP) | Project Name (Actual) | Minimum Retail SF Proposed (LVDCP) | Retail SF Developed or Approved (Actual) |
|---|---|---|---|---|
| Landmark Mall | Regional Town Center | Landmark Mall | 800,000 | 510,000-580,000 |
| Edsall/Pickett/Van Dorn | Mixed-Use Community Retail Center | Modera Tempo | 250,000 | 15,000 |
| Gateway II Pickett | Residential Mixed-Use | Cameron Park | 12,000 | 36,000 |
| Total | 1,062,000 | 561,000-361,000 |
Figure 34: Recent and Pending Development Activity on LVDCP Development Blocks Source: City of Alexandria
Source: CoStar ↩
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Most retail goods sold within the one-mile trade area of Eisenhower West reflect the Plan Area’s many car dealerships and auto parts stores.
As a result of the numerous car dealerships and auto parts stores in Eisenhower West, Motor Vehicles and Parts Dealers comprise 42% (or $270.2 million) of all retail sales within the one-mile trade area.
General Merchandise, which includes goods sold in department stores and warehouse clubs, also contributes heavily to local retail sales volume, with goods sold in stores such as Macy’s, Sears, and BJ’s Wholesale Club responsible for 28% ($104 million) of all retail sales within the one-mile trade area.
Twenty-six percent (or $170.5 million) of retail sales within one mile of Eisenhower West consists of convenience goods, including Personal Care (25%), Grocery (19%), and Miscellaneous Goods (1%).
Within the three-mile trade area, sales of comparison goods exceed other categories, including motor vehicles and parts.
Within the three-mile trade area, 30% (or $603.9 million) of retail sales within three miles of Eisenhower West consist of comparison goods, including General Merchandise (20%), Apparel (6%), Electronics (4%), Hobbies etc. (4%), Building Materials (4%), and Home Furnishing (3%).
These sales exceed sales of goods in Motor Vehicles and Parts Dealers, which comprise 28% (or $570.5 million) of all retail sales.
Grocery Store goods are responsible for 21% ($412.6 million) of all retail sales within the three-mile trade area.
⬚ figure
Figure 35: Retail Supply, 1 Mile Trade Area, 2013 ($ millions) Source: ESRI Business Analyst
⬚ figure
Figure 36: Retail Supply, 3 Mile Trade Area, 2013 ($ millions) Source: ESRI Business Analyst
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
As residential development continues to increase in Eisenhower West, there will be a greater demand for retail goods across all categories.
Residents and households within a three-mile trade area spend over $83 million on entertainment and recreation, including frequent attendance at movies and live theater.
⬚ figure
Figure 37: Total Retail Demand, 1-Mile Trade Area, 2013 ($ millions)
⬚ figure
Figure 39: Entertainment Demand, 3 Mile Trade Area, Residents, 2013 ($ millions) Source: ESRI Business Analyst
⬚ figure
Figure 38: Total Retail Demand, 3- Mile Trade Area, 2013 ($ millions)
⬚ figure
Figure 40: Percentage of all Households Participating in an Activity in the Last 12 months, 3 Mile Trade Area, 2013 Source: ESRI Business Analyst
Appendix C - Market Analysis EISENHOWER WEST Small Area Plan | 41
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
HR&A estimated the potential for retail development in Eisenhower West to meet unmet demand for retail goods.
Eisenhower West may be able to support additional grocery stores and miscellaneous convenience goods.
⬚ figure
Figure 41: Retail Gap Analysis Trade Areas
Unmet Demand =
Resident and Worker Spending > Existing Sales
| Resident + Worker Spending | Existing Sales | Unmet Spending Potential | Supportable Square Footage | |
|---|---|---|---|---|
| Grocery | $94M | $72M | $22M | 150,000 SF |
| Miscellaneous | $20M | $4M | $16M | 70,000 SF |
| Personal Care | $44M | $95M | ($0) | N/A |
| TOTAL | $158M | $171M | $38M | 220,000 SF |
Figure 42: Unmet Spending Potential, Convenience Goods Within a 1-mile Trade Area, 2013 Source: ESRI Business Analyst, 2013; Maxim Retail Sales
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Eisenhower West may be able to support additional establishments in comparison goods across all categories.
Eisenhower West may be able to support additional restaurants, including both full- and limited-service.
| Resident + Worker Spending | Existing Sales | Unmet Spending Potential | Supportable Square Footage | |
|---|---|---|---|---|
| General Merchandise | $732M | $280M | $452M | 1,140,000 SF |
| Apparel | $231M | $93M | $138M | 340,000 SF |
| Electronics | $106M | $64M | $42M | 62,000 SF |
| Building Materials | $101M | $61M | $40M | 150,000 SF |
| Hobby, Books, Music, Sports | $88M | $60M | $28M | 90,000 SF |
| Home Furnishings | $75M | $47M | $28M | 140,000 SF |
| TOTAL | $1.33B | $605M | $728M | 1,922,000 SF |
Figure 43: Unmet Spending Potential, Comparison Goods Within a 3-mile Trade Area, 2013 Source: ESRI Business Analyst, 2013; Maxim Retail Sales
| Resident + Worker Spending | Existing Sales | Unmet Spending Potential | Supportable Square Footage | |
|---|---|---|---|---|
| Full Service Restaurants | $213M | $100M | $113M | 264,000 SF |
| Limited-Service Restaurants | $231M | $109M | $122M | 282,000 SF |
| TOTAL | $444M | $209M | $235M | 546,000 SF |
Figure 44: Unmet Spending Potential, Dining Establishments Within a 3-mile Trade Area, 2013 Source: ESRI Business Analyst, 2013; Maxim Retail Sales
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Eisenhower West can therefore support additional retail, though it is likely that retail clusters elsewhere are capturing much of this unmet spending potential already.
⬚ figure
| With the exception of the redevelopment of the Landmark Mall and some mixed use development, there has been little new retail built in the areas near Eisenhower West in the past 20 years. | There is likely demand for retail stores and restaurants in newer facilities. |
| The City has estimated that the Landmark/Van Dorn corridor can support 1.4 million square feet of retail in new projects, though only three developments are imminent. | New retail development may absorb much of the trade areas’ existing demand in the near-term depending on the pace, but the addition of new residential units will introduce additional consumers, who may support additional neighborhood-serving retail in Eisenhower West in the future. |
| There is unmet demand for comparison goods within a three-mile trade area, particularly for both general merchandise and dining. | Excess demand may justify more general merchandise stores in a variety of formats near-term, and more dining establishments in Eisenhower West; both can be further supported as new residential development is added in the future. |
| There is unmet demand for grocery stores and miscellaneous convenience goods within a one-mile trade area. | A small grocery store could be supported in the near-term, preferably as part of a mixed use development project, and future residential development can support additional grocery in the long-term. |
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Eisenhower West lacks a robust office market.
Developers continue to deliver new office space throughout the region, though these buildings are likely build-to-suit or preleased; little has been built in Alexandria.
| Property | Year Built/Renovated | SF |
|---|---|---|
| 5150 Duke St | 1960 | 9,594 |
| Eisenhower Executive Office Building (4875 Eisenhower Avenue) | 1985 | 49,000 |
| Pickett Center (50 S Pickett Street) | 1988 | 70,000 |
| Victory Center (5001 Eisenhower Avenue) | 1973/2009 | 606,921 |
| Total | 735,515 | |
| Total Citywide Office Square Feet* | 22,192,871 | |
| Eisenhower West as % of City Office Square Feet | 3.3% |
Figure 46: Eisenhower West Office Inventory *The total inventory noted here includes federally owned office buildings and other owner-occupied office buildings in the City of Alexandria. These buildings are not a part of the market analysis explored herein, which focuses on investor-owned, renter-occupied properties. In addition, many industrial properties in Alexandria contain a small quantity of office space, which does not impact the broader office market and is also not included here. However, industrial properties which contain a significant quantity of office space (typically 50% of total SF or greater) are categorized as “flex” space, and are explored in the Industrial Market Assessment. Source: CoStar; City of Alexandria
⬚ figure
Figure 47: Deliveries, Absorption, & Vacancy, Class A Office, Washington MSA, 2000-2013 Source: CoStar
⬚ figure
Figure 48: Deliveries, Absorption, & Vacancy, Class A Office, Alexandria, 2000-2013 Source: CoStar
Northern Virginia Office Market, Q2 2014, Transwestern ↩
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
While low rates of Citywide employment growth may not support new office construction, competitively priced, existing Class A space can attract tenants to the area.
Both regionally and citywide, Class B rents have remained largely stable since 2007, though citywide vacancy has increased rapidly since 2010.
⬚ figure
Figure 49: Average Asking Rent and Vacancy, Class A Office, 2000-2013 Source: CoStar
⬚ figure
Figure 50: Average Asking Rent and Vacancy, Class B Office, 2000-2013 Source: CoStar
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The 2005 round of Base Realignment and Closure (BRAC) has resulted in numerous vacant office properties in the City of Alexandria.
⬚ figure
Figure 51: Total Square Feet of Office Space Vacated Due to BRAC,* City of Alexandria, 2011-2017
Eisenhower West only has four office buildings which account for just over 3% of the total office stock in the City of Alexandria.
Regional and citywide office rents have remained flat or declined since the recession, and vacancy rates in the City have surpassed those in the region.
Pre-leasing appears to be the most important factor for new office construction across the region.
Regionally, Class A buildings have higher vacancy rates than Class B buildings, though decreasing Class A rents may begin to attract tenants.
Eisenhower West is currently not the focus of office activity in the City.
In the near-term, the regional and local office market will continue to soften, indicating declining demand for office space in all markets.
There may be opportunities for Eisenhower West to accommodate new office development in the near-term, but likely only if a potential tenant is identified beforehand.
The Victory Center may find a tenant if these trends continue, though will still struggle to compete with more modern Class A buildings elsewhere.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The Eisenhower West industrial market makes up the majority of industrial product in the City, and is characterized by older buildings and limited new development.
Industrial buildings in Eisenhower West are home to a diversity of tenants in warehouse and flex buildings.
| Warehouse | Total Buildings | Total Square Feet | Median Year Built |
|---|---|---|---|
| Eisenhower West | 44 | 2,852,132 | 1967 |
| City of Alexandria | 115 | 3,231,257 | 1965 |
| Eisenhower West as % of City | 38% | 88% |
| Flex | Total Buildings | Total Square Feet | Median Year Built |
|---|---|---|---|
| Eisenhower West | 15 | 578,002 | 1982 |
| City of Alexandria | 62 | 1,161,167 | 1966 |
| Eisenhower West as % of City | 24% | 50% |
Figure 52: Eisenhower West Industrial Inventory
electrical contractors, retail distribution centers, as well as UPS and FedEx truck terminals located on Eisenhower Avenue. There is one large distribution center in the area, the 500,000 SF Plaza 500 building in adjacent Fairfax County, which houses Smoot Lumber and other tenants.
⬚ figure
Figure 53: Plaza 500, 6259 Edsall Road Source: CoStar
⬚ figure
Figure 54: PS Business Park, 4601 Eisenhower Avenue Source: PS Business Parks
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Though vacancy has continued to climb, there have been only a slight decline in rents both in Eisenhower West and the MSA.
The area has delivered few new industrial properties in recent years and has largely experienced negative absorption since 2009.
⬚ figure
⬚ figure
Figure 55: Average Asking Rent, NNN, Warehouse, 2000-2013 Source: CoStar
Figure 56: Average Vacancy, Warehouse, 2000-2013 Source: CoStar
⬚ figure
Figure 57: Deliveries, Absorption, & Vacancy, Eisenhower West, 2000-2013 Source: CoStar
A “triple-net,” or “NNN,” lease is an agreement where the tenant/lessee is solely responsible for all real estate taxes, building insurance, and maintenance on the property. Rental rates noted as “NNN” therefore include these costs, which is common for industrial and retail property (and occasionally office). ↩
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
While Flex in Eisenhower West has typically experienced lower vacancy than the City due to lower rents, in recent years vacancy has surpassed that of the City and the MSA.
The area has delivered no new Flex properties in recent years and has largely experienced negative absorption since 2008.
⬚ figure
Figure 58: Average Asking Rent, NNN, Flex, 2000-2013 Source: CoStar
⬚ figure
Figure 59: Average Vacancy, Flex, 2000-2013 Source: CoStar
⬚ figure
Figure 60: Deliveries, Absorption, & Vacancy, Flex, Eisenhower West, 2000-2013 Source: CoStar
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Excluding Restaurant Depot, no new industrial space has been developed since 1985, resulting in a very old and out of date industrial stock.
Eisenhower West drives the City’s warehouse and flex market, and rents have been consistently higher compared to the MSA.
Vacancy in Eisenhower West has increased for both warehouses and flex buildings, reflecting the age of the buildings and decline in key industry sectors.
The age of many of the buildings may be impacting their competitive advantage over properties elsewhere in the region with more modern layouts, which may negatively impact the long-term competitiveness of the area’s industrial building stock.
Eisenhower West will continue to be competitive in the near-term due to its location inside the Beltway and proximity to customers, and this demand may also drive some level of long-term investment in industrial property.
The future of industrial uses in Eisenhower West will depend in the area’s ability to continue to attract from growing industries and compete regionally.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Eisenhower West currently lacks a robust hotel market.
HR&A analyzed clusters of hotels in and adjacent to Alexandria and grouped them into "primary" and "secondary" markets of at least three hotels. HR&A also identified a single hotel – the Comfort Inn & Suites Alexandria – located near the study area.
Primary markets consist of hotels in areas that are key office clusters and/or heavily visited by tourists. Secondary markets consist of hotels in areas that do not have office clusters, but are adjacent to primary market areas or are accessible to major highways.
There are no hotels within Eisenhower West, and the Comfort Inn & Suites Alexandria is the only hotel nearby, located just outside of the plan area boundary.
Hotels in Eisenhower West are characteristic of those in secondary market areas that offer less expensive accommodations with Beltway access.
Hotels in primary markets primarily consist of the more expensive upper upscale, upscale, and upper midscale chains.1
Hotels in secondary markets primarily consist of economy and upper midscale chains for customers looking for less expensive options without sacrificing accessibility. The Comfort Inn & Suites Alexandria near Eisenhower West is representative of this group.
⬚ figure
Figure 61: Regional Hotel Supply Source: Smith Travel Group , HR&A Advisors
| Market | Hotels | Total Rooms | Primary Classes | Flags | Customer Base |
|---|---|---|---|---|---|
| PRIMARY | |||||
| Old Town/Carlyle | 16 | 2,657 | Upscale, Upper Upscale | Westin, Kimpton, Hilton, et al | Tourists and business visitors |
| Pentagon South | 4 | 934 | Upper Midscale, Upscale | Hampton Inn, Hilton, et al | Business visitors (Mark Center, Bailey’s Crossroads) |
| Tech Center | 3 | 465 | Economy, Upper Midscale | Courtyard by Marriot, Extended Stay, Springhill Suites | Tech Center visitors; customers looking for less expensive options near Old Town/Carlyle |
| Subtotal | 23 | 4,056 | |||
| SECONDARY | |||||
| Landmark | 4 | 552 | Economy, Upper Midscale | Days Inn, Comfort Inn, et al | Customers looking for less expensive options on the Beltway |
| Richmond Highway | 8 | 707 | Economy, Upper Midscale | Days Inn, Red Roof Inn, Holiday Inn, Springhill Suites, etc. | Customers looking for less expensive options near Old Town/Carlyle |
| Hotels Near Eisenhower West | 1 | 143 | Upper Midscale | Comfort Inn & Suites | Customers looking for less expensive options on the Beltway |
| Subtotal | 13 | 1,402 | |||
| Total | 36 | 5,458 |
Figure 62: Alexandria Hotel Markets Source: Smith Travel Group
Chain scales are grouped based on average room rates. In order of least expensive to most expensive, these groups are: economy, midscale, upper midscale, upscale, upper upscale, and luxury. ↩
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Hotel markets in western portions of Alexandria have delivered no new hotels since the late 1990s, and those near Eisenhower West were delivered even earlier.
The hotel market in Northern Virginia has grown, with steadily increasing demand and a similarly increasing supply resulting in a stable occupancy rates since 2008.
| Market | Market Type | Primary Classes | Years Built |
|---|---|---|---|
| Old Town/Carlyle | |||
| Old Town/Carlyle | Primary | Upscale, Upper Upscale | 1960-2014 |
| Tech Center | Primary | Economy, Upper Midscale | 1991-2011 |
| Richmond Highway | Secondary | Economy, Upper Midscale | 1954-2010 |
| Western Portions of Alexandria | |||
| Pentagon South | Primary | Upper Midscale, Upscale | 1975-1996 |
| Landmark | Secondary | Economy, Upper Midscale | 1972-1999 |
| Hotels Near Eisenhower West | |||
| Comfort Inn and Suites | Secondary | Upper Midscale | 1965 |
Figure 63: Alexandria Hotel Markets, Years of Construction Activity Source: Smith Travel Group
⬚ figure
Figure 64: Annual Supply and Demand, Northern Virginia, 2008-2013 (millions of rooms) Source: Smith Travel Group
⬚ figure
Figure 65: Occupancy Rate and RevPAR*, Northern Virginia, 2008-2013 Source: Smith Travel Group * "RevPAR" refers to "Revenue Per Available Room." This metric is calculated by multiplying the average daily room rate by the percentage occupancy, and represents the financial performance of a sample of hotels. RevPAR does not take into account revenue from other hotel services, such as restaurants.
Washington Suites, another hotel located near Eisenhower West, was converted from multifamily apartments to a hotel in 1984. However, the building is currently being converted back to multifamily apartments and is no longer a factor in the local hotel market. ↩
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
While occupancy rates have remained stable in the context of increasing supply and demand, RevPAR has declined significantly.
⬚ figure
The regional hotel market is highly competitive. The relative stability in occupancy rates has been achieved at the expense of hotel revenues, which will impact the potential for new development in both the short- and medium-term.
Hotels in secondary submarkets with flags most likely comparable to what could be supported in Eisenhower West are generally older, particularly in submarkets in western portions of the City and adjacent to the Beltway.
⬚ figure
There may be an opportunity in Eisenhower West for development of a new, mid-priced hotel that would compete with the older products in other highway adjacent locations.
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Appendix C - Market Analysis EISENHOWER WEST Small Area Plan | 55
The Department of Planning and Zoning conducted extensive up-front work to gather information, and frame the planning process. A Steering Committee comprised of landowners and their representatives, local residents, and stakeholders was convened to guide the planning process. A multi-disciplinary consultant team was engaged to provide technical assistance including SmithGroupJJR for urban design, planning, architecture, and energy expertise; HR&A Advisors for expertise with market economics and plan implementation; and Greening Urban for analysis and expertise on the sanitary sewer and sustainable stormwater management elements of the plan. Components of the planning process included:
Throughout the planning process, P&Z staff and the consultant team coordinated with representatives of other City departments including:
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The City conducted a concurrent transportation study for an area encompassing, but larger than, the Eisenhower West study area. The Transportation Study describes and addresses the transportation implications of future development in the area and the potential location, alignment, and impact of a new multi-modal bridge. The bridge would provide additional connectivity between Eisenhower Avenue and the Van Dorn Metrorail station to the south and roadways to the north. The Small Area Plan and the Transportation Study coordinated their efforts throughout the planning process.
In order to coordinate efforts on critical infrastructure elements that support the Small Area Plan, the project team also met with representatives of the following companies:
P&Z staff also coordinated with representatives of Fairfax County’s Department of Planning and Zoning who also attended Steering Committee and Community Meetings.
The Eisenhower West Small Area Plan was approved by the City Council on November 14, 2015..
The Eisenhower West Small Area Plan was developed through a multi-faceted and interactive community engagement process guided by the City-adopted Civic Engagement Principles and supporting practices established in the What’s Next Alexandria Handbook for Civic Engagement. This outreach approach was designed to maximize participation, gather ideas from residents and stakeholders, and ensure a successful and inclusive planning process to achieve the vision and goals for Eisenhower West.
⬚ figure
⬚ figure
Photos from Community Meeting #1
SMALL AREA PLAN MEETINGS
| #1 June 16, 2014 | Issues and Opportunities |
| #2 July 28, 2014 | Vision and Goals |
| #3 September 29, 2014 | Nodes, Connections |
| Green Connections | |
| #4 December 8, 2014 | Framework Plan |
| Conceptual Land Use Options | |
| #5 February 9, 2015 | Concept Plan |
| #6 September 19, 2015 | Draft Plan |
| February 19, 2014 | February 23, 2015 |
| April 29, 2014 | April 27, 2015, |
| June 12, 2014 | May 13, 2015 |
| June 30th, 2014 | May 19, 2015 |
| September 8th, 2014 | June 22, 2015 |
| September 25th, 2014 | July 27, 2015 |
| November 10, 2014 | September 9, 2015 |
| November 24, 2014 | October 14, 2015 |
| January 26, 2015 |
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Steering Committee In early 2014, the Alexandria City Council appointed a 12-member Steering Committee comprised of various commission representatives, community residents, stakeholders, and landowners’ representatives to provide guidance on process related issues, including reviewing and giving feedback on the proposed community engagement, the small area plan boundary, tools and strategies for engagement, agenda setting, community outreach and communications, among other tasks. They also weighed in on technical content elements, such as the project scope and development scenarios for consideration in the transportation study. All 17 Steering Committee meetings were open to members of the public.
Details and materials from all Steering Committee Meetings can be found at http://www.alexandriava.gov/planning/info/default.aspx?id=82036
Community Meetings Six community meetings were held during the course of the planning period and provided key guidance in shaping the vision of the plan. Each meeting consisted of a presentation by P&Z staff and the consultant team followed by interactive exercises designed to solicit ideas, opinions and feedback on the concepts, options and materials presented. The meetings were designed to be iterative; each successive meeting recapped the previous and built on its results. Doing so illustrated to participants the logical progression and layering of ideas that resulted in the major elements that make up the Eisenhower West Small Area Plan.
Materials from all meetings can be found at http://www.alexandriava.gov/82036
Community Meeting #1: Issues And Opportunities Planning and Zoning staff introduced the Eisenhower West Small Area Plan project and described the project boundaries, scope, schedule and planning process, and the role of the Steering Committee. They also described the scope of the Transportation Study and the coordination that would take place with the Small Area Plan. Participants engaged in a discussion of key issues and opportunities related to the major elements of the Small Area Plan.
Community Meeting #2: Vision And Goals An interactive exercise was conducted to help community members envision the future of Eisenhower West. Participants were asked to describe what they liked about Eisenhower West and what they would like to see improved. An artist recorded the results of the discussion, producing the graphic image shown below.
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
Photos from Community Meeting #2
Photos from Community Meeting #3
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Attendees also participated in a dot exercise indicating preferences regarding Land Uses and Building Heights, Parks and Public Spaces, and Amenities and Streetscape Elements for four sub-areas within Eisenhower West.
A third visioning exercise asked participants to think about the places that they were familiar with in Eisenhower West, and place dots on a map showing locations they thought should be preserved, enhanced, or transformed.
The draft goals for the Small Area Plan were described and participants were given the opportunity to comment on the wording. A small group drawing exercise followed in which participants identified the locations of key existing and future nodes, or centers of mixed-use activity. They also determined the appropriate scale for a network of blocks and street connections and where important new green connections and spaces should be placed as well as which existing spaces should be enhanced. Each group then presented their ideas for these framework elements for the plan to the larger group. The discussion revealed commonalities and presented new ideas for the group to weigh in on.
A presentation of two versions of a draft Framework Plan were presented, resulting from the small group exercises that were conducted at Community Meeting #3. The Framework Plan illustrated the general consensus that was developed during the previous meeting on the locations of future mixed-use nodes, a potential future grid of streets and blocks, and green connections and open spaces throughout Eisenhower West.
A discussion of land use types and a presentation of four conceptual land use options for the future of Eisenhower West followed. The options illustrated through diagrams and images different approaches for distributing land uses in order to achieve the community’s vision for the plan area, while integrating the elements of the Framework Plan. A small group exercise was conducted after the presentation during which participants discussed the strengths and weaknesses of the overall concepts and of specific elements of each concept. Each small group then presented their findings to the attendees for additional discussion and feedback.
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
⬚ figure
Photos from Community Meeting #4
Photos from Community Meeting #5
Appendix D - Community Engagement EISENHOWER WEST Small Area Plan | 59
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The concept plan developed throughout the community engagement process was presented including its component elements, such as the characteristics of a “Great Street” and land uses (retail, office, civic, institutional, mixed use, residential, flex space).
The presentation further described the idea of “green fingers”, options for the multimodal bridge, and how the refined land use concept plan was derived by layering the plan elements of nodes, existing streets, future streets and connections, parks and green fingers, blocks, land uses, and heights.
⬚ figure
⬚ figure
The Draft Small Area Plan was presented during the 6th and final community meeting and began with an introductory presentation by Planning Director Karl Moritz describing the background and goals of the plan for Eisenhower West. This was followed by a recap of the results of the planning process and previous community meetings. The major elements of the plan were presented including the overall concept for the plan; the land use, transportation and connectivity, parks and open space, and sustainability elements of the plan including energy, sanitary sewer and stormwater. An illustrative drawing and perspective renderings
⬚ figure
Photos from Community Meeting #6
⬚ figure
Image from AlexEngage web page for Eisenhower West
60 | EISENHOWER WEST Small Area Plan
Appendix D - Community Engagement
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
of the plan provided more detailed information on the plan and on proposed improvements to each of the 6 neighborhoods within the plan area. Participants then circulated to stations where they could discuss specific elements of the plan, ask questions and provide feedback to the planning team. The Draft report was posted on AlexEngage to solicit additional comments online.
An essential part of the engagement strategy was an interactive online component that supplemented the Steering Committee and Community Meetings. P&Z posted information from the meeting using the City's AlexEngage website (http://engage.alexandriava.gov) providing a platform for polling, comments, and feedback on specific questions. Both participants who attended the Community Meetings, as well as those who could not attend, had a platform for giving additional feedback. Online engagement played an integral role in updating the public on the progression of the planning process, and the concepts and ideas being developed.
The Eisenhower West Small Area Plan builds on and is informed by several previous plans and studies including:
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
⬚ figure
Eisenhower West Plan Area
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
The urban areas illustrated here are showbn at the same scale as the Eisenhower West plan on the previous page.
Similarities to Eisenhower West
⬚ figure
⬚ figure
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
| Phase 1 (1990) | Phases 1+2 (2009) | |
|---|---|---|
| Retail* | 240,000 sf | 360,000 sf |
| Office | 530,000 sf | 2.1 million sf |
| Residential | 360 units | |
| Theater | 13 screens | 13 screens |
| Hotel | 514 rooms | 514 rooms |
| Parking | 7,000 spaces (6 garages + 1 surface lot) | |
| Open Space | Fountain Plaza | Fountain Plaza |
| Site | 20.6 acres | 85 acres |
*Retail area includes theater
⬚ figure
Reston Town Center
⬚ figure
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
| Phase 1 (2012) | Phase 1+2 | |
|---|---|---|
| Target | 170,000 sf | 170,000 sf |
| Other Retail | 170,000 sf | 350,000 sf |
| Office | 75,000 sf | 170,000 sf |
| Residential | 782 apartments, 138 townhomes | |
| Theater | 8 screens | 8 screens |
| Hotel | 148 rooms | 148 rooms |
| Parking | 2,000 spaces | 4,000 spaces, 2 garages |
| Open Space | 1 acre park | 2 acres of park |
| Site | 31 acres | 31 acres |
TOWN CENTERS
⬚ figure
⬚ figure
Mosaic District
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
| Retail | 40,000 sf |
| Residential | 500 units |
| Site | 25 acres |
⬚ figure
⬚ figure
⬚ figure
⬚ figure
Hyattsville Arts District
TOWN CENTERS
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
| 2007 | |
|---|---|
| Office, Retail, Restaurants | 180,000 sf |
| Residential | 644 units |
| Library | 102,000 sf |
| Parking | 1,900 spaces |
| Site | 12.5 acres town center |
| 60 acres total |
Key Elements
⬚ figure
⬚ figure
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
| 2015 | |
|---|---|
| Walmart | 125,000 sf |
| Other Retail | 10,000 sf |
| Residential | 345 units |
| Parking | 775 spaces, below grade and structured |
| Site | 4.6 acres |
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
| 2008 | |
|---|---|
| Target | 180,000 sf |
| Other Retail | 695,000 sf |
| Local Retail | 15,000 sf |
| Parking | 1,000 spaces, below grade |
| Site | 5 acres |
Key Elements
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
| Tivoli Giant | 2005 |
| Giant | 55,000 sf |
| Parking | 2 levels above |
| Petworth Safeway | 2014 |
| Safeway | 62,500 sf |
| Residential | 218 units |
| Parking | 215 spaces, below grade |
⬚ figure
⬚ figure
Amended 12/16/23, Ordinance 5514 Please refer to Notes 1, 2, and 3 on page i
Posted on June 23, 2014 by Ilana Preuss
There is a new opportunity in our changing cities to connect more residents with economic opportunity. We can do so by integrating small-scale industrial uses into our city development. Let's call this mixed-use industrial real estate.
⬚ figure
Greenpoint Manufacturing and Design Center
We are seeing a resurgence of small, local producers who are harnessing low-cost technology and changing markets to sell hundreds and thousands of locally produced consumer products. Documented early on by Chris Anderson, and seen across the country today, these companies are often businesses with fewer than 20 employees and sell both in local markets and globally online.
These small-scale manufacturing business owners generally need dedicated production space of less than 5,000 square feet (often as little as 1,000 sq. ft), use clean technologies (think laser cutters), but need affordable, dedicated industrial/production space. They do not fit into office space because of noise, and most retail space is too expensive. So they often find marginal, cheap space at the fringes of our cities and survive on short-term leases or move far out into the suburbs.
The time is ripe for policy change and private sector investment to create this kind of development. The demand for small-scale consumer goods and locally made custom goods are growing, while access to tools and technology gets cheaper. We need to provide affordable space for our local producers to grow their businesses in our city neighborhoods. By doing this, we will be able to connect more people to good-paying jobs, strengthen our small business and startup sectors, and keep these jobs in the city.
Defining mixed-use industrial
A mixed-use industrial development is part of a reuse project that includes new buildings and rehabilitated older buildings, or the rehabilitation of an existing industrial/warehouse structure within a neighborhood with a variety of land uses. New construction is also possible, but the costs need to be offset within a larger project. Two examples begin to illustrate the opportunities for this product type.
⬚ figure
INDUSTRIAL MIXED-USE ZONING An analysis of design considerations AsianNeighborhoodDesign Draft: 02.23.07
"small-scale manufacturing business owner generally need dedicated production space of less than 5,000 sf (often as little as 1,000 sf), use clean technologies (think laser cutters), but need affordable, dedicated industrial/ production space. They do not fit into office space because of noise, and most retail space is too expensive"
"A mixed-use industrial development is part of a reuse project that includes new buildings and rehabilitated older buildings...within a neighborhood with a variety of land uses. New construction is also possible, but the costs need to be offset within a larger project."
At Greenpoint Manufacturing and Design Center "the average tenant is about 18 years in business, and average salaries are $48,000 - well above local service sector salaries. The tenants are predominantly local artisans building products for the local market, but at manufacturing scales."
Steps for shaping mixed-use industrial spaces:
Zone for it: Communities need to protect existing industrial properties in targeted locations. Small-scale production can also be added as an optional use to other existing zones.
Provide financing and incentives: ...tools such as New Markets Tax Credits or Rehabilitation Tax Credits will be important for industrial redevelopment efforts...
Support business development: Producers should organize themselves to strengthen their community and exposure. Activities like meetups, showcase events, and local competitions all help promote a local producer sector... Partnering with shared tool spaces like TechShop can help identify future business members.