Chapter 6 - Fiscal Management & Public Infrastructure

Table of Contents

Vision ........................................................................................................................................................ 3
Introduction .............................................................................................................................................. 3
Public Facilities ........................................................................................................................................ 4
Open Space Assets ................................................................................................................................... 7
Utilities & Infrastructure ......................................................................................................................... 10
Fiscal Management ................................................................................................................................. 13
Policies, Strategies, and Actions ........................................................................................................... 16
Reference Maps ....................................................................................................................................... 35

This page left blank for printing purposes.

Chapter 6 - Fiscal Management & Public Infrastructure

Vision

Provide high quality, efficient, and environmentally sensitive infrastructure systems supporting growth management goals and delivering innovative services to the community.

Introduction

Sustained growth since 2000 requires Loudoun County to meet a significant demand for new public facilities, such as parks and recreation, fire and rescue, and schools. While the County has maintained a reputation for quality facilities and services and sound fiscal management, funding and competing priorities have led to a shortfall or delay in certain public facilities. As the County has grown, the increasing scarcity of land and the diversity of facility and service needs has further affected the County’s ability to meet demands. Service providers have employed various measures to adapt to these challenges. Schools are being designed to fit on smaller parcels. Libraries are sharing commercial space in Brambleton and Stone Ridge and Sheriff’s Office substations are co-located with Fire and Rescue stations. The Loudoun County 2019 Comprehensive Plan (Comprehensive Plan) supports continued innovation, particularly in co-location and site design to not only add new facilities but to better adapt to changing community design, particularly in compact mixed use and transit-oriented developments.

Loudoun County maintains close connection between land use and fiscal planning. Managing utilities, principally sewer and water, has directly influenced where new development occurs. Consistent policies and close collaboration with Loudoun Water has allowed the County to maintain an urban growth boundary and to subsequently focus other investments in roads and public facilities in eastern Loudoun. Loudoun Water’s strategy for a long-term water supply and its investment in high-quality water and sewer treatment has provided the County with a strong basis for growth decisions. The Comprehensive Plan does not address the fiscal management and operational priorities of entities that operate key utilities serving County residents but are independent of the County. Nonetheless, the cooperative relationship between the Board of Supervisors (Board), Loudoun Water, the Virginia Department of Environmental Quality (DEQ) and other entities continues to ensure a close connection between infrastructure and land use planning.

The County’s fiscal policy requires the Board to adopt a ten-year Capital Needs Assessment (CNA) every four years and adopt a six-year Capital Improvement Program (CIP) during the Board’s budget deliberations. The annual CIP funding plan and budget then align annual capital expenditures with County fiscal policy. The County has relied on proffers to mitigate capital and transportation costs, consistent with the authority granted through state enabling statutes. That funding mechanism has proven less effective in recent years due to state-imposed constraints on use of proffers as well as a changing development environment. The Comprehensive Plan supports the continued use of proffers and proposes changing the calculation of capital facilities impacts to address transportation needs and expanding the proffer process to the Transition Policy Area. The

Plan also encourages the Board to seek legislation authorizing a reasonable impact fee program that would apply to all residential building permits throughout the County.

Loudoun County maintains a strong commitment to preserving open space and agricultural land and protecting natural, environmental, and heritage resources. Conservation easements in 2018 protect over 72,000 acres of land throughout the County. The County holds over 26,000 acres of these easements. Over the years, County policies have emphasized preserving open space in its natural setting, undisturbed, to protect the environmental value of the space. The Comprehensive Plan recognizes the community desire and economic value to expanding public access to and enjoyment of open space through trails and recreational uses. A key objective is to create a connected network of parks, trails, and natural areas, which can offer expanded environmental, design, and recreational benefits.

Public Facilities

The County’s fiscal management strategy is designed to anticipate and accommodate the impacts of increased demand for public services and facilities. As discussed in the Fiscal Management section of this chapter, careful development forecasting—including its location, type, and timing—is essential to anticipating facility needs. The County projects the capital needs associated with development proposals to determine expected impacts on public facilities and to calculate anticipated contributions to mitigate a project’s “fair share” of those impacts. Major components of the land use picture in Loudoun are public schools, parks and recreation, libraries, and emergency services. These important elements of the community fabric typically require land proximate to new development.

Loudoun County Public Library

Loudoun County Public Library (LCPL) is the information center of the community, providing free and equal access to innovative technologies and a full range of library resources to enhance the quality of life and meet the informational, educational, and cultural interests of the entire community. LCPL provides library materials, programs, technology, and services. It promotes the joy of reading and lifelong learning through early literacy programs, teen initiatives, humanities and arts events, technology training, and other educational opportunities.

⬚ figure

Brambleton Library is a 40,000 square foot facility located in Brambleton Town Center. The state-of-the-art facility includes a “maker space” with 3D printer, laser cutters, recording studio, and other creative technologies.

LCPL currently has ten branches ranging in size from 4,000 square feet to 42,000 square feet. The Ashburn, Cascades, Lovettsville, Middleburg, Purcellville, and Rust branches are standalone facilities, while Gum Spring, Law Library, Brambleton, and Sterling share structures with businesses or other County facilities. LCPL Administration shares space in Leesburg with the Leesburg Senior Center.

LCPL continues to evolve to meet the needs and expectations of the community. The Library is expanding language learning services to non-native speakers. It also offers more Science, Technology, Engineering, and Math (STEM) programs, which are complemented by “maker spaces” that include 3D printers, robotics, recording studios, design software, computer labs, and other equipment for creating and learning. High-speed wireless internet access is essential to customers and is available at every facility. In addition, demand for conference and study rooms continues to rise; thus large, multi-purpose rooms are an essential component for current and future branches. Also, as the number of residents without personal transportation increases, locations that offer ease of access through public transportation are increasingly important.

LCPL recognizes the need to locate in high community activity areas and adapt to the County’s changing development patterns. For example, in recent years LCPL has opened facilities in commercial space in Brambleton Town Center and in Stone Ridge. Libraries have also located with or near senior centers, parks, and schools. Library programming is similarly evolving to accommodate community activities and educational programs that meet new needs of area residents.

Department of Parks, Recreation, and Community Services

The Department of Parks, Recreation, and Community Services (PRCS) operates a system of County-owned or maintained facilities that includes over 1,700 acres of open space, more than 60 miles of trails, 200 athletic fields, 27 parks (including three regional parks), 18 playgrounds, 10 community centers, six sports complexes, two indoor and two outdoor swimming pools, four historic/heritage sites, three adult day centers, and three senior centers. PRCS also operates a senior activity center, a recreation center, a nature preserve, a nature center, a performing and visual arts center, an industrial catering kitchen, and administrative offices.

⬚ figure

Dulles South Recreation and Community Center features the latest fitness equipment, climbing wall, competition swimming pool, leisure pool with lazy river, vortex, 125-foot slide, hot tub, sports courts, and indoor jogging track. The Center also offers licensed preschool classes, full-day childcare, after-school programs, summer camps, trips, and other recreational opportunities.

PRCS and Loudoun County Public Schools cooperatively offer activities at County school sites. Programs and services comprise childcare, preschool, after-school care, sports and recreation, community outreach, aging services, youth services, adaptive recreation, summer camp, health and fitness, planning and development, facility maintenance, customer service, and environmental stewardship. Offerings include sports activities for youth and adults, instructional and interpretive classes, programs for senior citizens, visual and performing arts, child care, preschool, after school activities, trips, camps, special events, volunteer opportunities, educational and prevention programs for youth, and programs for individuals with disabilities. In 2018, annual park visits for special events totaled 875,000. Over 55,000 children participated on sports teams and over 156,460 meals were served to senior residents.

PRCS faces significant challenges securing additional parks and trails to meet the service demands of the County’s growing population. A lack of available land in eastern Loudoun, where the facilities are needed most, complicates the County’s ability to provide the desired facilities. A decreasing supply of land also means rising land values, which affects contributions of land for parks facilities. Changing development patterns in eastern Loudoun, such as the urban development around the Metrorail stations and other high-density developments, will require new recreation concepts. Changing demographics will likewise necessitate new types of facilities. For example, the population of residents 55 years and older increased nearly 50 percent from 2010 to 2016, resulting in higher numbers of older adults seeking not only recreational programs, but also other support services. PRCS offers community outreach events and increasingly serves as a conduit for a variety of services to the senior population.

Loudoun County Public Schools

Loudoun County Public Schools (LCPS) is the third largest school division in the Commonwealth of Virginia. Each year, approximately 2,500 new students enroll and one-to-three new school facilities are opened to accommodate them. In 2018, LCPS served more than 83,000 students in 92 facilities including 15 high schools, 16 middle schools, 57 elementary schools, and four special purpose schools (Academy of Engineering and Technology, Academy of Science, C.S. Monroe Technology Center, and Douglass School).

⬚ figure

The LCPS student Class of 2017 had an on-time graduation rate of 95.5 percent and earned more than $54.7 million in scholarships. The Virginia Department of Education reports that 100 percent of LCPS schools were fully accredited in 2017. The student body is ethnically and economically diverse, with 52 percent of the population reporting as African American, Asian, Hispanic, or multi-racial. Approximately 19 percent of the student population is identified as economically disadvantaged. This cultural and economic diversity raises the need for a variety of academic and extracurricular programs to assist students, particularly in elementary schools, which have the highest percentage of economically challenged students.

Increasing demand for services is placing significant pressure on the school system, which each year must hire hundreds of additional classroom teachers and staff, expand support systems, and open multiple new schools. Families continue to endure shifting school boundaries as new students are assimilated into the school system. Securing building sites for new schools that are cost-effective but that also reflect their important social and civic functions in terms of location and design is an ongoing challenge. Changing development patterns in eastern Loudoun further complicate these issues. In the past, the County has relied on the donation and timely delivery of proffered school sites from the development sector. However, the supply of sites has not kept up with demand or with the LCPS construction timetable.

Urban development around the Metrorail stations and other high-density developments will require innovative designs for new school facilities using less land and more vertical designs. Alternative school configurations that established urban communities have used successfully, such as shared space and public/private facilities, will become increasingly important.

As the population increases and continues to diversify, schools will likely continue to play a larger community role, such as accommodating a variety of non-school activities, sharing recreational facilities with the public, co-locating with compatible uses such as libraries, affordable housing and other services, and opening classrooms and space to other organizations.

Loudoun County Fire and Rescue

Loudoun County Fire and Rescue (LCFR) delivers essential emergency and non-emergency Fire and Emergency Medical Services (EMS) from 19 stations, responding to more than 29,000 incidents annually. LCFR, as part of the Loudoun County Combined Fire and Rescue System (LC-CFRS), provides administrative, operational, and logistical support to the County’s 15 volunteer fire-rescue companies, the LC-CFRS Executive Committee, and its governance structure. Through the Oliver Robert Dubé Training Academy, LCFR coordinates the delivery of certification and continuing education programs for all LC-CFRS members. LCFR functions as the Public Safety Answering Point (PSAP) for the County’s 9-1-1 system and operates the County’s emergency communications system. The Fire Marshal’s Office (FMO) has a multifaceted mission that includes fire prevention; fire lane plans review; life safety education; community risk reduction; investigation of fires, explosions, and hazardous materials releases; and an oversight of the bomb squad.

⬚ figure

The Loudoun County Combined Fire and Rescue System represents a joint effort of volunteer and career personnel responding to emergency incidents 24 hours a day.

LCFR has been in a consistent state of transition as the County has grown, moving from an all-volunteer system to a combined system, serving an increasingly suburban environment, and responding to growing service demands. As areas of the County transition to a more urban development pattern, LCFR will continue to adapt to different demands and environments. Compact and higher density development and the introduction of Metrorail will affect emergency response times and equipment and training needs, and introduce other new challenges. In rural Loudoun, ongoing areas of attention will include updating existing stations and meeting service demands associated with growth in the rural economy.

Open Space Assets

Open space assets as defined in this chapter include linear parks, trails, recreational areas, and passive open space. These assets make up much of the County’s network of natural resources and

may be held in private or public ownership. The County, conservation partners, and individual property owners manage these elements through the regulation of protective buffers, performance standards, and stewardship of open space easements

The open space assets addressed by this Chapter are aimed at enhancing and encouraging public interaction with the County’s network of natural resources through:

a. A network of linear parks and other recreational resources along or extending from the banks of the Goose Creek, Broad Run, Bull Run, Catoctin Creek, Potomac River, and other river and stream corridors to form an interconnected system of linear open space. b. Trails within and among communities that offer potential for walking and bicycling, and connecting neighborhoods to parks, schools, and other community destinations. c. Forested areas along public rights-of-way, within neighborhoods, and elsewhere to filter air pollutants, provide shade, screen uses, and define communities and places. d. A network of active and passive parks of various sizes and functions throughout each community to beautify neighborhoods and offer opportunities for recreation.

⬚ figure

Elizabeth Mills Riverfront Park consists of over 100 acres of passive parkland with access to the Potomac River and Goose Creek.

NOVA Parks

NOVA Parks is a regional park authority that is steward to over 12,000 acres of parkland in Northern Virginia, with over 3,800 acres within Loudoun County making a significant contribution to recreation and open space in the County. NOVA Parks' 16 Loudoun offerings include a large portion of the W&OD Trail, a working farm, two golf courses, a group camping site, a water park, and several historic properties. Annually, millions enjoy a ride or walk along the 45-mile W&OD Trail, which is a recreation and transportation artery for visitors and commuters year round. Many thousands camp, hike, boat, golf, swim, or otherwise spend their time in a regional park. Many of NOVA Parks' lands were acquired with the idea to preserve shoreline properties. With over 30 miles of river frontage, many of NOVA Parks' land holdings are among the most environmentally important areas and, with 12 parks region-wide with water access, its parkland is a hub for boating in and around the area.

NOVA Parks is the only regional park authority in the commonwealth and excels at partnerships. Three Counties and three Cities support the regional park system: Loudoun, Arlington, and Fairfax Counties, and the Cities of Alexandria, Fairfax and Falls Church. NOVA Parks' foundation of conservation, enterprise, and regionalism has served the public since 1959. As a public sector government agency, only 13% of operating revenue comes from tax dollars; the rest is generated from enterprise operations. Its member jurisdictions contribute $1.89 per capita for operating support.

NOVA Parks' contributions to parks, open spaces, and trails in Loudoun County include:

Aldie Mill Historic Park. Aldie Mill offers visitors and students a glimpse of life during a time when the Mill served as a vital center of the community. Aldie Mill emerged as the largest manufactory of its kind in Loudoun County and survives today as one of the best preserved historic mills in the Commonwealth.

Algonkian Regional Park. Loudoun County joined NOVA Parks in 1973, after NOVA Parks purchased 511 acres of land along the Potomac River that became Algonkian Regional Park.

Ball's Bluff Battlefield Regional Park. Preserves the site of the largest Civil War engagement in Loudoun County.

Battle of Upperville/Goose Creek Bridge Historic Park. In 2017, NOVA Parks acquired the Battle of Upperville/Goose Creek Bridge Historic Park, not far from Mt. Defiance.

Blue Ridge Regional Park. Located on the eastern slope of the Blue Ridge Mountains, this property offers an escape to the mountains for group camping.

Brambleton Regional Park and Beaverdam Reservoir Park. Loudoun Water has partnered with NOVA Parks to manage recreational activities and public access at Beaverdam Reservoir. When completed, the park will be among the largest NOVA Parks facilities offering rowing, a public boat launch, and an 8-mile hiking trail.

Gilbert's Corner Regional Park. Immediately adjacent to the Mt. Zion property is Gilbert's Corner Regional Park, which was the site of Civil War history.

Mt. Defiance Historic Park. Through a partnership with the Civil War Trust, NOVA Parks acquired Mt. Defiance Historic Park outside of Middleburg, a key point of the Battle of Middleburg.

Mt. Zion Historic Park. Mt. Zion Old School Baptist Church, built in 1851, sits at the intersection of the Old Carolina Road and the Little River Turnpike. The church was an eyewitness to much of the history of this area, in particular the Civil War.

Red Rock Wilderness Overlook Regional Park. This park is home to several historic buildings, native plants and wildlife, and scenic vistas of the Potomac River.

Rust Nature Sanctuary and Manor House. In 2013, NOVA Parks and the Audubon Naturalist Society entered into a partnership to manage Rust Sanctuary. The sanctuary has nature trails, event space, and education programs.

Seneca Regional Park. 104 acres of this park are located within the County at its border with Fairfax County. The park includes the remnants of George Washington's Potowmack Canal and is bisected by the Potomac National Heritage Trail.

Springdale. Located on the Potomac River, this 150-acre land holding with historic antebellum structures will become Springdale Regional Park as funding becomes available.

Utilities & Infrastructure

Sewer and Water (See also Chapter 2, Towns and JLMA)

On May 27, 1959, the Board took action to create the Loudoun County Sanitation Authority as a public body politic and corporate under the provisions of the Virginia Water and Waste Authorities Act. This body, now known as Loudoun Water, is chartered by the State Corporation Commission and is responsible for providing water and wastewater service to unincorporated areas of Loudoun County. As a political subdivision of the State, Loudoun Water is not a department of the County government and receives no tax money from the County. All Loudoun Water income is received from customers as payment for water and sewer service or as connection (tap) fees from land developers. Loudoun Water is governed by a Board of Directors consisting of nine members, each appointed by the County Board. Members of the Loudoun Water Board of Directors serve four-year terms and can be reappointed.

Loudoun Water owns and operates water and wastewater treatment facilities and systems and has purchased capacity for wholesale water supply from Fairfax Water and wastewater treatment from DC Water. These water and wastewater systems serve the eastern region of Loudoun County. The Potomac River is the primary source of water for Loudoun County and the greater Washington, D.C. Metropolitan Area. Loudoun Water further benefits from using the Goose Creek and Beaverdam Creek Reservoirs, and may use reservoirs created from retired rock quarries for storage in the future. With numerous water supply sources and local reservoirs, Loudoun Water has a resilient system to meet the demand for safe and healthy drinking water. To ensure the overall environmental quality of the water supply (watersheds and aquifers), Loudoun Water supports broad-based source water protection, management, and stewardship programs.

⬚ figure

In the western region of the County, Loudoun Water currently owns and/or operates smaller water and wastewater treatment systems. Community water and wastewater systems are freestanding systems usually serving residential developments that were installed by developers and are now operated and managed by Loudoun Water. These systems are also funded in part by the County, which has an active program of rectifying public health issues in a number of historic villages. There are additional expenses and inefficiencies associated with building and operating such systems and historically the cost was borne by the relatively few system users. In April 2016, the Loudoun Water Board of Directors adopted a single rate for all customers; that is, those served by the central facilities as well standalone community systems, the costs of which are materially greater to install and operate. Land use policies going forward need to recognize the added cost burden that central system customers bear due to standalone community systems.

Incorporated towns in the County operate their own municipal water and sewer systems. Water is drawn from springs or wells and, in the case of Leesburg, also drawn from the Potomac River.

Leesburg, Hamilton, and Round Hill have extended utilities into the surrounding Joint Land Management Areas (JLMA). The Comprehensive Plan does not recommend extending municipal systems into adjacent rural areas except when necessary to resolve public health issues in existing communities.

Loudoun Water’s Capital Improvement Plan (CIP) is a 10-year roadmap for creating, maintaining, and funding present and future infrastructure needs.1 The Loudoun Water CIP is approved by the Loudoun Water Board of Directors. Capital water and wastewater improvements are complex and interrelated and often require a great deal of planning over many years to define their extent, location, and cost. The underlying strategy of the CIP is to plan for facilities necessary for the safe and efficient delivery of water, wastewater, and reclaimed water services in accordance with policies, goals, and objectives adopted by Loudoun Water. A critical element of a balanced Capital Improvement Plan is to preserve and enhance existing facilities as well as provide new assets to respond to growth of the community and changing service needs as outlined in the Comprehensive Plan and other Board policies.

Waste Management

The Loudoun County Department of General Services, Waste Management Division operates the Solid Waste Management Facility (“landfill”) and provides recycling opportunities for residents and businesses. Landfill operations are fee-supported. The County also offers recycling drop-off centers, household hazardous waste collection events, collection of seven materials for recycling or diversion at the landfill, and educational programs. The County anticipates continuing operations at the Evergreen Mills Road landfill site and relying on continued recycling and commercial facilities to redirect a significant amount of waste material. International demand for recycled material is, however, a key factor in the success of recycling programs. Continued review and updating the County’s Solid Waste Management Plan will provide the more detailed management and planning necessary to meet State requirements to anticipate future needs.

Energy

Electrical demand in the region has steadily increased with the growth of business and residential development and the continued expansion of the data center industry. Data centers are among the highest consumers of electricity within the County. Electric providers in recent years have completed upgrades to existing high voltage transmission corridors and have received and/or are seeking approvals for other routes in the County to deliver bulk electricity to the region and to concentrations of data centers where existing and future load growth are forecasted. The County and electrical providers anticipate that additional construction and/or upgrades to the existing high voltage transmission network will be required in portions of the County to meet current and forecasted electrical demand associated with future development. These improvements to the transmission network are required to ensure that federally mandated reliability standards for the electric grid are maintained within certain limits if one or more components of the transmission network were to fail.

High voltage electrical transmission lines are crucial to the delivery of large volumes of bulk electricity over long distances from generating facilities to local utility substations where the high

Footnotes

  1. The Loudoun Water Capital Improvement Plan can be accessed at www.loudounwater.org.

voltage electricity is reduced to a lower voltage before being conveyed through a network of distribution lines to the end-users within the community. In Virginia, the Commonwealth regulates the placement of high voltage transmission lines which are electrical lines with voltages equal to or greater than 138 kilovolts (kV). High voltage transmission lines are generally constructed overhead on galvanized metal lattice, H-frame or monopole towers that range in height from 125-feet to 180-feet and require a cleared right-of-way (ROW) that is typically the approximate height of the towers. High voltage transmission lines may be placed underground in some instances, though construction costs are higher, underground utilities, fiber, roadway and environmental conditions may pose engineering challenges, and the maintenance, operation, and repair of the buried lines are more complex. As such, underground lines represent only a small percentage of the number of high voltage transmission lines within Virginia.

As of 2025, approximately 37 miles of 500 kV transmission lines, 125 miles of 230 kV transmission lines, and ten miles of 138 kV transmission lines have been constructed overhead, and two miles of 230 kV transmission lines have been constructed underground in the County. The backbone of the County’s transmission system is the 500 kV and 230 kV lines that run north to south through the middle of the County. The primary 230 kV transmission lines serving portions of eastern and western Loudoun are located proximate to portions of the Washington and Old Dominion Trail, the Broad Run, VA Route 7, US Route 50, and through “Data Center Alley” adjoining Waxpool Road and Loudoun County Parkway (see Electrical Infrastructure Map). Rather than a centralized, regional substation to serve the County’s growing electrical demands, smaller substations have been constructed to serve geographic areas and individual high energy users. As demand for increased electricity continues, greater consideration should be given to the location and appearance of transmission lines, substations and distribution lines to provide adequate siting and screening of these facilities to reduce the visual impact on the community.

Electrical services are provided under the purview of state and federal agencies, which limits the County’s ability to mitigate impacts of electrical infrastructure. For example, the county regulates the location of electrical substations but not the high voltage transmission lines to and from the substations. In Virginia, the State Corporation Commission (SCC) regulates the location and construction of high voltage transmission lines through the issuance of a Certificate of Public Convenience and Necessity.1 When reviewing and approving applications for high voltage transmission corridors and facilities, the SCC considers several criteria which include the need for the transmission line and the impact on the reliability of electrical service, impacts on the environment, including scenic assets and, historic and cultural resources, impact on economic development, and if requested by the County in which facilities are proposed to be built, duly adopted local comprehensive plans.2 Electric transmission lines of 138 kV or more, when approved by the SCC are deemed to satisfy the requirements of the Zoning Ordinance.3

The Loudoun County 2019 General Plan includes an Electrical Infrastructure Map that identifies all existing and approved high voltage transmission corridors and supporting policies that serve as a guide for the placement and development of electrical infrastructure. To minimize community

Footnotes

  1. Virginia Code-56-265.2.

  2. Virginia Code 56-46.1. (A & B)

  3. Virginia Code 56-46.1. (F.)

Loudoun County 2019 General Plan

and environmental impacts, the policies establish the County’s preference to collocate and/or expand existing and approved transmission corridors where feasible. The County also supports the deployment of new technologies, such as smart grids and advanced conductors to optimize the ability of the existing high voltage electric transmission network to efficiently serve the County and limit the need for new transmission corridors. The County’s electrical infrastructure is anticipated to evolve through the integration of renewable electric sources, energy storage facilities, and electric generation facilities that enhance the supply of electricity, as well as other technologies that improve the performance, efficiency and reliability of the electrical network.

The expansion and development of the County’s electrical infrastructure to address future load growth and ensure the reliability of the network requires deliberate planning and collaboration between both the County and electrical providers. The electrical policies provide guidance on the location, siting, design, and aesthetics of high voltage transmission corridors and electrical infrastructure that align with County and community objectives to minimize adverse effects on environmental, historic, and natural resources as well as existing and proposed land uses. The electrical policies serve as a guide for electrical providers, County Staff, elected officials, and other governmental decision-makers when planning and considering where and how high voltage transmission corridors and improvements to the electrical network are constructed and managed within the County.

Communication

Broadband internet service is an increasingly important asset to business in Loudoun as e-commerce grows throughout the nation. The lack of broadband service in western Loudoun is cited as a major constraint on the rural economy. It also puts western households and students in particular at a disadvantage. County efforts to extend broadband service have included regulatory changes to support new technologies. With limited control over market factors and federal regulation, the County will encourage landowners to install conduits and other infrastructure to help minimize the cost of extending the service, and will explore other incentives to encourage network expansion. The County may review the location of cell towers and monopoles for impacts on surrounding properties, but cannot prescribe locations and, therefore, cannot require broadband or communication service in underserved areas. The county does, however, work with providers to encourage improved service and locations

Fiscal Management

Loudoun County uses an integrated approach to land use and fiscal planning. This approach uses demographic forecasting models, as well as service and facility standards, to help determine current and future capital facilities needs in the County. The Board established Loudoun County’s Fiscal Impact Committee (Committee) in 1992. This Committee reviews assumptions about future growth and capital facility needs. The Committee also provides recommendations to the Board on four key documents that the County uses to coordinate land use and financial planning: 1) long-range forecasts and demographic, economic, and financial information included in the Fiscal Impact Committee Guidelines; 2) Capital Facility Standards (CFS); 3) CNA; and 4) Capital Intensity Factors (CIF).

The capital facility planning and budgeting processes are different, but completely interrelated. CFS, CNA, and CIF are the three main aspects of the capital facility planning process that shape

CHAPTER 6-13

the CIP budget. The capital planning processes are integral in the development of:

  1. Capital-facility-related cash, land, and other in-kind proffer dedications to the County as a result of land use applications;
  2. The development of the type, timing, and geographical placement of capital projects to be considered for funding in the CIP; and
  3. The programmed use of proffers for capital facility development in the CIP.

Capital Needs Assessment

The CNA divides the County into ten planning subareas and uses the County’s forecasted population growth and adopted CFS to identify the type and quantity of facilities needed in each subarea. The CNA time period extends for ten years beyond the most recent CIP period. Using the population standards set by the CFS and factoring in facilities that already exist or are funded in the CIP, the CNA determines which facilities are needed to meet the adopted CFS standards. The CNA is generally updated every four years.

Depending on the type of capital facility, either the countywide population or the population within each planning subarea drives the demand for facilities. In this way the County can identify more accurately where the demand is greatest and plan accordingly. The planning subareas define broad communities such as Leesburg and its environs or the three western towns along Route 7. The boundaries are based on Traffic Analysis Zones (similar to census tracts).

Capital Facilities Standards

The CFS determines the general size and scope of facilities by establishing a maximum land use area (acreage) and construction footprint floor area. As design and engineering of a facility progresses, and specific sites are chosen, acreage and floor area may differ from the CFS standard. County departments provide information on what standards to use for each of their facilities. The CFS also establishes a population threshold (“trigger”) for many facilities, with other being developed based on reaching a certain total number of facilities countywide

Example: The CFS determines a need for one fire station for every 25,000 persons in the Sterling planning subarea. The population forecast for Sterling shown in the FY 2029-2040 Adopted Capital Needs Assessment is 43,601 persons in 2028 and is projected to increase to 50,209 persons by 2039. As of 2028, the need for fire stations is 1.74 (43,601 divided by 25,000).

⬚ figure

There is already one fire station existing in Sterling. No other fire stations are under development or in the CIP for Sterling. The total need for fire stations will increase to 2.0 (50,209 divided by 25,000) by 2039, therefore, the CNA would identify one additional fire station by 2039.

Capital Intensity Factor

The CIF translates the anticipated capital cost and land requirements derived from the CFS into a per-housing-unit cost. The calculation determines costs per capita and costs per student, which then helps estimate the cost associated with different housing unit types based on average household sizes and students per household. The resulting cost per housing unit is valuable during development review to estimate impacts of individual applications and to evaluate proffer packages proposed by a rezoning applicant.

1993 Choices and Changes General Plan standardized the County's use of a CIF to calculate capital facilities proffers. The County, by policy, anticipated a landowner contribution of 25 percent of the anticipated capital impact of each residential unit over a base density of 1.6 units per acre. At that time, the CIF was a countywide number. The Comprehensive Plan carries forward the County proffer policy established in the 2001 Revised General Plan (RGP), which called for landowners to mitigate 100 percent of the capital facilities impact for each unit above a base density established by existing zoning or one unit per acre, whichever is lower. The RGP also featured a separate CIF for different planning subareas, some of which were combined into CIF regions. The refinement acknowledged notable differences in land costs and other differences associated with constructing facilities in each subarea. The Board has also incorporated a separate CIF for age-restricted housing. Recognizing a pressing need for certain transportation improvements, the County also allows landowners to redirect capital facilities contributions to transportation infrastructure in certain situations.

The proffer guidelines as set out in the Comprehensive Plan accommodate urban development concepts and more diverse housing. The Board adopted CIF figures effective July 2024 which include a way to reduce the CIF for smaller unit sizes (the “By-Size Differential” CIF option) and an “Urban MFA” CIF. The Board also adopted a new Roads CIF effective July 2024, replacing the prior regional roads contribution.

In light of state legislation adopted in 2016 that limits the use of proffers, the County also continues to explore other mechanisms to diversify funding opportunities, including impact fees, which could apply to residential developments whether permitted by-right or through legislative action. Additional state enabling authority would be necessary to effectively use impact fees: existing legislation is limited in scope and imposes difficult implementation requirements, leading very few localities to take advantage of this tool.

Capital Improvement Program

The six-year CIP refines the County's CNA-forecasted future capital facility growth, providing a six-year program of the County's general government and public schools' land, facility, and equipment needs, and a financing plan to implement each need. The CIP schedules land acquisition, design, construction, and capital equipment procurement for each project. Potential projects are evaluated in relation to each other to prioritize funding of specific projects. Essential improvements are planned in a manner commensurate with the County's ability to pay.

Loudoun County 2019 General Plan

The CIP is developed biennially, with the six-year period moving out an additional two years every other fiscal year. The CIP is a multiyear plan that does not constitute or require an appropriation of funds beyond those for the current fiscal year. Funding decisions concerning the CIP are made in conjunction with decisions regarding the County's operating budget. Most new facilities require an ongoing commitment in operating funds for new employees, utilities, and other costs.

As part of its strategic planning efforts on growth management, the County considers the impact of development proposals. Capital needs and costs are routinely considered including the need for county facilities, schools and transportation infrastructure. For large-scale projects, their economic and revenue benefits as well as their impact countywide can be considered. As such, during the developmental review process, the County evaluates 1) the impact of a rezoning application on the local transportation network and public facilities, 2) what the application is or is not doing to mitigate the impact, and 3) what facilities exist and/or are funded to serve the subject property and surrounding area during the development review process. In addition, the County has developed an analysis model to assist with evaluating the fiscal impact of future development.

Policies, Strategies, and Actions

Unless otherwise specified, the following policies, strategies, and actions apply Countywide, subject to and in compliance with any applicable limitations established by Code of Virginia Section 15.2-2303.4. In its consideration and acceptance of all proffers, the County will apply the standards of Code of Virginia Sections 15.2-2297, 15.2-2303, and 15.2-2303.4, as applicable, to evaluate the reasonableness of proffered conditions, and for those applications subject to Section 15.2-2303.4, the County shall accept only those proffers permitted or deemed reasonable under Code of Virginia Section 15.2-2297 and not deemed unreasonable under Code of Virginia Section 15.2-2303.4.

Fiscal Policy 1: Provide public facilities to meet identified needs.

Strategy

1.1. Use the CNA to plan and coordinate facility needs and location criteria to ensure adequate dispersal and timely availability of County facilities.

Actions

A. Support LCPS acquisition of needed sites through the fiscal planning and land development processes.

B. Co-locate public safety and other public facilities or uses like attainable housing whenever co-location will improve service efficiencies.

C. Make school-related open space and athletic fields available for joint use by PRCS.

D. Combine public open space and parks with public facilities and civic buildings, in community centers, town centers, and other gathering places and include amenities such as seating areas, public art, playgrounds, gardens, etc.

CHAPTER 6-16

E. Design public facilities to be a distinguishing feature of the community using sustainable materials, context-sensitive design, and attractive architectural features.

F. Design new public facilities to 1) be functional and efficient to persons with diverse abilities, 2) to reflect the physical character of the surrounding community, and 3) to maximize the broader social and cultural role the facility can play in the community.

G. Establish an expansion plan for the LCFR Training Academy based on a needs assessment of the existing campus as the needs of LCFR and the County increase. Ensure the requirements of LCFR training remain a priority during the development of surrounding areas.

H. Support proactive acquisition of sites for public facilities and to “bank” property for potential projects that may not yet be scheduled on the CIP.

Strategy 1.2. Support continued use of existing public facilities through ongoing capital asset replacement, renovation, and modernization, particularly where facilities play an important role in social and economic activity of the local community or are historically significant.

Action A. Maintain and modernize existing County facilities to meet resource demands, and changing customer and community needs.

Strategy 1.3. Strategically locate public facilities where they can serve the community efficiently and effectively.

Actions A. Locate new public facilities on sites that can accommodate future expansions and allow co-location with other public agencies with similar activities or clients when possible. Use the expansion space around new public facilities for parks, commuter parking, and other interim uses that are compatible with the new facility until expansion is required.

B. Investigate co-locating County facilities with complementary uses that would create a mutually beneficial relationship; for example, locate schools with attainable housing or libraries with parks and make surplus County lands available for attainable housing projects.

C. Locate LCFR and Sheriff’s Office facilities in accordance with adopted response time goals and at the most strategic point in a proposed service area.

D. Locate “high traffic” public facilities in highly visible, accessible locations with adequate automobile and pedestrian access; examples of such locations include mixed-use centers, towns, and villages.

E. Integrate housing, human services facilities, and services for special needs populations in the Urban, Suburban, and Transition Policy Areas, Towns, and JLMAs to provide ease of access to associated commercial services, jobs, and amenities.

F. Link new public facilities and adjacent neighborhoods with sidewalks, greenways, and trails.

G. Locate new public facilities in western Loudoun in close proximity to the Towns and JLMAs when suitable land is available and locations can meet response time and other service standards.

H. Establish and maintain effective levels of public open space in all residential and mixed-use communities.

I. LCPS will determine the need for new public school sites and public facilities in Loudoun County. The County will coordinate with LCPS to identify suitable sites based on the Loudoun County 2019 Comprehensive Plan and its land use and growth policies in concert with LCSB’s standards and levels of service as adopted by the Board of Supervisors.

J. The County will acquire school sites in advance of LCPS’s recognized short and long-term future needs to minimize school transportation costs and to structure future planned growth.

Strategy

1.4. Encourage partnerships that contribute toward significant, meaningful, shared public facilities.

Actions

A. Support and encourage partnerships that develop sustainable housing for special needs populations, including the elderly, the mentally and physically handicapped, low income persons, and the homeless.

B. Support the acquisition of land and development of facilities such as the Potomac Heritage National Scenic Trail.

C. Work with the United States Department of the Interior, the Virginia Tech Conservation Management Institute, the Virginia Department of Historic Resources, NOVA Parks, and other local, regional, and state organizations and the incorporated Towns to define and recommend areas for open space preservation and development of a trail network that links the County’s natural, historic, and recreational resources.

D. Work with homeowners’ associations (HOA) and other property owner associations (POA) to encourage greater public access to association open space and facilities.

E. Collaborate with Loudoun Water and NOVA Parks to support safe, compatible public access and recreation at water supply reservoirs.

F. Coordinate recreation planning efforts with the Towns to prevent duplication of services.

G. Identify opportunities, such as public/private partnerships and co-location, to work with the private sector to provide public facilities.

Emergency Services Development Standards

Fiscal Policy 2: Enhance efficient and effective public safety and emergency services response through the implementation of appropriate development standards.

Strategy

2.1. Ensure adequate fire suppression for residential uses that are not served by an on-site water source and/or are located outside minimum response times of existing stations.

Actions

A. Create and maintain development regulations that require an adequate water supply, such as dry hydrants or tanks, for new residential subdivisions of more than five dwelling units when an alternative water source is not available on site.

B. Encourage and offer incentives to voluntarily provide sprinklers in new residential construction.

C. Higher densities proposed in compact and mixed-use communities, and design concepts such as narrower streets, reduced yards, and less space between buildings, should be contingent on installation of sprinkler systems in all buildings.

D. As part of residential rezoning applications in areas that are subject to approved small area plans or approved Metrorail service districts, recommend that sprinklers be installed in all new residential construction that is located outside of the recommended emergency services response times established in agency services plans.

Strategy

2.2. Ensure adequate and efficient access for emergency vehicles.

Actions

A. Eliminate non-contiguous street names, duplicate street names, and sound-alike street names, and ensure that addresses reflect the access location.

B. Coordinate with Virginia Department of Transportation (VDOT) to ensure that all new traffic signals are equipped with signal preemption equipment to provide priority access to emergency vehicles responding to a call.

C. Establish a program that retrofits existing traffic signals, subject to VDOT approval, with signal preemption equipment to provide priority access to emergency vehicles responding to a call.

D. Require development applications to demonstrate adequate access for emergency apparatus.

E. Ensure that development regulations address the installation and maintenance of emergency apparatus access roads for fire and rescue resources.

F. Discourage the use of “emergency access only” gates and other roadway barriers.

Open Space (see also Chapter 3, Natural, Environmental, and Heritage Resources)

Fiscal Policy 3: Retain the County’s unique combination of urban, suburban, and rural communities by using open space to protect natural resources and habitat, to create a network of high-quality active and passive recreation spaces, and to delineate our built environments.

Strategy

3.1 Use contiguous linear parks, connected trails, and natural open space corridors to improve public access to open space, encourage healthy lifestyles, and link destinations throughout the County.

Actions

A. Build on and encourage links to current planned trails and park areas, placing greater emphasis on connected, publicly usable, and accessible open space and identify desired locations and connections of future trails and parks to facilitate acquisition and development.

B. Establish programs and regulatory mechanisms to increase publicly accessible open space through easements, land dedications, and purchase; ensure that such programs and mechanisms are consistent with County facilities plans.

C. Incorporate open space amenities into the design of stormwater facilities and link such facilities by trails to create a network of water-based parks and greens.

D. Ensure that new developments extend publicly-accessible trails and linear parks into and through their projects with the intent of creating a network of public trails that is consistent with the County plans.

E. Encourage applicants requesting residential rezonings to include language in HOA/POA bylaws that allows public access to some or all linear parks and trails, particularly those connecting to public facilities and to outside trails or parks.

F. Establish and maintain desirable levels of usable, public open space in all residential and mixed-use communities.

G. Increase the number of access points to key trail systems from adjacent neighborhoods and destinations.

H. Seek through public purchase, proffer, donation, or third-party easement, the preservation of natural areas and the development of linear parks, recreation space, and trails.

I. Continue the Open Space Preservation Program, to the extent permitted by Code of Virginia Section 15.2-2303.4, linking the loss of open space associated directly with

Loudoun County 2019 General Plan

low-density land use to the provision of open space or funds towards the purchase of open space that provides publicly accessible and usable open space as follows:

i. In the Suburban Policy Area, residential neighborhoods or land bays proposing densities lower than 4 dwelling units per acre or floor area ratios of less than 0.4 should augment required open space with voluntary participation in the Open Space Preservation Program by providing: a. The equivalent of 40 percent public open space in the Suburban Neighborhood place type and 20 percent in the Suburban Compact Neighborhood and Suburban Mixed Use place types, consisting of onsite open space required by development regulations and additional usable and publicly accessible open space proximate to the development, or b. A cash contribution, equivalent to the value of the additional open space, towards the Open Space Preservation Program. ii. In the Urban Policy Area, projects in areas planned for Urban Mixed Use and Urban Transit Center place types that propose floor area ratios of less than 1.0 should augment required open space with voluntary participation in the Open Space Preservation Program by providing: a. The equivalent of 20 percent open space consisting of on-site open space required by the zoning regulations and design standards, and additional usable and publicly accessible open space proximate to the development, or b. A cash contribution, equivalent to the value of the additional open space, towards the Open Space Preservation Program. iii. Link modifications reducing on-site open space, buffer widths, or landscaping requirements with the provision of an equivalent or greater amount of open space or an equivalent cash contribution towards the Open Space Preservation Program. iv. Use open space easements or funding provided by projects in the Urban and Suburban, Policy Areas through the Open Space Preservation Program to extend existing public trails, provide active and passive parks or to protect priority sites (see 3.1.K., below).

J. Institute a program whereby the County facilitates acquisition of conservation easements by others by providing assistance such as a revolving loan program to reduce or defer the landowner cost of establishing conservation easements. The program should emphasize protecting the priority open space areas that are identified in this Plan that are not otherwise protected.

K. Encourage protection of the following priority open space areas through open space easements acquired by the County or conservation easements acquired by others, participation in the Open Space Preservation Program, development design, and other means:

CHAPTER 6-21

i. Key natural, environmental, and heritage resource features not already protected from development by open space or conservation easements or regulation; ii. Rural areas immediately adjacent to the Towns, JLMAs, and Rural Villages that help form greenbelts and gateway buffers; iii. Areas adjacent to the Potomac River, Catoctin Creek, Bull Run, Goose Creek, and Broad Run floodplains, to protect water quality; iv. Properties on or eligible to be listed on the State or National Registers of Historic Places and within local historic districts; v. Corridors and sites identified for trails and parks and additions to existing parks; and vi. Other areas of local natural, historic, or cultural significance including but not limited to designated scenic rivers and roads, ridgelines, and battlefields. vii. Amend the zoning ordinance and development regulations as needed to permit a percentage of the open space required on an individual site to be met through off-site permanent open space that creates a more usable, desirable, or environmentally significant open space (see 3.1.J, above) located in the same planning subarea identified in the latest CNA.

Sewer and Water (see also Chapter 2, Towns and JLMA)

Fiscal Policy 4: Work with Loudoun Water and the Health Department to ensure timely provision of central, community, or on-site sewer and water in accordance with the land use policies of this Comprehensive Plan. The County will encourage water and wastewater service to be provided in the most efficient and effective manner possible and promote the use of the best utility system in accordance with the policies of this Plan.

Countywide Strategies

Strategy 4.1 Implement strategies to resolve sewer and water issues in existing communities.

Action A. Pursue funding sources to rehabilitate homes that currently lack adequate sewer and water systems.

Strategy 4.2 Define specific service areas for utility systems to protect the viability of County land use goals.

Actions A. Establish the geographic limits of standards-based utility service, and ensure adequate capacity and supply safeguards through the Commission Permit process prior to

expanding existing service boundaries, or adding new boundaries in the case of the Rural Policy Area.

B. Prohibit connection to water distribution and wastewater collection systems when such requires crossing land outside a defined water or sewer service area, except as allowed herein.

Strategy

4.3 Prohibit the use of any standalone or community system that does not ensure long-term safe, sustainable, and environmentally sound water supply and wastewater treatment.

Actions

A. Require development proposals outside of areas served by central system facilities to demonstrate a safe, adequate, and long-term sustainable potable water supply and sewage treatment capacity in accordance with the land use policies of this Comprehensive Plan.

B. Encourage concentrating development away from water supply reservoirs and water supply sources.

C. Implement a pollution prevention and mitigation program to protect and improve the County’s surface water quality.

D. Permit pump-and-haul operations only as a last resort and a temporary wastewater disposal method and only to address a proven public health issue.

Urban, Suburban & Transition Policy Areas – Central Sewer and Water

Strategy

4.4 Loudoun Water will be responsible for the provision of central water and sewer service in the Loudoun Water Central System area as shown on the Water/Sewer Service Areas Map.

Actions

A. Collaborate with Loudoun Water to ensure safe and adequate long-term water supply and wastewater treatment systems to meet County development goals.

B. Facilitate development and efficient operation of retired quarries as water supply reservoirs and protect reservoirs by establishing effective and sustainable watershed protection measures.

C. Expand the use of Loudoun Water’s reclaimed water network.

D. Require new development in the Urban, Suburban, and Transition Policy Areas to connect to Loudoun Water’s central water supply and wastewater treatment systems.

E. Encourage existing residences and communities served by onsite or community facilities to connect to central water or sewer facilities when such facilities become available via long-term financing or other incentives.

F. Assist existing communities or residences to connect to a nearby central water or sewer system if on-site water supply or waste treatment capability has deteriorated to a point where there is a potential public health risk.

G. Construct new central wastewater and water lines and facilities in a manner that causes the least environmental risk and visual disruption.

Rural Policy Area – On site and Community Systems

Strategy

4.5 Protect the rural character of western Loudoun by considering the ability of an area to support onsite or community water and wastewater systems for any areas proposed for development.

Actions

A. Prohibit extension of central water and wastewater service into the Rural Policy Area, except to address a public health threat to an existing rural community or to serve public facilities on contiguous parcels immediately adjacent to the western boundary of the Transition Policy Area.

B. Institute a wellhead protection program in all areas not served by central system facilities to ensure adequate water quality.

C. Discourage the use of groundwater for nonagricultural irrigation such as automated lawn sprinklers and swimming pools and other nonessential purposes.

D. Maintain oversight of siting, design, installation, and maintenance of conventional and alternative on-site sewage disposal systems.

E. Require the installation of technology that treats groundwater to a surface water level of treatment standard, in accordance with Loudoun Water’s Engineering Standards Manual, as a condition of approval for development of potable water supplies in any portions of the Limestone Overlay District and/or where subsurface karst geology exists.

F. Implement an inspection and maintenance program for conventional on-site sewage disposal systems and provide homeowner educational materials on this and related well and septic safety for residents in the Rural Policy Area, particularly in the Limestone Overlay District.

Strategy

4.6 Collaborate with the Health Department in conjunction with Loudoun Water to identify viable alternative water supply and wastewater treatment methods to individual well, septic and drainfield-based systems, including community treatment plants and onsite treatment to support clustered residential development.

Actions

A. Implement water and wastewater treatment and disposal standards for alternative systems that protect water quality. B. Allow community water and wastewater systems in the Rural Policy Area: i. to serve rural economy uses and residential clusters as defined in this Comprehensive Plan, ii. to solve potential public health risks, and iii. to serve public facilities. C. Support construction of community systems for existing rural communities facing a potential public health risk. In such cases, the community system may be available to undeveloped lots within the existing community to support development that extends the viability of the community and is consistent with the scale, density, and character of the community. D. Require Loudoun Water to own and operate all public community water and wastewater systems with more than 15 connections. E. Require a Commission Permit, establishing a defined service area, prior to the construction of any community water or wastewater system. F. Permit the extension of municipal (town) sewer and water into the Rural Policy Area to serve public facilities or to address a potential public health risk. G. Require financing of community water and wastewater systems by the developer or by those who will be directly served by the system. A financing plan will be required to address initial capital costs and operating costs. The system must be designed, organized, and operated to be financially self-sustaining to pay all costs incurred by Loudoun Water for operation and maintenance and to provide appropriate reserves. The County may provide financial assistance in the form of loans or grants to assist in the construction of such a facility for existing rural communities if the system is needed to solve a significant public health threat.

Solid Waste Management

Fiscal Policy 5: Continue to implement an integrated solid waste management strategy that prioritizes reduction, reuse, and recycling of solid waste above resource recovery, incineration, and disposal into landfills.

Strategy

5.1 The County Solid Waste Management Plan will identify the type and level of service to be provided in the community.

Actions

A. Continue to ensure that the County always has an acceptable means of local waste disposal through the County landfill operations, should other waste disposal alternatives fail or become ineffective.

B. Continue to seek private sector support for the provision of current and future Solid Waste Management Services.

C. Develop a hazardous waste education program and increase residential access to the safe disposal of hazardous waste to protect groundwater resources.

D. Reduce landfill waste by promoting recycling and composting.

Electrical

Fiscal Policy 6: Support expanded electrical capacity and reliability, while balancing economic growth with the goal of minimizing negative impacts on the community, cultural and historic resources, and the environment.

Strategy

6.1 Utilize existing and approved corridors for transmission line expansion where feasible, to minimize community, visual, and environmental impacts.

Actions

A. Encourage the safe grouping, burying, and colocation of new transmission lines and electrical infrastructure within existing and approved transmission corridors as depicted on the Electrical Infrastructure Map to minimize community and environmental impacts.

B. Utilize and upgrade existing transmission infrastructure to support the reliability of the electric grid, whenever feasible, to reduce the need for new transmission infrastructure.

C. Support rebuilding, voltage conversions and upgrades, and modernization of existing electrical infrastructure and transmission corridors to better utilize resources and minimize impacts on existing and future development.

D. Encourage underground electric transmission lines within existing overhead transmission lines easements when expanding the width of an existing transmission corridor to collocate transmission lines is not feasible.

E. When feasible construction new electrical transmission and distribution lines within and along existing utility, Metro rail, and road ROW in appropriate locations identified in the Fiscal Management and Public Infrastructure policies in Chapter 6 of the Loudoun County 2019 General Plan to minimize impacts on existing and future development.

F. Design and site proposed electrical infrastructure to preserve areas necessary for future ROW acquisition and ancillary easements for construction of utility and road improvements, while recognizing certain utilities (such as water and sewer) may have limitations on colocation with electrical infrastructure.

Loudoun County 2019 General Plan

Strategy

6.2 Minimize the impacts of transmission corridors and electrical infrastructure through appropriate location, siting, and design techniques to ensure compatibility with the surrounding built and natural environment.

Actions – Transmission Lines

A. Existing transmission corridors should be expanded only, when necessary, with no greater than the minimum width required to accommodate the proposed transmission lines and electrical infrastructure to minimize impacts.

B. Locate new transmission corridors and electrical facilities in areas planned for commercial or industrial corridors. Mixed-use and residential areas should be avoided.

C. Encourage, where feasible, the use of location, siting, and design techniques that minimize the visual impact of overhead high voltage transmission corridors and electrical infrastructure. Such measures may include existing forest and vegetative screens, landscape berms, and landscape buffers.

D. Utilize design techniques and route alternatives for new overhead transmission corridors to avoid community and visual impacts to urban centers, mixed-use developments, residential neighborhoods, towns, rural villages, and rural landscapes.

E. Support the undergrounding of high voltage electric transmission lines to minimize community and visual impacts to urban centers, mixed-use developments, residential neighborhoods, towns, rural villages, and rural landscapes.

Actions – Substations

A. Work with electrical providers to identify potential substation locations that minimize impacts on key travel corridors, sensitive cultural and historic resources, and existing residential communities.

B. Encourage the use of design techniques that will minimize the visual impact of electrical substations adjacent to major travel corridors or residential communities including the use of stealth design techniques.

Strategy

6.3 Place transmission lines underground when proximate to urban centers, mixed use development, residential neighborhoods, towns, rural villages, and rural landscapes to preserve the character of exiting communities, sensitive rural landscapes, cultural and historic resources, and significant cultural landscapes.

Actions

A. Construct underground transmission lines in strategic segments where visual, environmental, or safety concerns call for the investment to mitigate impacts.

B. Construct underground transmission lines along existing or planned utility, Metro rail, and road ROW to minimize impacts on existing and future development.

C. Encourage consolidating underground transmission and distribution lines in joint

CHAPTER 6-27

conduit systems or other means to create an organized, and methodical arrangement of easements for new projects.

D. Mitigate the visual impact of transition stations utilized to place overhead transmission lines within an underground configuration by providing appropriate siting, screening and buffering of facilities from adjacent uses.

Strategy

6.4 Accommodate additional local electrical demand through the optimization of existing transmission lines and electrical infrastructure, and the development of local electrical generation in appropriate locations.

Actions

A. Promote reconductoring and voltage conversion to increase capacity within existing transmission corridors before considering the construction of new transmission corridors.

B. Support the use of new technologies, such as smart grids and Grid-Enhancing Technologies designed to improve grid capacity, reliability, and efficiency and limit the need for new transmission corridors.

C. Establish zoning regulations and design standards that permit alternative electrical generation such as wind and solar generation by and for individual users.

D. Encourage renewable energy integration into the electrical grid through the implementation of the County’s 2023 Energy Strategy, by promoting energy efficiency, supporting renewable energy projects, and engaging businesses and the community through education and outreach.

E. Encourage local electrical generation and energy storage facilities in appropriate locations to provide additional electrical capacity and enhance the reliability of the network.

F. Support expanded electrical capacity through generation facilities that produce low emissions of pollutants, utilize environmentally sound fuel sources, and incorporate energy efficient designs.

G. Support integrating electric generation and energy storage systems behind the meter within existing and new developments to reduce the need for more electrical infrastructure.

H. Continue to monitor and minimize energy use in County facilities and create a program that would encourage benchmarking energy use for private-sector buildings.

I. Encourage the incorporation of emerging technologies and innovative solutions that enhance the efficiency, reliability, and sustainability of the local electrical grid by supporting pilot projects, research initiatives, and collaborations with technology developers.

Loudoun County 2019 General Plan

Strategy

6.5 Support the development of interconnected trails and the preservation and enhancement of natural resources and wildlife habitat within transmission corridors.

Actions

A. Collaborate with electric providers to create and plan for multi-use trails within existing and proposed transmission corridors and easements where feasible to provide public access to open space, encourage healthy lifestyles, and link destinations throughout the County.

B. Encourage environmentally friendly Integrated Vegetation Management programs that allow native plant species and habitat for wildlife to flourish within transmission corridors.

C. Support the development of a “Utility Corridors Greenway Strategy” to align utilities, recreation, and conservation goals and integrate transmission corridors into the County’s Linear Parks and Trails System where safe and feasible access can be provided.

D. Initiate partnerships with electrical providers to formalize access agreements for trail development and land management, and establish agreements for vegetation management plans that support pollinators, native grasses and low-shrub habitat.

E. Encourage and support integrated habitat restoration within transmission corridors.

F. Support wildlife connectivity studies to identify priority habitat area and movement corridors when managing and planning for natural areas and passive uses within transmission corridors.

Strategy

6.6 Support and facilitate ongoing education and collaboration with the community regarding future planning of high voltage transmission corridors fostering open communication, building trust, and providing accessible resources.

Actions

A. Support early community engagement with electric providers, property owners, stakeholders, and local government on transmission corridor projects when considering improvements and expansions of existing high voltage transmission corridors or the establishment of new transmission corridors.

B. Work with electrical providers to plan for future electric transmission and infrastructure needs in conjunction with demand forecasting associated with approved business, commercial, and residential development.

C. Support efforts to improve coordination with electric providers and high energy users in identifying future facilities and infrastructure needs to proactively plan improvements to the transmission network and distribution system that minimize community impacts.

CHAPTER 6-29

D. Through ongoing education and collaboration, continue to refine the County’s policy positions and legislative priorities regarding electrical transmission and generation infrastructure and advocate for state legislation through appropriate processes (e.g. Board of Supervisors’ annual Legislative Program).

Communication

Fiscal Policy 7: Support the development of a high-quality wired and wireless telecommunications network to serve businesses, residents, and visitors.

Strategy

7.1 The County’s Strategic Land Use Plan for Telecommunication Facilities and other regulations and standards will be regularly updated to address emerging technologies, to create an environment attractive to businesses, and provide high-quality services to meet the demands of the County.

Actions

A. Review and update the County’s Strategic Land Use Plan for Telecommunication Facilities to facilitate the expansion of fiber and broadband service throughout the County.

B. Adopt zoning regulations and design standards that require open access conduit to all development projects to facilitate future broadband extensions.

C. Establish performance standards for wireless communication facilities to minimize the need for legislative action.

D. Incorporate the capacity to locate broadband and wireless facilities into the design, approval, and construction of all public facilities.

E. Locate telecommunications facilities and equipment associated with public safety agencies in accordance with communication utility standards and the Comprehensive Plan.

Fiscal Management

Fiscal Policy 8: Link the goals of the Board of Supervisors’ adopted Fiscal Policy and the County’s Comprehensive Plan.

Strategy

8.1 Maintain a diversified and stable revenue structure by balancing residential and non-residential development.

Actions

A. Seek further revenue diversification to increase fiscal stability and thereby mitigate tax burdens on Loudoun County taxpayers.

B. Direct the majority of public investments into currently developed communities, Towns and non-residential areas of the County where development is planned.

according to the Comprehensive Plan and give priority to the redevelopment and enhancement of existing infrastructure, capital facilities, and services.

C. Where permitted by law, continue to seek private sector support for improvements or provision of current and future public facilities and sites, including proposals of cash and in-kind assistance for public facilities in addition to the timely provision of dedicated sites.

D. Seek authority from the state legislature to establish impact fees and a reasonable implementation process applicable in areas of the County where rezonings are not anticipated or where the provision of improvements and facilities through proffers associated with rezonings for new residential development is restricted by State law.

Strategy

8.2 Capital facility planning and budgeting will reflect anticipated needs based on forecasted development.

Actions

A. Update financial and planning tools regularly to evaluate long-term land use, fiscal, and demographic issues under the oversight of the Board of Supervisors and its advisory committee, the Fiscal Impact Committee.

B. Maintain long-range forecasts of residential and non-residential development, population, households, and employment.

C. Develop demographic, economic, and financial data that are used as inputs to demographic forecasts and for fiscal impact modeling.

D. Develop and regularly update the CIF – the dollar amount of the capital facilities impact measured by unit type or unit characteristics and geographic location that is calculated using CFS and demographic inputs. The County uses the CIF to assess the capital facilities impacts of new residential development and provide a guideline to evaluate and consider residential rezoning applications and proposed proffers.

E. Regularly refine the CFS, including the type, acreage, and size of future capital facilities, along with “triggers” based on population, policy area, place type, community characteristics, or other community factors.

F. Regularly refine the CNA, including the type and number of capital facilities needed over a ten-year planning period beginning at the end of the current six-year CIP.

G. Where permitted by law, seek to ensure that an equitable and proportionate share of public capital facility and infrastructure development costs that are directly attributable to a particular development project will be financed by the users or beneficiaries.

H. Evaluate, consistent with the Code of Virginia Sections 15.2-2283 and 15.2-2284 and other applicable law, the adequacy of existing and planned public facilities and services when assessing impacts of any legislative application for more intensive use or density. To fairly implement and apply this policy, the County may consider the following:

i. existing facilities;

ii. facilities included in the CIP;

iii. the CFS and the effect of existing and approved development, and the proposed development, on the CFS;

iv. service levels of the existing transportation system – the effect of existing and approved development and the proposed development on those service levels and the effect of proposed roads which are funded for construction;

v. commitments to phase the proposed development to the availability of adequate services and facilities;

vi. the availability of non-profit or HOA facilities to provide equivalent public access and programming; and

vii. other mechanisms or analyses as the County may employ that measure the adequacy of such services and facilities for various areas or that measure the County’s ability to establish adequate services and facilities.

Strategy

8.3 Until such time as state law provides authority for other options, the County will consider landowner proposals of cash and in-kind assistance to mitigate capital facilities costs associated with new development, subject to the limitations established by Code of Virginia 15.2-2303.4.

Actions

A. Consider proposals of the timely dedication of land, cash, and in-kind assistance from a landowner through proffered conditions submitted in accord with Code of Virginia Sections 15.2-2303, 15.2-2303.4, and 15.2-2297, as applicable, in the provision of public facilities identified in the CIP or CNA.

i. The County expects that such proposals of public facility and utility assistance by developers will occur in conjunction with any rezoning request seeking approval of densities above the existing zoning regulations and design standards.

B. Ensure that an equitable and a proportionate share of public capital facility and infrastructure development costs that are directly attributable to a particular development project are financed by the users or beneficiaries.

C. Apply all of the proffer policies and actions and guidelines set forth in this document subject to and in compliance with the applicable limitations established by Code Virginia Section 15.2-2303.4. In its consideration and acceptance of all proffers, the County will apply the standards of Code of Virginia Sections 15.2-2297, 15.2-2303, and 15.2-2303.4, as applicable, to evaluate the reasonableness of proffered conditions.

D. For those land development applications subject to Code of Virginia Section 15.2-2303.4, the County shall accept only those proffers permitted or deemed reasonable

under Code of Virginia Section 15.2-2297 and not deemed unreasonable under Code of Virginia Section 15.2-2303.4.

E. Where and to the extent permitted by law, the County will structure residential proffer guidelines based upon the respective levels of public cost of capital facilities generated by various factors such as size, location, and type of dwelling units.

F. To assist the County in an equitable and uniform evaluation of developer proffers and other proposals, for proposed densities above the specified base density for each planning policy area, which otherwise conform with the policies of this Comprehensive Plan, the County anticipates developer assistance valued at 100 percent of capital facility costs associated with such increased densities.

G. The County will consider differentiating between conventional suburban housing and other types of housing such as age-restricted, accessory, and micro units, and consider commitments to small unit sizes or affordability in estimating the capital facility needs and CIF.

H. Consider developing capital standards for roads to incorporate into the CIF.

Strategy

8.4 Adoption of this Comprehensive Plan delineates the boundaries within which Small Area Plans may be established, authorized under Code of Virginia Section 15.2-2303.4 and which boundaries, encompassing the Urban Policy Areas, Suburban Policy Area, Transition Policy Area, Leesburg JLMA, and the three Silver Line Metrorail Stations within the County as shown on the Small Area Plan Boundaries Map. The planned land use within these boundaries will reflect the land uses specified under the Comprehensive Plan for each policy area until such time as the Board adopts more detailed small area plans for more specific areas within these boundaries.

Strategy

8.5 Use the following capital facilities proffer guidelines to evaluate proposed capital facility proffers subject to and in compliance with the limitations established by Code of Virginia Section 15.2-2303.4 as applicable.

Actions

A. Use the following definition of “Capital Facility Proffer” to evaluate proffers: “A contribution consistent with County policies and service needs, in cash or in kind (land or improvement), that is intended to mitigate capital facility impacts of the development and is agreed to as a condition of a rezoning.”

To be considered a proffer based on this definition, the following criteria shall apply:

i. The proffered facility is dedicated to the County or to a local, state, federal, or regional authority or otherwise satisfies a need identified in the CFS, CNA, or CIP;

ii. The measure of credit will be determined based on the service needs of the proposed development and should not exceed what the County would expect to supply given the CFS and the population served at the date of official acceptance of the application or at the date of reactivation of an inactive application;

iii. The contribution has a quantifiable value;

iv. The value of land contributed for public use or use as a public facility site is recognized as a capital facility proffer;

v. Land for County facilities should be conveyed to the County or its designee;

vi. Cash contributions should be the equivalent of the capital facility impacts of the proposed development as determined by the CIF adopted by the Board of Supervisors at the time the applications is considered;

vii. The contribution would not be required under existing statutes or ordinances; and

viii. The proffer is irrevocable.

B. Seek annual adjustments for proffers involving cash contributions based on the Consumer Price Index (CPI).

C. Base density thresholds beyond which capital facilities proffers will be anticipated are specified by planning policy areas as follows:

i. Rural Policy Area: The planned density for the Rural Policy Area is implemented by the existing zoning pattern and zoning amendments are not anticipated. However, for zoning map amendment applications within existing villages and other similar applications, include capital facility proffers for units above the density permitted by current zoning regulations.

ii. Transition Policy Area: Evaluate capital facilities proffers against the base density permitted by current zoning regulations.

iii. Suburban and Urban Policy Areas: Evaluate capital facilities proffers against the base density permitted by the current zoning regulations or a base density of 1.0 dwelling unit per acre, whichever is lower.

iv. Joint Land Management Areas: Evaluate capital facilities proffers against the base density permitted by the current zoning regulations or a base density of 1.0 dwelling unit per acre, whichever is lower.

D. To evaluate proffers for public use sites, determine the per-acre value of unimproved land by a market appraisal of the site compared to properties with the same densities proposed by the applicant. The appraisal shall be conducted by an appraiser agreed to

by the County, paid for by the developer, and the results provided to the County. For improved sites, consideration will be given as applicable to:

i. Site-preparation including clearing and grubbing, grading, erosion control, and related engineering and permitting costs.

ii. Project infrastructure such as stormwater management ponds, sanitary sewer lines, and major off-site and on-site roadways serving the site.

iii. A proportional share of improvements directly related to providing access to the site (pedestrian underpasses, construction of adjacent streets, trails, and sidewalks).

Reference Maps

Existing and Planned Facilities (Map #2026-008)

Small Area Plan Boundaries (Map #2025-125)

Trails and Parks (Map #2026-009)

Water/Sewer Service Areas: 2019 (Map #2023-064)

Electrical Infrastructure (Map#2026-022)

Loudoun County

Existing and Planned Facilities

2019 General Plan

▲ Animal Control ¶ Comm Facility ⚒ Courts 🛡 Fire & Rescue ☗ General County Facility ⌂ Historic Site ▤ Library ✜ Park ● Park & Ride 🅿 Parking ■ Recreational 🏛 School: Administration ⚗ School ⬤ Sheriff ◆ Social Service ▲ Waste Mgt

County Owned & Leased

■ County Work Site ■ County Leased ■ County Owned

⬚ figure

Loudoun County IS NOT LIABLE for any use of or reliance upon this map or any information contained herein. While reasonable efforts have been made to obtain accurate data, the County makes no warranty, expressed or implied, as to its accuracy, completeness, or fitness for use of any purpose.

Map Number 2026-008

CHAPTER 6-36

Loudoun County

Small Area Plan Boundaries

2019 General Plan

⬚ figure

Small Area Plans

  • Ashburn
  • Dulles
  • Potomac/Sterling

Loudoun County IS NOT LIABLE for any use of or reliance upon this map or any information contained herein. While reasonable efforts have been made to obtain accurate data, the County makes no warranty, expressed or implied, as to its accuracy, completeness, or fitness for use of any purpose.

0 0.5 1 2 3 4 Miles Map Number 2025-125

CHAPTER 6-37

Loudoun County Trails and Parks 2019 General Plan

— Existing/Planned Bike Lane/Roadside Trail — Existing Recreation Trail — NOVA Parks Trails — Potential Trail Corridor — Lake/Reservoir — County Owned/Leased — NOVA Parks — State & Federal Parks

⬚ figure

Loudoun County IS NOT LIABLE for any use of or reliance upon this map or any information contained herein. While reasonable efforts have been made to obtain accurate data, the County makes no warranty, expressed or implied, as to its accuracy, completeness, or fitness for use of any purpose.

0 1 2 4 6 8 Miles Map Number 2026-009

CHAPTER 6-38

Loudoun County Water/Sewer Service Areas: 2023 2019 General Plan

⬚ figure

Municipal System Loudoun Water Service Area Community System Loudoun Water Central System

Loudoun County IS NOT LIABLE for any use of or reliance upon this map or any information contained herein. While reasonable efforts have been made to obtain accurate data, the County makes no warranty, expressed or implied, as to its accuracy, completeness, or fitness for use of any purpose.

Map Number 2023-064

CHAPTER 6-39

Loudoun County Electrical Infrastructure 2019 General Plan

⬚ figure

High Voltage Transmission Line Classification

      • Approved 138-287 Kilovolt (kV) —— Built 138 - 287 Kilovolt (kV)
      • Approved 500 Kilovolt (kV) —— Built 500 Kilovolt (kV)

*This data is available to the public to view on Weblogs & download on Loudoun County GeoHub.

Loudoun County IS NOT LIABLE for any use of or reliance upon this map or any information contained herein. While reasonable efforts have been made to obtain accurate data, the County makes no warranty, expressed or implied, as to its accuracy, completeness, or fitness for use of any purpose.

Map Number 2026-022 CHAPTER 6-40