0:20Welcome to the public works committee.
0:24And we have, oh, and by the way, all our members are here.
0:30All the committee members are here.
0:32Hanlin, we have Bill 29.
0:46$50,000 to find certain public works capital projects.
0:53Good evening, Vice President Moda.
0:55Good evening, City Council.
0:56So what you have before you this evening are four capital improvement projects that were approved as part of the 2026 budget.
1:05So what we're doing this evening is we're coming before council and appropriating the funding and get it into the correct expense accounts so we could start doing work on these projects.
1:15One of the projects that you could see here that we're undertaking this year is the Canal Street Bridge that's currently at the entrance to Canal Park.
1:36So the bridge deck there is compromised and it's there's weight restrictions, it's reduced to one lane of travel.
1:44This bridge here is 86 years old.
1:47It was built in 1940.
1:49So with all the structural deficiencies that we're having with this bridge, uh we're requesting funding this year to do a design.
1:56Once the design is completed, then we're going to be putting this project out to bid for construction.
2:03I know that we have to put this out to bid, but um do you have sort of like um uh do you happen to know how much you know around the range?
2:16How much will this be?
2:18Yes, so the for for this for the um did this the design work is 250,000, uh, which we're expecting an entire year of design work, so we won't begin construction until roughly the first quarter of 2027.
2:34So we'll have to come back before council once the design is completed to request the funding to complete the construction.
2:40Can you tell me what happened with this bridge?
2:43It's just uh over the years.
2:45It it took a beating, it's old, it's 86 years old.
2:49Um there's wear and tear with any bridge or roadway that we have within our city limits, and it's just at a point in time where it's just past its its life expectancy, and it's it's time for replacement.
3:02So people can um the cars cannot pass uh through that bridge at all?
3:07They can, but it's reduced to a single lane of travel.
3:10The area to the right there where it's the area that's closed off is is where we're having the most issues with the with the bridge decking.
3:19So what we did temporarily was we blocked off that area to preserve the bridge as long as we can, but we're at a point now where the bridge just has to be replaced.
3:32Well, we'll be the second.
3:43I did have a question about this one here.
3:45So given you know the state of bridges in Pennsylvania, it's a kind of universal issue around here.
3:51Where any like grants looked at for potential bridge or bridge replacement costs at all, or is there any way that the any of this is covered through outside sources?
4:01We did look into it and there was currently no grant opportunities out there.
4:05Uh but we before we get into the construction, we're gonna take a look another look just to make sure at least cover the construction component of it.
4:13Uh but the 250,000 dollars is is just an estimate to get the design done.
4:18Once the design is completed, then we'll pretty we'll have a project that's shovel ready and it'll qualify and become eligible for additional grant funding, future grant funding.
4:29Okay, so do we have any comments then?
4:36Do we have any comments from all of us or just no?
4:41I guess we're gonna go one by one then.
4:45Oh, I was thinking about going you know through everything, but let's let's let's do it like that.
4:50We don't yeah, go ahead.
4:51Do you have any comments?
4:54Or for something later.
4:55Any any other comments from the dais?
5:00Okay, any comments from the public?
5:04Okay, so the second project, Capital Project is over at the streets department.
5:09And this is the salt dome that we call it.
5:12Uh this is where we keep our entire winter supply of uh of road salt stockpiled.
5:18As you can see in the pictures here, the roof is bursting at the seams.
5:22Uh there's structural deficiencies within the foundation of the salt dome.
5:27Uh our current stockpile capacity is only 3,000 tons.
5:31Uh so what we're proposing under this new capital improvement plan is to replace this salt dome with a larger salt dome.
5:39Um, and we want to double the stockpile capacity from 3,000 tons to 6,000 tons.
5:46Uh this winter that we faced was a challenging winter.
5:49Uh there was a huge demand for road salt, and with the colder temperatures that we had, the supply unfortunately couldn't meet the demand.
5:57Uh so there were a lot of municipalities out there that were running out of salt or facing salt shortages.
6:04And in turn, you know, we there was a few instances where we had to purchase salt at a much higher rate uh from other vendors just to keep up with winter operations.
6:14So with increasing our stockpile capacity, 6,000 tons, that should be enough road salt to get us through an entire season without having to worry about a shortage or pay an increased cost.
6:26Okay, I have a question.
6:27So how much is a ton?
6:30We currently pay $90.64 per ton.
6:35And uh when you send emergency, how much is it that we're paying?
6:38We were paying up to 150 dollars per ton on on an emergency basis.
6:44So that means that if we do this, then it will be a cost savings for us.
6:48There'll be a cost savings, and we'll be able to purchase the entire year's supply of salt at a much cheaper rate, and we'll have enough salt for our winter operations.
6:57And I I would like to share that uh Miss Ortega and I, like a month and a half ago, we did uh we did a video there, and um it's about time that he gets fixed because he looks really beat up.
7:12It's it's long overdue.
7:14Um this salt shed here is 60 years old.
7:17Uh in a city our size, we should be in a position where we can uh double our stockpile capacity.
7:24Citadfield the city of Philadelphia currently has a salt dome that's capable of storing 20,000 tons.
7:31Uh so we're we're gonna be in a much better position here with doubling our stockpile capacity, 6,000 tons.
7:42So I see in the bill we have an allocation of about $800,000 for the salt shed.
7:46Is that enough for the full replacement and demolition of it?
7:50Or is it going the same spot?
7:51Are we going somewhere else?
7:53It's going in the same spot, and we're expecting that the entire $800,000 will cover demolition and the the addition of a new structure.
8:02And given that the structure, any I mean, design requirements for that.
8:06I mean, I know sometimes design can be a little costly as well.
8:10So I mean, is that allocating design and construction?
8:13That's design and construction.
8:16Any other comments from the Days?
8:18Any comments from the public?
8:24So the third project is the roof replacement project.
8:28There's two major big roofs.
8:30Uh the first one is at the bridgeworks facility, uh, and the second one is at the central fire station.
8:37Uh both roofs are in complete disrepair.
8:40We have large amounts of water that are coming into both buildings.
8:44And I could speak from first hand experience over at the bridgeworks facility.
8:49Um, our crews, our work crews in the traffic department after each rainstorm, rather than being out there in the work field getting work done, they're in the garage squeegeeing water to the floor drains.
8:59I mean, we have substantial amounts of water that are that's entering into our building.
9:04Uh so what under this capital project here?
9:07Uh we're proposing to replace both two roofs at two different locations.
9:12First one's at the bridgeworks location, and second one's at Central Fire.
9:16How much will that be?
9:18That's a total of a million dollars between the two roofs.
9:26Which one are you doing first?
9:28Bridgeworks is first, and then Central Fire second.
9:33That's that that roof there is it's a larger roof, and that's where we have the majority of the water coming in.
9:39Uh so we felt that one was more critical than Central Fire.
9:46Any other comments from the comments from the public?
9:52So um, if I recall from this is I believe last year, but and and I say this noting that um one of the directors noted their water feature in Central Fire when they're in their office.
10:03So I acknowledge the need to have this done.
10:05But my question was did we do some roofing last year for Central Fire?
10:11I remember one of the council people bringing up the expense for it given that it was going to be replaced.
10:16I'm just kind of trying to understand how much did we spend last year and how much are we spending this year for that roof?
10:22So we've done some temporary repairs.
10:24Unfortunately, I don't have the cost with me, but I could certainly get that to you.
10:27What we spent in terms of temporary repairs over the last two years.
10:30But we're at a point where these band-aids are just popping off, and yeah, we can't continue to put band-aids on something that's actively leaking.
10:38Okay, I was just trying to understand because I know that I I tried to find it this morning that they we're talking about some sort of large amount of money, but I'm wondering if that maybe just didn't happen.
10:45It was just uh someone saying something.
10:47So all right, thank you.
10:48And is that gonna go through the process of dating?
10:51Oh, yeah, that'll be part of an RFP process that we put out the bid.
10:57Any comments from the public?
11:02Okay, so the the last project here is it's called the VAV project.
11:07It's a variable air volume project that we're undertaken in City Hall.
11:11Um, and this is upgrades to our HVAC system.
11:15Over the years, uh we've we've spent good amounts of money on improving our HVAC system.
11:22We've replaced both air handlers, we've replaced the chiller system, and we've replaced the boiler.
11:28This is the last component of upgrading our entire HVAC system.
11:32And with this project here, what we'll have the ability to do is we'll be able to actually regulate the temperature on each floor of city hall.
11:41So right now we're in a position where when the heat is on, it's just on.
11:46All five floors are being heated.
11:48Uh some floors are warmer than others, other floors are cold.
11:53Um the the airflow is just not properly circulating through the building.
11:58So with this very variable air volume project, we'll be able to make sure number one that the airflow is circulating throughout the building properly, and more importantly, we'll be able to regulate the temperature than on each floor of city hall, and each floor would have their own thermostat where they'd be able to regulate the temperatures.
12:16Will that affect um the new police station that um that the uh the administration is planning to build?
12:26No, the the new police station will have their own system, so this will have no effect on it.
12:32Okay, and how much will this be?
12:34This project here is three million dollars.
12:45How old is the HB um system?
12:50Do you happen to know?
12:51The major components of this, I don't have the age of the actual system, but the major components of the system all have been upgraded within the last three years.
12:59Um the air handlers, the boiler, the chiller, those are the most expensive pieces of the system.
13:06Uh and this is the last step here.
13:07If we ever want to get ourselves to a position where we could actually control the airflow and the temperatures at each floor of City Hall, this is the last step of the process.
13:17So once we get through this step here, essentially our entire HVAC system is brand new.
13:23Okay, that's good to know.
13:25And any comments from the um quick question is your has your department or maybe working with um you know sustainability.
13:33Have you determined any cost savings with some of these replacements when it comes to efficiency and so forth?
13:38That's a good good question, uh, President Napoli.
13:41Um I just we didn't have an opportunity to really dig down and compare energy costs after these components were installed.
13:48Um but after that we get through this step here, this will this will be a good case study for us to monitor.
13:57Uh, we talked about the police department.
13:59Well, this I then it's not gonna be built for a couple years, and we know they went through a lot last year.
14:03Will this help them?
14:05This will also help them.
14:06It will provide uh relief on their end, and they'll be able to um so this system here will feed both public safety and city hall, but when the construction takes place, they'll have their own operating system.
14:20This year, possibly next year.
14:24Yeah, just in the one more over here.
14:27Um so on a similar note, I was just curious.
14:30So I know we're saying they're independent systems from the police station.
14:33I'm glad to hear we got a new air handling units by the same time.
14:37I think if there's any investigation that's been done as far as any efficiencies by potentially combining any sort of systems, obviously they're independent buildings, but if there's any sort of plant, you know, whether it's chiller units that are tied into both buildings or any any opportunity to size the unit to serve both buildings.
15:00I mean, it sounds like we've already replaced the major equipment here in the city hall, but it I you know, especially as design progresses, I would encourage us to look into hey, how do any of the components in that project potentially supplement the needs of this one or vice versa?
15:11Um, I think there's an opportunity to future proof there.
15:16Thank you for that comment.
15:17Definitely take it into consideration.
15:21Any other comment from the tallest?
15:25Any comments from the public?
15:34Do you um would you like to share something else?
15:38Um the only thing that I'll share with city council is uh we've unfortunately last week uh we we abruptly lost our facilities manager, Nick Ruber, to Lafayette College.
15:49Umfortunately, there was a better opportunity for him there, making a whole lot more money.
15:54Uh so we're currently in the in the process of searching for facilities manager.
15:59Uh the good news is that we've had 24 people that applied for the position and I've been spending my entire week this week and next week with conducting interviews.
16:08So hoping within the next two weeks or so we could find our a replacement for our facilities manager.
16:17Any comments on the dias?
16:20Any comments from the public?
16:23I need someone to make a motion.
16:26Um I'll second that motion.
16:30Those in favor say aye.
16:32Okay, so Bill 29 will be um is voted favorably in front of full council.
16:42Okay, so at this point, this meeting is adjourned.