OpenPublica

Accountability starts with access.

© 2026 · Filed for the public record

Use casesAboutAPIPrivacyTermsLinkedIn
Home/Bentonville, Arkansas/Planning Commission
OPENPUBLICA · PUBLIC MEETING RECORD
Record of Proceedings

Bentonville Planning Commission Meeting - April 21, 2026

Planning Commission — Tuesday, April 21, 2026
BodyBentonville, Arkansas
SessionPlanning Commission
DateTuesday, April 21, 2026
StatusFILED
Video Record
0:00 / 36:13

Original source
Transcript — VerbatimClick a timed line to jump · ⧉ to share it

Speaker numbers apply only to this recording.

Speaker 1

0:27

All

Speaker 2

0:27

right, I see it's 4 30, so I'm gonna go ahead and call to order the meeting of the Venville Planning Commission technical review for April the 21st.

0:38

And we will begin with uh any changes to the minutes.

0:45

May have any changes?

0:47

Modifications.

0:49

Okay, let's move on to the consent agenda.

0:53

So we have those three items.

0:55

Um any of those items that there were the commissioner would like to have removed from the commit consent agenda or have any questions about

Unassigned speaker

1:04

for

Speaker 2

1:04

tech with you.

Speaker 3

1:06

The bright box condos, the utilities on G Street would be underground.

1:12

There's a little bit of overhead there right now, but I'm assuming that's going underground, what I can tell.

1:17

All right.

Speaker 4

1:18

That's

Speaker 3

1:18

right.

1:19

Okay.

Speaker 4

1:20

All right.

1:21

Thank you,

Unassigned speaker

1:22

John.

Unassigned speaker

1:25

Is that

Speaker 5

1:25

all you had,

Speaker 2

1:26

Danny?

Speaker 3

1:26

Yeah.

Speaker 2

1:30

So all three of those items will stay on the consent agenda.

1:32

We'll move on to new business.

1:34

The first is the waiver uh fourth street alley waiver.

1:39

Um

Speaker 4

1:41

so this is on the south side of fourth between B and C Street.

1:46

Uh it came to us as a single family uh building permit.

1:52

And the alley sits today as a 12-footer.

1:56

And uh engineering staff asked for a 16-foot paved, 20-foot easement.

2:03

Uh

Speaker 1

2:06

20-foot, the extraway, 16 feet of pavement.

2:10

Okay, the extra is what has to come out of their property.

Speaker 3

2:19

There's a there was a comment in there that the uh think a right-of-way permit, they marked up how it could work, but you don't have a copy of whatever markup was from the engineering.

2:30

Uh looks to me like it's on there too, but yeah.

Speaker 5

2:34

We've got the some of this.

2:36

Um, so we did submit a right-of-way permit.

2:40

Let me let me just back up a little bit.

2:41

Um, in the staff report, I think it mentions uh that there was a lot split here, and you may be able to see yeah, the two parcels there.

2:49

Um, you know, having to dedicate that additional eight feet on top of the five foot setbacks uh for that alley side, whether in the new code or the old old old code, it's it just doesn't work.

2:59

It's not big enough to build a house there.

3:01

Um these are these are narrow lots, as I'm I'm sure you can see.

3:05

Um we did not I at least I haven't seen any kind of markup from the engineering department on how it could work.

3:11

Um the comments that we got were just um uh that we yeah, we needed some kind of waiver uh uh to reduce the what they're requiring and in your street specifications of 20 foot right-of-way width alley um to this existing 12-foot alley.

Unassigned speaker

3:29

We

Speaker 5

3:30

the the right-of-way is there, we'd like to just utilize that for our two lots to provide rear rear loading to those two lots and not have to have a driveway and a front door.

3:40

Um right there uh on the front edge.

3:43

And um, I think he can get one one house built, but that it just ruins the other lot.

3:47

We it was not wide enough building.

Speaker 3

3:49

So staff has made comments within right away permit to make improvements to meet the MSP requirements, I just don't know what those

Unassigned speaker

3:56

are.

Speaker 3

3:56

Which is what Tom just said, right?

Speaker 4

3:58

Dedicate 20 feet and build 16.

Speaker 1

4:06

Is there a setback requirement from the right-of-way to the garage door?

4:10

Yeah, there's always a setback from the right-of-the-art.

Speaker 3

4:12

I thought they had an actual solution study.

4:16

Um there was a discrepancy.

4:21

I think uh I think your letter that was in the submission referenced 38-foot uh lot width and yet it's 30.5 on the survey.

4:32

Each lot

Discussion Breakdown — Share of Meeting
Zoning And Land Use█████████████████████████████████████████████77%
Procedural███████████18%
Public Engagement██3%
Drainage Infrastructure█2%
Summary of Proceedings

Bentonville Planning Commission Meeting - April 21, 2026

The Bentonville Planning Commission held a technical review session at 4:30 PM followed by the regular meeting at 5:00 PM on April 21, 2026. The commission considered several land development applications, including lot splits, a large-scale development, an alley width and pavement waiver, and two rezoning requests. All items were approved, with the rezoning of the Esslinger property generating notable discussion about zoning transitions and building heights.

Consent Calendar

  • Lots 2 & 3 of Hanwa Addition Lot Split (2500 SW Regional Airport Blvd, LS22-0051) – Approved unanimously.
  • Brightbox Condos Large Scale Development (802 SE G Street, LSD25-0041) – Approved unanimously; a commissioner noted that utilities on G Street would be underground.
  • McKissic Springs Addition, Lots 2 & 3 Lot Split (South of Motley Rd, east of SW Hydrangea Rd, LS26-0006) – Approved unanimously.

Public Comments & Testimony

  • Esslinger Rezoning (RZ26-0021): No members of the public spoke at the hearing, but the city received objection letters from neighboring properties at 302 and 304 Henry Street, which the applicants addressed during the discussion.
  • Rankin Rezoning (RZ26-0022): No public comments were made.

Discussion Items

  • 4th Street Alley Waiver (WAV26-0007) – The applicant, representing AAIGT, LLC, requested a waiver to use the existing 12-foot alley width instead of the required 20-foot right-of-way and 16-foot pavement for two narrow lots at 433 SW 4th Street. Engineering staff noted that while the waiver does not follow the Master Street Plan, it would not cause negative impacts if approved. The commission discussed lot dimensions, drainage, and the feasibility of building homes with the reduced alley width.
  • Esslinger Rezoning (RZ26-0021) – Brad and Cindy Esslinger sought to rezone 306 SE 2nd Street from DN-3 (T4.2) to DN-4 (T5.1) to align with the City Center Place Type. Commissioner Bennett expressed concerns about density and compatibility with surrounding R-1 districts. Staff explained that the T5.1 district includes transition zones that would limit building height to 36 feet within 100 feet of R-1 properties, which is more restrictive than the current T4.2 district (which allows up to 50 feet without transition height limits). This alleviated some concerns.
  • Rankin Rezoning (RZ26-0022) – The applicant sought to rezone 101 Oakhurst Street from A-1 (T2.1) to R-1 to match adjacent development. Staff noted significant topography on the site. The commission approved without discussion.

Key Outcomes

  • Consent calendar (3 items) approved unanimously (5-0).
  • 4th Street Alley Waiver approved unanimously (5-0).
  • Esslinger Rezoning (RZ26-0021) approved unanimously (5-0).
  • Rankin Rezoning (RZ26-0022) approved unanimously (5-0).
  • The planning office's move to 3200 SW Municipal Dr was noted as an informational item.

Meeting Transcript

All right, I see it's 4 30, so I'm gonna go ahead and call to order the meeting of the Venville Planning Commission technical review for April the 21st. And we will begin with uh any changes to the minutes. May have any changes? Modifications. Okay, let's move on to the consent agenda. So we have those three items. Um any of those items that there were the commissioner would like to have removed from the commit consent agenda or have any questions about for tech with you. The bright box condos, the utilities on G Street would be underground. There's a little bit of overhead there right now, but I'm assuming that's going underground, what I can tell. All right. That's right. Okay. All right. Thank you, John. Is that all you had, Danny? Yeah. So all three of those items will stay on the consent agenda. We'll move on to new business. The first is the waiver uh fourth street alley waiver. Um so this is on the south side of fourth between B and C Street. Uh it came to us as a single family uh building permit. And the alley sits today as a 12-footer. And uh engineering staff asked for a 16-foot paved, 20-foot easement. Uh 20-foot, the extraway, 16 feet of pavement. Okay, the extra is what has to come out of their property. There's a there was a comment in there that the uh think a right-of-way permit, they marked up how it could work, but you don't have a copy of whatever markup was from the engineering. Uh looks to me like it's on there too, but yeah. We've got the some of this. Um, so we did submit a right-of-way permit. Let me let me just back up a little bit. Um, in the staff report, I think it mentions uh that there was a lot split here, and you may be able to see yeah, the two parcels there. Um, you know, having to dedicate that additional eight feet on top of the five foot setbacks uh for that alley side, whether in the new code or the old old old code, it's it just doesn't work. It's not big enough to build a house there. Um these are these are narrow lots, as I'm I'm sure you can see. Um we did not I at least I haven't seen any kind of markup from the engineering department on how it could work. Um the comments that we got were just um uh that we yeah, we needed some kind of waiver uh uh to reduce the what they're requiring and in your street specifications of 20 foot right-of-way width alley um to this existing 12-foot alley. We the the right-of-way is there, we'd like to just utilize that for our two lots to provide rear rear loading to those two lots and not have to have a driveway and a front door. Um right there uh on the front edge. And um, I think he can get one one house built, but that it just ruins the other lot. We it was not wide enough building.

SUMMARIZED BY OPENPUBLICA AI
TRANSCRIPT VIA PUBLIC VIDEO
openpublica.com