0:02I'd like to welcome everyone to this special call meeting by the mayor.
0:07Purpose of the meeting, of course, is to uh do an agenda review.
0:11So uh need a motion to approve or approve the content of the meeting.
0:19All right, move by Mr.
0:21I'll say all right, second by Mr.
0:26Tisdale, anyone else?
0:31Motion carries unanimous.
0:36Not quite, but almost.
0:38Um we'll go ahead and go around the room.
0:41So uh we'll start with Mr.
0:46Any items you want to discuss or any ideas after reviewing the initial content?
0:52Um sure, Kenny, if you if you don't mind, would you review the public hearing process because we've got a tree hearing on tomorrow's uh agenda, and that's gonna be new for the new council members.
1:07So if you could just go over the format.
1:09All right, as I understand it, uh we'll have opening remarks um by Mr.
1:16Uh there is a time uh uh Jerry Crew.
1:20Uh there is a uh time constraint on those opening remarks that he'll have uh somewhere around the 10-15 minute uh mark, then the opposing uh or or the counter uh to Jerry will have their time.
1:34It's also around 10 or 15 minutes.
1:36I'll I'll clarify that uh tomorrow, and then there's a final rebuttal that's uh five or ten minutes, and then we'll conclude that uh hearing with any other uh questions or or comments.
1:51So what is the purpose of this public hearing at the council before the yeah?
1:57So the public hearing is just that we call a public hearing to inform any informed uh concerned citizens that want to come to this hearing to to listen uh into this discussion about uh the trees.
2:12I believe that it's a tree removal, right?
2:14Is that what we're discussing?
2:16And to hear uh information to clarify exactly why we are having this uh debate on on 26 trees or 32 trees or however many it is.
2:29This is uh this is an appeal by the individual of the planning commission's decision.
2:40But but then so once that's concluded, then we go into our policy agenda where it's the first thing on the policy agenda.
2:48So so does anything come out of the public hearing?
2:52It's a hearing, just a hearing to listen to both sides.
2:55There's no action that's taken during the hearing per se.
2:59Any action would be taken during council during our council meeting.
3:03Yeah, nor normally had there been no appeal, this would just come on uh normally for the council to approve the recommendation of the planning commission.
3:14Since there's an appeal, it's basically an extra public hearing uh that they're afforded.
3:20So uh they filed an appeal from the planning commission's decision, and that kicked in an extra public hearing before the rule before y'all's meeting.
3:31So that was from the roll straight into it after not the tree committee, the planning commission.
3:39No, the planning commission approved the recommendation of the tree committee.
3:45So it's been through two stages.
3:47They've still appealed.
3:49I think the appeal is just allowed basically for additional public comment.
3:53That's why they uh that's what they the benefit they're receiving by this appeal.
3:58And they'll give their basis of that appeal and and the logic behind their appeal uh during their time uh during this process.
4:06So do we have input during the public hearing?
4:10We are allowed, I think we are allowed some questioning during during the hearing, yes.
4:19Yes, the next item is is item five eye, and this is uh I had two questions.
4:26One was the use of the the X-ray machine, but I spoke with uh Chief Debeck, Assistant Chief D back, and he explained that.
4:35Um but the this deals with a budget amendment, and are we amending the budget because this was something that was ordered in the last fiscal year but was not delivered in the last fiscal year, or is this something the police department because I'm from I'm familiar with the item and we we approved this last year?
5:13Five item five I under the consent agenda.
5:18So it really is just what's right.
5:22Why what's what's the reason for the budget amendment?
5:26It was just might have been overlooked in the budgeting process for this this piece of equipment, or it could have been something that was, like I said, ordered in the last fiscal year but wasn't delivered in the last fiscal year.
5:38No, this is uh what I told you earlier, I was thinking about a different one.
5:42That was the Tremble system.
5:43This would be for the uh the bomb team.
5:46So usually we're getting the budget amendment should be because we're gonna get reimbursed by the Federal Government.
5:55So we'll be in reimbursed for that through the grant.
6:02Um everybody uses it, including us.
6:08Also, there are two items, item C and item B.
6:15And if if Rachel, if you don't mind, as a contracts manager, could you come up and explain exactly what we're because we're we're moving money from project to project and require some action by the council and approval and so forth.
6:33But for the benefit of everybody else.
6:37I think I understand, but I want to be sure I understand and the others may have questions as well.
6:46It's hard to talk about one without the other.
6:49We have two projects.
6:50We have Tanglewood and Bay Vista.
6:53Both are funded with MCWI grants that are required to be matched by ARPA.
6:58We've completed the Tanglewood project, and we have about 600,000 of ARPA and 600,000 of MCWI money left.
7:06We're moving that money to Bay Vista now.
7:11So those two resolutions, and that would be one right before Z in Z.
7:21It requires us to sign two separate agreements.
7:31B B is B is a is a different item.
7:35This deals, and as I recall, we had um approved a similar agency agreement last year, Peter.
7:43I don't know if you recall or not.
7:44I I remember we did something like this last year.
7:48Job training with uh through South Mississippi Planning and Development District, and it focuses on um job skills for older adults.
8:02And under item two specifications, it says the host city, which would be us, agrees to the following training specifications.
8:11Then it lists the position, city hall reception assistant.
8:14So is that a somebody's coming to us?
8:17Yes to help with that.
8:19Okay, that's what I thought.
8:30And they are limited to 29 hours a week, and then I also believe we have to provide workers' comp coverage uh for the participants.
8:43All of that is provided through SMPD D.
8:47I just wanted to be sure.
9:04And how you spread that 29 hours of work over the week is I guess up to us.
9:10Thank you, gentlemen.
9:11Schumacher, any items?
9:16So real quick on that Tanglewood Bay Vista deal, the the the if it was uh 1.2 that was shifting?
9:28So was that project not fully funded, or they need that to complete that project?
9:32That project was fully funded, that is left over after completion.
9:36We have done the entire project, and we have 1.2 million dollars left.
9:48Um, regarding this issue A on the policy agenda that we're gonna get to, and I'm gonna I'm assuming that the our our land ordinance, so there's total of what, how many trees?
10:00Um so regarding this issue A on the policy agenda that we're gonna get to, and I'm gonna I'm assuming uh the our our land ordinance, so there's total of what how many trees now according to the ordinance, if they have a public works permit, they can cut down trees that are within the areas of the infrastructure that they needed to build as long as they have the public works permit.
10:26And from my understanding, they have the public works permit, and that would cover I think 13 trees that they would be able to cut down just under that permit, correct?
10:39Actual specifics is probably as far as the merits of what's going on.
10:45Uh I don't have all the details, probably better just to clarify any of that tomorrow.
10:52I know they're allowed to cut down a certain amount since they are exceeding that amount.
10:57That's why they had to go through the tree committee in the first place.
11:04Protected protected tree.
11:06There could be other conditions like the uh the condition of the tree uh that that kind of plays into all of this as well.
11:15So and then the the mitigation with uh replacing the trees, they're wanting to do cedar trees instead, but that's not what the mitigation calls for.
11:26Mitigation calls for it has to be one of the three trees that they gotta do.
11:31We can't be we can't be the cedar tree, correct?
11:35All right, so we'll get into more depth tomorrow with that.
11:42So item five F so that's well, it's a hundred and thirty-four thousand and some change that is that we're short.
11:58I mean, that we won't have, or that we're saving our August two months.
12:14That's just reconciliation for the end of the year balance because when we do our budget, it's a it's we start like in June or July.
12:23So that's on estimated, and then we have expenses through September, so that's just cleaning up and selling for the new year.
12:39All right, so on the routine agenda agenda.
12:48If we could, uh I notice in that routine agenda that we have an invoice from Brian Keith Heard for two invoices for 8,000 apiece for a total of 16,000.
13:02Did we get any reports along with that?
13:10It is can we have those for the meeting tomorrow?
13:13And then also in there, there's a and I'm assuming Jamie, the is some parks and rec stuff.
13:23That's just us giving deposits back.
13:25Is that what we're doing here?
13:27At the very end, I would think yes, sir.
13:57The commercial weed eaters from steel that we have been doing, what we did was we went ahead and bought five ones that were props ferry, and we're trying them out this year, but we had to go ahead and purchase the other ones too.
14:17Or trying these other five out.
14:19I didn't want to sell the money on the ones that are not tried out.
14:24Or doing those five that we bought the other day, and we're gonna finish up or we'll have a comparison on those.
14:39I mean grade weeding.
14:47That's more in your area of expertise than mine.
14:52That's the reasoning behind the steel versus the five that we bought the other day.
14:57Try them talking to Mr.
15:00That's by the improvement.
15:07Right before you bought five.
15:23Any other ideas or thoughts uh for tomorrow that you have on your mind that's not on the agenda that you you plan to try to clarify?
15:32So perhaps uh we can give the administration a little bit of time to do some homework.
15:42We proper time, we've got a couple of litigation matters to deal with an executive session.
15:48We'll we'll get to those in a minute.
15:50I just want to know if there's there's anything on your council report or uh we don't come from left field or right field or or whatever tomorrow.
15:59I I did have one one thing.
16:01One question I was gonna ask is the so over on Oak Street, there's a church that's building a big uh addition.
16:09Uh do we know who that contractor is?
16:13And the court I was just wondering if they put up that whole building less than three months, and we can't get carpet loom for the Sanger.
16:21Can we get them to do something?
16:24Can we get them to help us at the Sankor?
16:32Uh yeah, just I just thought I'd bring that up to see if we can move the Sanger along quicker.
16:37Okay, maybe I can get that answer to you by tomorrow, Councilman.
16:41Gray, you have anything?
16:45Just curious, and it may have been answered or asked already.
16:49But are these pre-meetings before the meeting on Tuesdays?
16:52Is this gonna be something new that we're gonna do every week before we have a council meeting?
17:47I'm gonna add this too.
17:48So the everybody gets a copy of the agenda by Thursday.
17:54And so we have a chance Thursday, Friday, Saturday, Sunday, Monday, and up until our meeting begins on Tuesday, uh, to look at the content.
18:04And a lot of times what happens on Tuesday, we get in here and either you couldn't make that phone call or you couldn't connect with the mayor's office or Rick.
18:14And this is one last chance to be able to close that gap of some communication and clarification so that we have a smoother running meeting and no misunderstandings, or all of a sudden we have a big disagreement that could have been avoided.
18:30And and I think the mayor is attempting to have these on to answer your question, councilman, on on Mondays prior to our uh meeting tomorrow, just to make sure that if he needs to get prepared, he can get those answers for you, or maybe answering them in these meetings, and then everything goes smooth a lot more smoother uh in our Tuesday meetings.
18:51That that's how I I view it.
18:53Does that answer a little bit?
18:55Yeah, that answers my question.
18:56I'm not necessarily saying I agree with the meeting before the meeting.
19:00Some of y'all may, that's fine.
19:02I just feel that's one extra thing that we have to do.
19:05I've since I've been on the council.
19:07If I have an issue, I'll talk to the mayor.
19:12I'll talk to the CAO, I'll talk to the director of a department before my meeting.
19:16I can't say we don't have issues up here during a meeting, but I just thought that's kind of what meetings were for.
19:23And every city, I don't know of any other city, and I may be wrong that has the meetings before the meetings.
19:28I mean, if that's something we're gonna do, uh I don't know.
19:32I I I personally, and I know everybody showed up, everybody's taking time to come here.
19:39But I have a meeting before the meeting, I just don't know that I I'm on board with that.
19:45I think we should be able to air out what we need to air out tomorrow.
19:47And if it's an issue, like I think most of us have done is get with that person prior to the meeting, like you said, when when you get the agenda, look at it.
20:00Contact the CAO with their I've I've never had any issues and get it done, get it handled before the meeting.
20:05That's just my two cents.
20:06Councilman Schumaker, I don't disagree with you, but I I think what has happened, you know, we got new council members, and we're we're trying to find that sweet spot and communicating.
20:16I think it will evolve with that.
20:18I think that's the hope that maybe in a short period of time we'll find that we don't need these meetings.
20:24Just to follow up on that, and and I appreciate the administration looking to move the days.
20:30It's not that Monday's an issue, it's that my issue to follow up on councilman shoemakers is we're meeting on an agenda that's put in place the day before we take up the agenda.
20:43I in my personal opinion, I think it would be better to meet on the day before the agenda is set to discuss the items that are going to be on the agenda that possible possibly are comp uh controversial that we can discuss before they get on agenda rather than after the agenda.
21:01And I I had mentioned that to these guys just for a possibility if we meet before the agenda is set rather than meet after the agenda set before we take it up the next day.
21:11So all of those are open.
21:14This was just the mayor's first time.
21:16This is the second time we've had this meeting.
21:18So as we discuss this, everything is uh is on the table right now.
21:23Um we go into executive session.
21:34Umly right now I've had discussion with multiple of y'all about some additional money that's been left over from the CDD.
21:42So what I've asked is Mr.
21:44kind of come in and lay out everything.
21:47First kind of take a look and see what's out there, right?
21:53So let our talk and we'll see.
21:56And uh this is just something hopefully is beneficial for everyone to be able to see.
22:01Dates, the times, and what available things.
22:12I get to carry the mic.
22:16So I know in previous meetings there's been a lot of talk about you know the CDBG funds and how to be spent and et cetera, et cetera.
22:27The point I'm what we're trying to explain tonight is when I know Susan's mentioned repeatedly that you know it's a 30-day comment, 15-day public hearing, all of these steps that we were that go into changing anything that is in our um whether it be the action plan or at this point the consolidated plan that we haven't that's already in place.
22:52So when we say that, and I know there's been talk with the CDBG fund, the CV, the COVID funds, that there is some left over, and there are two different thought processes on how that could be spent.
23:04We have submitted both ideas um to HUD.
23:07I know one was for you know, water bottle fillers at various locations, and then another is potentially a sign.
23:14We submitted to HUD, we have not heard a response back on whether that would be eligible.
23:19But if depending on this is how you would go about changing that given the time constraints that we are up against, given the money expires um in June.
23:29So if this happened, and starting what would happen a week from today, would be sending over the the process of hey, what are we gonna do?
23:40This is the plan to from we the mayor and the the mayor, Rick, they would tell Susan and myself, we don't make the decisions on how the money is spent.
23:50That is completely up to the administration, you know, as it goes forward.
23:56We have to have a public hearing.
23:58So we would submit the notice to be put in the newspaper to say there will be a public hearing on a given date.
24:06So in this case, send it out on Tuesday, it'll be published on Sunday, which would be the 30th of November.
24:14I have to get to the meeting.
24:16So in this case, the hearing would be on December 16th.
24:20So that is when our hearing is is held.
24:23After that, there is a 30-day comment period.
24:27So we have to count the 30 days from there.
24:32Comment period would end on the 16th.
24:34We then have to take all of the ideas, everything put together to then combine it to get to the council to have it on the agenda for approval.
24:45That is also giving us time because even if we get all of these comments, we have to get approval to HUD that it's even something that can happen.
24:55Then we'd have to send if it passes, y'all agree this is what we're gonna do, it goes to HUD for final approval.
25:03They may take up to 45 days to give us their final approval.
25:07Okay, so right now we're in January.
25:35Um we get approval from HUD.
25:38The earliest that we could begin to procure, because everything with federal dollars must go through the procurement process, would be February 9th, in which case we have to advertise that this is going to be procured, which gives another 30 days for it to be procured.
26:00That brings us to we're now in March.
26:03Somewhere around the 18th.
26:06Just type of project and what we're looking to do.
26:16April, we're not able to do anything because that is during everything is being advertised.
26:24If it's a construction process, a project or anything that requires environmentals, design, then this that would be occurring, you know, potentially.
26:36And even advertise for construction get to May.
26:41The deadline for all of these funds be spent and closed out, which means we have to have all the receipts back submitted to HUD is June 1st.
26:54So that doesn't give you a great deal of time, depending on what you're wanting to do.
26:59If if that gives you a little bit more clarity.
27:37All while you're also going to be doing the HVAC at the Groich Center and some of the other projects that we have going as well.
27:46So approvals may we got 30 days to have everything spent closed out and receipts.
27:54So would because the money, the COVID money expires.
27:58So would we would we pay for it and then use that money to reimburse so all of these funds are on a reimbursable basis, which means we would enter into the contract, the company would go and do the work, they submit their receipts to us where we have to validate, you know, everything was done, how it was supposed to be done, make sure it's within the you know, they're following what they're supposed to be doing for oversight.
28:27Then we're able to do a voucher into IDIS to then have the money drawn down to them.
28:33So we would have less than 30 days once we get approval to have it.
28:40If it's and we're at the mercy of the contractor to get us the receipts and do the work and just can't do any.
28:53So the two things that Susan is put up right now is a digital sign at the Groit Center that I've heard from multiple council members that we were talking about.
29:03And then the discussion based off COVID funds was also those waterless or touchless water fountains throughout the parks, the wreck buildings, and the city buildings throughout the city.
29:14So we've submitted both of those up to see which one that they would be open to to see.
29:20If we go the direction of the sign, there's gonna have to be an a design put into that, which is gonna take longer as well.
29:30Not as much on doing the plumbing for the other.
29:34So we're gonna see what it is and present that when the mayor gets back, and then see which way the council wants to go.
29:43It will be, but that's no that all of it will be covered underneath.
29:47But I have no idea how much a sign costs right now either.
29:50I know how much money we have.
29:52Question how much money do we have?
30:01So even doing the the water fountains, we could run into the same issue if they have problems.
30:10No, I totally agree.
30:11And uh so those are things that we've got to take a look at, but what we're looking at is what are gonna be some of our options, and if you have other ideas, please let me know.
30:20Those are just the two that we submitted because we have to submit that up to HUD for them to say yes, go forward and we're approve these projects for that.
30:31So that is an actual timeline.
30:35We're in that process.
30:37Well, we're waiting on HUD, and then what we'll do is have more thorough discussion tomorrow, and ultimately it'll be up to the council to tell me which what y'all approve and don't approve, and then we'll know which direction to go.
30:50So once we get the answer back from HUD, then we'll make sure that you're aware of it.
30:54And if it's both, then we get a choice.
30:57If it's one or the other, then you get a choice if you want to go forward with that or not.
31:02So those are what we're looking at.
31:04And if you have other suggestions, we're very open to listening to what what else I'm constrained.
31:09I I I agree with you, sir.
31:11Since they're COVID funds, I mean they've got to be spent on this by this deadline.
31:16And there's no carry the strings that are attached to them based off the COVID side of the house.
31:24I thought this money can only be spent at the growing center.
31:30I don't think we've ever talked about it doing air conditioning.
31:42Yeah, oh, I didn't know if the other 320-something had to be spent at the growth center, but it can be different places for for the uh with the touchless waterfront.
32:38Also, receive programs all are myself when we are working towards that program that we've touched up.
33:26You sure he was wrong with me.
33:30I don't believe nothing that may until he's a politician.
33:36We may need to have a two uh Wednesday meeting, Monday and Wednesday.
33:42Uh how long have we had this money?
33:47How long have we had this money?
33:50How long have we had it?
34:03And we sent over the five amendments that we did.
34:08And we've had this money for a while, and we've done five amendments to try to spend this money.
34:22Either NIMBY got involved or HUD shut it down.
34:25And then they told us the money was going away.
34:29That we could spend it, so we stopped.
34:32Then they came back, they extended the program.
34:36They came to the city, met with the staff, the mayor, and said, let us help you spend this money.
34:46That's how we came up with the growage project.
34:49And here we are now.
34:51So just help us understand this.
34:54Every time you did it five times before, so every time was this lengthy process?
35:02To do it, and that's why it took so long.
35:04It takes any time you do any kind of amendment, you have to go the process.
35:09You have to do the 15-day notification, the public hearing, a 30-day comment period, then come to the council for approval, and then send it to HUD.
35:20It's not like we didn't want to do anything with this money.
35:24We're just trying to figure, you know, at five different projects, just HUD wouldn't let y'all do.
35:30And they would tell us the dumbers weren't there, the COVID dumbers, because everything had to tie it.
35:34Well, nobody was spending that money.
35:36What were the other projects?
35:40The other amendment.
35:41What kind of projects were they?
35:44Well, we were we were dealing with uh we were addressing the homeless situation.
35:49We were doing a uh a resource center.
35:52We started out with uh rental assistance because everybody was without jobs.
36:00They said you couldn't pay arrears, so they shut us down for 18 months.
36:04Then they told us we could start it again.
36:07Well, by that time there was other monies available.
36:10And that's one reason why we submitted both of those to HUD, and we're waiting on that to come back to say move forward this direction, this direction, or both directions are good.
36:20We don't want to give y'all any thing to vote on that we know is not gonna be approved by the case.
36:26And like we just said, uh, we don't know even if we start tracking this, we don't know what the other side is gonna come back and tell us at any minute.
36:35So we're we're trying to put this in the hopper to move forward.
36:39It'd be nice if we can do both these projects, but you know, we'll see where it goes.
36:44The when we talked to HUD, we we did a phone conversation with them.
36:50And the program that we're gonna be trying to work on, the housing rehab program actually qualified it.
36:58We're talking directly to HUD.
36:59I believe it was you was on the phone, Mr.
37:04They approved it on verbally.
37:05They said, Yeah, that could be done if you can get it done in time.
37:09Okay, so we know that'll work.
37:11So can we send a third one out?
37:13If we don't do but one house, 30 days, if if it didn't knock out one house, that'll help.
37:22That's why we submitted that, and that's why this plan that I thought we talked about last week was to put that program together.
37:29The program together, six, and then move forward with all the funding.
37:34It takes time to put a program in place, Mr.
37:38Well, we're asking is that we got um we got Big Bay Mission.
37:43Can we let's ask them?
37:44Can you do something if they got a 45-day or 30-day time frame?
37:47Could he go in and do one floor, one house?
37:50We have money left over unit, we're gonna lose it.
38:00I don't know who the answer.
38:01I I know I do respect uh Ms.
38:03Pickage's uh expertise, and uh can it be done?
38:07We we won't know until we uh engage with something or initiate something.
38:13Uh but we're we also gotta listen uh to Susan.
38:17So if we put a third program in place, this rehab emergency or the the uh rehab, is that a possibility to use this money for?
38:33Don't run Paula off now.
38:35I mean, you got one person that's come in here.
38:37I mean, you know, she she's new, she's gonna be great, but you got her, she's still learning the IDIS system.
38:46She's gonna have the co the growth center, she's got the road project, she's putting this in place.
38:51Yes, if if the mayor and rick say let's do it, let's do it.
38:56That's another thing for her to have to do.
38:58Okay, that's it's a backup.
38:59In other words, you got you got one backup, do another backup.
39:03When you get through, we say you come up you don't spend 200, that's another hundred thousand.
39:08And I know for a fact, you guys, dear people.
39:11We went to their houses.
39:12If we can go if back baby can go in and fix one house, you would there, Mr.
39:18Why send it back to the to the federal government?
39:20We could take it in and do that bathroom floor, the kitchen floor, throw a roof on, be through with it.
39:26So let me ask the question.
39:28Pickage, could we have a backup plan ready if these two fall through, or are we gonna uh again run in your words run her off if we try to put a backup plan?
39:39I say it's we keep I'm gonna be professional.
39:43We keep talking about this.
39:45Let's start the process, see what happens.
39:49Okay, it's quite because by June, it's going away.
39:53I agree with that, and that's what I'm saying.
39:55Just call back by mission and tell them to do it.
39:57Everything has to be procured.
40:00We understand we're just getting it.
40:01We're just getting up getting an uh uh just getting an element in the shoe, just in case.
40:05This is fine with the council.
40:07This is what I will ask.
40:13Request for our two courses of action currently.
40:18Tomorrow, we'll send the other one up.
40:21We should get the approval back within 4872 hours on the other two.
40:26Same thing on that one.
40:29Or disapproval, either way.
40:31So what we'll do is if we get it back tomorrow or Wednesday, then I'll let you know this one is good.
40:39This one was good, or this one was bad, this one was bad.
40:42Then we'll work on the other.
40:44I understand what you're saying.
40:46I still say going forward as we discussed and actually putting a silent plan, build these homes, fix these houses, is gonna be the best bet for all of us.
40:57Because if we don't, there is a significant risk of losing money on there.
41:02If we can go forward with the two courses of action in which we're in reference to currently, then also we'll submit that tomorrow for those, and then take a look and see which one the council decides to approve.
41:21All they have to do is just tell the administration, we don't approve it up front.
41:28We go through the process and then approve it because you got the citizens' input at the public hearing and then approval.
41:36So unless y'all change the way the citizens participation plan, it doesn't have to be approved ahead of time.
41:43So if I may ask a question here, to me, the pivotal question is because the process was outlined, and at the at the end of the process, whenever that was the last public hearing and all that information is is compiled, then that money has to be expended by June 1st.
42:09So you if I recall correctly, I may not.
42:12So you've got basically if everything worked perfectly.
42:17You better have, if you got one house, that house better be done within 20 working days.
42:26Yeah, with no termites or anything you don't find.
42:29Because if those dollars are not expended, you're gonna lose that money.
42:34And I'm I'm thinking, based on what I heard, you got you have to follow the process.
42:40I think we all understand that.
42:43Marshall, your point is, well, if we have 20 days, what can we do in 20 days?
42:48And if uh all of our fingers are crossed, we might get a house done.
42:53Applicate applicants.
42:55I think well, if right for those applicants, and all of that you can have that.
43:01Right, but that that would be part of the timeline, right?
43:04It's just the fact that we've got regardless of what you want to do.
43:08If it can't be done and completed, construction started and ended within 20 days, you're not getting paid for that.
43:16And what happens if that contractor says, cheese, we're gonna miss it by two days.
43:22Who's gonna pay that contractor for the 20 days they've done and for the you know what I'm saying?
43:28So we're gonna need more meetings, gentlemen.
43:31We're gonna need more meetings.
43:33So anyway, all right, but I don't want to be sure I understood.
43:37Marshall final word on this, and then we're gonna go into executive session.
43:40Marshall, it's just an option.
43:41Can you just submit it like you just said, just go on submit it, and we'll hash out if we possible with possible if not if not if it's not approved, then you see even going any further.
43:50If it says okay, yeah, then we work out the logistics of it.
43:53But give you in the pipe right now.
43:55Thank you, gentlemen.
43:57Um thank you, Susan.
44:01All right, I need uh I need a motion that the council go into closed session for the purposes of examining the necessity to go into executive session, discuss uh potential litigation uh in a matter uh uh uh potential litigation with Airbnb, and the other is potential litigation with me case.
44:26I'll make that motion.
44:28Second made and second at all in favor all opposed, motion carries.
44:34Need a motion that the council conclude and close uh session and reconvene in an open meeting.
44:40I'll make that motion.
44:41All right, made by Mr.
44:42Tisdale, seconded by shoemaker.
44:44All in favor, those opposed.
44:47All right, need a motion to go into executive session.
44:50I'll make that motion.
44:53All right, made by Mr.
44:54Tisdale, second by Mr.
44:57Those opposed, we're in executive session.
1:15:56Uh gentlemen, I need a um motion that the council conclude uh the executive session and reconvene as an open meeting.
1:16:03I'll make that motion.
1:16:09I'd like to note that there was no action taken in executive session.
1:16:14Uh any other business.
1:16:17There being none, I'll make that motion.
1:16:24Tisdale, second by Mr.
1:16:38Those opposed end of the session.