FY 2026 Budget Workshop: Corpus Christi Water Proposed Budget and Rates – August 13, 2025

City Council — Wednesday, August 13, 2025
BodyCorpus Christi, Texas
SessionCity Council
DateWednesday, August 13, 2025
StatusFILED
Video Record
0:00 / 2:51:58

Original source
Transcript — VerbatimClick a timed line to jump · ⧉ to share it

Speaker numbers apply only to this recording. Names come from transcript evidence. “Possibly” marks uncertain attribution.

Speaker 1

18:08

Okay.

18:09

Good morning, everyone.

18:10

I'd

Speaker 2

18:10

like to call this meeting to order, Miss Martha.

18:12

Could you please call the role?

18:14

Mayor Palette Wahardo.

18:15

President.

18:16

Council members Roland Baretta.

18:17

Here.

18:18

Sylvia Campos.

Unassigned speaker

18:19

Eric Anthu is absent.

Speaker 2

18:21

Gillard Hernandez.

18:22

Calen Paxson.

18:25

Everett Roy.

Speaker 3

18:26

Present.

Speaker 2

18:27

Mark Scott.

18:28

Carolyn Bond.

18:30

City Manager Peter Zanoni.

18:31

Present.

18:32

City Attorney Miles Resley.

18:33

Mayor and Council of Quorum of the Council and the Require Charter officers are present to conduct the meeting.

Speaker 1

18:44

No, ma'am.

18:45

Okay.

18:46

So good morning, everyone.

18:47

This morning we are going to have an overview of the Corpus Christie or my Corpus Christi Water of the fiscal year twenty twenty-six operating and capital improvement program proposed budget and rates.

Speaker 4

20:01

Mr.

20:02

Wes Nebgen, our director of infrastructure services will present to you two decision packages for your consideration.

20:09

One will approve our ability to maintain our infrastructure, and the second will improve our ability to serve our community with type 1 effluent or reclaimed water.

20:35

With the ultimate goal of all rate paying all rate classes rate customers paying their true cost of service.

20:43

We have achieved this objective, and you will see the results of this cost of service analysis in the upcoming slides.

20:52

It's important to point out that CCW operates as an enterprise fund.

20:57

An enterprise fund is a dedicated fund to support the operations of the water and wastewater utility.

21:05

We are not supported by taxes.

21:07

We are financially independent and self-sustaining and are not part of the general fund.

21:12

We operate this fund just like a not-for-profit business would, with the purpose of being good stewards of our ratepayers' investments.

21:20

And while we are not here to make a profit, we are here to ensure that the ratepayer is being served efficiently.

21:26

Our ratepayers are the community that we serve, and we strive to meet their needs every

Unassigned speaker

21:31

day.

Unassigned speaker

21:33

So

Speaker 4

21:33

let me start with the proposed 2026 budget for the wastewater fund.

21:38

Before we get into the numbers, we want to highlight a few achievements.

21:42

I won't read the entire bulleted list here, but just select a few key projects, which includes our two largest wastewater treatment plants and our largest lift station.

21:52

So just this past May, we issued a 102 million dollar construction award to rehabilitate infrastructure and improve treatment processes at the Greenwood wastewater treatment plant.

Unassigned speaker

22:03

The

Speaker 4

22:04

OSO wastewater treatment plant, which is our largest wastewater treatment plant, saw a 111 million dollar investment last year to modernize the ammonia removal system, which will lower the operational cost and increase plant capacity to 18 million gallons a day.

22:20

This is a four-year project.

22:22

And at our largest lift station in the entire city, the Williams Lift Station, we've achieved substantial completion for the $12.2 million project.

22:32

Our team continues to inspect, clean, and perform preventative maintenance of our collection system.

22:38

The IDIQ contracts are an excellent implementation tool for rehabilitating and replacing wastewater pipelines across the city, which included replacing approximately 32,000 linear feet of wastewater lines and rehabilitating 100 manholes.

22:55

Rapid deployment of these resources to address aging infrastructure is essential, and we are meeting our key performance indicators of the consent decree.

23:05

And so speaking of the consent decree, as you can see here, the decree continues to be a major initiative that drives virtually everything that we do in our wastewater department.

23:14

Just as a reminder, the consent decree was implemented in January of 2021 as a result of the city not meeting the Clean Water Act.

23:22

The 15-year decree mandates that the city improves maintenance functions and the infrastructure associated with the system.

23:29

To improve the system, the consent decree is sp establishes specific targets and goals that we are either meeting or exceeding today.

Unassigned speaker

23:37

As

Speaker 4

23:37

part of the CD, we're required to initiate pre-design and design for parts of our wastewater system that have had uh hydraulic constraints, and constraints are typically another way to say parts of the system that are not large enough to move flow through them.

23:54

So we are gonna continue to implement these types of projects through, especially through our IDIQ contracts, as mentioned earlier.

24:03

Here's a list of consent decree milestones, and as we can see, we've completed uh 10 out of the 17 milestones, and the remaining milestones are either on schedule or ahead of schedule.

24:19

As part of the CD, as part of the consent decree, we are self-performing much of our own work.

24:26

This is a little different than other cities where a greater portion of work in cities that have CDs are typically subcontracted out.

Discussion Breakdown — Share of Meeting
Water And Wastewater Management█████████████████████████████████████████████68%
Budget Equity Analysis█████7%
Capital Improvement Planning███5%
Public Information Management███5%
Infrastructure Projects███4%
Personnel Matters██3%
Public Engagement█2%
Zoning And Land Use█2%
Public Safety█2%
Summary of Proceedings

FY 2026 Budget Workshop: Corpus Christi Water Proposed Budget and Rates – August 13, 2025

On August 13, 2025, the Corpus Christi City Council held a budget workshop on Corpus Christi Water’s (CCW) proposed FY 2026 operating budget, capital improvement program, and rates for both the wastewater and water funds. Mayor Paulette Guajardo called the meeting to order and roll call established a quorum. Staff and consultants presented cost-of-service studies, rate proposals, infrastructure achievements, consent decree progress, and two decision packages. The agenda stated the meeting was informational only, and no formal action was taken.

Wastewater Fund Highlights

  • Major wastewater projects in FY25 included a $102 million construction award for rehabilitation and treatment improvements at the Greenwood wastewater treatment plant; a $111 million investment at the OSO wastewater treatment plant to modernize the ammonia removal system, a four-year project increasing plant capacity to 18 million gallons per day; and substantial completion of the $12.2 million Williams Lift Station project.
  • CCW replaced approximately 32,000 linear feet of wastewater lines and rehabilitated 100 manholes through IDIQ contracts.
  • The consent decree, in effect since January 2021, remains a major driver of wastewater work. Staff reported that 10 of 17 consent decree milestones are complete, with the remaining milestones on or ahead of schedule.
  • The projected average residential wastewater rate in Year 10 of the consent decree is now $94, compared with the original analysis of $80 to $90, primarily due to inflation of about 24.8% between 2020 and 2025 versus the original 15% assumption.
  • The proposed FY26 wastewater fund includes $113.6 million in expenditures and $99.4 million in revenue plus fund balance. Revenues increased by $2.6 million from FY25, while expenditures increased by $100,000, for an overall increase of 0.1%, below the water/sewer consumer price index of 4.86%.

Wastewater Decision Packages

  • Decision Package 1 proposed adding nine maintenance positions and heavy equipment, with an $800,000 annual cost and a $1.5 million one-time cost. Staff stated the treatment plants have not added staff in at least 15 years despite infrastructure upgrades, and that current maintenance workloads include about 183 preventive and 155 corrective work orders per month.
  • Decision Package 2 proposed adding seven positions to operate the OSO reclaimed-water fill station. The station currently provides reclaimed water free of charge, distributes about 20,000 gallons per day, and is open 1–5 p.m. Monday through Friday and 8 a.m.–noon Saturday and Sunday. It typically sells out by mid-afternoon. The station has more than 500 permits and averages 40–42 customers per day, with an estimated 70% residential and 30% commercial split. Staff warned that without additional staffing, the station may have to close or severely limit hours. Construction of a 48-inch OSO gravity main could also force a temporary closure this fall unless alternatives are funded.

Wastewater Rates and Cost of Service

  • NewGen Strategies presented the cost-of-service study. The proposed wastewater volumetric rate would increase by $0.34, from $0.807 to $0.841 per 1,000 gallons.
  • For residential customers inside city limits, the monthly minimum charge would increase from $35.11 to $38.29. For residential customers outside city limits, it would increase from $30.05 to $33.12.
  • For commercial customers inside city limits, the monthly minimum charge would decrease from $46.10 to $38.29. For commercial customers outside city limits, it would decrease from $39.45 to $33.12.
  • The stormwater legacy debt phase-in was explained: total legacy debt service is split 50% to wastewater and 50% to water rates. In FY26, water rates would recover $2 million, or about 17%, of the $5.882 million water-side portion; wastewater rates would absorb 50%; and wastewater fund balance would absorb the remaining 33%. In FY27, another $2 million shifts to water rates, with full 50/50 recovery reached in FY28.
  • The cost-of-service results showed residential wastewater customers slightly under-recovering and commercial customers slightly over-recovering their cost of service, with classes netting to zero overall.

Water Fund Highlights and Proposed Budget

  • Water achievements included a new water supply dashboard; improvements to the Mary Rhodes Pipeline that allow full use of 70–72 million gallons per day; dredging at the O.N. Stevens water treatment plant; substantial completion of the $13.2 million Nueces Bay Boulevard 24-inch water line under the ship channel; and replacement of approximately 47,500 linear feet of water lines across the city.
  • The proposed FY26 water fund includes $183.4 million in expenditures, with $177.9 million in revenue plus $5.5 million in fund balance. Revenues increased by $8.3 million and expenditures increased by $7.9 million, a 4.5% increase, below the water/sewer CPI of 4.8%.
  • For FY24 billed use, industrial users, including wholesale and retail industrial customers, accounted for 54% of all raw water consumed. For treated water, municipal use and wholesale municipal use accounted for approximately 48% of demand, while large-volume users and wholesale industrial users accounted for approximately 52%.

Water Rates

  • For the average residential customer inside city limits with a 5/8-inch meter, the proposed monthly minimum charge increases from $15.83 to $17.25, including the stormwater legacy debt component. Outside city retail charges are lower because outside customers do not benefit from stormwater infrastructure.
  • The proposed rate structure includes a new charge for the first 2,000 gallons for residential, commercial, and irrigation customer classes.
  • The large-volume taker-pay amount for the first 10 million gallons increases by 30%.
  • Proposed wholesale contract rates include public agency wholesale raw water at $1.33, wholesale treated water at $1.80, wholesale treated water network at $25, and non-rate-payer wholesale raw water at $1.36. Composite raw water customers Alice, Beeville, and Mathis remain at $1.03, with annual updates required by contract.
  • Sample bill impacts were provided: average residential customer total impact of $8.98 per month; typical restaurant impact of $17.93 per month; irrigation accounts up 39%; large-volume accounts up 14%; and wholesale treated customers down an average of 3%.

CIP Program

  • The proposed FY26 wastewater CIP totals approximately $110 million across 24 projects, down from about $182 million in FY25. Staff said the reduction was not due to cancelled projects but to re-timing budgets based on actual design and construction durations. Of 29 wastewater projects in pre-engineering, design, or construction, 23 were on schedule, or about 79%. Six projects were delayed due to the Greenwood bid overrun, CDBG mitigation grant funding delays, and rescoping/rebidding.
  • The proposed FY26 water CIP totals approximately $390 million across 51 projects. Of 53 water projects in pre-engineering, design, or construction, 46 were on schedule, or 87% by project count and 92% by budget. Seven projects were delayed for reasons including additional design needs, property acquisition, subsurface utility exploration, and drought-related delay of the Wesley Seale Boat Ramp.
  • The FY26 water CIP includes one new project, the Nueces River groundwater well program supported by state grant funding, and moves three long-range projects into the short-range program beginning in FY28: the Rand Morgan 16-inch water main, citywide highway line crossings, and Upriver Road water line replacement.

Council Discussion and Follow-Up

  • Councilmember Hernandez questioned overtime levels, noting wastewater overtime of about $1.15 million, or roughly 9% of $12.9 million in personnel expense, and water overtime of $942,420, or about 5% of $18 million in personnel expense. He also cited a 10% vacancy rate and a 27% increase in FTEs since 2021, and encouraged staff to work toward less than 5% overtime as a management goal. Staff responded that 24/7 operations, emergency response, and consent decree work require overtime, and that in-house work has saved about $29 million compared with contractor costs.
  • Councilmembers Roy, Vaughn, and Scott expressed support for charging a fee for reclaimed water, with several saying the fee should be nominal or phased in, because some users are providing paid lawn-watering services and ratepayers currently subsidize the program. Councilmember Paxson cautioned against charging during the drought, since reclaimed water offsets drought restrictions. The city manager said the free service was intended to build familiarity and use, with a possible fee after the program is established. NewGen estimated that a fee of $75.61 per 1,000 gallons would fully cover the seven proposed reclaimed-water positions and make the operation net zero, and a phased fee option was available if directed by council.
  • Councilmember Paxson asked about a steep increase in wholesale raw-water usage shown on a chart; staff said they would analyze the cause. Councilmember Scott asked whether wholesale customers must follow the city’s drought contingency plan; staff said contracts require drought plans and CCW works with wholesale customers, but enforcement outside the city is difficult.
  • Councilmember Hernandez identified inconsistencies between debt-service figures in the presentation and the budget book, and staff agreed to review the figures with him after the meeting.
  • Staff acknowledged that the water conservation plan is two to three years behind schedule. An updated plan is being developed with Plummer Engineering and is expected to be brought to council in fall 2025 or early 2026.
  • Staff also acknowledged that reduced water use due to conservation and drought restrictions creates a revenue shortfall that must be recovered through rates because fixed costs remain unchanged.

Public Comments & Testimony

  • No public comment was solicited or taken during this workshop. Staff and council referenced previous citizen testimony, including a resident’s remarks about the reclaimed water program and the station closing before opening time.

Key Outcomes

  • No motions, votes, or formal decisions were made; the meeting was informational only.
  • Staff will follow up on the wholesale raw-water usage increase, debt-service line-item discrepancies, reclaimed-water fee options, and a benchmark comparison with other large Texas cities.
  • An updated water conservation plan is expected to return to council in the fall or early 2026.

Meeting Transcript

Okay. Good morning, everyone. I'd like to call this meeting to order, Miss Martha. Could you please call the role? Mayor Palette Wahardo. President. Council members Roland Baretta. Here. Sylvia Campos. Eric Anthu is absent. Gillard Hernandez. Calen Paxson. Everett Roy. Present. Mark Scott. Carolyn Bond. City Manager Peter Zanoni. Present. City Attorney Miles Resley. Mayor and Council of Quorum of the Council and the Require Charter officers are present to conduct the meeting. No, ma'am. Okay. So good morning, everyone. This morning we are going to have an overview of the Corpus Christie or my Corpus Christi Water of the fiscal year twenty twenty-six operating and capital improvement program proposed budget and rates. Mr. Wes Nebgen, our director of infrastructure services will present to you two decision packages for your consideration. One will approve our ability to maintain our infrastructure, and the second will improve our ability to serve our community with type 1 effluent or reclaimed water. With the ultimate goal of all rate paying all rate classes rate customers paying their true cost of service. We have achieved this objective, and you will see the results of this cost of service analysis in the upcoming slides. It's important to point out that CCW operates as an enterprise fund. An enterprise fund is a dedicated fund to support the operations of the water and wastewater utility. We are not supported by taxes. We are financially independent and self-sustaining and are not part of the general fund. We operate this fund just like a not-for-profit business would, with the purpose of being good stewards of our ratepayers' investments. And while we are not here to make a profit, we are here to ensure that the ratepayer is being served efficiently. Our ratepayers are the community that we serve, and we strive to meet their needs every day. So let me start with the proposed 2026 budget for the wastewater fund. Before we get into the numbers, we want to highlight a few achievements. I won't read the entire bulleted list here, but just select a few key projects, which includes our two largest wastewater treatment plants and our largest lift station. So just this past May, we issued a 102 million dollar construction award to rehabilitate infrastructure and improve treatment processes at the Greenwood wastewater treatment plant. The OSO wastewater treatment plant, which is our largest wastewater treatment plant, saw a 111 million dollar investment last year to modernize the ammonia removal system, which will lower the operational cost and increase plant capacity to 18 million gallons a day. This is a four-year project. And at our largest lift station in the entire city, the Williams Lift Station, we've achieved substantial completion for the $12.2 million project. Our team continues to inspect, clean, and perform preventative maintenance of our collection system. The IDIQ contracts are an excellent implementation tool for rehabilitating and replacing wastewater pipelines across the city, which included replacing approximately 32,000 linear feet of wastewater lines and rehabilitating 100 manholes. Rapid deployment of these resources to address aging infrastructure is essential, and we are meeting our key performance indicators of the consent decree.