OPENPUBLICA · PUBLIC MEETING RECORD
Record of Proceedings

Special City Council Workshop on Inner Harbor Desalination Contract - April 10, 2026

City Council — Friday, April 10, 2026
BodyCorpus Christi, Texas
SessionCity Council
DateFriday, April 10, 2026
StatusFILED
Video Record
0:00 / 1:47:33

Original source
Transcript — VerbatimClick a timed line to jump · ⧉ to share it

Speaker numbers apply only to this recording.

Unassigned speaker

6:02

Okay,

Speaker 1

6:03

good morning, everybody.

6:04

I'd like to uh call this meeting to order.

6:05

Ms.

6:05

What would you please call the roll?

6:08

Mayor

Speaker 2

6:08

Paulette Wahardo President.

6:10

Council members Roland Barreta.

6:12

Sylvia Campos is absent.

6:15

Eric Ganthu is absent.

6:17

Um he would like to uh he asked that we read a statement on his behalf.

6:21

He says I will not be in attendance at today's workshop.

6:24

Yesterday I buried my father.

6:26

After a loss like that, I'm going to be exactly where I'm supposed to be, at home with my family, taking the time to grieve and honor the man who made me who I am.

6:34

I have always shown up for the city and will continue to show up, but today I'm choosing to be a son first.

6:40

Some things in life matter more than any meeting.

6:42

I will be back focused, locked in and ready to continue the work.

6:46

Thank

Unassigned speaker

6:46

you.

Speaker 2

6:47

Gillard Nandis.

6:50

Kaelin Paxon.

6:51

Perfect timing.

Speaker 1

6:53

Everett Roy.

6:54

Here.

Speaker 2

6:54

Mark Scott.

6:56

Carolyn Vaughn.

6:57

Here.

6:57

City Manager Peter Zanoni.

6:59

Present.

7:00

City Attorney.

7:01

Deputy City Attorney Buck Bryce.

7:03

President.

Unassigned speaker

7:04

Okay,

Speaker 2

7:04

we do have a quorum present to conduct the meeting.

7:07

And our condolences to Councilmember Ganthew and his family.

Speaker 1

7:11

Absolutely.

7:11

Thank you.

7:12

We send uh our condolences to him and his family.

7:16

Well, this morning I called, or I'm sorry, not this morning, but I called this meeting originally to bring forth the Inner Harbor Desalination contract for council consideration, given the urgency that this project demands.

7:27

Today is about accountability, ensuring that the public clearly understands where this process stands, the efforts that have been made to expedite this contract, and what remains to bring it forward without further delay.

7:41

The council has studied and debated desalination while our water supply faces real and escalating risks.

7:47

And that time must be over.

8:11

The public deserves clear, transparent answers.

8:25

Uh significant effort has also gone into pursuing financing and continues to, and there is strong alignment at every level to ensure that the project continues to move forward.

8:36

So Peter, since you're not able to deliver this contract today, I'm asking for one simple and critical answer, and that is what is the exact date for execution of the final Inter Harbor uh desalination contract.

8:48

Not a not a timeline or a range.

Speaker 3

8:53

Yeah, we plan on bringing the contract to City Council on April twenty-eighth on Tuesday, April 28th for consideration of approval.

Speaker 1

9:03

Okay.

9:04

And that is gonna be I mean, you're you absolutely feel comfortable that that's kind of

Speaker 3

9:10

yeah, I dwell with a couple of caveats.

9:12

So one uh the the two primary principles in Corpus Christi D cell partners, which is Axiona and uh Maztech, they have put extra hours in and uh and a lot of work to get it ready for the twenty-eighth.

9:26

Uh the twenty-eighth was the original plan that we had, so they've been working diligently to have it ready for the twenty-eighth.

9:33

So uh it we're pretty confident it will be substantially complete by the twenty-eighth.

9:39

Uh one caveat is at the Texas Water excuse me, the Texas Water Development Board has to agree with the contract terms uh because of the uh SWIFT loans that we have.

Unassigned speaker

9:50

So uh we we we uh they don't report to us obviously, so their schedule is is is there you know, on their timeline, so that's the only caveat is they there could be they said about two weeks is what it would take for their review.

Unassigned speaker

10:00

So that's the only caveat is they there could be they said about two weeks is what it would take for their review.

Speaker 3

10:03

So if they hold to that two-week timeline, we should be in good shape uh by the 28th of April.

Speaker 1

10:09

Okay.

Speaker 3

10:09

Yeah.

Speaker 1

10:10

Very good.

Discussion Breakdown — Share of Meeting
Water And Wastewater Management█████████████████████████████████████████████72%
Public Engagement█████████████20%
Environmental Protection███4%
Procedural██3%
Contract Management█1%
Summary of Proceedings

Special City Council Workshop on Inner Harbor Desalination Contract - April 10, 2026

On April 10, 2026, the Corpus Christi City Council convened a Special Workshop at the request of Mayor Paulette Guajardo to provide a public update on the Inner Harbor Desalination project and contract. The workshop, which featured presentations from city staff and project partners, was intended to ensure transparency and accountability on the timeline, costs, and outstanding issues. No formal votes were taken, consistent with the workshop format.

Public Comments & Testimony

  • As a workshop, no formal public comment was solicited. Multiple council members referenced significant public interest and scrutiny from national media. Mayor Guajardo addressed individuals in the audience regarding disruptive behavior, underscoring the meeting's livestreamed and public nature.

Discussion Items

  • Contract Execution Date: City Manager Peter Zanoni committed to presenting the finalized design-build contract for City Council consideration on April 28, 2026. He noted Texas Water Development Board (TWDB) review of SWIFT loan compliance is a caveat, estimating a two-week review period.
  • Project Cost & Financing: Staff presented a total project cost of $978.77 million, a 25% reduction from the $1.3 billion Kiewit proposal rejected earlier. Currently, $757 million in TWDB SWIFT loans are secured. Staff expressed confidence in obtaining a third SWIFT loan to cover the gap. Councilwoman Paxton clarified these are loans repaid with interest by ratepayers, not grants. Councilman Scott requested a conversation on the potential cost of expediting construction to deliver water sooner than November 2029.
  • Timeline: The projected delivery of water was updated from October 2029 to November 2029.
  • Farfield Modeling Study: Conducted by Sferos, this is described as the most comprehensive study ever of the Corpus Christi Bay system, including the ship channel and Nueces Bay. Draft findings on salinity and temperature are expected by April 28, but a full report including dynamic simulation is not due until June. Councilwoman Vaughan and Councilman Hernandez stressed this study was crucial for making an informed decision.
  • PFAS/PFOS Concerns: Councilman Hernandez brought forward significant concerns regarding PFOS contamination in the Inner Harbor. He requested written guarantees on removal via reverse osmosis. Staff confirmed PFOS is not part of the current Farfield model scope. Staff promised a formal response on PFOS testing and removal guarantees by the April 28 meeting.
  • Alternative Water Projects: Several council members highlighted the city's progress on projects like the Evangeline Laguna pipeline, brackish water wells, and wastewater reuse, which staff said totals 76 MGD in supply. Councilman Hernandez argued this council has secured more water than any previous council and that the near-term curtailment risk was caused by years of inaction.
  • Staff Resources: Councilwoman Paxton questioned the staff time spent on the meeting, noting the project timeline was not accelerated. Mayor Guajardo defended the workshop as essential for public transparency and accountability.

Key Outcomes

  • Confirmed Vote Date: The City Council is scheduled to vote on the final contract for the Inner Harbor Desalination project on April 28, 2026.
  • Action Items for Staff: Staff was directed to provide formal memos on 1) PFOS/PFAS removal guarantees and testing data, 2) cost-to-ratepayer analysis (ranges with and without additional SWIFT funding), and 3) details on debt defeasance and comparisons of debt vs. long-term lease obligations.
  • Farfield Modeling Schedule: Farfield committee meetings are set for April 15 and 23. Sferos will present draft findings on April 28, with the full report to be delivered in June 2026.
  • Public Discourse: The debate revealed a divided council, with some members (Mayor Guajardo, Councilman Budetta) framing the project as an urgent necessity following a year of delay, and others (Councilwoman Vaughn, Councilman Hernandez, Councilman Roy) insisting on completing due diligence, including the Farfield study and PFOS analysis, before any vote.

Meeting Transcript

Okay, good morning, everybody. I'd like to uh call this meeting to order. Ms. What would you please call the roll? Mayor Paulette Wahardo President. Council members Roland Barreta. Sylvia Campos is absent. Eric Ganthu is absent. Um he would like to uh he asked that we read a statement on his behalf. He says I will not be in attendance at today's workshop. Yesterday I buried my father. After a loss like that, I'm going to be exactly where I'm supposed to be, at home with my family, taking the time to grieve and honor the man who made me who I am. I have always shown up for the city and will continue to show up, but today I'm choosing to be a son first. Some things in life matter more than any meeting. I will be back focused, locked in and ready to continue the work. Thank you. Gillard Nandis. Kaelin Paxon. Perfect timing. Everett Roy. Here. Mark Scott. Carolyn Vaughn. Here. City Manager Peter Zanoni. Present. City Attorney. Deputy City Attorney Buck Bryce. President. Okay, we do have a quorum present to conduct the meeting. And our condolences to Councilmember Ganthew and his family. Absolutely. Thank you. We send uh our condolences to him and his family. Well, this morning I called, or I'm sorry, not this morning, but I called this meeting originally to bring forth the Inner Harbor Desalination contract for council consideration, given the urgency that this project demands. Today is about accountability, ensuring that the public clearly understands where this process stands, the efforts that have been made to expedite this contract, and what remains to bring it forward without further delay. The council has studied and debated desalination while our water supply faces real and escalating risks. And that time must be over. The public deserves clear, transparent answers. Uh significant effort has also gone into pursuing financing and continues to, and there is strong alignment at every level to ensure that the project continues to move forward. So Peter, since you're not able to deliver this contract today, I'm asking for one simple and critical answer, and that is what is the exact date for execution of the final Inter Harbor uh desalination contract. Not a not a timeline or a range. Yeah, we plan on bringing the contract to City Council on April twenty-eighth on Tuesday, April 28th for consideration of approval. Okay. And that is gonna be I mean, you're you absolutely feel comfortable that that's kind of yeah, I dwell with a couple of caveats.

SUMMARIZED BY OPENPUBLICA AI
TRANSCRIPT VIA PUBLIC VIDEO