Edmonds City Council Parks and Public Works Committee Meeting – April 22, 2026
Edmonds City Council Parks and Public Works Committee Meeting – April 22, 2026
The Edmonds City Council Parks and Public Works (PPW) Committee met on April 22, 2026 (the agenda is dated April 21, 2026, at 3:00 PM; the provided timestamp states the meeting occurred on April 22, 2026, at 20:30 UTC). Chair Vivian Olsen, Councilmember Chris Eck, and Council President Michelle attended, with Council President Michelle serving as ex officio member. Facilities Manager Tom Sullivan and Transportation Engineer Bertrand presented. The committee discussed the first-quarter Job Order Contracting report, the City Hall roof replacement, the Safety Action Plan, and two Highway 99 Revitalization supplemental agreements; all items were recommended for full council action. The transcript indicates the meeting was called to order at 3:00 PM and adjourned at 3:56 PM.
Job Order Contracting (JOC) Quarterly Report
- Tom Sullivan presented the 2026 first-quarter JOC report, the first such report to the committee. He explained the legislature authorized JOC in 2019 and the city amended its purchasing policy in 2022-2023 to allow it.
- About 50 projects were assessed for JOC suitability; 25-30 were viable, and 26 price proposals had been initiated. The program supports nine or ten departments/divisions and is being used to spend bond funds and address deferred maintenance.
- Asked by Councilmember Eck about quality compared with low-bid contracting, Sullivan said JOC projects rarely produce change orders unless the city initiates them; prime contractors are selected through an RFP with pre-negotiated rates, may perform only 10% of the work, and the rest is subcontracted using the RS Means price book.
- Chair Olsen praised the report, and the committee agreed to refer it to the full council as a receive-for-filing item.
City Hall Roof Replacement – Job Order Contract
- Sullivan said the City Hall roof is at least 26 years old, near the end of a 30-year lifespan, and replacement is recommended three to five years early because of the building's critical role and available funding.
- His initial estimate was $300,000; the JOC price proposal came in at $189,600. The roof is technically complex partly because about 20 HVAC units are located on it.
- Olsen said she had considered deferring the work, but expected construction price increases of 16% per year and fuel/trip/delivery surcharges made early replacement the right choice. Eck agreed.
- The committee agreed to place the contract on a future consent agenda for mayor approval.
Adoption of the Safety Action Plan
- Transportation Engineer Bertrand presented the draft Safety Action Plan, developed with federal Safe Streets for All funding as part of a joint application with other agencies. The plan's Vision Zero goal is to eliminate traffic fatalities and serious injuries by 2040, with an interim 50% reduction by 2035 and formal progress revalidation every five years.
- The plan used data analysis of the high-injury network, vulnerable road user high-injury network, corridor risk factors, equity metrics, points of interest, and public outreach. Outreach included farmers markets, an open house, and festivals during summer 2025.
- Eleven projects were identified, including citywide signalized intersection improvements, downtown core unsignalized intersections, Highway 99 corridor projects, 76th, 228th, 100th, 220th, Puget Drive, 9th/Main, and SR 104 adaptive signal improvements. Bertrand said the projects are not prioritized and are eligible for upcoming Safe Streets for All grants.
- Olsen expressed strong support, saying bikes and people deserve to share the road and that grants reduce the burden on city funds. She raised concerns about 84th, noting the 25 mph speed limit is not observed and pedestrians are close to traffic; she asked staff to advocate for Snohomish County to include the Esperance portion in its safety plan and asked whether the Edmonds portion could be added.
- Bertrand responded that 84th was reviewed, but most of the corridor is in Esperance, speeds are low, and there is no serious-injury crash corridor in the Edmonds portion; the county is working on its own safety action plan, and he will follow up.
- The committee agreed the plan should go to the full council as a presentation rather than as a consent item, so the city can apply for Safe Streets for All funding by the May 26 deadline.
Supplemental Agreement 4 – Highway 99 Revitalization Project, Stage 3
- Bertrand presented a fourth supplemental agreement for Stage 3. New work includes preparing pedestrian crossing memos at three locations where pedestrian crossings are not allowed, and adding utility service connections from the joint utility trench/vaults to private property for PUD and communication lines.
- Design is at about 30% and nearing 60%; the consultant fee proposal is still being negotiated. The project has no local funding, with costs covered by Connecting Washington and Move Ahead funds.
- The committee agreed to forward the agreement to the full council consent agenda.
Supplemental Agreement 1 – Highway 99 Revitalization Project, Stage 4
- The first supplemental agreement for Stage 4 includes complete streets and bike lane elements, stormwater design reports, WSDOT design analysis, driveway regrading, environmental site assessments, cultural resources work, right-of-way services, structural work on the tunnel under 220th for a second westbound left-turn lane, and underground utility/service connection work.
- Fee proposals are still being negotiated. Funding sources include Connecting Washington, Move Ahead funds, a federal design/right-of-way grant, and traffic impact fees.
- Olsen asked about impacts to businesses and whether alternatives had been explored. Bertrand said sidewalks would typically widen from 7 to 16 feet with planter, sidewalk, and bike lane, but would taper where buildings are close. An open house was scheduled for Thursday; there had been some pushback but generally positive feedback, and right-of-way discussions with property owners would intensify after the 60% design submittal.
- Council President Michelle asked about the Dragon Tire Casino parking lot redesign. Bertrand explained that the second westbound left-turn lane at 220th requires widening on the north side because the building prevents widening to the south; retaining wall removal and parking/driveway redesign are needed, and the work connects to the Interurban Trail.
- The committee agreed to forward the agreement to the full council consent agenda.
Key Outcomes
- The committee unanimously recommended: the Q1 JOC report be received/filed by the full council; the City Hall roof replacement, Stage 3 Supplement 4, and Stage 4 Supplement 1 go to the full council consent agenda; and the Safety Action Plan be presented to the full council for approval.
- The Safety Action Plan approval is time-sensitive because Safe Streets for All grant applications are due May 26, 2026.
- No formal roll-call votes were taken; decisions were by committee consensus.
Meeting Transcript
But good afternoon, everybody. It's 3 p.m. And I'm calling to order the meeting of the Edmund City Council Parks and Public Works Committee. And it is 3 p.m. in attendance. It's myself as Chair Vivian Olsen with Councilmember Chris Eck as the other committee member and the council president. Who is the ex officio member? And our first item of business. I hope I said that it was calling to order. Our first order of business is the 2026 first quarter job order contracting report. And we have public works and utilities as the department for that. And I think it said on the agenda memo that it was director room. So I guess when he is in the panelist room, we will need to promote him or whoever else might be there from public works. I'm sending a promotion to um merchant house. Okay, we might need Andy room too. I think Bertrand is the later items on the agenda. And Tom Sullivan, Andy and Tom are probably the first ones. If it's the um regarding first quarter, that's not that's not for me because I got the safety action plan and the highway 99. Okay, I have Tom coming. I have Tom coming in. Thank you. And director Ru might want to be in here also. Hi, Tom, how are you? Hello. Thank you for joining us today. And if it's okay with you, we can uh do first names for everybody. Uh absolutely. I'm not certain if Andy is going to be here. Uh I know he's uh been at the wastewater treatment plant with the busyness going on down there this week. So if he is not in the crowd, then we can go ahead and that point. I see him on the attendees list, but um it's fine if um you're ready to talk to the items anyway. Sure. Okay, well, um if you'd like to introduce that would be great. Sure. Um first off, I I think I know everyone. I'm Tom Sullivan, I'm the city's facilities manager. Nice to see everyone. And the first item is uh the quarterly job order contracting report. Uh this is the first time we've done this. So um if in the future you want to see it in a different format, uh, we're happy to do that uh as well. Um gonna be a busy year uh for job order contracting. So just a quick update. Um legislature allowed us to do this in 2019. We adopted it in 2022, 2023 uh by amending our purchasing policy to allow job order contracting. Um basically the parameters are will the project uh the use of job order contracting benefit the public. Uh and pretty much the rapid, you know, deployment of uh project resources outside of project management uh shows a public interest. So uh we're utilizing it to the best of our ability this year, uh trying to spend our bond money and uh knock down some of the deferred maintenance items that we've uh uh incurred over the years. And so the actual project uh report here is in the uh since the beginning of the year we've assessed about 50 projects that uh we thought might work for job order contracting, and really 25 or 30 of those have uh turned out to be viable. Um and thus far we've initiated 26 price proposals. So uh that's just getting the the general pricing, kind of the not to exceed number on these projects uh before we really go into some more development and you know decide we're gonna execute these projects.