Public Involvement Meeting for County Highway MM Underpass Project - August 28, 2026

Common Council & City Boards — Friday, August 28, 2026
BodyFitchburg, Wisconsin
SessionCommon Council & City Boards
DateFriday, August 28, 2026
StatusFILED
Video Record
0:00 / 28:08

Original source
Transcript — VerbatimClick a timed line to jump · ⧉ to share it

Speaker numbers apply only to this recording.

Speaker 1

0:00

Stay connected everywhere you go.

0:03

Pitchburg is on your phone and your tablet and your laptop and TV.

0:08

Download the app.

0:09

It's free.

0:11

Access Pitchburg.

0:12

This is your city at your fingertips.

Unassigned speaker

0:29

Hi,

Speaker 2

0:30

I'm Jeremy Crosby, and I'm Nick Boucher.

0:32

We're your host for the program that's all about your city, Talking Fitchburg.

Speaker 3

0:36

Every weekday, we pull together the news, events, and information you need to stay on top of what's happening in the city of Pitchburg.

Speaker 2

0:42

Find Talking Fitzburg on Cable TV, Roku, Amazon Fire, Apple TV, and our live stream on the web.

0:48

Plus, you can find all our headlines and stories on Facebook, YouTube, and our video on demand service.

0:53

This

Speaker 3

0:53

is your city.

0:54

Keep up with Talking Fitchburg and the issues affecting you and your neighbors.

Speaker 4

1:10

Hello everybody.

1:12

Hopefully everybody can hear me.

1:13

I know we don't have sound in this room, but this is for FACTV later on.

1:18

I'm Ross Kaler.

1:19

I'm the transportation engineer for the city of Fitchburg and the city project manager for this County Highway MM Underpass project.

1:29

So any city questions, uh happy to answer.

1:34

Um I also have Josh Swaino here with me.

1:37

He's uh from our designer MSA for this project.

1:41

Um, and more technical questions, uh, he's better to answer than I am.

1:46

So he's gonna give a quick overview of this project, and then we'll kind of get into a more open house style where we can answer your questions uh kind of individually.

1:58

So thank you guys for coming.

Unassigned speaker

2:00

Okay.

Speaker 5

2:01

Thanks, Ross.

2:03

Okay, so obviously, this is the public involvement meeting for the County Highway MM Underpass uh project.

2:12

So just to start out the planned schedule for the project.

2:16

I mean, we are currently in design.

2:18

This is a pretty fast moving project.

2:20

We're planning to have design wrapped up by the end of the year so that the project can be bid early in 2027 with the intention for construction to start by the summer of 2027 and ultimately be wrapped up during the summer summer slash going into they there might be some stuff with the trail work that extends beyond the start of school in 2027.

2:45

The intention is for County Highway MM to be back open before the start of school for that 2027 year.

2:54

Um but as I said, we are currently in design.

2:59

The intention is obviously a pedestrian underpass.

3:03

The structure itself will be a culvert.

3:05

Uh it will have a clear width of 14 feet, a clear uh clear height of 10 feet, all based off of I mean your bike pet accommodations.

3:18

The trail itself will have a paved 10-foot width, and the exhibits we have up here are the layout of the trail and the structure.

3:28

The structure itself is kind of in the middle of the page.

3:31

The trail starts a little beyond.

3:35

If you guys are familiar with where there is the the trail ends on the east side of the road, just south of uh Lionel Court, the that gravel entrance.

3:47

There is a current ending point for the trail on the east side.

Speaker 6

3:51

This is on McCoy Road.

Unassigned speaker

3:53

No,

Speaker 5

3:53

we are on MM.

Speaker 6

3:54

So you're still on MM.

Speaker 5

3:55

Yes.

3:56

Yep, MM is right here.

3:57

All right.

3:58

Yes.

3:58

Um, so we're gonna connect back into that existing trail a little south of its current dead end point.

4:05

The reason that's happening is because following bike pad accommodations, there's we are there are certain curb horizontal curves and vertical grades that we have to follow.

4:18

So that is ultimately what has dictated the layout of the trail because of the fact that we are going down, the distance that we are to go under the road, and

Unassigned speaker

4:28

it's

Speaker 5

4:29

so it's the combination of down and um your horizontal accommodations to sweep into that structure that ultimately is kind of dictated what the layout is.

4:39

Uh but let's see.

4:44

And then on the west side of the road, we will come out of the structure and the project will lead up into what is planned redevelopment to I mean it basically a kind of a determined dead end point where we kind of match in back into existing topography.

Unassigned speaker

5:00

That will be the end of the project for now.

Speaker 5

5:01

And then obviously the intention is to finish that trail in the future.

Discussion Breakdown — Share of Meeting
Transportation Safety█████████████████████████████████████████████59%
Engineering And Infrastructure██████████████18%
Technology and Innovation██████████13%
Historic Preservation████5%
Water And Wastewater Management████5%
Summary of Proceedings

Public Involvement Meeting for County Highway MM Underpass Project - August 28, 2026

On August 28, 2026, the City of Fitchburg held a public involvement meeting for the proposed County Highway MM underpass project. Ross Kaler, Transportation Engineer and city project manager, along with Josh Swaino of the project designer MSA, presented the design, schedule, funding, and answered questions from attendees. The project aims to construct a pedestrian and bicycle underpass and associated trail to improve connectivity and safety.

Discussion Items

  • Project Description: The underpass will be a 14-foot-wide by 10-foot-high box culvert with a 10-foot-wide paved asphalt trail (concrete inside the culvert). Approximately 905 linear feet of trail will be built, and about 450 feet of County MM will be reconstructed with beam guard and a paved width of 36 feet. The road profile will not change.
  • Schedule: Currently in design; design completion scheduled for the end of 2026. The project will be bid in early 2027, construction will start in summer 2027, and County MM is expected to re-open before the start of school in 2027. Some trail work may extend slightly beyond that.
  • Funding: The project received a Transportation Alternatives Program (TAP) grant from WisDOT for $430,000, originally covering about half of the $900,000 estimated total cost. The remaining cost will be funded by the City of Fitchburg through its CIP (borrowing). The grant requires the project to proceed on the described timeline.
  • Route and Connectivity: The trail will connect to the existing trail on the east side of MM, south of Lionel Court. It will go under MM and exit on the west side into an area of planned redevelopment. Future developments (e.g., Syncopation) will extend the trail northward, eventually linking to the Capital City State Trail at McCoy Road. That connection is not part of this project and depends on development timing.
  • Safety Purpose: The underpass will provide a safe way for children and residents to cross County MM, especially for access to Forest Edge Elementary, and fills a gap in the pedestrian network.

Public Comments & Testimony

  • Several attendees asked about the choice of an underpass versus an overpass or at-grade crossing. The designers explained that the existing topography (a deep ditch on the east side and significant slopes) makes the underpass the most feasible option.
  • One resident asked whether the tunnel would be lighted; staff confirmed that lighting will be installed inside the structure. Lighting on the approaches is not currently planned.
  • Questions about drainage and potential flooding were addressed: the culvert will have a continuous grade with the low point outside the structure on the west side, and water will be directed via a flume to the existing ditch. No standing water is expected.
  • A member of the public requested that salt not be used on the trail; staff noted that city parks staff will handle snow and ice control with salting, brining, and plowing.
  • Concerns were raised about future connectivity: the underpass does not eliminate the existing at-grade intersection crossing at MM and McCoy, and on-street bike lanes will remain.
  • Logan, a city staff member, clarified the grant timeline, emphasizing that the grant deadlines are driving the project schedule.
  • Steve, a resident, discussed the history of Fitchburg’s opportunistic trail-building approach and the long-term plan to link trails.
  • No formal opposition to the project was expressed; questions focused on details and implementation.

Key Outcomes

  • The project design is proceeding with input from the public meeting; no formal decisions or votes were taken.
  • The underpass will be built to current plans, with construction expected to begin in summer 2027 and completion by fall 2027.
  • The city will fund the local share through CIP borrowing; the TAP grant constrains the timeline.
  • Future northward trail connections will be built by private developers as parcels develop; the city has no set schedule to complete the link independently.
  • Staff will consider feedback on lighting, drainage, and salt use in final design.

Meeting Transcript

Stay connected everywhere you go. Pitchburg is on your phone and your tablet and your laptop and TV. Download the app. It's free. Access Pitchburg. This is your city at your fingertips. Hi, I'm Jeremy Crosby, and I'm Nick Boucher. We're your host for the program that's all about your city, Talking Fitchburg. Every weekday, we pull together the news, events, and information you need to stay on top of what's happening in the city of Pitchburg. Find Talking Fitzburg on Cable TV, Roku, Amazon Fire, Apple TV, and our live stream on the web. Plus, you can find all our headlines and stories on Facebook, YouTube, and our video on demand service. This is your city. Keep up with Talking Fitchburg and the issues affecting you and your neighbors. Hello everybody. Hopefully everybody can hear me. I know we don't have sound in this room, but this is for FACTV later on. I'm Ross Kaler. I'm the transportation engineer for the city of Fitchburg and the city project manager for this County Highway MM Underpass project. So any city questions, uh happy to answer. Um I also have Josh Swaino here with me. He's uh from our designer MSA for this project. Um, and more technical questions, uh, he's better to answer than I am. So he's gonna give a quick overview of this project, and then we'll kind of get into a more open house style where we can answer your questions uh kind of individually. So thank you guys for coming. Okay. Thanks, Ross. Okay, so obviously, this is the public involvement meeting for the County Highway MM Underpass uh project. So just to start out the planned schedule for the project. I mean, we are currently in design. This is a pretty fast moving project. We're planning to have design wrapped up by the end of the year so that the project can be bid early in 2027 with the intention for construction to start by the summer of 2027 and ultimately be wrapped up during the summer summer slash going into they there might be some stuff with the trail work that extends beyond the start of school in 2027. The intention is for County Highway MM to be back open before the start of school for that 2027 year. Um but as I said, we are currently in design. The intention is obviously a pedestrian underpass. The structure itself will be a culvert. Uh it will have a clear width of 14 feet, a clear uh clear height of 10 feet, all based off of I mean your bike pet accommodations. The trail itself will have a paved 10-foot width, and the exhibits we have up here are the layout of the trail and the structure. The structure itself is kind of in the middle of the page. The trail starts a little beyond. If you guys are familiar with where there is the the trail ends on the east side of the road, just south of uh Lionel Court, the that gravel entrance. There is a current ending point for the trail on the east side. This is on McCoy Road. No, we are on MM. So you're still on MM. Yes. Yep, MM is right here. All right.