Forest Grove City Council and Planning Commission Joint Work Session on Data Center Code Amendments - November 9, 2026

City Council — Monday, November 9, 2026
BodyForest Grove, Oregon
SessionCity Council
DateMonday, November 9, 2026
StatusFILED
Video Record
0:00 / 1:24:13

Original source
Transcript — VerbatimClick a timed line to jump · ⧉ to share it

Speaker numbers apply only to this recording.

Unassigned speaker

0:01

It helps if I turn on the microphone.

Unassigned speaker

0:03

Okay, good evening, folks.

Speaker 1

0:05

Call to order this work session of the Forest Grove City Council.

0:09

This is a joint work session with our Planning Commission and our City Council.

0:14

The topic is data center development code amendments.

0:18

And do we want to call?

0:21

Do we all just want to go around the table and introduce ourselves really quick?

0:25

I'll start.

0:26

Let's see, everyone's joined.

0:27

I'll start with myself.

0:28

My name's Mayor Wenzel, Forest Growth City Council.

Speaker 2

0:33

Nicole Ellis, Planning Commission.

Speaker 3

0:37

Dan Rudin, Senior Planner.

0:42

Tim Farrell, Planning Commission.

Speaker 4

0:44

Karen Martinez, City Council.

Unassigned speaker

0:47

Don

Speaker 4

0:48

Augustuson, City Council.

Speaker 5

0:51

Kim Ezel, Assistant City Manager.

Speaker 6

0:54

Seth Birdall

Speaker 7

0:56

Planning Commission.

0:58

Dave Anderson Planning Commission.

Speaker 8

1:01

Brian Polk, Community Development Director.

Speaker 9

1:07

Angel Falconer, City Council.

Speaker 10

1:12

Mariana Valenzuela, City Council.

Speaker 11

1:16

And Brian Shamel, City Council.

Speaker 1

1:24

Okay, at this point, I'm gonna pass it over to our senior planner, Dan Rearnan to take it.

1:30

Or does our assistance manager?

1:32

Okay, I'm gonna pass it to Dan.

Speaker 12

1:35

Planning Commissioner Brandon Kilbertson is also on Zoom.

Unassigned speaker

1:43

Great.

Unassigned speaker

1:44

Hi.

Unassigned speaker

1:48

Thank

Speaker 3

1:48

you, Mayor.

1:48

Dan Rudin, Senior Planner with the City of Forest Grove.

1:51

It's really great to see everyone this evening, everyone on the council and the in the planning commission.

1:55

Thanks for coming out.

1:56

We have a lot to uh go over this evening related to data centers, and uh we'll jump right into it.

2:02

Have a PowerPoint presentation I'd like to share.

2:05

Um I'm hoping that this will be more of a conversation, more of a discussion.

2:09

So there are several places where we'll pause and ask for questions and discussion, opportunity for any um clarifying statements.

2:18

Um the next the first slide basically provides the agenda for this evening's meeting, and as it shows, we have quite a bit to cover.

Unassigned speaker

2:25

Uh,

Speaker 3

2:25

we'd like to go over a little bit of background and history of where we've been with data centers, uh, what has happened so far, provide a little bit of context about data centers,

Unassigned speaker

2:34

go

Speaker 3

2:35

over the existing development code, what we currently have in the development code related to industrial development generally.

2:41

Um, start a discussion about location considerations of where

Unassigned speaker

2:46

uh

Speaker 3

2:46

data centers are currently allowed

Unassigned speaker

2:49

in

Speaker 3

2:49

the city and where they could potentially be allowed or not allowed in the city and what type of data centers might be allowed.

Unassigned speaker

2:55

Um

Speaker 3

2:55

and then we'll get into a little bit more details about uh the proposal moving towards uh next steps.

Speaker 8

3:01

Next slide, please.

Speaker 3

3:03

So the purpose of tonight's uh work session is to basically start a discussion, or I should say continue a discussion about developing specific regulations for data centers specifically.

3:14

Currently, the code does not have specific regulations for data centers.

3:17

We do for industrial development,

Speaker 8

3:18

but we don't for data centers specifically.

Speaker 3

3:21

We'd also like to discuss potential land use and operational standards related to data centers, and most importantly, get policy direction tonight from the city council and planning commission about how to move forward to help inform preparation of specific development code amendments that we'd like to bring forward at subsequent work sessions.

Speaker 8

3:39

Next

Speaker 3

3:39

slide, please.

Discussion Breakdown — Share of Meeting
Data Center Regulation█████████████████████████████████████████████67%
Land Use███████████16%
Urban Planning█████7%
Environmental Protection███4%
Procedural█2%
Public Health█2%
Water And Wastewater Management█2%
Summary of Proceedings

Forest Grove City Council and Planning Commission Joint Work Session on Data Center Code Amendments - November 9, 2026

This joint work session of the Forest Grove City Council and Planning Commission focused on developing specific regulations for data centers, following a 120-day temporary moratorium adopted by the City Council on October 12, 2026. The moratorium, which ends on February 9, 2027, halts acceptance of new data center applications. The session aimed to discuss land use and operational standards and to obtain policy direction for drafting development code amendments. Staff presented background on data center types (primary vs. accessory), existing code provisions, location considerations, and a proposed two-phase approach: phase one addressing where data centers can be located, and phase two addressing how they are built (development standards).

Discussion Items

  • Background and Moratorium: Senior Planner Dan Rudin reviewed the moratorium’s purpose, the existing industrial zone height limit of 45 feet (with a setback formula allowing taller buildings), and the absence of data-center-specific standards. He noted that data centers are currently permitted under the broad “information” use category in industrial and town center zones.

  • Data Center Types: Staff distinguished between primary data centers (standalone facilities) and accessory data centers (supporting a primary use, such as a hospital or university). A proposal was made to define “data center” and create a separate use category in the development code.

  • Accessory Data Center Proposal: Staff proposed allowing accessory data centers in town center, community commercial, and business industrial park zones, with limitations: no more than 30% of the gross building floor area, exclusively serving the primary use, and no noticeable off-premise impacts (noise, vibration, etc.). Councilor Valenzuela and Commissioner Culbertson suggested also capping power usage (e.g., 5 megawatts) for accessory data centers, and staff noted this could be considered in phase two.

  • Primary Data Center Proposal: Staff proposed allowing primary data centers only in general industrial and light industrial zones, with potential buffer limitations: 250 feet from residential zones and 1,000 feet from schools. Maps were shown illustrating these buffers.

  • Location and Buffer Discussion: Several council and commission members expressed concern about the adequacy of the 250-foot residential buffer, with Councilor Falconer and others favoring a larger buffer. Commissioner Bertall supported prohibiting primary data centers in light industrial zones. There was broad support for including Pacific University in the school buffer (1,000 feet). Councilor Valenzuela raised concerns about protecting sensitive natural areas like Fernhill Wetlands and the Council Creek Trail, and about retroactive protections for the existing Crane Data Center near Neil Armstrong Middle School. Staff clarified that the Crane project was approved under prior code and any future modifications would be subject to new rules.

  • Outright Ban Consideration: Councilor Shamel asked about the possibility of an outright ban on new primary use data centers. Staff and Assistant City Manager Kim Ezel noted that an outright ban is legally possible and would simplify the process, but would create a non-conforming use for the existing Crane facility. Councilor Valenzuela expressed interest in seeing pros and cons of a ban, including tax and revenue implications. Councilor Falconer supported exploring both regulating and removing the option for primary use data centers.

Key Outcomes

  • Consensus Direction for Staff: Staff will prepare draft code amendments based on the following direction:
    • No primary use data centers in light industrial zones.
    • Increase the residential buffer from 250 feet (staff to bring maps showing larger buffers, e.g., 500 feet, and assess impact on parcel availability).
    • Include Pacific University in the school buffer of 1,000 feet.
    • Explore options for both regulating primary data centers and removing the ability for new primary use data centers (i.e., limiting to accessory only).
  • Next Steps: Staff will present these options at a future work session, likely November 23, 2026, and will initiate public notice for any code amendments. Phase two (development standards) will proceed after Hillsboro completes its environmental and economic analysis and the state data center advisory committee issues recommendations. Staff will also summarize this session for record.

Meeting Transcript

It helps if I turn on the microphone. Okay, good evening, folks. Call to order this work session of the Forest Grove City Council. This is a joint work session with our Planning Commission and our City Council. The topic is data center development code amendments. And do we want to call? Do we all just want to go around the table and introduce ourselves really quick? I'll start. Let's see, everyone's joined. I'll start with myself. My name's Mayor Wenzel, Forest Growth City Council. Nicole Ellis, Planning Commission. Dan Rudin, Senior Planner. Tim Farrell, Planning Commission. Karen Martinez, City Council. Don Augustuson, City Council. Kim Ezel, Assistant City Manager. Seth Birdall Planning Commission. Dave Anderson Planning Commission. Brian Polk, Community Development Director. Angel Falconer, City Council. Mariana Valenzuela, City Council. And Brian Shamel, City Council. Okay, at this point, I'm gonna pass it over to our senior planner, Dan Rearnan to take it. Or does our assistance manager? Okay, I'm gonna pass it to Dan. Planning Commissioner Brandon Kilbertson is also on Zoom. Great. Hi. Thank you, Mayor. Dan Rudin, Senior Planner with the City of Forest Grove. It's really great to see everyone this evening, everyone on the council and the in the planning commission. Thanks for coming out. We have a lot to uh go over this evening related to data centers, and uh we'll jump right into it. Have a PowerPoint presentation I'd like to share. Um I'm hoping that this will be more of a conversation, more of a discussion. So there are several places where we'll pause and ask for questions and discussion, opportunity for any um clarifying statements. Um the next the first slide basically provides the agenda for this evening's meeting, and as it shows, we have quite a bit to cover. Uh, we'd like to go over a little bit of background and history of where we've been with data centers, uh, what has happened so far, provide a little bit of context about data centers, go over the existing development code, what we currently have in the development code related to industrial development generally. Um, start a discussion about location considerations of where uh data centers are currently allowed in the city and where they could potentially be allowed or not allowed in the city and what type of data centers might be allowed.