Community Development Committee Meeting - August 26, 2025
STREAMING COPY IN PREPARATION — RECORDING AVAILABLE FROM THE ORIGINAL SOURCE
Community Development Committee Meeting - August 26, 2025
The Community Development Committee met on August 26, 2025, at 9:30 AM to consider six resolutions. All items were approved unanimously. The meeting was chaired by the committee chair, and presentations were led by staff members including Mr. Berkman and Ms. Enriquez.
Discussion Items
-
Resolution awarding a contract for Oxford Trail improvements: The committee approved a contract with Earhart Construction for $5,015,335.98 for reconstruction and extension of the Oxford Trail from Wealthy Street to Hall Street. The total project cost is not to exceed $9 million. Funding comes from city ARPA funds and DGRI greenway funding. The project aims to connect the Black Hills and Roosevelt Park neighborhoods. Two bids were received, and Earhart came in under the engineer's estimate. Earhart will subcontract 15% of the work to an MLBE firm. The motion passed unanimously.
-
Resolution rejecting bids for Oxford Street reconstruction (Norwich to Godfrey): The committee voted to reject all five bids received on July 31, 2025, for reconstructing 800 feet of Oxford Street, including combined sewer separation and bridge rehabilitation. The low bid exceeded the $1.9 million estimate by approximately $1 million (over 50%). The city plans to review the scope and reissue a bid package in fall 2025 for construction next year. The motion passed unanimously.
-
Resolution approving a construction agreement and accepting 10 public utilities easements for Walnut Woods: The committee approved a construction agreement for a private residential development of 62 single-family homes in Kentwood, covering installation of public sanitary sewer and water main. Acceptance of easements gives the city rights to maintain those utilities. The motion passed unanimously.
-
Resolution accepting a utility easement at 220 Graham Street SW for water main relocation: The committee accepted a permanent easement on the south side of the property at 220 Graham Street SW for $19,800, related to the MLK Jr. Street bridge replacement project. Payment will come from the Vital Streets Fund. The motion passed unanimously.
-
Resolution granting a noise variance to MDOT for MLK Jr. Street bridge replacement: The committee granted a noise variance allowing MDOT to perform construction operations on up to 45 nights between March 30 and November 20, 2026, for the eastern portion of the MLK bridge replacement. Extremely loud operations (e.g., pile driving) remain prohibited between 10 PM and 7 AM. A public hearing on August 12, 2025, received no comments. Residents within 600 feet were notified. The motion passed unanimously.
-
Resolution setting a public hearing for special assessment nuisance roll 8800: The committee set Tuesday, September 9, 2025, at 2:00 PM as the date for the city commission to sit as the board of review to hear appeals on unpaid charges for services and code violations from January to June 2025. Property owners were notified on August 8, 2025. The motion passed unanimously.
Key Outcomes
- All six resolutions were approved unanimously.
- The Oxford Trail construction contract was awarded to Earhart Construction.
- Bids for Oxford Street reconstruction were rejected, with a new bid package to be issued in fall 2025.
- A noise variance for the MLK bridge replacement was granted.
- A public hearing for special assessment appeals was scheduled for September 9, 2025.
Meeting Transcript
Good morning. The time is now 9 30, and we'll go ahead and call our community development committee meeting to order. For once we have a little bit smaller agenda, so we'll let you take a little break, Tim. Um, you know, but that's not as many as Mr. Berkman usually has, but we appreciate his work. Um so the first item is a resolution awarding a contract with Earhart Construction for improvements to Oxford Trail in the amount of five million fifteen thousand three hundred and thirty-five dollars and ninety-eight cents with a total amount not to exceed of nine million dollars. Do you have a motion? So moved. Or moved and supported. Good morning, everyone. So I'm here to talk about the Oxford Trail project. This project is a partnership between downtown Grand Rapids Inc. and the City of Grand Rapids Parks Department. What we are looking at is the existing Oxford Trail. It starts on Wealthy, just on the west side of the river. It travels south through Butterworth, it crosses over the Grand River, which if you haven't been on that pedestrian bridge, you should go. It's lovely. And then continues down to Oxford Street currently. So our project will reconstruct that section that I just mentioned, and then also extend the trail down to curve and then down to hall. So that work is looking to start in September. Air Hart would like to get started really quickly so that they can meet the timeline associated with the funding. The funding for this project is city ARPA funds as well as the DGRI greenway funding for the entire project. The goal of this project really is to connect the Black Hills and the Roosevelt Park neighborhoods to each other and then also to downtown. And having this trail extend to Hall is just another section for us to get closer to connecting this trail system to Roosevelt Park, and then eventually we'll have you know the Plaster Creek. Silver Creek Trails connect to Roosevelt Park as well and have a complete trail system. So we only had two bids for this project. However, the engineer's estimate was the middle bid in between those two bids, so that's perfect. Um so we felt really happy with the cost that we got for it and really excited that um air heart actually came a little bit um under budget for that. And there is some MLBE participation on this project. It was it's not allowed because of the funding to be able to utilize bid discounts. However, Earhart is still subcontracting 15% of their work to an MLBE. And I think that is everything I have. So if there's any questions, say look at Mr. Berkman got Miss Enriquez to to do the presentation on that one. But um any questions? It's great to see this project. Um the the state money, the greenway money, that was also ARPA dollars from the state, or was that additional it was it was separate, so it's part of that $55 million greenway funding. But yeah, I couldn't remember if that was that if that was COVID dollars that they got or if that was you know when there was an additional surplus in the budget, but that's okay. We got the money. So we exactly have the money. So okay. Um all those in favor? Aye. Aye. Any opposed? Motion carries. Thanks, Gary. Um, item number two is a resolution rejecting bids for construction of Oxford Street from Norwich Avenue to Godfrey Avenue. Do you have a motion? I'll move.