The Greensboro City Council held a public hearing on August 17, 2026, to discuss a proposed 120-day moratorium on hyperscale data center development and related ordinance. The meeting began with a recusal request from Mayor Pro Tem Denise Roth and featured extensive public testimony from over 30 speakers, the majority calling for a longer 32-month moratorium. Due to the number of speakers and a scheduled Planning and Zoning Commission meeting, the council recessed the hearing to the following day.
We are in the Katie Dorset Council Chambers, and let the record reflect we do have a few council members who are on the way, Mr. Allen and Mr. Halston. And also uh Denise Roth, our Mayor Pro Tim is on Zoom. Uh Denise, are you there? Yes, I am. Thank you, Mayor. Great. So before we go into the meeting today and allow the public hearing speakers, uh Mayor Pro Tim would like to uh bring something before council right now. Mayor Pro Tim. Thank you, Mayor. Uh yes, uh Mayor, I'm asking today for the permission of council to recuse me. Wait, wait, just a moment. We can't hear you. The door is open. Hold on just a moment. I'm sorry. Okay, go ahead, Mayor Pro Tim. Thank you, Mayor. I today I'm asking council to recuse me from votes related to the data center ordinance and related moratorium as we go forward. As counsel is aware, I serve on the board of Gateway Research Park, where the proposed Dream Center project is planned. As our discussions have progressed, the Dream Center has become an increasingly prominent part of the discussion surrounding both the proposed moratorium and the development of the city's data center ordinance. I have conferred with the city attorney and understand that I do not have an actual or direct conflict of interest. The moratorium and the ordinance are citywide policy matters that apply broadly to data centers and are not specific to the Dream Center or Gateway Research Park. However, the broader policy discussion and the discussion surrounding the Dream Center has become increasingly intertwined. Given my role on the gateway board, I believe the appropriate course is to request recusal in order to avoid even the perception of a conflict of interest. For that reason, I am requesting council's permission to recuse myself from deliberations and votes related to the proposed data center moratorium in the development and adoption of the data center ordinance. But uh as we are we are here. And I also apologize for not being there. I had a conference that was planned, but given the timeliness and importance of this discussion, we wanted to go forward with the uh public hearing, but I do think that this is an important effort. But I do think that this is an important effort. Thank you, Mayor Pro Tim. I believe there's some discussion. Councilmember Black. Um, I just wanted to ask some clarifying questions to uh Madam City Attorney as it relates to the Dream Center. Um just for clarity for the public to have clarity and to know where uh the city is positioned with this project. So my first question is the site plan that was approved in July of 2023. Is there a current site plan that exists at this moment? Councilwoman Black, there is not an approved site plan. That 2023 site plan approval expired July of 2025. There has not been another site plan uh presented to the city for approval. And a site plan must be on file to move forward. Say one more time. A site plan must be on file for a project to move forward. Yes. Uh my next question is has there been a water feasibility study done on this project to date for the nine megawatts or anything outside of that? Mr. Bortras has sent me an email and that said yes, a feasibility was performed for what he would call an extension within the research park at 2901 Gay City Boulevard back in 2001. I believe that feasibility study was for a project that was not this particular project, but that project was for the north side of the campus, and then it decided it was not going to put that project there, and I think it relocated to Brown Summit. And the north the north campus is closer to Brown Summit, correctly?