The Capital Improvement Board (CIB) met on November 13, 2026, to receive financial and operational reports, approve contracts, and address public testimony regarding contractor compliance. A routine contract approval for the Gainbridge Fieldhouse was rescinded following allegations against a subcontractor, leading to a formal investigation ordered by the board.
Don't have that gap. We'll go ahead and get started. We're trying to connect work number Maggie Lewis via the internet, but we have several things in reports to go through initially that we can make it. So I guess it's working. And Mary's on to all right. Still ball. So if there are any court case to work out, we have several reports before anything to be voted on except the interval of minutes. Since we can't uh people remote, we'll be doing all call rights today. So uh first order of business today, our approval of the minutes from October 2nd. Chair Day or K about any question or discussion? Okay, please call the role. Uh Marcy. Yes. David. Mick. All right. Yes. All right. Jen. I Maggie. I. Jane. I thank you. The next item on the January 4th. And that's the first PC CIP month in financial project. Thank you. Good morning. September 2026. Finish solidly with revenues and expenses of $7.8 million, which is about $2 million more than September of last year. It's $9 million more than budget and $4 million more than the monthly average. When comparing to the prior year, the line items that make up that favorable variance are emissions tax, labor reimbursements, and capital outlays. And then I'll go in more detail on each of those later. So getting into details, tax revenues total $15 million, which is about a million dollars more than prior year and the monthly average. Largest variable there, variance there is of emissions tax, which is about a million dollars or 56% more than the prior year. It's directly related to Gen Con, which this year was in September. The taxes did. And then last year was in August, so it's just a timing difference between the two years. So we believe that that's causing that admissions tax to be up. Operating revenue was seven million dollars, which is more than per year by two million dollars or 45%. Largest variable variance there is labor reimbursement line, which it comes from the NCS Safety Convention, which was about $800,000 in labor reimbursements, and also the Bruno Mars concert, which had about $1.2 million in labor reimbursements. Had a variance of about $304,000 directly related to the labor for the Bruno Mars concert. And then also employee medical expense had about $154,000 there, which was due to the prior year we had a reimbursement for late a stop loss payment, about $250,000 that's causing that variance there. But it's because last year was lower. Not this, not anything this year. Supply category there is um less than prior year by about $430,000 or $49%.