Redevelopment Authority October 22, 2026 Meeting Summary

Common Council & Committees — Thursday, October 22, 2026
BodyLa Crosse, Wisconsin
SessionCommon Council & Committees
DateThursday, October 22, 2026
StatusFILED
Video Record
0:00 / 26:10

Original source
Transcript — VerbatimClick a timed line to jump · ⧉ to share it

Speaker numbers apply only to this recording.

Speaker 1

2:32

Good evening and welcome to the October meeting for the redevelopment authority of the city of La Crosse.

2:38

Welcome to those uh joining online in person.

2:42

Um before we get to actually we'll do we'll start with our approval of minutes.

Unassigned speaker

2:46

Uh entertain a motion and a second for approval.

Speaker 1

2:50

Motion by Ed, second by Julie for approval.

2:53

Any questions, comments on the minutes as presented?

2:56

Seeing none, all in favor of the motion, I or thumbs

Unassigned speaker

2:58

up.

Speaker 1

2:59

All opposed, same sign?

Unassigned speaker

3:01

All

Speaker 1

3:01

right, motion carries.

3:03

Uh before we get into tonight's agenda, I want to take uh just a minute to um if you haven't already heard, uh Lee Haremza, who we have worked with quite extensively for uh with Right Key on several projects for River Point District.

3:16

Um lost uh some family members tragically over the last uh couple weeks um in a plane crash.

3:22

Um, including his uh a son of his, his wife, and his mother in law.

3:27

Um we just want to let you know um, and we obviously extend our deepest condolences to um Lee and his family, um, and to those close to him.

3:36

Um Jason and uh Andrea been in contact with Lee.

3:39

Um and you know understandably we're gonna uh pause work at least for the short time to let him uh more and more on the loss.

3:48

So just for your aware awareness and and again know that um we continue to be in close contact with them.

3:54

So again, condolences to Lee and his family.

3:56

And um that's really all we can say at this point.

Unassigned speaker

4:01

Okay,

Speaker 1

4:01

uh, let's get into our agenda.

4:02

Uh, first agenda items twenty six uh one zero nine three, the monthly project management update for River Point District.

4:09

Welcome uh Jason Gilman to the meeting.

4:10

Uh welcome, Jason.

Unassigned speaker

4:14

Thank

Speaker 2

4:15

you, and good uh good evening.

4:17

Um I have a couple of things I wanted to go through uh on the administrative side uh the last thirty days.

4:23

I've been working on two things.

4:25

One is uh undergrounding of the XL Energy Lines.

4:29

Um you might recall we have uh uh quote from them to do it.

4:33

It is about one point three five million dollars uh to do that.

4:38

Um there's some uh a variety of things that we're working through with them.

4:45

Well one is just to verify the quote that it's all inclusive, that there isn't any uh hidden costs or things that the city would be responsible for that isn't listed in their quote.

5:10

And then the other thing is uh the timing of it.

5:13

We'd really like to try to sync the timing with the parkway construction so that we're not tearing up brand new park uh improvements, and there could be some economy of scale, you know, if there's equipment there and we're moving dirt.

5:27

Uh so that's underway.

5:29

We're also investing it.

5:32

We're investigating uh funding for that uh because historically there has been alternative alternate funding or third-party funding for these types of projects that are uh typically in the category of uh safety and sustainability or resiliency for uh power lines.

5:49

So we've inquired with XL about the availability of those uh funds uh through state and federal channels.

5:56

And uh so that's all ongoing.

6:00

We had a big internal meeting with our engineering staff and Andrea uh a few weeks back and uh talked through all this, and we're in contact uh week weekly with XL Energy.

6:11

Um another item is uh updating the the website for River Point District.

6:15

I've been working with Cherie in the mayor's office on that, and I sent her uh some timeline changes, updates, uh news stories, uh, some new photography, and a few other things, and she's uh working on that right now, so stay tuned.

6:30

I I would I would welcome you to take a look at the website too.

6:33

And if you see anything that you'd like updated, uh please do let me or Sheree know.

6:38

I'm happy to uh usher that through uh also.

6:43

And then uh just for excuse

Unassigned speaker

6:46

me,

Speaker 2

6:47

just for development updates.

6:49

I thought we could kind of do an around the horn with you know some of the uh different sites.

6:53

So 360 real estate on the corner by Copeland and River Bend Drive.

6:57

They tore down that building.

6:59

I don't know if you saw it's uh all demolished now, and they have it fenced in and they're grading.

7:04

Um Jeremy Novak uh last I talked to him, he said that they're revising their site plan to avoid that concrete monolith that's on the north uh or on the west end of that site.

7:15

Uh so we will probably have a presentation fairly short shortly.

7:19

I mean, within the next month, I would say, from 360 showing how they're modifying that whole uh site plan.

7:26

My expectation is they'll probably have two buildings rather than three, and the two buildings will be a little bit larger in scale.

7:33

If you you might recall that the front building toward the east on Copeland was just a single-story commercial building, that's probably gonna be mixed use multi-story now to rearrange things.

7:46

Uh and then moving toward the waterfront uh edge with lots 11 and 12.

Discussion Breakdown — Share of Meeting
Economic Development█████████████████████████████████████████████47%
Procedural██████████████████████████████████35%
Engineering And Infrastructure███████████11%
Public Market Redevelopment███████7%
Summary of Proceedings

Redevelopment Authority Meeting Summary — October 22, 2026

The Redevelopment Authority of La Crosse, Wisconsin met on Thursday, October 22, 2026 at 4:01 PM in Council Chambers. The meeting covered project updates, financial reports, contract approvals, and a closed session for property acquisition strategy. All action items were approved unanimously by voice vote unless noted.

Discussion Items

  • Monthly Project Management Update (River Point District) – Project manager Jason Gilman reported on undergrounding XL Energy Lines (estimated cost $1.35 million), website updates, and development progress at multiple sites: 360 Real Estate (demolition complete, revising site plan for two mixed-use buildings); Cowboy Jack's (planning April 2027 construction, 9-month build); Rike Key's 'the 11' (60 units with commercial space); War Eagle's condominiums (90% plans complete, awaiting Bridgeville Plaza agreement); Unwind 42 townhomes (first phase spring 2027); MSP senior housing (165–180 units, ~$80M, expecting update in November). Gilman also shared positive developer feedback from two completed projects (War Eagle and the LOFTS), noting quick lease-up and smooth city processes.
  • Monthly Financial Update – October 2026 – The financial statement was provided; no questions were raised.
  • Second Extension to Option to Purchase Agreement – Cowboy Jack's (Lot 2 of Lot 11) – Approved by voice vote (motion by Janssen, seconded by Przytarski).
  • Second Extension to Option to Purchase Agreement – Cowboy Jack's (Lot 12) – Approved by voice vote (motion by Janssen, seconded by Henline).
  • Property Maintenance Agreement for Snow Removal – Property Reliance LLC – Approved by voice vote (motion by Henline, seconded by Przytarski). Payments to come from planning option agreement payments.
  • Resolution Approving Quit Claim Deed – City to RDA for Cowboy Jack's parcel – Staff explained the deed transfers ~300–2,500 sq ft (speaker discrepancy) of park-dedicated land needed for Cowboy Jack's concert deck; the land will be combined with the main parcel for sale. Approved by voice vote (motion by Janssen, seconded by Przytarski).
  • Memorandum of Understanding for Letter of Map Revision (Lot 10) – Professional services to remove lot from floodplain; cost not to exceed $15,000, split with War Eagle LLC. Funding source directed to planning option agreement payments (motion by Janssen, seconded by Henline). Approved by voice vote.
  • Contract with Project for Public Spaces for Public Market – Pre-phase 1 contract at $45,000 from $600,000 urban renewal funds. Scope includes site visits, stakeholder meetings, market demand analysis, and a final report. Members noted previous 2018 study was by a different company. Approved by voice vote (motion by Henline, seconded by Przytarski).
  • Resolution Approving Fund Transfer for Property Acquisition at River Point District – The Authority moved into closed session (Wis. Stat. 19.85(1)(e)) via roll call vote (motion by Przytarski, seconded by Janssen). In closed session, a status update was given and the item was advanced with no recommendation. The meeting adjourned in closed session at 4:42 PM.

Key Outcomes

  • All open-session action items (seven total) were approved unanimously by voice vote.
  • Closed session held for negotiation strategies; no public action taken.
  • Next regular meeting expected in November 2026.

Meeting Transcript

Good evening and welcome to the October meeting for the redevelopment authority of the city of La Crosse. Welcome to those uh joining online in person. Um before we get to actually we'll do we'll start with our approval of minutes. Uh entertain a motion and a second for approval. Motion by Ed, second by Julie for approval. Any questions, comments on the minutes as presented? Seeing none, all in favor of the motion, I or thumbs up. All opposed, same sign? All right, motion carries. Uh before we get into tonight's agenda, I want to take uh just a minute to um if you haven't already heard, uh Lee Haremza, who we have worked with quite extensively for uh with Right Key on several projects for River Point District. Um lost uh some family members tragically over the last uh couple weeks um in a plane crash. Um, including his uh a son of his, his wife, and his mother in law. Um we just want to let you know um, and we obviously extend our deepest condolences to um Lee and his family, um, and to those close to him. Um Jason and uh Andrea been in contact with Lee. Um and you know understandably we're gonna uh pause work at least for the short time to let him uh more and more on the loss. So just for your aware awareness and and again know that um we continue to be in close contact with them. So again, condolences to Lee and his family. And um that's really all we can say at this point. Okay, uh, let's get into our agenda. Uh, first agenda items twenty six uh one zero nine three, the monthly project management update for River Point District. Welcome uh Jason Gilman to the meeting. Uh welcome, Jason. Thank you, and good uh good evening. Um I have a couple of things I wanted to go through uh on the administrative side uh the last thirty days. I've been working on two things. One is uh undergrounding of the XL Energy Lines. Um you might recall we have uh uh quote from them to do it. It is about one point three five million dollars uh to do that. Um there's some uh a variety of things that we're working through with them. Well one is just to verify the quote that it's all inclusive, that there isn't any uh hidden costs or things that the city would be responsible for that isn't listed in their quote. And then the other thing is uh the timing of it. We'd really like to try to sync the timing with the parkway construction so that we're not tearing up brand new park uh improvements, and there could be some economy of scale, you know, if there's equipment there and we're moving dirt. Uh so that's underway. We're also investing it. We're investigating uh funding for that uh because historically there has been alternative alternate funding or third-party funding for these types of projects that are uh typically in the category of uh safety and sustainability or resiliency for uh power lines. So we've inquired with XL about the availability of those uh funds uh through state and federal channels. And uh so that's all ongoing. We had a big internal meeting with our engineering staff and Andrea uh a few weeks back and uh talked through all this, and we're in contact uh week weekly with XL Energy. Um another item is uh updating the the website for River Point District. I've been working with Cherie in the mayor's office on that, and I sent her uh some timeline changes, updates, uh news stories, uh, some new photography, and a few other things, and she's uh working on that right now, so stay tuned. I I would I would welcome you to take a look at the website too. And if you see anything that you'd like updated, uh please do let me or Sheree know. I'm happy to uh usher that through uh also. And then uh just for excuse me, just for development updates.