City Council Work Session: Rotary Park Pump House Replacement Authorization – August 31, 2026

City Council — Monday, August 31, 2026
BodyMontrose, Colorado
SessionCity Council
DateMonday, August 31, 2026
StatusFILED
Video Record
Meeting Thumbnail
⇩ GET FROM SOURCE

STREAMING COPY IN PREPARATION — RECORDING AVAILABLE FROM THE ORIGINAL SOURCE

Original source
Transcript — Verbatim

Speaker numbers apply only to this recording.

Unassigned speaker

0:40

John,

Speaker 1

0:41

I like the new hat.

0:42

Is that Jim where I sweep?

Unassigned speaker

0:44

Is that that was a good idea?

Unassigned speaker

0:48

I have an interactive problem.

Unassigned speaker

1:22

Hey, how can you like sleep in a while?

Unassigned speaker

1:28

I can't remember what it's like.

Unassigned speaker

1:30

I do remember.

Unassigned speaker

1:39

Okay.

Unassigned speaker

3:36

Uh

Speaker 2

3:36

public comment will be accepted on topics listed under discussion items.

3:40

Please note that no formal action will be taken on the matters raised during this time.

3:44

Comments made during this time should be addressed to the council and pertain to the agenda item on which the comment is made.

3:50

City council or city staff may respond or engage in discussion should the comment provoke discussion.

3:56

Please refrain from any personal attacks and disagreements, personnel or employment matters.

4:01

The use of profanity or ethic ethnic, racial, or gender-oriented slurs that may be considered disorderly conduct, which violates state or local law.

Speaker 3

4:33

This project has been a few years in the making.

4:51

Yeah.

4:51

Dave uh Dave handles a massive amount of sites systems facilities across the city.

Unassigned speaker

5:00

And I know we've had a lot of compliments on the condition of irrigated turf throughout the summer season.

Speaker 3

5:03

And it was a difficult season.

5:05

That happens in large part because of Dave and his expertise and the work that he puts in.

5:12

He's also been a big help on this project in terms of getting the Monroe pump skid spec'd uh and and assisting with the bid.

5:21

So wanted him here, and just to take a minute to recognize him as we get towards the tail end of the irrigation season.

5:29

It is definitely not me out there fixing broken irrigation systems.

5:34

It's Dave.

5:36

So thank you, Dave.

5:38

In terms of the the project for today, the rotary pump house replacement.

5:44

The general scope is demo of the current pump house, building the new pump house, installing a new pump station, updating the intake system for that structure, and then reconnecting to the existing main for the irrigation system and testing the new unit.

6:04

By unit, I mean the pump house pump station.

6:09

The demo is pretty straightforward on this one as there is not much to the current structure.

6:13

It's a concrete slab, you know, wood frame with metal siding on it.

6:19

And you know, I think if you took a good running start at it, you might be able to knock it over yourself at this point.

6:25

So that should be a pretty quick demo.

6:29

We will be building the new pump house in nearly the same place.

6:32

It'll move back several feet from the creek as the current house is nearly undercut by the water course.

6:39

It's starting to eat away towards the edge of the slab.

6:42

The new pump house will generally look like the one that serves Buckley and Lions Park.

6:47

Uh, if anyone is familiar with that, it was built in the past few years.

6:51

It's a CMU block structure with uh corrugated metal roof.

6:55

Uh nothing too fancy.

Unassigned speaker

6:56

There is an overhead door, and then there's also a mandor in the structure.

Speaker 3

7:00

So uh more or less a CMU block garage.

7:04

I think it's 15 by 18 in the plans.

Unassigned speaker

7:10

Uh

Speaker 3

7:10

the complexity of the project is is really more indoors as uh the new building will house a Monroe pump station.

7:17

Uh this unit comes skid mounted, so all of the assembly is on a skid unit uh with the very variable frequency drive, the panel, the filtration system, all the pumps, the electronics valves, uh, and then that skid will sit on a 60-inch diameter concrete wet well interior to the structure.

7:38

Um that is a different design than we've utilized before, but should be uh quite a bit more efficient.

7:45

Um the unit can supply up to 240 gallons per minute to the irrigation system, uh, and that sounds pretty intense until you consider that this actually waters about eight to eight and a half acres of irrigated turf, stretches from South Twelfth uh clear through Rotary Park to Niagara with a spur going out towards Mesa Avenue as well.

8:09

So it's everything you see essentially outside of the school district fence uh and minus the the fields, those are served by the adjoining pump house owned by uh Montrose County School District.

Unassigned speaker

8:23

Uh

Speaker 3

8:23

the wet well, which when I say wet well, I mean that 60-inch diameter concrete um standpipe more or less uh is filled by a line that comes from a settling basin uh which will be installed exterior to the building.

8:36

Uh this is a large concrete box that uh water flows from the headgate through the delivery system and uh fills up one chamber of the box, pours over onto a screen that can be cleaned.

8:49

Uh that's a pre-filter basically before the water goes down and uh enters the pump house and fills the wet well.

8:57

Uh if you want to see what that structure looks like, it will be similar to the one that serves the school district pump house out at Rotary.

9:04

Uh and that structure is uh concrete bunker uh looking uh building that is right next to the existing pump house.

9:13

Uh settling basin is fed by a line from the arroyo.

9:16

Um the existing headgate will remain in place.

9:20

Uh this serves the school district pump house as well as the city facility.

9:24

Uh there will be some adjustment to the routing of this line in order to add a splitter box uh to serve the city pump house because currently we just have a suction valve, a foot valve that comes directly out of the pump house, lays in the muddy creek, and uh pulls direct from the water source, will now be fed through the headgate, uh, which is um advantageous um to having to fight that foot valve laying in the mud.

Discussion Breakdown — Share of Meeting
Engineering And Infrastructure████████████████████████████████32%
Procedural█████████████████17%
Parks and Recreation████████████████16%
Environmental Protection███████████11%
Personnel Matters████████8%
Budget Equity Analysis████████8%
Public Safety████████8%
Summary of Proceedings

City Council Work Session: Rotary Park Pump House Replacement Authorization – August 31, 2026

This work session focused on the proposed replacement of the Rotary Park pump house, followed by general council discussion and staff updates on a fuels reduction project at Ceres Park and recent police department activities. No formal action was taken on any item.

Discussion Items

  • Rotary Park Pump House Replacement: Parks Superintendent Jon Waschbusch presented the project scope, which includes demolition of the existing structure, construction of a new CMU-block pump house (15x18 feet), installation of a skid-mounted Monroe pump station with a 60-inch-diameter concrete wet well, and a new settling basin and intake system. The pump station can supply up to 240 gallons per minute to irrigate approximately 8 to 8.5 acres of turf stretching from South Twelfth Street through Rotary Park to Niagara, with a spur to Mesa Avenue. The low bid was $467,283, with a recommended 10% owner's contingency of $46,728, resulting in a total proposed contract of $514,011. The over-budget amount ($14,011) would be covered by savings from other public works projects. Council members asked about foundation design (engineered footers, not micro piles), insulation (not insulated; the system is winterized), and the contingency budget (only used for change orders, not a built-in overrun). No public comments were received.
  • Ceres Park Fuels Reduction and Invasives Eradication Project: Staff member Mike provided an update on a project funded by a congressional grant received last April. Work is scheduled to begin September 14, 2026, and last approximately five weeks. The project involves removing Russian olive and tamarisk trees across about 25 modules (first 7-8 mechanized, remainder handwork) on both sides of the river near Ceres Park, from the dog park south to the McNeil ball fields. Large timber will be hauled to Jamco for milling; slash will be chipped on site. Restoration work (seeding, planting, supplemental irrigation) will follow 12-18 months after. A council member inquired about using the wood for biochar, but staff noted no air curtain burner is available in western Colorado. Public will be notified via press release and signage; disc golf baskets will be removed during work.
  • Police Department Update: Staff reported that eight officers attended the International Association of Chiefs of Police Women in Leadership Institute; the department taught an alcohol server class, worked Cornfest, conducted mounted patrol training for three employees and one volunteer with two horses, and presented on e-bikes at Rotary Park. Seizures for the past month included 15.9 grams of cocaine, 236 grams of methamphetamine, 0.25 grams of hydrocodone, and 0.32 grams of fentanyl.

Key Outcomes

  • No formal actions were taken; the council discussed the Rotary Park pump house replacement authorization and asked clarifying questions. Staff recommendations were noted but not voted upon. The Ceres project and police update were informational only.

Meeting Transcript

John, I like the new hat. Is that Jim where I sweep? Is that that was a good idea? I have an interactive problem. Hey, how can you like sleep in a while? I can't remember what it's like. I do remember. Okay. Uh public comment will be accepted on topics listed under discussion items. Please note that no formal action will be taken on the matters raised during this time. Comments made during this time should be addressed to the council and pertain to the agenda item on which the comment is made. City council or city staff may respond or engage in discussion should the comment provoke discussion. Please refrain from any personal attacks and disagreements, personnel or employment matters. The use of profanity or ethic ethnic, racial, or gender-oriented slurs that may be considered disorderly conduct, which violates state or local law. This project has been a few years in the making. Yeah. Dave uh Dave handles a massive amount of sites systems facilities across the city. And I know we've had a lot of compliments on the condition of irrigated turf throughout the summer season. And it was a difficult season. That happens in large part because of Dave and his expertise and the work that he puts in. He's also been a big help on this project in terms of getting the Monroe pump skid spec'd uh and and assisting with the bid. So wanted him here, and just to take a minute to recognize him as we get towards the tail end of the irrigation season. It is definitely not me out there fixing broken irrigation systems. It's Dave. So thank you, Dave. In terms of the the project for today, the rotary pump house replacement. The general scope is demo of the current pump house, building the new pump house, installing a new pump station, updating the intake system for that structure, and then reconnecting to the existing main for the irrigation system and testing the new unit. By unit, I mean the pump house pump station. The demo is pretty straightforward on this one as there is not much to the current structure. It's a concrete slab, you know, wood frame with metal siding on it. And you know, I think if you took a good running start at it, you might be able to knock it over yourself at this point. So that should be a pretty quick demo. We will be building the new pump house in nearly the same place. It'll move back several feet from the creek as the current house is nearly undercut by the water course. It's starting to eat away towards the edge of the slab. The new pump house will generally look like the one that serves Buckley and Lions Park. Uh, if anyone is familiar with that, it was built in the past few years. It's a CMU block structure with uh corrugated metal roof. Uh nothing too fancy. There is an overhead door, and then there's also a mandor in the structure. So uh more or less a CMU block garage. I think it's 15 by 18 in the plans. Uh the complexity of the project is is really more indoors as uh the new building will house a Monroe pump station. Uh this unit comes skid mounted, so all of the assembly is on a skid unit uh with the very variable frequency drive, the panel, the filtration system, all the pumps, the electronics valves, uh, and then that skid will sit on a 60-inch diameter concrete wet well interior to the structure. Um that is a different design than we've utilized before, but should be uh quite a bit more efficient. Um the unit can supply up to 240 gallons per minute to the irrigation system, uh, and that sounds pretty intense until you consider that this actually waters about eight to eight and a half acres of irrigated turf, stretches from South Twelfth uh clear through Rotary Park to Niagara with a spur going out towards Mesa Avenue as well. So it's everything you see essentially outside of the school district fence uh and minus the the fields, those are served by the adjoining pump house owned by uh Montrose County School District.