Mountain View Zoning Administrator Public Hearing - September 11, 2025
STREAMING COPY IN PREPARATION — RECORDING AVAILABLE FROM THE ORIGINAL SOURCE
Mountain View Zoning Administrator Public Hearing - September 11, 2025
Note: The transcript indicates the meeting was held on September 10, 2025, but the assigned date for this summary is September 11, 2025. This discrepancy is noted.
Presiding Officer Amber Blazinski called the hybrid meeting to order at 4:00 p.m. Two agenda items were considered: a continuance request for a LinkedIn development agreement amendment and an approval for an El Camino Hospital expansion. No oral communications on non-agenda items were received.
Public Comments & Testimony
- Item 3.1 (LinkedIn): No public comments were offered.
- Item 3.2 (El Camino Hospital): Two community members spoke in support:
- Chris Cow, a resident of East Palo Alto and whose wife works at El Camino Hospital, expressed support and praised the hospital’s landscaping and the vision for the campus.
- Genevieve Lurch, a long-time neighbor and hospital user, expressed support and asked about the construction timeline and parking mitigation for staff and construction workers.
Discussion Items
-
Item 3.1 – 700 and 800 East Middlefield Road, 1101 Maud Avenue (LinkedIn): The applicant requested a five-year extension of the term for Phase 2 of an approximately 429,000 sq ft office development project. Earlier on the day of the hearing, the applicant requested a continuance to allow further discussions with city staff on the development agreement details. Planner Diana Pantrolet recommended continuation. Zoning Administrator Blazinski concurred, noting the need for staff analysis and that her decision is a recommendation to the City Council, which has final authority. The item was continued to a date uncertain, with a new public hearing notice to be sent per city code.
-
Item 3.2 – 2500 Grant Road (El Camino Hospital): Planner Jeff Shemura presented a request for a planned community permit and development review permit to construct a 42,839 sq ft three-story addition (Wing J) to the main hospital building, along with two new courtyards, a connector to the behavioral health services building, and site modifications. The project is a seismic replacement of demolished facilities and is categorically exempt under CEQA Guidelines Section 15302. Applicant Ken King (Chief Administrative Officer, El Camino Health) stated this is the final element of the campus completion plan envisioned since 2016. In response to public comments, Mr. King explained that the construction site is centrally located with ample laydown space, minimizing disruption to parking and traffic. He noted that the hospital actively manages parking through four garages and that the commencement of this project will coincide with a reduction in overall contractor vehicles as other projects finish. Communication with neighbors will be handled via the hospital website and direct contact.
Key Outcomes
- Item 3.1 (LinkedIn): Continued to a date uncertain. The applicant will work with staff on the development agreement details before a future hearing.
- Item 3.2 (El Camino Hospital): Approved by Zoning Administrator Blazinski based on the findings and conditions of approval in the staff report. The decision is appealable to the City Council within 10 calendar days. The meeting adjourned at 4:14 p.m.
Meeting Transcript
Okay, guys. All right. So good afternoon. Welcome to the administrative zoning public hearing of September 10th. My name is Amber Blazinski. I'm presiding over the hearing today as the zoning administrator. I'll call the meeting to order at 4 p.m. So today's hearing will operate in a hybrid format. Staff, the applicants, and some community members are in person. However, we'll also ask if community members joining us virtually want to speak on an item at certain points in the meeting. When those opportunities arise, typically during the public comment portion of each agenda item, members of the public wishing to comment may do so by clicking on the raised hand feature in Zoom when I announce the item on which you wish to speak. Speakers will be notified of their turn shortly before they're called on to speak. All speakers, virtual or in person will have three minutes to provide comments with the timing dependent on the total number of speakers for each item. If you're in person and you guys are applicants, right? Yeah. If you're in person and wish to comment on either of the items, please also fill out a yellow speaker card for us so we're able to accurately spell your name. The next portion of the meeting is oral communications from the public. This is the time set aside for people wishing to address the zoning administrator on any matter not on the agenda. Speakers are limited to three minutes and state law prohibits any action on any items which are not on the agenda. So for anyone who's virtual, we don't have anybody in the room that isn't an applicant. So I'm asking virtually if there's anyone who'd like to speak on an item that's not on the agenda. None. Okay, great. So I'll now move to item three, which is the zoning administrator public hearing. So item 3.1 is 700 uh and 800 East Middlefield Road and 1101 Maud Avenue and LinkedIn with a request to amend a previously approved development agreement to grant a five-year extension of the term for phase two of an approximately 429,000 square foot office development project. Um the EIR for the project was adopted by the city council on November 27th. And the proposed amendment to the development agreement term does not alter the project conditions assessed in the adopted EIR and no additional environmental review is necessary. Diana Pantrolet is a project planner. Diana, do you have a staff presentation? Thank you. Um Diana Pincholi, principal planner and project manager for this product. In light of a request received from the project applicant earlier today to continue the discussion on this item to allow for further discussions between the city and the project applicant LinkedIn Corporation on the details of the development agreement. Staff is going to forego a typical uh project presentation and recommend that the item be continued to a future date, which will be noticed separately. This continuation will allow staff and the applicant to have further discussions on the item before bringing it back for a formal project review with the zoning administrator and ultimately to the city council. Thank you. Thank you. Um, so uh I believe our applicants are uh joining us virtually. Um you do not need to say anything today. Um, however, if you did want to speak, can you please raise your hand in Zoom? Again, you'll have an opportunity to present in the future hearing, but um anybody raising their hand, Roxanne? Okay. So um so I I appreciate the remarks. I understand um the position and the updated recommendation. Um so uh just with respect to that, I want to still provide an opportunity for members of the public who've taken the time to attend today's meeting to provide public comment today if there are any online for this item. So um, you know, at the future hearing, um, you know, staff, the applicant, any public comment uh will also be accepted at that hearing. Um, but I don't want anyone to feel like we didn't listen to them today. I'm looking at the camera because we don't have anyone in the room who's from the public who who would speak on this item. So um, if anybody online wanted to, uh please raise your hand and let us know. Then okay. Um, all right.