All right, Tom.

0:07

Like the call to order the agenda for Thursday planning board meeting, October 16, 2025.

0:15

Held at 7 p.m.

0:16

PBD City Hall low level conference from 24 Wall Street PBD Mass.

0:22

First item on the agenda is approval of the minutes of the October 2nd, 2025 meeting.

0:38

We have a second.

0:39

Second.

0:40

All those in favor?

0:43

Unanimous.

0:44

Thank you.

0:46

A and R and Land Code, we have none.

1:02

Mr.

1:02

Chairman, just before Attorney Kelty here uh comes to uh I guess I was going to say the stage, but before he comes before the board will this evening, uh, I just want to give everybody an update, which I'm sure Kelty will also give.

1:14

Uh as you know, at the last meeting I mentioned that uh the air's project had gone up to peer review for the stormwater.

1:21

That peer review had then since come back and it was sitting uh on the desk at our Department of Public Services.

1:27

Since then, DPW has reviewed that and they have provided with you as a late, it would be a late ad this evening if the board wishes to vote to accept um a close out memo for this where you uh Mr.

1:39

Paulitz, the director of engineering lays out uh a series of conditions uh for the applicant to meet if they were the board so chooses to vote to accept the laid ad and then accepts uh votes to move forward uh approving this project.

1:56

Um I've talked with Mr.

1:58

Paulitz about it.

1:59

There the project is still in front of Conservation Commission.

2:02

Uh so this would not be the one and done for them.

2:05

They would still need to go back in front of CONCOM.

2:07

But you'll see that uh Mr.

2:09

Pauls has laid out a series of 13 conditions in the uh memo.

2:14

And then this was also forwarded to Attorney Kelty as well.

2:20

Ms.

2:20

Chairman, in a matter of 15 Solomon Street, I move to receive a late communication from William Paulett's Director of Public Services PBD.

2:29

Uh the date on the memo is October 16th.

2:31

It's a two-page memo, and it uh lays out comments and concerns uh with this project.

2:40

Move to receive.

2:42

We have a second.

2:44

Second.

2:45

All those in favor.

2:47

Aye.

2:48

Unanimous, thank you.

2:49

Uh Dr.

2:50

Otto and uh Dennis, I uh I I'll drop it into the uh online folder right now for you.

3:01

Thank you.

3:03

It will be it'll just be under the 15th Sylvan Street folder.

3:17

Um the board needs a minute to review this.

3:20

It it there's two pages uh from Mr.

3:24

Paulitz, but then he also included the latest peer review that Warsley Wooden did as well.

3:34

Yep.

3:35

Attorney Kelty, if you want to present.

3:37

No, I really don't have much to add.

3:40

I uh uh on the uh list of uh participants this evening at uh is Eric Dubiel Dubio from uh uh bowler engineering.

3:51

Uh however, he has not had the opportunity to see this memo.

3:55

I will send it to him in the morning, and it uh looks as though it in through my conversation with uh Mr.

4:02

Pollitz this afternoon.

4:04

He made note of the fact that the uh project is still before uh Danvers, uh, but most notably is before our conservation commission at their November meeting.

4:16

Uh we believe that this uh can serve as a and will uh can serve as a closeout memo uh sending us off to complete.

4:28

I think that any motion uh should certainly say subject to uh approval by conservation commission and uh uh the incorporation of the recommendations uh into final plans.

4:42

Have any questions from the board?

4:44

I just have a couple questions if long as the board.

4:47

I know everyone's meeting, so I've had time to look at it, but I can wait.

4:53

Um

5:00

Um uh in his memo, he said the he should uh uh we should address the following issues.

5:37

Uh and there are nine items, and it appears that those are taken from uh the uh document which is attached to his memorandum in which uh Hors Lee Witten uh made these recommendations, and so Will is um reiterating them, and then he adds four conditions at the bottom, which we would agree to.

6:00

We do agree to.

6:02

And you still need a positive vote from Thon Farm?

Discussion Breakdown — Share of Meeting
Engineering And Infrastructure████████████████████████████████████████████44%
Public Safety█████████████████████████████████████37%
Zoning Changes████████8%
Procedural██████6%
Licensing█████5%
Summary of Proceedings

Planning Board Meeting - October 16, 2025

The Peabody Planning Board met on Thursday, October 16, 2025, at 7:00 PM in the PBD City Hall low-level conference room. The board approved previous minutes, received a late communication, and conditionally approved the 15 Sylvan Street project after extensive discussion on entrance/exit design and emergency vehicle access.

Consent Calendar

  • Approval of Minutes: The minutes of the October 2, 2025 meeting were approved unanimously.
  • Late Communication: A motion to receive a late memo from William Paulitz, Director of Public Services, dated October 16, 2025, was approved unanimously. The memo outlines 13 conditions for the 15 Sylvan Street project and includes a peer review from Horsley Witten.

Public Comments & Testimony

  • No public comments were made.

Discussion Items

  • 15 Sylvan Street – Closeout Memo and Conditions: Attorney Kelty and Eric DeBrule (Bowler Engineering) presented the project status. The project is still before the Conservation Commission and requires a favorable order of conditions. The DPW memo lists nine items from peer review plus four additional conditions. Key discussion centered on the entrance/exit on Sylvan Street:
    • The board, police department, and DPW wanted a vertical granite curb to prevent left turns out of the site.
    • The applicant proposed a 4-inch sloped curb to allow emergency vehicles (fire trucks, delivery trucks) to mount it.
    • Board members debated options, including angling the exit to naturally discourage left turns, using signage, or adding plantings. It was noted that the current design already includes a sloped curb at 4 inches, which is more robust than the typical 2-3 inch mountable curb.
    • Captain Richards of the police department expressed concern that the sloped curb might not sufficiently deter left turns across two lanes of traffic. The board emphasized the need for a design that satisfies both police and fire department requirements.
    • Ultimately, the board decided to condition the approval on the applicant working with the police and fire departments to finalize an acceptable design for the entrance/exit.

Key Outcomes

  • Motion and Vote: The board unanimously voted to conditionally approve the 15 Sylvan Street project with three conditions:
    1. The project must receive a positive vote or recommendation from the Conservation Commission.
    2. The applicant must comply with the 13 conditions outlined in Mr. Paulitz’s memo dated October 16, 2025.
    3. Regarding the entrance and exit on Sylvan Street, the applicant must work with the police and fire departments to achieve a satisfactory design (including curb type, signage, and geometry).
  • The board also noted that any redesign for the entrance/exit would need to come back for board approval if substantial changes are made.
  • The meeting adjourned after the vote.

Meeting Transcript

All right, Tom. Like the call to order the agenda for Thursday planning board meeting, October 16, 2025. Held at 7 p.m. PBD City Hall low level conference from 24 Wall Street PBD Mass. First item on the agenda is approval of the minutes of the October 2nd, 2025 meeting. We have a second. Second. All those in favor? Unanimous. Thank you. A and R and Land Code, we have none. Mr. Chairman, just before Attorney Kelty here uh comes to uh I guess I was going to say the stage, but before he comes before the board will this evening, uh, I just want to give everybody an update, which I'm sure Kelty will also give. Uh as you know, at the last meeting I mentioned that uh the air's project had gone up to peer review for the stormwater. That peer review had then since come back and it was sitting uh on the desk at our Department of Public Services. Since then, DPW has reviewed that and they have provided with you as a late, it would be a late ad this evening if the board wishes to vote to accept um a close out memo for this where you uh Mr. Paulitz, the director of engineering lays out uh a series of conditions uh for the applicant to meet if they were the board so chooses to vote to accept the laid ad and then accepts uh votes to move forward uh approving this project. Um I've talked with Mr. Paulitz about it. There the project is still in front of Conservation Commission. Uh so this would not be the one and done for them. They would still need to go back in front of CONCOM. But you'll see that uh Mr. Pauls has laid out a series of 13 conditions in the uh memo. And then this was also forwarded to Attorney Kelty as well. Ms. Chairman, in a matter of 15 Solomon Street, I move to receive a late communication from William Paulett's Director of Public Services PBD. Uh the date on the memo is October 16th. It's a two-page memo, and it uh lays out comments and concerns uh with this project. Move to receive. We have a second. Second. All those in favor. Aye. Unanimous, thank you. Uh Dr. Otto and uh Dennis, I uh I I'll drop it into the uh online folder right now for you. Thank you. It will be it'll just be under the 15th Sylvan Street folder. Um the board needs a minute to review this. It it there's two pages uh from Mr. Paulitz, but then he also included the latest peer review that Warsley Wooden did as well. Yep. Attorney Kelty, if you want to present. No, I really don't have much to add. I uh uh on the uh list of uh participants this evening at uh is Eric Dubiel Dubio from uh uh bowler engineering. Uh however, he has not had the opportunity to see this memo. I will send it to him in the morning, and it uh looks as though it in through my conversation with uh Mr. Pollitz this afternoon. He made note of the fact that the uh project is still before uh Danvers, uh, but most notably is before our conservation commission at their November meeting.

SUMMARIZED BY OPENPUBLICA AI
TRANSCRIPT VIA PUBLIC VIDEO
openpublica.com