The City County Bicycle Advisory Committee (SacBAC) met on Thursday, November 9, 2017, at 6:00 p.m. in city chambers. The committee reviewed two major infrastructure projects, received a funding overview, and discussed the transition to separate city and county bicycle advisory bodies. The meeting included a consent calendar, three information items, and committee updates.
Consent Calendar
- Approval of Meeting Minutes of October 19, 2017 – Approved with a minor amendment (removing the word "acting" from the Chair's description). One abstention recorded.
- Bicycle Advisory Committee Log – Received and filed without changes.
Public Comments & Testimony
- No members of the public spoke during the public comment period for matters not on the agenda.
Discussion Items
Franklin Boulevard Project (Item 3)
- Presenter: Megan Johnson, City Associate Civil Engineer, presented the Franklin Boulevard Complete Streets project for the northern segment (38th Avenue to Sutterville Road, 1.5 miles).
- Key data: Existing average daily traffic: 19,000 vehicles; 85th percentile speed: 47.5 mph; only one city street tree along the corridor. The project emerged from a grassroots community effort.
- Two alternatives:
- Alternative 1 (Buffered Bike Lanes, Class II): Road diet from four lanes to two lanes with a center median, 3-foot buffer, widened sidewalks, and on-street parking with tree wells. Estimated construction cost: ~$13 million.
- Alternative 2 (Raised Class IV Bikeway): Raised bikeway adjacent to the sidewalk, with grade separation and landscaping. Estimated construction cost: ~$17 million.
- Community outreach: Walking tours, public workshops, a pop-up demonstration, and a steering committee. The community preference is leaning toward the raised alternative.
- Concerns raised by committee members:
- Conflicts between pedestrians and cyclists with the raised design, especially near driveways.
- Potential hazards from uneven surfaces and street furniture.
- Support for either option, but preference for the buffered lane from a “cyclists as traffic” perspective.
- Next steps: Preliminary engineering and environmental documentation (CEQA/NEPA) ongoing; targeting construction in 2020 pending grant funding.
Auburn Boulevard Bike & Pedestrian Improvements (Item 4)
- Presenter: Anthony Voo, County Associate Civil Engineer, presented a $1.4 million HSIP-funded project on Auburn Boulevard (0.6 miles from Annadale Lane to just west of Winding Way).
- Safety data: Between 2009–2014, 12 bicycle-related and 8 pedestrian-related crashes, including two fatalities.
- Existing conditions: Four-lane arterial with 40 mph posted speed (85th percentile 44 mph), ADT >20,000, narrow shoulders (2–3 ft eastbound, 4–7 ft westbound).
- Proposed improvements:
- Restripe to provide a 10-foot two-way left-turn lane, 11-foot travel lanes, and 5–6 foot bike lanes.
- Install a pedestrian-activated HAWK signal near the Powerhouse Science Center Discovery Campus.
- Upgrade traffic signal at Norse Avenue to video detection for bicycles.
- Improve bus stop accessibility and add infill street lighting.
- Concerns: Committee noted high-speed traffic near the I-80 interchange and expressed interest in future improvements east of Winding Way.
- Next steps: CEQA exemption and NEPA categorical exclusion received; final design and right-of-way acquisition; construction anticipated in 2019.
City Funding 101 (Item 5)
- Presenter: Jennifer Donlon Wyant, Active Transportation Program Specialist, explained how bike projects are funded.
- Key points:
- Transportation is not funded from the general fund (except a one-time $2.25 million mid-year allocation for bikeways).
- Sources: gas tax, Measure A (new construction), TDA, and grants. Local match is typically 11.47%.
- The Active Transportation Program (replacing the Bikeway Program) has about $1.4 million per year for local match.
- Over the past five years, 21% of the city’s total transportation budget was spent on biking. This percentage is higher than in comparable cities, but the overall transportation budget is smaller.
- SB1 (new state gas tax) is expected to provide $8 million in the first year (rising to $14 million ongoing), primarily for pavement maintenance, with opportunities to add bike lanes during repaving.
- Questions: Committee discussed the 21% figure and how SB1 funds will be allocated; staff will bring a list of corridors with bike improvements to the next meeting.
Update on New City Bicycle Advisory Commission (Item 6)
- Presenter: Jennifer Donlon Wyant reported that the proposal to form a city-only Bicycle Advisory Commission will go to the Law and Legislation Committee on November 14, 2017, then to City Council in January.
- Structure: 13 members (12 council district appointees plus two at-large, with a mayoral appointee). The current joint committee will be dissolved in December 2017.
- Timeline: Recruitment and appointments likely in early 2018; first meeting anticipated in late spring.
- Committee comments: Members expressed hope for continuity and asked about authority; the commission will have no additional authority unless granted by council.
Committee Comments & Updates
- Vision Zero: Drew Hart announced that a public draft plan will be released in December 2017; public comment period will remain open.
- Special Meeting: The committee will hold a special meeting on Tuesday, November 14, 2017, at 6:00 p.m. in Room 1119 to review the Bike Plan Implementation Plan (Section 3).
- County Advisory Committee: Dave reported that the county will propose a separate county-only bicycle advisory committee to the Board of Supervisors on December 12, 2017, with effective date January 1, 2018. Appointments will follow a similar process. No applications are being accepted yet.
Key Outcomes
- Consent Calendar approved with one abstention.
- No formal votes on the information items; the committee offered comments and feedback for staff to consider.
- Next regular meeting: December 14, 2017, at 6:00 p.m. in the same chambers.
- Special meeting: November 14, 2017, at 6:00 p.m. for the Bike Plan Implementation Plan.
- Staff will provide a list of SB1-related corridors with bike improvements at the next meeting, and continue outreach on the Franklin and Auburn projects.
Meeting Transcript
Are you awake? It's our tech in the back. All right, hold on. Hold on out on my buttons. Oh, you've lost your buttons. Okay, great. Um, let's come to order and call the roll. Sorry, I'm out of sorts today. Um Vice Chair Farland. Member Lee? Member Seaford. Member Casey. Present. Member Mirante. Member Gurma. Chair Whalen. Here. Member Lang. Member Meldon. Present. Member Castle. Member Coffer. Member Casarda. Okay. Very good. Wrestling with the parking meter out. Two out of three falls. All right. We are, I think one short for a quorum. No, we have a quorum. So we have a do have seven. We have a quorum. Good. Great. All things. Let me get to the rest of the blood and bones. Yes. This meeting meeting is broadcast live and is available on the city website. If you have a cell phone, please silence it. Speaker slips are located in the back. If you'd like to speak on a matter, please fill one out. Fill it out and give it to Drew Hart sitting over by the computer over there. Your speaker limit time is three minutes. And we also have a cordless microphone and assistive listening devices, should you need one. I need one. Thank you. First item on the agenda is the uh consent calendar, the minutes, and the bicycle log. Um I didn't notice any changes in the bike log, and I have one small amendment to the minutes. I've already made Drew aware. The minutes characterize me as acting.