The meeting on August 26, 2025, addressed several routine contracts, a long-term agreement for the Kentuck Festival of Arts, and a detailed update on the Downtown University Quarter streetscape project. The committee approved all consent items and received a phased cost and planning report for the quarter project.
Any members have had a chance to review. I would entertain a motion to approve. Second. Got a motion and second. All in favor say aye. Aye. Senates are approved. Item number one is approval of a minor public works contract with tri-state abatement for asbestos abatement services at 613 23rd Avenue East. The total is $4,400. Selvin, welcome. Welcome. Good evening, Counselor. Good evening. Thank you all for your attention. This council has approved a residential property at this location for demolition. Upon inspection, we have determined that there is asbestos at this property. So this service contract will provide for the uh appropriate removal and disposal of that asbestos. We have two bidders on this work. Uh we consider the most responsible bidder to be that of Tri-State at the amount noted for $4,400. This is covered in our operations. Question motion. Second. Motion second. All in favor say aye. Aye. Item number one is approved. Item number two. Thank you, Selvin. Is approval of professional service agreement with uh Porter Higginbotham Engineering for Engineering Services on the 36th Avenue East Rainbow Drive Culvert Replacement Project. Totals 49,761 dollars. Zach, welcome. Good afternoon, Council. Good afternoon. You'll remember this as part of the uh drainage presentation. This is one of the short term or get it budget for locations at 36th Avenue East at the intersection of Rainbow Drive. There's basically a C and P pipe your district. It's on the road. And so this is the corrugated metal pipe. The bill or has a failing spot and is deteriorating. Fullet works went out and patched the spot. It's on the edge of the road. It's on the outside edge of the road, but you can see the joint in the pipe there. So this is just going to continue to happen until we replace this pipe. If approved, what's the time frame getting this done? The bid will most likely be in January. Um we have it determined. We're trying to part of this design of this is going to be to minimize the closure on this road as we replace the pipe. So that'll be to be determined, but um should bid January. I would think no more than 30, 45 days for construction. Questions?