Item number one is approval to award a public works contract to civil works for the waterfall roadway drainage improvement project.

0:10

The total is $155,000.

0:12

Mike, welcome.

0:13

Good afternoon.

0:16

Asking to uh move forward with this recommendation.

0:22

If you'll remember this was one of the neighborhood drainage projects that we brought to you a few months ago.

0:28

This one in particular, we had a had budgeted 250,000 for.

0:34

So we're very pleased with the uh the low bid that we've got.

0:38

We received bids from four four different companies.

0:41

Uh and civil works was the lowest responsive bidder.

0:45

Um just a little excerpt uh of the plan set where we're gonna be adding some drainage structures and tying into some existing storm sewer uh in this location.

0:56

But uh very pleased that this came in uh under our anticipated budget.

1:01

That's real good.

1:02

It came in on the budget.

1:03

Yep.

1:03

It's good that'll help us do some other stuff.

1:05

Questions?

1:07

Most when they get ready to start.

1:10

We're gonna wait till after the holidays to start.

1:12

Um did don't want to disrupt this neighborhood during the Thanksgiving and Christmas holidays, so we're planning on having the contractor mobilized shortly after New Year's year.

1:22

All right, and then roughly how long do you think it'll take 30 to 45 days, Max?

1:27

Depending on whether motion is second.

1:30

All in favor say aye.

1:31

Aye.

1:32

Item one is approved.

1:33

Item number two is approval, balancing change order with Taylor Electric for the University Boulevard East Bridge Lighting Project, deductive total of $50,000.

1:42

Zach, welcome.

1:43

Good afternoon, Council.

1:44

Good afternoon.

1:45

Yes, this is a deductive change order for $50,000.

1:49

Um this is the lighting project for the bridge going into Alberta.

1:53

We put in 27 pedestrian style lights and about 1,200 feet of fiber conduit.

1:59

Good thing.

2:00

Motion.

2:01

Motion second, all in favor say aye.

2:03

Aye.

2:04

Item two is approved.

2:05

Item three is approval to award the 2025 CMP lining project to inliner solutions.

2:12

Totals 329,510.

2:15

Zach.

2:16

Yep.

2:16

So this is our uh 2025 CMP lining project.

2:19

We've identified three locations across town to line.

2:24

Let's see.

2:25

First is Fredericksburg, which is in the Academy Drive Subdivision.

2:29

We have a 42-inch CMP pipe that's we've had to patch the road and try to patch the pipe a few times, so this will line that pipe under the road.

2:37

The next is a third is a two 36-inch CMP pipes.

2:42

This is in the Woodland Forest Subdivision on Red Bud Lane, just south of Paul Brant High School.

2:49

And then the last is a 72-inch pipe that's in the build.

2:54

It's on a crossing Bellevue Drive in the Skyland Park subdivision.

2:59

This ties into the Bellevue Drive drainage pipe replacement that we did earlier, so this is gonna align the rest of that pipe segment so we don't have any more failures like that section did.

3:08

Questions.

3:12

Are we waiting a year to be doing a 2025 CMP lining project?

3:15

Or is this one of a succession of projects?

3:18

Uh I think we typically do these once a year.

3:21

Um so this one fell this year.

3:23

We I think last year we did the 2024 when it went into 2025, so this one will go into 2026 during construction.

3:30

But this is it for the year.

3:34

Yes, sir.

3:35

I have no other questions.

3:37

Motion second second, all in favor say aye.

3:40

Aye.

3:40

Item three is approved.

3:41

Item four is approval of a contract award with Dominion construction for the runway and taxiway extension project.

3:47

Total is 18,852,848 dollars and forty cents.

3:53

Jeff, welcome.

3:54

Good afternoon.

3:56

Good afternoon.

3:56

Uh like you said, we're requesting to award the construction contract to the runway 42 to extension and taxiways to Dominion Construction uh construction company in the amount of 18,852,848 dollars and forty cents.

4:12

This project is funded through a grant partnership with the FAA, Al Dot and the City of Tuscaloosa.

4:17

Uh the improvements that were in dot identified in our airport master plan and our critical components of our long-term airfield development program.

4:27

I've got a few slides here, kind of just showing the overview of what's included in the project.

4:31

Our bid results, uh, we had five bids received, uh had a bid advertisement of around 49 days, and our recommended award to Dominion includes local contractors, Dominion themselves, ST Bum, and the TTL is a subcontract subcontractor for us and our resident project management.

4:50

Uh our own field uh representation throughout the projects.

4:55

Project scope uh is 495 days to extend the runway.

5:00

We'll be able to upgrade our electrical vault, relay, relocate the F-A's navigational equipment, realign water vein, install casing for future sewer expansion, and also apply SIL coat for the entire runway length so we don't have to come back in a year or two to do the remaining portion of the runway.

5:17

Our benefits are to extend the runway and the tax base for larger aircraft, improve airfield capacity and operational safety, and this will ultimately drive regional growth and support for future economic development.

5:31

So here's uh the current layout of our runway on the south end of the airport, and then here's the overlay of the extension.

5:39

Yes.

5:42

And then uh the breakout of the funding.

5:43

We started out with a 26 million of federal funding.

5:46

It was 90% federal share at that time, so we went ahead and budgeted the most conservative at 10% of the city share.

5:53

If the state was unable to participate since then, they've modified that to 95% federal.

5:57

The state has participated at two and a half.

6:00

So that will change our uh originally budgeted of three miles three million uh down to six hundred and seventy thousand for this overall project.

6:09

And there on the right, you'll see the kind of the breakout of not just construction but the other professional services that are involved with this scale of the project.

6:18

And then our our timeline for this project there in the grays where we at are today from federal funding authorized to bid opening.

6:24

Our next uh step is project award, is what we're here before you today.

6:29

Uh we have a construction admin work authorization for engineer, and we project construction started in April of 2026 and can construction completion in June of 2027.

6:40

Yeah, what is WA work authorization?

6:46

That's in we'll be coming back to council.

6:51

Uh December 25.

6:54

No, I'm sorry, December 25.

6:56

You're correct.

6:56

That's a top one mining.

6:58

Okay.

6:58

I was thinking fiscal year 26.

7:00

So work authorization coming up next month and then construction in the spring.

7:05

Yeah.

7:06

We hope to be starting before April, just be in the wet months and the amount of dirt work that's involved.

7:12

Uh could start early in April, but that's just our projected timeline.

7:15

And that extension was to 7200 feet.

7:18

Going from 6500 to 76.

7:20

So I love that.

7:21

What can you get on 7200 that you couldn't on 65?

7:24

Uh, we some of the aircraft we operate today, like our team charters, they can't use the full weight load of the aircraft.

7:31

They'll be able to get almost 100% of their weight load, and now we'll be able to go up to a 767.

7:36

And that's more specific to our cargo operations that we're looking down the down the road.

7:42

Okay, it's good.

7:42

And we have representative from both the contractor dominion and our engineer is also here.

7:49

Gentlemen, uh this just my curiosity.

7:53

Is it gonna be hard to get the dirt?

7:55

I mean, we've talked about how much dirt is.

7:58

Yes, sir.

7:59

I mean, Ken Cook's got a bunch of dirt sitting.

8:02

Uh my understanding is that the the source of material they have has already been pulled out of the ground.

8:07

Okay, they simply will just have to transport from their field site to the airport.

8:11

Okay, because that's a lot of dirt.

8:13

You got sir.

8:14

That's good.

8:16

Other questions?

8:17

I just want to say, Jeff, thank you for all your work out in there.

8:19

Yeah, I appreciate it.

8:20

Amazing.

8:21

It's been a lot of hard work.

8:23

Been a lot of hard work.

8:25

I know we have a five-minute conversation here, but these guys have been putting thousands of hours.

8:29

There's been over a hundred people involved up to this step, and uh they deserve a lot of credit for that.

8:34

This is a huge project.

8:37

I entertain a motion.

8:38

Second, motion second.

8:40

All in favor say aye.

8:41

Aye.

8:41

Item four is approved.

8:43

Item five is approval of professional services contract with MIMECASP 365 protect, total not to exceed 67,237 eighty-six for one year.

8:53

Jason, welcome.

8:54

Thanks, sir.

8:55

Good afternoon.

8:56

Good afternoon.

8:56

Uh, this is a uh replacement of an existing products uh that does our uh email spam filtering.

9:05

It's uh our we feel it's a little more functional and a little less expensive than our current platform.

9:13

Questions.

9:18

Is this somebody we've done business with before?

9:20

Uh no, sir.

9:22

So new company.

9:24

Uh we we weren't 100% satisfied with our existing provider.

9:28

We went out and demoed a number of solutions, and this is the one that we landed on.

9:34

Okay.

9:37

Uh, this is from the uh IT uh software maintenance budget.

9:44

I don't have any other questions.

9:45

Got a motion on the table.

9:47

Second second, all in favor say aye.

9:50

Aye.

9:51

Item five is approved.

9:52

Item six, approval professional services contract with target solutions learning.

9:56

DBA vector solutions total not to exceed 44,1876 for one year.

10:00

Uh this is from the uh IT uh software maintenance budget I don't have any other questions got a motion on the table second second all in favor say aye aye item five is approved item six approval professional services contract with target solutions learning DBA vector solutions total not to exceed 4418766 for one year chief doubt well good afternoon council this is a uh a renewal of a training platform that we've been using for a few years this keeps track of our EMT but also our fire training hours so this is reportable for our ISO ratings and also FF FAA any of that training that needs to be done this just keeps track of that but it also allows us to assign some of that training to the individuals within the department questions yeah I'm I you're lost me one more time please all right so this is the platform that that all of our guys can log into the training staff assigns them a platform so whether it's training on company level training it could be on hose deployment could be on a policy that we have they assign them that that that record is there so that way when ISO comes in town and does our checks we can we can quantify the hours that that our guys have trained on and that's on the fire and the EMS side on both of those okay is this is this new utilization of this particular company or no sir this is we've had this a few years uh same same company that we've got this is just a renewal of that.

11:12

Okay motion second motion second all in favor say aye aye item six is approved our next public projects committee meeting will be in two weeks on November the 18th is there any business to be brought before this committee here hearing none I would entertain a motion to adjourn.

11:30

So moved second moved and seconded all in favor say aye aye

Discussion Breakdown — Share of Meeting
Engineering And Infrastructure█████████████████████████████████████████████61%
Economic Development██████████14%
Technology and Innovation███████10%
Water And Wastewater Management██████8%
Procedural█████7%
Summary of Proceedings

City Council Meeting Summary - November 4, 2025

The Tuscaloosa City Council convened on November 4, 2025, to address six primary agenda items, focusing on public works contracts, airport infrastructure improvements, and IT service renewals. All items were discussed with input from departmental staff and unanimously approved by the council. Additionally, minutes from a previous meeting were approved, and the council set the date for the next public projects committee meeting before adjourning.

Consent Calendar

  • Approval of the transcript/minutes from the previous meeting.
  • Approval of the public works contract to award Civil Works $155,000 for the Waterfall Roadway Drainage Improvement Project.
  • Approval of a $50,000 deductive change order with Taylor Electric for the University Boulevard East Bridge Lighting Project.
  • Approval of the 2025 CMP Lining Project contract to Inliner Solutions totaling $329,510.
  • Approval of the runway and taxiway extension contract with Dominion Construction totaling $18,852,848.40.
  • Approval of a professional services contract with Mimecast SPG (noted as MIMECASP 365 Protect) for email spam filtering, not to exceed $67,237.86.
  • Approval of a renewal contract with Target Solutions Learning (DBA Vector Solutions) for training management, not to exceed $44,187.66.

Public Comments & Testimony

  • No public comments or testimony were recorded during this session.

Discussion Items

  • Waterfall Roadway Drainage: Staff presented a low bid from Civil Works ($155,000) against a $250,000 budget for drainage structures and storm sewer tie-ins. The Council expressed satisfaction with the cost savings. Work is scheduled to mobilize after the holidays (post-New Year's) to avoid holiday disruptions, with an estimated duration of 30 to 45 days.
  • University Boulevard Bridge Lighting: A deductive change order of $50,000 was reviewed for the Alberta entrance bridge lighting project, which includes 27 pedestrian lights and 1,200 feet of fiber conduit.
  • CMP Lining Project: Staff identified three locations for the 2025 CMP lining project: Fredericksburg (42-inch pipe in Academy Drive Subdivision), Woodland Forest (two 36-inch pipes on Red Bud Lane), and Skyland Park (72-inch pipe on Bellevue Drive). The project is scheduled for 2026 construction despite the 2025 fiscal year designation. Staff confirmed this is a standard annual occurrence, similar to the 2024 project.
  • Airport Runway Expansion: Staff detailed the $18.85M award to Dominion Construction to extend the runway from 6,500 to 7,200 feet. The project, funded by a 95% federal share and state participation, aims to allow larger aircraft (including Boeing 767s) to operate at full weight capacity. Construction is projected to begin in April 2026 (targeting pre-spring wet months) and conclude in June 2027. Council members inquired about material sourcing, with confirmation that dirt material has already been stockpiled by the contractor.
  • IT Service Contracts:
    • Email Security: Staff introduced a new provider for email spam filtering (replacing an unsatisfactory existing provider), citing improved functionality and lower cost.
    • Training Platform: Staff explained the renewal of Vector Solutions for tracking EMT and fire training hours for ISO ratings and FAA compliance, ensuring accurate quantification of staff training hours.

Key Outcomes

  • Unanimous Approval: All six agenda items were approved by a voice vote ("All in favor, say aye. Aye.").
  • Airport Project Timeline: The runway extension project is authorized for construction to start in April 2026, with an estimated completion in June 2027.
  • Next Meeting: The Public Projects Committee is scheduled to meet in two weeks, on November 18, 2025.
  • Adjournment: The meeting was adjourned with no further business brought forward.

Meeting Transcript

Aye. Aye. Minutes are approved. Item number one is approval to award a public works contract to civil works for the waterfall roadway drainage improvement project. The total is $155,000. Mike, welcome. Good afternoon. Asking to uh move forward with this recommendation. If you'll remember this was one of the neighborhood drainage projects that we brought to you a few months ago. This one in particular, we had a had budgeted 250,000 for. So we're very pleased with the uh the low bid that we've got. We received bids from four four different companies. Uh and civil works was the lowest responsive bidder. Um just a little excerpt uh of the plan set where we're gonna be adding some drainage structures and tying into some existing storm sewer uh in this location. But uh very pleased that this came in uh under our anticipated budget. That's real good. It came in on the budget. Yep. It's good that'll help us do some other stuff. Questions? Most when they get ready to start. We're gonna wait till after the holidays to start. Um did don't want to disrupt this neighborhood during the Thanksgiving and Christmas holidays, so we're planning on having the contractor mobilized shortly after New Year's year. All right, and then roughly how long do you think it'll take 30 to 45 days, Max? Depending on whether motion is second. All in favor say aye. Aye. Item one is approved. Item number two is approval, balancing change order with Taylor Electric for the University Boulevard East Bridge Lighting Project, deductive total of $50,000. Zach, welcome. Good afternoon, Council. Good afternoon. Yes, this is a deductive change order for $50,000. Um this is the lighting project for the bridge going into Alberta. We put in 27 pedestrian style lights and about 1,200 feet of fiber conduit. Good thing. Motion. Motion second, all in favor say aye. Aye. Item two is approved. Item three is approval to award the 2025 CMP lining project to inliner solutions. Totals 329,510. Zach. Yep. So this is our uh 2025 CMP lining project. We've identified three locations across town to line. Let's see. First is Fredericksburg, which is in the Academy Drive Subdivision. We have a 42-inch CMP pipe that's we've had to patch the road and try to patch the pipe a few times, so this will line that pipe under the road. The next is a third is a two 36-inch CMP pipes.

SUMMARIZED BY OPENPUBLICA AI
TRANSCRIPT VIA PUBLIC VIDEO
openpublica.com