City Council Meeting Summary - January 13, 2026
STREAMING COPY IN PREPARATION — RECORDING AVAILABLE FROM THE ORIGINAL SOURCE
City Council Meeting Summary - January 13, 2026
The City Council convened on January 13, 2026, to review and approve seven agenda items, primarily consisting of contract amendments, change orders for infrastructure repairs, and public works contracts. The meeting addressed ongoing engineering services for the Northern Riverwalk Phase 2, various sewer rehabilitation close-outs, facility roof replacements, security enhancements, and an authorization for an airport hangar lease transfer. All presented motions were approved unanimously with no recorded opposition.
Consent Calendar
- Engineering Services Contract Amendment (Item 1): Council approved an amendment with McGifford to finalize engineering services for the Northern Riverwalk Phase 2. The amendment extends services to cover 100% design completion (from 90%) and construction phase engineering, including compaction testing for approximately 1.6 to 7 miles of pavement. Total cost: $518,680.
- Sanitary Sewer Rehab Change Order (Item 2): Council approved Change Order No. 5 with Price Civil for the 2023 sanitary sewer rehab project. This close-out order adds $12,884 to cover remaining funds from the operational account. The contract facilitated 49 work orders last year, approximately 70% proactive and 30% reactive.
- Third Avenue E-Trunk Sewer Repair Change Order (Item 3): Council approved a balance and change order with Suncoast Infrastructure adding $15,390 to the Third Avenue e-trunk sewer repair project. The increase resulted from discovering a 50-foot pipe section requiring replacement (vs. an assumed 10 feet) during a sinkhole inspection. The project is complete.
- City Hall Annex 1 Roof Replacement (Item 4): Council approved a minor public contract with Metal Roofing Solutions ($39,000) to replace the portico roof on the East Annex 1. The original 1989 roof leaking into the two-story entrance below grade will be replaced with a durable TPO thermoplastic membrane system with new framing and copper pellet copings, while retaining the existing granite structure.
- City Hall Annex 2 Re-keying (Item 5): Council approved a minor public work contract with Building Specialty Company ($45,000) using the facility renewal security budget. This project finalizes the re-keying of all City Hall buildings, specifically securing the municipal court building after the main building, Annex 1, and Annex 3 had previously been completed.
- Electric Service Contract Amendment (Item 6): Council approved Amendment No. 1 with Taylor Electric Contractors to increase the "not to exceed" limit from $20,000 to $40,000. This adjustment addresses a staff vacancy and higher-than-normal repair volumes in the first quarter, with current expenditures at $1,900 of the original $2,000 allowance.
- Airport Hangar Lease Authorization (Item 7): Council authorized a lease agreement with High Maintenance Pursuits for a hangar located west of the terminal. The lease involves a change in ownership from the previous tenants (who passed away or left aviation 14 months ago) to the new tenant. The annual lease rate was increased from approximately $1,800 to $2,800 to align with market-based rates approved by the Council, with a term of 10 years and a 5-year option.
Public Comments & Testimony
- No public comments or testimony were recorded during this meeting transcript.
Discussion Items
- Northern Riverwalk Phase 2 Details: Staff clarified that the project connects the end of Phase 1 (Randall only park trailhead) to the northeast end of the McWright's Ferry Road pedestrian bridge. The discussion noted the route largely follows a gravel water and sewer maintenance road and involves a 12-foot wide multi-use path.
- Sewer Repair Assumptions: Discussion highlighted that the $15,390 increase for the Third Avenue project was necessary because 50 feet of pipe required replacement after uncovering, differing from the initial assumption that only 10 feet needed replacement due to a section that could not be inspected.
- Electric Staffing Shortage: Discussion emphasized that the contract increase for Taylor Electric was a proactive measure to cover a vacant staff position and anticipated higher repair volumes over the coming 8.5 months.
Key Outcomes
- Approved Motions: All seven items were approved via unanimous vote ("All in favor" / "Aye").
- Next Steps:
- McGifford to proceed with final design and construction engineering.
- Taylor Electric to continue supplemental electrical repairs under the increased contract limit.
- High Maintenance Pursuits to assume the hangar lease.
- No further discussion held on a motion to dismiss, which was moved but not recorded as a separate vote in the transcript.
Meeting Transcript
Approve agenda item number one approval contract amendment to the engineering service contract with McGifford for the Northern Riverwalk Phase 2 project total $518,680. Mike? Well, not much. It was Mike loves the spotlight. I had to fight until let me take the podium. Um good afternoon, Council. This is as it says here, an amendment to the engineering services contract with McGifford. This should be the final amendment for this contract. This will take uh the support for McGifford all the way through the remaining design and all the way through the construction phase. Uh in the amendment, what we're adding here is the final design service is to go from 90% to 100% for the design, as well as engineering services during construction. So that's observations, making sure the quality that we want from the construction projects being delivered, as well as some testing services during construction. So this is about 1.6 or 7 miles of pavement, making sure that we get the right compaction during the construction phase. That's what this uh amendment is due to provide. Bill, what's the the big pieces of the river walk project? This is phase this is the last 10% of phase two. Is that right? Yes, sir. So the 10% is referring to the execution of the design. So where we're at right now, um the the final design, and I don't mean to mix terminology here between final and 90% 10%. The final design is the changes that were requested when they submitted the preliminary design. So McGifford's working through those, they'll submit to us. We'll make sure everything's 100%. And so that's that 90% to 100%. We're talking about the design portion of the project, and then the project itself. Uh if you recall, about five miles north of here, this is going to connect the end of Northern Riverwalk phase one, which is the Randall only park trailhead portion up to to the northeast, the end of the McRights Ferry Road pedestrian bridge. So the construction project, uh 12 foot wide paved path, multi-use path, uh largely follows the the route of the water and sewer maintenance road. It's a gravel road through that area today, and it'll um extend the end of the northern riverwalk phase one, that gold star at the bottom left to the northeast, the end of the pedestrian bridge from McWright's Ferry Road. Did we not have a second item related to this on the project's agenda as well? There is an item, I believe, on the finance committee related to this, which will be to put the budget in place. There's a WAPR on finance, but yes, sir. I thought that was another one. Okay. I don't have one motion. Second. All in favor. Thank you. Thanks, Blue. Just item number two, approval change order number five with price civil served for 2023 sanitary sewer rehab and repair projects and done $12,884. Yes, sir. Um, so this is the close-out change order for the sanitary sewer rehab and repair contract. So it's this is funded from all from an operational count, uh, water sewer pipe, manhole repair and rehab. Um we had so this is our on-call contract for when we get a call out, we need to fix something. We'll go out there and fix it. We'll also use this to uh make repairs that uh proactively as they become evident through our video inspection through that process. So last year through this contract, we had 49 uh work orders, about 70 percent were proactive, third percent reactive. Um so any questions. Does that run calendar year? Runs calendar year what uh yeah, I'm sorry, fiscal year. Run this year. So after the beginning of October, this 12 and change is what was left over.