OPENPUBLICA · PUBLIC MEETING RECORD
Record of Proceedings

City of Wilmington Design Adjustment Committee Meeting - October 16, 2024

Board of AdjustmentWednesday, October 16, 2024
BodyWilmington, North Carolina
SessionBoard of Adjustment
DateWednesday, October 16, 2024
StatusFILED
Video Record
0:00 / 1:41:53

Transcript — Verbatim
0:02

We're gonna call the meeting of the design adjustment committee to order.

0:07

Um before we get started, I have to read an introduction.

0:11

The design adjustment committee's purpose is to establish clear and measurable review criteria for the consideration of major deviations from the city's technical standards and specifications manual.

0:22

The design adjustment committee does not consider housing type, cost of the proposed unit, occupants, building material, unit size, number of bedrooms, or the architectural design of the structures.

0:33

These hearings are quasi-judicial evidentiary hearings.

0:36

That means it's like a court hearing, and the committee's decisions are constrained by the standards and the ordinance and based upon the facts presented.

0:44

All variance requests require a four-fifths vote of the committee to grant the variants.

0:49

Appeals of committee decisions are to Superior Court.

0:52

The parties of these cases are entitled to an impartial board.

0:55

If a board member has a fixed opinion on the matter, a financial interest in the outcome, a close relationship with an affected person or has had any ex parte communication about the matter.

1:06

Please disclose that information to determine if a recusal is necessary.

1:10

City staff will introduce the proposed project to the committee and committee members may ask questions.

1:15

The applicant may present additional information about the project, and members may ask questions.

1:20

If anyone wishes to provide evidence at today's hearing, witnesses must sign in on the clipboard in the back of the room and be sworn in.

1:28

Because witnesses are to provide sworn testimony.

1:32

Please focus on the facts and the standards, not personal preference or opinion.

1:37

When a witness comes forward to give testimony, please come to the podium, state your name and address for the record and speak clearly.

1:44

With this tongue, staff will if administer the oath for all individuals who intend to provide witness testimony.

1:53

If I could have all staff applicants and any members of the public who wish to speak, please stand up and raise your right hand.

2:01

Do you swear that the testimony you're about to give is the truth, the whole truth, and nothing but the truth?

2:07

Thank you.

2:10

Thank you.

2:10

Our first item of business is approval of the September 18th minutes.

2:18

Has everyone has anyone everyone had a chance to uh take a look at those, and if so, any discussion or Mr.

2:26

Chair, as I was not present for that meeting, I will be abstaining from voting on those minutes.

2:30

Understood.

2:32

Any other comments about the minutes?

2:35

I have no comments, but I'd make a motion to approve.

2:38

I will second that motion.

2:40

All in favor say aye.

2:41

Aye.

2:42

Aye.

2:43

Opposed.

2:45

Thank you.

2:48

All right.

2:50

First item up for business is the Circle K on Market Street.

3:06

Good evening, Mr.

3:07

Chair and members of the committee.

3:08

This is evidentiary hearing number one, located at 4500 Market Street.

3:14

The site includes 1.39 acres and is located within RB Regional Business District.

3:19

The site is currently vacant.

3:21

The proposals for a new convenience store with fuel pumps along Market Street.

3:26

At the September 18th meeting, the applicant requested relief from the standard driveway offset from the intersection and relief from the standard driveway width.

3:34

The request for relief from the standard driveway offset was granted to the applicant.

3:37

The request for relief from the standard driveway width was continued.

3:46

At the September 18th meeting, the applicant proposed a right-in, right-out driveway along South Kerr Avenue with a width of 45 feet.

3:54

The applicant is now proposing a right-in, right-out driveway along South Kerr Avenue with a width of 40 feet.

3:59

The technical standards and specifications manual specifies minimum standards for driveway width.

4:05

A two-lane two-way driveway, which provides access to a commercial use, has a maximum driveway width of 30 feet, measured at the property line.

4:13

The applicant has provided justification for the request on attachment three of your package.

4:18

Just to reiterate to members of the committee and the public, this exhibit is what is currently being proposed by the applicant.

4:26

This exhibit is what was previously proposed at the September 18th meeting.

4:31

This concludes SAF's presentation.

4:33

I'd like my case summary to be entered in the record.

4:35

I'm also happy to answer any questions you may have, and the applicant is here as well.

4:41

Any questions for staff?

4:44

Thank you, Zach.

4:46

Does the applicant wish to speak?

4:55

Good afternoon, Amy Schaefer on behalf of the applicant.

4:57

I want to say thank you all for continuing this to let us take a look at this.

Discussion Breakdown — Share of Meeting
Zoning And Land Use███████████████████████████████████████████43%
Engineering And Infrastructure██████████████████18%
Affordable Housing███████████11%
Flooding██████6%
Procedural█████5%
Public Works█████5%
Parking Management███3%
Water And Wastewater Management███3%
Public Engagement██2%
Summary of Proceedings

City of Wilmington Design Adjustment Committee Meeting - October 16, 2024

The Design Adjustment Committee met on Wednesday, October 16, 2024, at 1:30 p.m., was called to order at 1:32 p.m., and adjourned at 3:14 p.m. The committee approved one set of minutes, two design adjustments under old business, and three requests plus a preliminary plan under new business. All substantive motions passed 5-0; the minutes approval passed 4-0 with one abstention. Note a location discrepancy: the agenda lists Skyline Center, 929 North Front Street, while the minutes state City Council Chambers, 102 N. 3rd St., 2nd floor.

Consent Calendar

  • Approval of the September 18, 2024 meeting minutes passed 4-0. Ms. Painter abstained because she was not present at the September meeting.

Public Comments & Testimony

  • Circle K, 3803 Peachtree Avenue, and Fales Landing: no public speakers appeared.
  • 3990 Independence Blvd.: Malcolm Pharr of 465 Hollins Road, Southgate, expressed concern about existing drainage and flooding in the area. He asked for adequate retention ponds and drainage improvements so the new development would not cause Southgate to flood.

Discussion Items

Old Business: Circle K - Market Street (DAC-2-924)

  • This continued request sought relief from the standard driveway width for a convenience store with fuel pumps on a 1.39-acre vacant site at 4500 Market Street, zoned RB Regional Business.
  • The applicant revised the proposed right-in/right-out driveway on South Kerr Avenue from 45 feet to 40 feet; the city standard maximum width is 30 feet.
  • Applicant representative Amy Schaefer and engineer Jacob Dooley stated that auto-turn modeling showed a narrower driveway would not work for the trucks that need to access the site. Vice-Chair Vielkanowitz questioned whether unused width remained in the turn analysis; Captain Elrod said a narrower driveway could force trucks into adjacent lanes on South Kerr Avenue.
  • The committee approved the 40-foot width 5-0 with a condition that the sidewalk be aligned at the narrowest point of the proposed driveway.

New Business: 3990 Independence Blvd. (DAC-3-1024)

  • The applicant requested three design adjustments for a proposed 580-unit residential development on 60.9 acres, currently zoned MD-17 and IND, with a proposed MD-17 CD rezoning.
  • Adjustments requested: (1) non-standard residential collector street cross sections with variable right-of-way widths of 48, 64, and 77 feet and pavement widths from 22 to 38 feet; (2) private driveway lengths exceeding the 500-foot maximum, with a maximum around 935 feet; and (3) a cul-de-sac length of 1,945 feet versus the 500-foot standard.
  • Applicant Cindee Wolf stated that New Hanover County owns the property and Northwood Raven would be the developer. She said the design matches draft city technical standards, preserves wetlands, provides traffic calming, and uses temporary turnarounds until future street extensions are possible.
  • The committee discussed the lack of road stubs from adjacent projects, wetlands, stormwater pond placement, street tree soil volume, and the proposed 2-foot plaza widths in some sections.
  • Adjustment 1 was approved 5-0 with a condition that the applicant demonstrate to the Technical Review Committee that adequate soil volume is provided for street trees located within the 2-foot-wide plaza. Adjustment 2 was approved 5-0 based on site constraints and good internal circulation. Adjustment 3 was approved 5-0 based on adequate internal connectivity and turnarounds. The preliminary plan was conditionally approved 5-0 with staff-recommended conditions.
  • Note: the minutes contain an apparent typo listing this project at 4500 Market Street; the agenda and testimony consistently state 3990 Independence Blvd.

New Business: 3803 Peachtree Avenue - Midtown Flats (DAC-4-1024)

  • The applicant requested a payment in lieu of open space for a 34-unit multi-dwelling project on a 0.99-acre site zoned MD-17. The required open space is 20% of the lot, or 8,610 square feet; the project proposed 6,350 square feet, leaving a 2,260-square-foot shortage.
  • Based on the New Hanover County tax value of $340,400, the rate is $7.89 per square foot, producing a proposed payment of $17,831.40.
  • Applicant Howard Resnick cited tree preservation, the narrow lot, open-space width restrictions, and parking constraints. He noted the site is close to the Cross City Trail and Empie Park, about one-third of a mile away. Staff confirmed the project provides the minimum parking of 46 spaces and receives a density bonus for affordable housing.
  • Ms. Painter disclosed an email discussion with city staff about whether the payment could be used for Empie Park improvements.
  • The request was approved 5-0 with conditions that the fee be paid prior to final zoning approval and that staff may require an additional payment or reduction at $7.89 per square foot if the plan changes. The transcript also indicates an accepted condition that the funds be used for Empie Park or Cross City Trail connectivity; the adopted minutes list only the first two conditions.

New Business: Fales Landing (DAC-5-1024)

  • The applicant requested relief from minor street improvement standards for roadway improvements adjacent to a 10.09-acre subdivision at 8055 Masonboro Sound Road, zoned R-15.
  • The request concerned Seabreeze Boulevard, a city-maintained gravel road approximately 31 to 40 feet wide. The applicant sought to avoid paving a roughly 400-foot section, instead proposing grading, ABC stone, gravel, and drainage improvements, with no sidewalks, curb, or gutter.
  • Applicant Amy Schaefer said lots 6 and 7 would not access Seabreeze or Benton Avenue due to an agreement with Oyster Bay, and that paving Seabreeze was unnecessary because it has no sidewalks, connections, or redevelopment plans. Committee members debated gravel erosion and runoff concerns versus utility preference for gravel access.
  • The waiver was approved 5-0 with a condition requiring a payment in lieu of sidewalk installation; the Technical Review Committee will calculate the amount based on frontage.

Key Outcomes

  • Approved September 18, 2024 minutes, 4-0, with one abstention.
  • Approved Circle K driveway width adjustment, 5-0, with sidewalk alignment condition.
  • Approved all three 3990 Independence Blvd. adjustments and the preliminary plan, each 5-0, with conditions including street tree soil volume demonstration.
  • Approved Midtown Flats payment in lieu of open space, 5-0, with payment and adjustment-rate conditions plus the additional Empie Park/Cross City Trail use condition reflected in the transcript.
  • Approved Fales Landing minor street waiver, 5-0, with payment in lieu of sidewalk installation.
  • Meeting adjourned at 3:14 p.m.

Meeting Transcript

We're gonna call the meeting of the design adjustment committee to order. Um before we get started, I have to read an introduction. The design adjustment committee's purpose is to establish clear and measurable review criteria for the consideration of major deviations from the city's technical standards and specifications manual. The design adjustment committee does not consider housing type, cost of the proposed unit, occupants, building material, unit size, number of bedrooms, or the architectural design of the structures. These hearings are quasi-judicial evidentiary hearings. That means it's like a court hearing, and the committee's decisions are constrained by the standards and the ordinance and based upon the facts presented. All variance requests require a four-fifths vote of the committee to grant the variants. Appeals of committee decisions are to Superior Court. The parties of these cases are entitled to an impartial board. If a board member has a fixed opinion on the matter, a financial interest in the outcome, a close relationship with an affected person or has had any ex parte communication about the matter. Please disclose that information to determine if a recusal is necessary. City staff will introduce the proposed project to the committee and committee members may ask questions. The applicant may present additional information about the project, and members may ask questions. If anyone wishes to provide evidence at today's hearing, witnesses must sign in on the clipboard in the back of the room and be sworn in. Because witnesses are to provide sworn testimony. Please focus on the facts and the standards, not personal preference or opinion. When a witness comes forward to give testimony, please come to the podium, state your name and address for the record and speak clearly. With this tongue, staff will if administer the oath for all individuals who intend to provide witness testimony. If I could have all staff applicants and any members of the public who wish to speak, please stand up and raise your right hand. Do you swear that the testimony you're about to give is the truth, the whole truth, and nothing but the truth? Thank you. Thank you. Our first item of business is approval of the September 18th minutes. Has everyone has anyone everyone had a chance to uh take a look at those, and if so, any discussion or Mr. Chair, as I was not present for that meeting, I will be abstaining from voting on those minutes. Understood. Any other comments about the minutes? I have no comments, but I'd make a motion to approve. I will second that motion. All in favor say aye. Aye. Aye. Opposed. Thank you. All right. First item up for business is the Circle K on Market Street. Good evening, Mr. Chair and members of the committee. This is evidentiary hearing number one, located at 4500 Market Street. The site includes 1.39 acres and is located within RB Regional Business District. The site is currently vacant. The proposals for a new convenience store with fuel pumps along Market Street. At the September 18th meeting, the applicant requested relief from the standard driveway offset from the intersection and relief from the standard driveway width. The request for relief from the standard driveway offset was granted to the applicant. The request for relief from the standard driveway width was continued. At the September 18th meeting, the applicant proposed a right-in, right-out driveway along South Kerr Avenue with a width of 45 feet. The applicant is now proposing a right-in, right-out driveway along South Kerr Avenue with a width of 40 feet. The technical standards and specifications manual specifies minimum standards for driveway width. A two-lane two-way driveway, which provides access to a commercial use, has a maximum driveway width of 30 feet, measured at the property line. The applicant has provided justification for the request on attachment three of your package.

SUMMARIZED BY OPENPUBLICA AI
TRANSCRIPT VIA PUBLIC VIDEO
openpublica.com