The Wilmington Historic Preservation Commission met in special session on July 7, 2026, to review the proposed Programmatic Agreement for the Cape Fear Memorial Bridge Replacement Project and discuss its potential impacts on historic resources. Planning Director Linda Painter and staff presented the project alternatives, timeline, and draft agreement issues. Commissioners and public speakers raised concerns about the fixed-span alternative, the limited study area, tolling, and the HPC's role. No formal vote was taken; the commission agreed to develop a written recommendation for City Council.
I want to hereby call the meeting to order the special HBC special meeting on July 7th dealing with the Cape Fear Memorial Bridge replacement project and the proposed programmatic agreement. Everyone, please introduce yourself starting on my right. Christopher Yerwell. Ashley Wilson. Stephen Sulkey. Carrie Williams. Beth Redledge. Paul Lawler. Christopher Yermal is our normal chair. He's here, and there's no conflict of why he chose not to be chair today. So as I said before, this is having to do with the uh proposed programmatic agreement for the Cape Verde Memorial Bridge Replacement Project and discuss the potential impacts on historic resources. So we're going to do this meeting a little differently from normal. We're going to take some time that everyone's going to be able to speak if they're here from the public or commissioners for possibly three minutes. We'll limit the amount of time that everyone's going to speak. Okay. Is that clear to everybody? So we'll start with the staff presentation. Linda. And I didn't introduce staff if they'd like to introduce themselves as well. Linda Painter, Director of Planning and Development. Brian Chambers, Assistant Director. Gina Essie, Assistant City Attorney. And Amy's not here. All right. So with that, I'm just going to do a brief presentation and Ben is going to pipe in whenever he needs to because of the two of us, he is the expert on the section 106 process. I am not. So we're here to talk about the proposed replacement of the Cape Fear Memorial Bridge. The timeline that you see on your screen has been provided to us by the Wilmington Metropolitan Planning Organization. They received this, I believe, from NCDOT. So what you'll see by the red star is that the NCDOT and Federal Highway are anticipating that they will complete their environmental assessment of the proposed project sometime in between June and July, at which point they will then have a public comment period on the environmental assessment and a public hearing after which they will select a preferred alternative. So the proposed alternatives under review. Alternative A would be a movable span with 135 feet of vertical clearance when raised. So when I say maintain, please do do not do not take that to mean it's the existing ramps today. It's more the locations of how those ramps are going to interact with our streets. Obviously, all the ramps would be new under both uh under both scenarios. Alternative B would be a fixed span with 135 feet of uh vertical clearance. Uh and one of the main points to realize with this is because you have that higher that higher bridge, you need a longer span. Uh and as a result, uh what we have so far, not having seen the environmental assessment, is that the on and off ramps uh to Wooster and Dawson would shift from third street to Fifth Avenue. So, which would be a major major change from what it is today. Both alternatives would be located to the south of the existing bridge, uh, and would include six uh 12-foot wide travel lanes, median and a multi-use path on the north side of the bridge. So this is a rendering that NC D OT provided of alternative A. So this is the movable span bridge. You can see the ex they've shown the existing bridge for for ease of use to understand where where this bridge will will come. And then this is the plan uh that they have provided that shows the ramp structure uh and where how the how the new ramps will be located, the impacts, as well as how it can again connecting into third street. Alternate B, this is the rendering that NCDOT has provided. This is the 135 foot vertical clearance fixed span bridge. Unfortunately, their rendering leaves off the long longer extended ramps to Fifth Avenue. So it kind of cuts off before you even see Third Street there. But you can see that there is the on off ramp for Front Street would continue to exist. It loops back under.