Chapter 7:
ACTION PROGRAM
The Historic Preservation Element has 66 actions. Implementing all of them will be ambitious and will probably take years to complete.
The City’s "Action Program" for completing the actions is set forth in Table 7-1. The table divides the actions into four priority groups, states the "priority factors" determining the groups and, in a "comments" column, discusses the priority factors further and identifies some of the specific implementation issues to be considered for each action. To facilitate reference, Table 7-2 lists the actions in numerical order showing the priority group for each.
The "Implementing Organization" column identifies City departments or other organizations with primary responsibility for completing each action. The Office of Planning and Building, Comprehensive Planning Division will have overall responsibility for coordinating the Action Program’s completion and for monitoring the progress of other organizations with primary responsibility for implementing specific actions. The Comprehensive Planning Division should be assisted by the Landmarks Preservation Advisory Board and the Board’s staff in performing these functions. The Board should also assist identification of future changes to the Action Program and to the Element itself as the need for changes becomes apparent.
For further discussion of implementation issues, see the text accompanying each action in Chapters 3-6 and in the corresponding chapters of the Technical Report.
The Element’s 66 actions are distributed among the four priority groups as follows:
| Priority Group 1 | 22 |
| Priority Group 2 | 29 |
| Priority Group 3 | 11 |
| Priority Group 4 | 4 |
| TOTAL | 66 |
Within Priority Group 1, three actions (1.1.1, 1.1.3, and 1.2.1) have already been started as part of the Oakland Cultural Heritage Survey and Action 5.1.12 has been started by the City Clerk’s Office. An additional action (3.9.1) will be part of the Oakland General Plan’s Land Use Element and is probably the most ambitious. Eleven Priority Group 1 actions relate to Objective 2 (Preservation Incentives and Regulations) and should be implemented as a package. Two Priority Group 1 actions (5.1.2 and 5.1.3) will probably be very easy to implement.
Within Priority Group 2, some actions are listed together because they relate to the same subject (e.g. Housing Code compliance), have the same implementing organization (e.g OHND or OEDE) or are variations of each other and require special expertise (e.g. design guidelines).
Priority Group 1 includes all actions which are considered to have "windows of opportunity" because of either availability of special funding, significant public or staff support, or linkage opportunities with other projects or studies.
Implementation of the four priority groups will probably overlap: once significant work (but not all work) has been completed on a particular group, work on the next highest priority group will begin. Work on some actions (e.g. Action 3.9.1) may be spread over several years and could overlap all the groups.
Future changes to the priority group assignments may be made by staff, but only after the City Planning Commission and Landmarks Preservation Advisory Board have been given an opportunity to comment on the changes. The Commission could also refer the changes to the City Council for direction. These changes will not require formal amendments to the Historic Preservation Element nor to other Oakland General Plan components.