Astoria City Council Regular Meeting Summary – April 3, 2026
Astoria City Council Regular Meeting Summary – April 3, 2026
The Astoria City Council convened to consider two contract amendments for the Sewage Lift Stations Rehabilitation Project. Both agenda items were approved unanimously by a 5-0 vote. Note: The agenda and minutes provided identify the meeting date as Monday, March 23, 2026, at 6:00 PM; this summary uses the designated meeting date of April 3, 2026, as instructed.
Consent Calendar
- None. No consent calendar was presented at the meeting.
Public Comments & Testimony
- No public comment was offered on either agenda item, and no non-agenda public comment was received, either in chambers or online.
Discussion Items
7.a Early Work Package Contract Amendment with Emery & Sons Construction Group
- Staff, including City Manager Scott Spence and Assistant City Engineer Cindy Moore, presented the Sewage Lift Stations Rehabilitation Project involving Lift Stations 3, 4, and 5 along Marine Drive/Highway 30.
- The project will replace aging Archimedes screw systems and sluice gates originally installed in the 1970s, resurface concrete channels, and modernize control mechanisms and motors.
- Staff emphasized the need for early procurement of long-lead equipment, including screw pumps and sluice gates, to avoid interfering with the construction schedule; equipment delivery was expected around January if approved.
- Staff provided project funding context: two Oregon DEQ grants totaling about $385,000, and a Clean Water State Revolving Fund (CWSRF) loan of up to just over $3.2 million, half of which is forgivable, for a total funding package of nearly $3.6 million. Staff stated costs remained within budget expectations.
- Councilor Adams asked for clarification that the CWSRF funding is still a loan with a forgivable portion, not a full grant. Staff confirmed that the full amount is taken out and half is forgiven before the first payment.
- Councilor Davis identified a discrepancy between figures shown in the presentation and the motion amount. Staff confirmed that the motion amount of $1,199,207.70 was correct and that previously approved pre-construction fees should not be included.
- Councilor Mazzarella expressed appreciation for staff's work and the years of maintenance that kept the existing system operating beyond its expected life.
7.b Contract Amendment with Richwine Environmental
- City Manager Scott Spence requested approval of a $81,520 contract amendment with Richwine Environmental for additional design services.
- The additional scope includes continued design development, preparation of design drawings, and construction support services for the Sewage Lift Stations Rehabilitation Project.
- There were no council questions or public comments on this item.
Key Outcomes
- Motion 7.a: Moved by Councilor Andy Davis, seconded by Councilor Joshua Conklin, to approve the contract amendment with Emery & Sons Construction Group, LLC in the amount of $1,199,207.70 for the Early Work Package for the Sewage Lift Stations Rehabilitation Project. Approved 5-0; voting for: Mayor Sean Fitzpatrick, Councilor Elisabeth Adams, Councilor Andy Davis, Councilor Andrea Mazzarella, and Councilor Joshua Conklin. Voting against: none.
- Motion 7.b: Moved by Councilor Andrea Mazzarella, seconded by Councilor Andy Davis, to approve the contract amendment with Richwine Environmental, Inc. in the amount of $81,520 for the Sewage Lift Stations Rehabilitation Project. Approved 5-0; voting for: Mayor Sean Fitzpatrick, Councilor Elisabeth Adams, Councilor Andy Davis, Councilor Andrea Mazzarella, and Councilor Joshua Conklin. Voting against: none.
- The regular meeting was adjourned at 6:14 PM following no new business and no public comment.
Meeting Transcript
This evening, it's not a regular meeting night. Uh, so we are going to uh start with a roll call. Mr. Spence. Councilor Davis. Here. Council Mozzarella. Here. Counselor Adams. Here. Counselor Conklin. Here. Mayor Fitzpatrick. Sure. Unless there are reports of counselors and I don't see any. Uh there are no changes to the agenda and there is no consent calendar. So we're going to go straight to item 7A, which is consider approving an early work package contract amendment with Emory and Sons Construction Group for the sewage lift stations rehabilitation project. Before I call on our city manager, I will remind people that all agenda items will be open for public comment following deliberation by the city council. And rather than asking for public comment after each agenda item, I ask that audience members raise their hands if they want to speak to the item, and they will be recognized. And in order to respect everyone's time, comments will be limited to three minutes. Mr. Spence, if you could bring us up to date regarding item 7A. Thank you, Mayor and City Council. As you know, we have a planned lift station upgrade rehabilitation for the three lift stations that uh pretty much uh are alongside uh Marine Drive or uh Highway 30. Um there are some long lead times for procurement, especially the Archimedes screw and also the sluice gates, and we need to come to council to make sure that we have enough time to procure those items so it does not interfere with the construction schedule. I'm gonna call on the assistant city engineer Cindy Moore. She has a quick slide presentation so we can see what an Archimedes screw looks like and a sluice gate. All right, Cindy Moore, Assistant City Engineer. Thank you for considering these items today. Next slide. Um there are two items related to the lift stations that you'll be seeing tonight. Um, but first let's just set the stage where we are. Just a reminder. Um, there's an aerial there of Astoria, shows where the wastewater treatment plant is on the east. And so three, four, and five going um east to west along um the highway, as um city manager mentioned there. Um kind of shows where it is with the with five being by the roundabout. Next slide. And then just a few photos again where they're at. Lift station three is by the park medical building, four is across the street from Josephson's smokehouse, and five is by the roundabout. Next slide. Um a reminder what this project is all about with our three lift stations um that are along the interceptor route. We have two Archimedes screw systems that sit within open chutes, um, covered with grates and then concrete slabs at those um locations that you saw. Those were built in the 1970s and they've been operating 24-7 since then. So really grateful to our operations staff that have been keeping those going for so long. Um, as you might imagine, it's time to replace those on the right. You can see an example of an Archimedes screw. Those are not ours. Ours are not very photogenic. So um, but that shows what they look like there. And then um, we're also replacing sluice gates.