0:44Good evening, everyone.
0:46Um, we'll call the meeting to order.
0:49Um, I would like to welcome those in attendance at tonight's meeting.
0:53City Planning Commission is a nine-member commission whose function is to make recommendations to the city commission regarding requests for land use classification changes, subdivision plots, unconditioned conditional use permits, zoning ordinance amendments, and other matters.
1:10The commission makes their recommendation based on the adopted comprehensive plan for the physical development of the city of Brookings and the surrounding area.
1:19As a matter of policy, all motions are made in the positive.
1:23After a motion is moved and seconded, it is open for debate.
1:26Those supporting the motion shall in turn give their reasons.
1:30Those opposing the motion shall then offer their reasons.
1:33After everyone has given a chance to be heard, the commission shall review the testimony and information presented, make finding of facts, and forward their recommendation to the city commission.
1:46Ryan, would you call roll?
1:50Uh roll is noted with all present except uh Heinrich is on via phone.
1:59Is there a motion to approve the tonight's agenda?
2:14Uh next item approval of um last meeting's minutes.
2:20Is there a motion to approve the November 4 2025 minutes?
2:32Um minutes are approved.
2:35Number four, open forum.
2:36At this time, any member of the public may make a brief announcement or imitation or request time on the agenda for an item not listed.
2:46Items to be added to the agenda will be scheduled at the end of the meeting.
2:50Any requested action items may be scheduled for a future meeting date.
2:54Individuals will state their name and a city of residence for the record.
2:59Public comment is limited to a maximum of three minutes per person.
3:03The comments and views expressed by the public are those of speakers and do not necessarily reflect the views or positions of the city of Brookings or City Planning Commission.
3:14Is there anyone that would like to be heard?
3:18Seeing none, moving on, item number five.
3:24Um annexation of block one and mills third edition.
3:35Notices hereby given the access that access holding L C has submitted a petition for annexation of the following described real estate situated in Brookings County, South Dakota, to wit.
3:46Block one of Mills third edition in the Northwest Quarter, excluding H1 and H2 thereof, Section 6, Township 109, range 49.
3:57Ryan, would you introduce the topic?
4:02Access Holdings LLC has submitted a petition for annexation of block one and mills, third edition in the northwest quarter of section six, township one oh nine range 49, excluding lots H1 and H2.
4:16The property is generally located southwest of the 20th Street exit on Interstate 29.
4:21The development review team is supportive of the request.
4:25South Dakota codified law nine-4 describes the annexation process.
4:29The governing body of a municipality upon receipt of a written petition describing the boundaries of any territory contiguous to that municipality sought to be annexed to that municipality, may by resolution include such territory or any part thereof within such municipality.
4:46If the petition is signed by not less than three-fourths of the registered voters and by the owners of not less than three-fourths of the value of the territory sought to be annexed to the municipality.
5:00The single parcel for annexation is 3.1 acres in size and is contiguous to the city limits along the western and southern sides of the property.
5:09The area is located in a phase two annexation priority area, indicating that it is intended for annexation as development reaches the area.
5:19Water services available to the site.
5:20Sewer service is not currently available and will require a lift station.
5:25Access to the parcel will be controlled by the Department of Transportation.
5:28A subsequent rezone to business B2 district will be proposed by the owner.
5:34The area is located in urban high intensity future land use category, which would support the business B2 rezone.
5:40There are no floodplain issues, and that ends staff's presentation and will stand for any questions.
5:51We will now open the public hearing.
5:55Is there oh excuse me?
5:58Is there a motion to approve the annexation?
6:06We will now open public hearing.
6:08Is there anyone here that would like to speak in favor of the annexation?
6:20Seeing none, we'll close the public hearing and open for board comment questions.
6:26Anyone seeing none, uh, we'll call the vote.
7:03Next item on the agenda 5B conditional use permit.
7:08Umtices hereby given that Ostreme Investments LLC has submitted an application for a conditional use permit on the following described real estate in the city of Brookings.
7:28The northeast quarter of the northeast quarter, except H1 and that part east and north of H1, Section 14, Township 109, Range 50, also known as 21625 471st Avenue.
7:46The request is for a concrete asphalt and crushing facility used in the industrial I1 light district.
7:54Ryan, would you introduce the topic, please?
7:59Austrian Investments LLC has applied for a conditional use permit to operate a concrete, asphalt, and rock crushing facility in the industrial I1 light district.
8:09Staff recommends approval.
8:14Concrete, uh asphalt and rock crushing facilities are described in section 94 264.7.
8:23All asphalt and rock crushing facilities shall be located at least 300 feet from any non-industrial or non-agriculture zoned district boundary line.
8:32The crushers and stockpiles of material shall be set back a minimum of 100 feet from the property line and or right-of-way line.
8:40Hours of operations shall be limited to 7 a.m.
8:44Monday through Saturday when a butting agriculture or industrial zone properties, and 8 a.m.
8:50Monday through Friday when a budding property zoned other than agriculture or industrial.
9:08The following shall be provided on an application for a conditional use permit.
9:11A site plan drawn to scale showing the location of buildings, areas of outdoor processing and storage, fences, walls, landscaping, and screening vegetation, and the location of a stream, river, lake, wetland, and major topographical feature within 300 feet of the site.
9:32A dust management plan describing dust emissions sources, their quality, the quantity and composition, and indicating conformance with all applicable applicable air quality regulations, a drainage plan for stormwater management, and runoff indicating conformance with all applicable storm water regulations, a traffic plan describing the number of truck vehicle trips the proposal will generate, and the principal access routes to the facility, including a description of the facility's traffic impact on the surrounding area.
10:07The applicant currently has historically operated a concrete asphalt and rock crushing facility at this location.
10:16The operation has been go has been ongoing uh prior to the adoption of ordinance 2515, which was uh passed by city council just this year, which now requires a conditional use permit for such activities.
10:27So to comply with the updated ordinance, the applicant is seeking a conditional use permit to continue um their historic operations.
10:34The property is zoned industrial I1 light district where concrete asphalt and rock crushing operations are permitted under the conditional use permit.
10:44Uh the applicant did submit um a statement on the traffic and dust control um traffic management will be insignificant as this operation will not generate any extra road traffic.
10:55Uh the access point is on the southeast corner of the property.
11:00It's the current access point that the contractor shop yard already uses.
11:06That will be the the uh access point for the crushing facility as well.
11:10Uh dust control will consist of keeping all surrounding crushing areas moist and therefore minimizing dust emissions.
11:16If weather becomes a factor and the operators are unable to control dust from traveling to neighboring dwellings, they will postpone the operation until more favorable weather day.
11:26And that ends the staff report, and we would stand for any questions.
11:36Is there a motion to approve the conditional use permit?
11:47Uh motion has been moved and seconded.
11:49We'll now um open up the public hearing.
11:54Is there anyone here that would like to speak in favor of the matter?
12:03I guess that's my cue.
12:06I'm Andrew Ostrine, owner of Austrian excavating Austrian investments, whatever we want to call ourselves today.
12:13Um basically, as Ryan pointed out, it I just kind of got caught in a crossfire of a new city city ordinance.
12:21Um we're not doing anything different than we have been uh business as usual, as we have been for the last almost five years at that site, and uh basically just trying to comply with the ever changing uh dynamics, I guess.
12:35So if there's any questions, I have a quick question since you're up here.
12:41Um I think you already answered half of it, so you didn't have to change operations at all because of the ordinance.
12:47We haven't uh haven't yet.
12:50Uh so the crutching operation happens once a year, probably.
12:55We stockpile the rubble.
12:57Yeah, that was my second question.
12:59Pressure comes in, he works for week, you know, and he leaves.
13:03So it's uh it's not really uh it's not like it's an everyday thing or anything.
13:10Thank you very much.
13:12Uh I have a quick question too while you're up here.
13:15Um, how many vehicles would you say I and I know it's it's not any different than what's going on right now, but how many vehicles would you say come in maybe per week related to the concrete crushing?
13:26So crushing itself is a couple pieces of machinery coming and then leaving.
13:31Um as far as that you know, stockpiling the rubble, crushing it.
13:37It all depends on you know what's going on in around town, what kind of jobs we get, what kind of I mean, this isn't just stuff we generate either, it's other people as well.
13:47But uh it all depends.
13:49Um, the reality of it is we either bring rubble in and crush it and haul it back out as crushed concrete, or we haul gravel in, stockpile, and haul back out as gravel.
13:59Um same number of trucks no matter what.
14:04I mean, you might have 10 trucks a day.
14:07That I mean could be 30.
14:09It I mean it's all there's days that there probably isn't any uh just kind of I don't know, I'd have to get out there with a clicker and count at the driveway, I guess.
14:29Is there anyone else that would like to speak in favor of the this matter?
14:36I come up front, state your name, please.
14:45I live at Porter's Bait Farm, just on the east side.
14:48And I guess I'm not in favor or not in favor.
14:51I just have a couple questions about how this works.
14:55Uh I've lived there my whole life at Porter's Bait Farm.
15:00So when you talk about the historically being there, um, this is not historical.
15:04This is like a within three to five years, I would say.
15:08And my question or issue is when they crush this, it's usually a seven to ten day window.
15:18And when the wind blows out of the west or northwest, all the dust goes directly to my residence, my family's residence.
15:29There's three of us that live there.
15:31Um that coincides with there is more than 10 trucks per day, um, knowing that I live there and there is increased um traffic volume when he is doing the crushing.
15:48I'm all in favor of the man making a living.
15:51I'm okay with that 100%, but is there some way to when the wind is out of the west northwest for them not you know to put the neighbor into consideration?
16:04That's my question to you guys.
16:07Um a stipulation in there as far as that goes.
16:11So that's that's really all I have.
16:15Any questions from you guys?
16:17I'd like to I can answer them.
16:25Brian, would you want to address that?
16:28I would just state uh going back to the application and the staff report, it does indicate on their dust uh control plan that if weather factors be if weather becomes a factor and the operators are unable to control dust from traveling to neighboring dwellings, they will postpone the operation until a more favorable weather daily.
16:45That was their plan according to the application, so they would be it would be tied to that uh as their being their dust control plan who adjudicates that or who determines that the off-drime or the neighbors it would be up to the operator to determine.
17:07That's it, that's all I have.
17:14Ryan, and then a follow-up to that statement.
17:19How would Alstram then communicate that or make that determination for the neighbors there's no requirements to um communicate or to uh notify of when the operations are or are not taking place?
17:40I think the um the owner would have to notify their their crushers, obviously, if they're bringing people in from another location to come in and crush, if the weather's not favorable that day, they would have to notify their their crusher to not come and crush.
17:54Uh but there's no requirement to notify neighbors of when or when they will not take place.
18:06Uh uh what recourse do the neighbors have if there's dust issues with the city.
18:13Do they go to the can you hold that?
18:17I think there was another gentleman since we are at still in the public meeting.
18:20I think there was another gentleman that would like to speak.
18:23Yes, my name is Dennis Walping, and I live kitty corner from the site, and Andrew's been a good neighbor, don't get me wrong.
18:31My only concern is some of the dust control, and of course the noise, but the dust control would be the main thing, and the amount of trucks entering that curve on the highway with the speed limit.
18:44And this was not part of Ostram's deal, but as they come down that highway, head off onto that gravel road, they're not obeying the speed limits at all.
18:55That's not Andrew's people necessarily, but in general.
19:00But my concern with Andrew would be the dust control and the noise why they're crushing.
19:05And the amount of trucks that have to that maybe he could seal that duster on the driveways mainly.
19:14Where the trucks are entering.
19:15And I don't know if it's a safety issue on that entering right in that curve.
19:20There's a lot of trucks going down there.
19:28With the truck driving out and the speed on that highway.
19:31Come and get to that curve.
19:33Andrew's been a great neighbor.
19:35I really like what he's done there.
19:37But there are just some issues that I would like to bring your attention.
19:41Mainly being traffic flow, dust control, and a little bit of noise.
19:45The noise, if it's only a certain window, I was under the end.
19:50I'll just add it was gonna be continuous.
19:53You know, he's gonna expand this and just keep crushing all the time.
19:57Well, that don't sound like the deal.
20:00So I'm not totally against it.
20:01But I concern it's the safety and the dust control.
20:08Appreciate your comments.
20:13Andrew, do you have anything to add or we'll close the public hearing?
20:16And if you would please come up.
20:18I was gonna ask Andrew, can you kind of explain how the crushing operation functions and the spray that they have available to moisten the material?
20:30So yeah, so cover that first, I guess.
20:33Um so that the the equipment does have a way to add water to it as it as it crushes.
20:40Um I know the the contract I've used previously didn't really like to use it, but we have several times, depending on you know if it was creating dust or which way the wind was blowing, things like that.
20:53Um he has since gotten out of the business, so he won't be coming back.
20:56When I find the new contractor, we'll see what you know what they've been doing, but they I mean that's what they do.
21:03They they crush concrete.
21:04That's I'm assuming that they have the uh ability to do the same thing.
21:10Um I obviously will have to be more on top of it and manage that as well, make sure that uh it's not blown towards the neighbors.
21:18Um as far as the putting some of the stuff.
21:20Denny was talking about with the trucks and stuff.
21:22Um that isn't what this is about.
21:26This is about crushing the concrete.
21:28Uh the truck traffic and that is irrelevant basically to this.
21:34If you you know follow what I'm saying there, we have trucks coming in out, that's what's what we do.
21:39Um so what what we're voting on today isn't uh doesn't have to do with trucks.
21:56Um can you did you ask did you get your question answered there?
22:00Or yeah, I I think so.
22:02I mean there's kind of best practices when there's winds at a certain speed, which in South Dakota there's very few days that the wind isn't blowing.
22:14Um, but when you get up into those higher, it's just not recommended to crush those days.
22:20Um and if you are crushing, you would you know definitely need to um utilize you know water kind of spray the material so it keeps the dust from you know filtering off site.
22:33Uh then there are times where occasionally you have your stockpile of materials and you may need to water them down at times so that the tops of them don't start uh getting caught in the wind and blowing off site too.
22:47So they moisture is a a good way to kind of help hold that material down.
22:53Um, with this operation, the the traffic impact is very minimal because it's a contractor's shop and they have a uh fair amount of truck traffic as is the material that is coming into the site, it comes in various times throughout the year, depending on what types of construction projects are occurring, and they're taking that spent material, they're bringing it out and stockpiling it.
23:24For example, for um Berkings Municipal Utilities, they typically bring a crusher in about once every three years.
23:31So when they have water main brakes or something, they have to dig up asphalt or concrete.
23:37Um they haul it out to their site and stockpile it until they have enough material that it justifies bringing in a crusher.
23:45So it's it's accumulation, probably in Australia's uh um scenario where it's maybe throughout the year, or there's other places that are maybe they don't have as much volume, and so it may take them three to five years to stockpile enough material to justify bringing in a crusher for you know a few days or or or a week.
24:08So it's not like it's these are always everyday type um traffic impacts where the materials coming coming into the site.
24:19Uh it's typically stockpiled until you have a sufficient amount that it justifies bringing in a crusher for a week to ten days, and then the material goes out as it's needed for particular job sites.
24:46Uh we will now close public hearing and open for board questions and comments.
24:55So yeah, back to the previous question.
25:01I'm not I'm not I'm not saying I'm opposed to this.
25:05I just want to know like what recourse do the neighbors have if there is a dust problem.
25:11Well, they'd have the you know, if they feel it's it's a sufficient, they could certainly call the city and we could send somebody out there, and if it's uh violation, then we could shut down the operation, or we could have them make adjustments to their crushing activities to do a better job of controlling the dust.
25:45Um yeah, so I've been trying to look online to see if there's any specific like EPA regulations or anything like that.
25:52And the closest thing I found thus far is OSHA has some things that's more necessarily for like workers' rights and things like that, but is there maybe something of of making sure that there's an OSHA certified representative or some other thing to be able to make a measurable um determination of like what is the actual amount of dust being produced, what is an acceptable amount, things like that, something that is actually like actionable if it does become a problem.
26:21So when we dealt with this issue a year, year and a half ago, it was a different location.
26:29Um the state was called, they sent a inspector out.
26:35Um the state does have I think some permitting requirements.
26:41Um it all depends on whether or not they're testing that particular day.
26:47Um it's really we're not gonna get into regulations that we can enforce, and so it's that's why we put the catch all in there that any necessary state or federal um permitting that they would need to go through.
27:06I believe in this particular case they are permitted through the state of South Dakota.
27:11They have to get a permit.
27:12So if they have specific requirements to maintain that permitting or that licensure, that would be a state requirement.
27:34Seeing no other comments, we will call the vote.
28:05Um last item on the agenda is a five C election of officers for 2026.
28:13Um does the nomineating committee have their recommendations for chair and vice chair.
28:22Chair, the nominated committee um submits the following nominations for leadership positions for the upcoming term for chair Jacob Limmer for Vice Chair Nick Schmeichel.
28:34Uh the nominated nominees have been contacted beforehand.
28:38My understanding is that they have expressed interest in serving in those roles.
28:49Chair, I move nomination cease.
29:03Yeah, nomination cease.
29:06I'll second that if needed.
29:20Uh nominations are so moved.
29:26Um seeing no other items, uh, sir, call for adjourn.
29:39Just like to remind everyone tomorrow evening is the mayor's holiday party out of the Dakota Bank Center.
29:45You're welcome to attend.