0:07

Good evening.

0:08

Welcome to the May 12th Brunswick Planning Board meeting.

0:12

I'll introduce members of the board here on my far right, Kelly Matson next to Kelly, Rob Burgess, Planning Board Vice Chair.

0:21

Next to Rob Steve Walker, next to Steve, Chris Baldwin.

0:29

Laura may be joining us.

0:30

I'm not positive.

0:33

On my near left, Alison Harris, next to Alison, Julie Erdman, Director of Planning and Development, and next to Julie, Matthew James, our land use planner.

0:45

We have four projects before us tonight.

0:57

Wilbur Woods, we have a public hearing for a site plan amendment.

1:03

The Vaughn Shack wall replacement replacing a crib wall with riprap.

1:11

And 117 Bath Road Motor Vehicles Fueling Station.

1:20

With that, Matt, would you introduce Thomas Point?

1:24

First up, we have case number 2614, Thomas Point Campground Phase 3.

1:30

The planning board will review and act upon a major development review sketch plan application submitted by SFC Engineering Partnership Inc.

1:38

on behalf of Thomas Point RV LLC for the relocation of 33 campsites outside of the 125 foot shoreland protection overlay setback area.

1:49

Electricity, private sewer, and water will be extended to each of the proposed gravel campsites.

1:54

And the subject property is located on 29 Meadow Road, Map 43 Lot 3A, and within the Rural Protection 1 or RP1 zone, the Shoreline Protection Overlay or SPO subdistrict, the Rural Protection Stormwater Management Overlay or RPSMO subdistrict, the Shoreland Protection Overlay, Stream Protection or SPO SP subdistrict, and the Shoreland Protection Overlay Resource Protection or SPORP subdistrict.

2:23

Thank you, Matt.

2:24

And before I ask you to come up, Tara, Laura Hatmakers joined us.

2:30

And now Tarlac Aquilina, it's your show.

2:40

Good evening, Chairman, members of the board.

2:42

It's good to see you all again.

2:44

My name is Tara Aquilina.

2:46

I'm a civil engineer with SFC Engineering representing Thomas Point RV LLC, and here with me tonight, Brian Lund.

2:53

I'm presenting our sketch plan application for phase three at 29 Meadow Road, map 43 lot 3A.

3:01

The property fronts on Meadow Road in the Butts Thomas Bay, about 78 acres of land.

3:07

The property has been occupied by an existing campground since the 1950s.

3:12

The campground recently received both town and state approval for phase one and two, which includes upgrades to 91 campsites, which are currently under construction.

3:22

Moyes Environmental Services had completed a natural resource delineation of the property, identifying a stream and a coastal wetland.

3:30

The stream is subject to a 75-foot buffer while the coastal wetland is subject to 125-foot buffer.

3:37

The property is served by a private transient non-community public water system with two wells.

3:42

Both wells were tested in August of 2025, which demonstrated the existing wells provide sufficient yield to meet the campground's design demand and have no adverse effects on the abutters wells.

3:56

The engineer septic system serves the campground.

4:00

It has been designed to have capacity for all three phases.

5:00

The goal is to remain below three acres of impervious, which is main site law threshold.

5:05

The sketch plan you each have shows stormwater management areas, which we propose bioretention areas to treat runoff and attenuate flow, peak flow.

5:15

We are also looking into implementing forested and meadow buffers for our stormwater features.

5:23

We have water distribution system to serve the campsites and connect to the existing uh private transient non-community public water supply well.

5:32

They'll be new underground electric brought to each site, and the septic collection system will connect each site and flow to the septic tanks for treatment.

5:41

In response to the staff review comments from last month, the campground will have no proposed remote road names in emergency.

5:49

The appropriate address will be 29 Meadow Road and then the site number.

5:52

We've added to the phase three sketch plan site numbers to each also a trip generation and erosion control plan will be included in the final development plan.

6:02

And the stormwater BMPs will be sized and designed as a part of the final development review application with the goal of locating the BMPs outside of the 125 shoreline coastal buffer where it's feasible.

6:14

So that concludes my presentation for the phase three sketch plan for Thomas Point campground at 29 Meadow Road.

6:22

This proposed plan brings the campground up to current standards in my moving all the sites out of the 125 shoreline coastal buffer and complies with all applicable zoning and design requirements.

6:33

And I am happy to answer any questions you all may have.

6:36

Okay.

6:37

Thank you, Tara.

6:38

Um I'd like a motion before we come to the board that the staff review committee concurs or that the planning board concurs with staff's conclusion that the basic sketch plan major development review application materials have been submitted and that the application is complete such that the committee, the board may proceed with substantive review of the application and identification of any further information required from the applicant.

7:06

Motion by Chris, second by Laura.

7:09

All those in favor, that's unanimous of the board.

7:15

Okay.

7:16

All right.

7:17

Who would like that?

7:18

Laura, would you like to start?

7:20

Uh sure.

7:22

Um I just concur that moving stormwater outside of that to 125-foot buffer would be preferable, as was up stated by staff.

7:31

Um this is I'm glad that you all did the well testing.

7:36

I just had a slight question just because we've been having a lot of drought recently.

7:42

Um is there anything that's going to be set in place during operations that's going to help monitor wells?

Discussion Breakdown — Share of Meeting
Engineering And Infrastructure█████████████████████████████████████████████50%
Zoning Regulations████████████████18%
Environmental Protection████████████13%
Affordable Housing█████████10%
Procedural█████5%
Fiscal Sustainability███3%
Public Engagement1%
Summary of Proceedings

Brunswick Planning Board Meeting – May 12, 2026

The Brunswick Planning Board met on May 12, 2026, at 4:00 PM (ET) to review four major development applications: a sketch plan for Thomas Point Campground Phase 3, a site plan amendment for Wilbur's Woods 2, a sketch and final plan for the Von Shack wall replacement, and a sketch plan for a new motor vehicle fueling station at 117 Bath Road. The board approved all applications with conditions.

Thomas Point Campground Phase 3 (Case 2614) – Sketch Plan Approval

  • Applicant: Tara Aquilina (SFC Engineering) on behalf of Thomas Point RV LLC. The project relocates 33 campsites outside the 125-foot shoreland protection overlay, with new electric, water, and septic connections. The property is at 29 Meadow Road (Map 43 Lot 3A) in the RP1 zone with multiple overlays.
  • Key Discussion: Board members discussed well monitoring (two wells tested in August 2025 demonstrated sufficient yield; backup well provides larger flow), stormwater bioretention placement outside the 125-foot coastal buffer, and septic pumping to the existing field. Steve Walker raised concerns about setback mapping: the 125-foot coastal wetland buffer on the southwest corner appeared artificially snapped across a salt marsh, and the central wetland may be tidal and subject to a 125-foot setback rather than a stream setback. He advised field verification of high tide lines and proper buffer delineation.
  • Public Comment: Jim Cruzania asked where stormwater leaves the site (into the bay) and urged backup systems for sewer pumping during peak season.
  • Outcome: The board unanimously approved the sketch plan application, allowing the applicant to proceed to final development review.

Wilbur's Woods 2 (Case 2615) – Site Plan Amendment Approval

  • Applicant: Chris Marshall and Nate Green (Green Mars) on behalf of Wilbur's Woods LLC. The amendment modifies the exterior design of an 18-unit 100% income-restricted multifamily building (9 units at 80% AMI, 9 at 100% AMI) approved in 2024. Changes include removal of a rear dormer (reducing windows for the abutter), revised window layout due to floor plans, and an ADA accessible rear pathway.
  • Key Discussion: Board members discussed buffering (fence agreed upon after neighbor concerns), architectural design (belly band with contrasting color, black trim windows, varying clapboard widths to break up massing). Staff confirmed that the 170-foot building length does not trigger architectural compatibility standards for breaks in massing (those apply only to GM and GI districts). The board noted that the affordability narrative had been submitted per a prior condition, though the program changed from 100% MHA to a split 80/100% to meet town requirements without MHA financing.
  • Public Comment: John Eldridge (online) raised concerns about financial capacity (a $570,000 gap between project budget and Bath Savings letter), prior condition 5.2.9E (affordability narrative before building permit), and architectural compatibility (massing of the 170-foot roofline; no break every 100 feet). Staff responded that a revised financial capacity letter was received that afternoon, the affordability narrative was in the file, and the break requirement did not apply.
  • Outcome: The board unanimously approved the amendment with conditions: (1) update HOA covenants for snow removal around fire hydrants, (2) add fences to site plan, (3) select contrasting color for the belly band, all satisfactory to the Planning Director.

Von Shack Wall Replacement (Case 2617) – Sketch and Final Plan Approval

  • Applicant: Tim Forrester (Flycatcher LLC) on behalf of the Von Shack revocable trust. The project replaces a failing two-tier timber retaining wall (about 8 feet tall) with riprap sloped retaining wall at 11 Monumental Lane (Map MP1 Lot 10). The site is in RP1 zone with multiple shoreland overlays. The project has DEP and Corps of Engineers approval.
  • Key Discussion: Board members discussed alternatives (living shoreline not feasible due to ledge and wave velocity), stone sizing (toe stones approximately 5 feet in diameter, blasted quarry stone), filter fabric quality, removal of dead men timbers, and vegetation buffer (existing buffer exceeds 10 feet; supplemental planting may not be needed). Kelly noted that Maine Geological Survey and Maine Inland Fisheries and Wildlife provided comments; no MNAP comments were received. Chris asked about erosion potential and was satisfied the wall is proactive, not reactive. The board requested adding riprap size and filter fabric specifications to drawings.
  • Public Comment: None.
  • Outcome: The board unanimously approved the application with conditions: (1) provide evidence of financial capacity prior to building permit, (2) obtain Shoreline Protection Overlay permit from Code Enforcement Officer, (3) add note identifying riprap stone size on site plan, (4) add note identifying filter fabric specifications. The applicant estimated project cost at $278,000.

117 Bath Road Motor Vehicle Fueling Station (Case 2618) – Sketch Plan Approval

  • Applicant: Joe Mardin (Site Lines PA) on behalf of Lunar Development LLC. The project demolishes an existing self-service car wash and constructs a motor vehicle fueling station with three fuel islands (six fueling positions), two payment kiosks, no staff, and 24-hour operation. The property is at 117 Bath Road (Map CC1 Lot 6) in the GM4 zoning district and Cook's Corner Overlay.
  • Key Discussion: Board members raised significant concerns about: (1) a natural drainage swale on site believed to be a stream—Steve Walker and Laura argued it is a stream, not just a drainage way, and should be buffered; (2) stormwater and spill containment—catch basins with separators and oil-water separators were suggested to prevent gasoline and fire retardant from reaching the Androscoggin; (3) fire suppression—automated system with call button to 24/7 staff; (4) traffic impact—a traffic study is needed, and left turns out will not be possible due to median; (5) unattended operation—vandalism and spill response concerns; (6) alignment with Cook's Corner Master Plan—Robert questioned whether a gas station furthers the walkable village vision. Staff noted that the DEP threshold for stormwater is not triggered due to minor impervious increase. The applicant committed to a wetland delineation and comprehensive traffic study.
  • Public Comment: Jim Cruzania asked which comprehensive plan was referenced; staff confirmed the adopted one.
  • Outcome: The board unanimously approved the sketch plan, allowing the applicant to proceed to final development review with substantial work on traffic, stream determination, spill containment, and design standards.

Key Outcomes

  • Thomas Point Phase 3: Sketch plan approved unanimously; proceed to final plan.
  • Wilbur's Woods 2: Site plan amendment approved unanimously with four conditions.
  • Von Shack Wall: Sketch and final plan approved unanimously with four conditions, including financial capacity and design specifications.
  • 117 Bath Road Fueling Station: Sketch plan approved unanimously; final review will require detailed traffic study, wetland delineation, stormwater/spill plans, and compliance with Cook's Corner standards.

Meeting Transcript

Good evening. Welcome to the May 12th Brunswick Planning Board meeting. I'll introduce members of the board here on my far right, Kelly Matson next to Kelly, Rob Burgess, Planning Board Vice Chair. Next to Rob Steve Walker, next to Steve, Chris Baldwin. Laura may be joining us. I'm not positive. On my near left, Alison Harris, next to Alison, Julie Erdman, Director of Planning and Development, and next to Julie, Matthew James, our land use planner. We have four projects before us tonight. Wilbur Woods, we have a public hearing for a site plan amendment. The Vaughn Shack wall replacement replacing a crib wall with riprap. And 117 Bath Road Motor Vehicles Fueling Station. With that, Matt, would you introduce Thomas Point? First up, we have case number 2614, Thomas Point Campground Phase 3. The planning board will review and act upon a major development review sketch plan application submitted by SFC Engineering Partnership Inc. on behalf of Thomas Point RV LLC for the relocation of 33 campsites outside of the 125 foot shoreland protection overlay setback area. Electricity, private sewer, and water will be extended to each of the proposed gravel campsites. And the subject property is located on 29 Meadow Road, Map 43 Lot 3A, and within the Rural Protection 1 or RP1 zone, the Shoreline Protection Overlay or SPO subdistrict, the Rural Protection Stormwater Management Overlay or RPSMO subdistrict, the Shoreland Protection Overlay, Stream Protection or SPO SP subdistrict, and the Shoreland Protection Overlay Resource Protection or SPORP subdistrict. Thank you, Matt. And before I ask you to come up, Tara, Laura Hatmakers joined us. And now Tarlac Aquilina, it's your show. Good evening, Chairman, members of the board. It's good to see you all again. My name is Tara Aquilina. I'm a civil engineer with SFC Engineering representing Thomas Point RV LLC, and here with me tonight, Brian Lund. I'm presenting our sketch plan application for phase three at 29 Meadow Road, map 43 lot 3A. The property fronts on Meadow Road in the Butts Thomas Bay, about 78 acres of land. The property has been occupied by an existing campground since the 1950s. The campground recently received both town and state approval for phase one and two, which includes upgrades to 91 campsites, which are currently under construction. Moyes Environmental Services had completed a natural resource delineation of the property, identifying a stream and a coastal wetland. The stream is subject to a 75-foot buffer while the coastal wetland is subject to 125-foot buffer. The property is served by a private transient non-community public water system with two wells. Both wells were tested in August of 2025, which demonstrated the existing wells provide sufficient yield to meet the campground's design demand and have no adverse effects on the abutters wells. The engineer septic system serves the campground. It has been designed to have capacity for all three phases. The goal is to remain below three acres of impervious, which is main site law threshold. The sketch plan you each have shows stormwater management areas, which we propose bioretention areas to treat runoff and attenuate flow, peak flow. We are also looking into implementing forested and meadow buffers for our stormwater features. We have water distribution system to serve the campsites and connect to the existing uh private transient non-community public water supply well. They'll be new underground electric brought to each site, and the septic collection system will connect each site and flow to the septic tanks for treatment. In response to the staff review comments from last month, the campground will have no proposed remote road names in emergency. The appropriate address will be 29 Meadow Road and then the site number. We've added to the phase three sketch plan site numbers to each also a trip generation and erosion control plan will be included in the final development plan. And the stormwater BMPs will be sized and designed as a part of the final development review application with the goal of locating the BMPs outside of the 125 shoreline coastal buffer where it's feasible. So that concludes my presentation for the phase three sketch plan for Thomas Point campground at 29 Meadow Road. This proposed plan brings the campground up to current standards in my moving all the sites out of the 125 shoreline coastal buffer and complies with all applicable zoning and design requirements. And I am happy to answer any questions you all may have. Okay. Thank you, Tara. Um I'd like a motion before we come to the board that the staff review committee concurs or that the planning board concurs with staff's conclusion that the basic sketch plan major development review application materials have been submitted and that the application is complete such that the committee, the board may proceed with substantive review of the application and identification of any further information required from the applicant. Motion by Chris, second by Laura.