Bullhead Area Transit System Commission Meeting Summary - May 5, 2025
Bullhead Area Transit System Commission Meeting - May 5, 2025
The Bullhead Area Transit System Commission met on May 5, 2025. All members were present except Olivia Hendrickson, and Commissioner Cindy Frizel participated by telephone. The meeting included a design presentation for the proposed Bullhead Area Multimodal Transit Facility, public comment, approval of prior minutes, and staff reports on transit grants and operations.
Consent Calendar
- The commission unanimously approved the minutes of the February 3, 2025 commission meeting by voice vote after a motion and second.
Presentation: Proposed Multimodal Transit Facility
- Rob Sampson of Salberg Associates, joined by associate Barisa Barraza, presented construction documents for the new multimodal transit facility on Lomus Way, located east and north of the current meeting site.
- The proposed site plan includes five bus pull-in areas in a sawtooth configuration, a terminal building, a maintenance building, employee and public parking, park-and-ride spaces, bicycle parking, and the ability to add electric vehicle charging later. Renderings show covered parking; solar panels are not in the current plans but could be added later.
- The terminal building is 4,200 square feet and includes a 560-square-foot air-conditioned lobby, ticketing and dispatch areas, management offices, unisex restrooms with an adult changing station, a secure training room, and a private bus driver lounge.
- The maintenance building has a 5,100-square-foot footprint excluding mezzanine storage. It includes three general service bays, a wash bay, oil and sand interceptors, eight portable lifts that can raise two buses at once, locker rooms, unisex showers, and mezzanine storage for tires and parts.
- The design is meant to give Bullhead Area Transit a single identity, match city building themes, and allow intermodal connections. Greyhound does not currently serve the city, but one end bay could accommodate a Greyhound or similar large bus.
- Designers chose not to shade the bus stops closest to the terminal building to encourage riders to use the lobby and to preserve the building’s iconic appearance. City Manager Cotter had raised shade as an issue, and the design team said they reached a consensus on the approach. One commissioner praised the design as beautiful and said they were excited for it, while another commissioner questioned the practicality of unshaded, hot benches in summer.
Public Comments & Testimony
- Scotty from Bullhead opposed the unisex bathroom plan, saying there are only male and female, and asked whether it would cost more and whether electric vehicle charging sites would be included.
- Scotty expressed support for portable lifts instead of underground pits, based on his school board experience, and suggested the city investigate lift types when bidding.
- Scotty said artificial intelligence is coming and that he did not see provision for it in the plans, suggesting some spaces may go unused.
- Scotty emphasized the need for shade, especially for elderly riders waiting during wheelchair boarding, and noted that his own bus stop had been removed and he now has no place to sit except the curb.
Department Reports & Discussion
- Mr. Peluso reported that the 5311 grant is being wrapped up: ADOT had delays, FTA extended processing, the August reimbursement was accepted, and the final reimbursement submission was planned for the next day. A final 5311 recap is expected at the August commission meeting, and a new FTA apportionment grant period is expected to begin in October.
- First-quarter ridership is trending as expected, with an uptick in March continuing through late May and early June, leveling off in summer, increasing in fall, and dropping in winter.
- The senior van has had no rides since late December because it is operated 100% by volunteers and only two volunteers were available, both with medical issues. Staff is advertising for volunteer drivers through Bullhead City Human Resources and hopes to restore service in the summer.
- No passenger complaints were received in the last quarter.
- For the 5307 program, staff is preparing the application and taking an updated Title VI plan to City Council the next day. Because Bullhead Transit is no longer an ADOT sub-recipient, it must adopt its own Title VI plan; staff hoped to complete needed steps by late June or early July.
- Staff and the Bullhead City MPO were awarded a $250,000 5305E planning grant for a new short-range transit plan. The grant covers about 93% of the cost, with about $12,000 to $13,000 in local match to be provided by the MPO, possibly through in-kind services. The previous long- and short-range plan became about 75% obsolete after the UZA designation. The new plan is expected to take about a year and will include public involvement.
- A commissioner relayed a community member’s commendation of transit staff as professional, always on time, and helpful, allowing him to volunteer in the community.
- Commissioner Frizzell asked about naming the transit system; staff said naming is included in the short-range plan’s marketing component and should come forward within about a year. Staff also identified MPO interim director Johnny Loera and Human Services department head Jeff Tipton.
- Upcoming non-service days are May 26 for Memorial Day, June 19 for Juneteenth, and July 4 for Independence Day.
Key Outcomes
- The commission unanimously approved the February 3, 2025 minutes.
- No formal vote was taken on the facility design; the presentation was for discussion, with city council consideration as the next step.
- Staff planned to submit the final 5311 reimbursement, continue 5307 application steps, develop the MPO short-range transit plan RFP, and advertise for senior van volunteers.
- The meeting adjourned by unanimous voice vote after a motion and second.
Meeting Transcript
Good evening. This is the Bullhead Area Transit System Commission meeting for May 5th, 2025. Madam Secretary Roll Call. All commission members are present except for Olivia Hendrickson. And tonight we have Cindy Frizel joining us via telephone. Can you hear us, Cindy? Yes, thank you, Deb. Thank you. Thank you. Ladies and gentlemen, please join me in the Pledge of Allegiance. Pledge allegiance. Undergone. Thank you. We have a uh presentation this evening by Selburg Associates to discuss the plans for the new Bullhead area multimodal transit facility. Good evening. The floor is yours. Good evening, Mr. Chairperson and uh fellow uh commissioners. It's uh my great pleasure to be here today. My name is Rob Sampson with Salberg Associates. I have my associate Barisa Barraza here with me as well, who also worked on the plans. We're uh super excited to uh be here in front of you today. Thank you. Right. How do I turn it on? There we go. All right. Brief introduction. So as uh Mr. Peluso may have made you aware at uh some numerous meetings that you guys have had. We uh started this project about say a couple of years ago and went through a planning process and went through a number of different um meetings where we were programming to make sure that we had the right um information going into this facility. Uh we had a couple of site visits where we uh toured um other facilities that you guys work with in general to make sure that we had the needs that were being met to amalgamate all the services that you guys currently work with uh and bring them under one roof, so to speak. So uh this plan that we have today, we've got construction documents we're happy to share with you guys that we can put up on the screen as well. But what we're doing today is just a brief overview to kind of show you what we're proposing in the building, um, how the final plans are currently look, if there's anything that uh any of the commissioners feel are important or any of the public feels is important that we haven't already addressed, we'll be happy to look at those and and discuss them with uh ownership and and kind of go through there. Um first off, just a brief reminder that this site is uh located on the Lomus Way. Uh we're essentially from this building we're to the uh outlined in red as you'll see on the screen, and we're located to the uh east and rightly to the north of the building we're sitting in right now. This is our site plan. The site plan is uh essentially the result of a number of site visits that we did in person and virtually, um, looking at different transportation centers across um, you know, the area that had similar things to deal with as far as climate, as far as sun control, as far as uh heat and so on. So, what we did is uh looked at a couple of different ones. This one here is the drive area, the drive aisle that you'll see on the left side of the page is for the buses. It's dedicated directly for the buses. Um there's five areas for buses to pull in. Um the reason we looked at this uh layout, and this was not the first site plan that we worked with. This is uh result of a number of site plans that we kind of started with. We based a couple of them off um kind of intentions that we'd originally started with, and then as we developed and and spent more time looking at other facilities, we realized that there's better ways for safety to make sure that uh pedestrians and patrons aren't walking behind buses that are moving or in front of buses that are moving. So, what we wanted to do is make sure that uh we had space for the five buses. We wanted to have private uh parking for the employees. We also wanted to have public parking for anyone who wanted to do like a park and fly or park and ride, so to speak. And also we need to make sure that buses could get into the maintenance and to the back area when they're taken out of service in the evenings safely. So we have a dedicated uh access on the north part of the page, which is uh the top part of the page here.