Special City Council Meeting – September 15, 2026: Kane Park Restrooms Renovation Approval

City Council Meetings — Tuesday, September 15, 2026
BodyCleveland Heights, Ohio
SessionCity Council Meetings
DateTuesday, September 15, 2026
StatusFILED
Video Record
0:00 / 23:47

Original source
Transcript — VerbatimClick a timed line to jump · ⧉ to share it
0:10

Okay, I'd like to call the special Cleveland Heights City Council meeting to order.

0:15

It is Tuesday September 16th.

0:19

15th.

0:20

15th, right?

0:21

15th.

0:22

Thank you.

0:24

It's 532.

0:25

I'll call the roll.

0:26

Councilman DeWitt Foy.

0:28

Here.

0:29

Council President Kuda is here.

0:31

Councilman Cobb.

0:32

Here.

0:32

Councilwoman Cohen.

0:34

Here.

0:34

Councilwoman Stone.

0:36

Vice President Larson.

0:38

Here.

0:39

Very good.

0:39

And Councilman Posh is on vacation.

0:44

All right.

0:45

So we have one ordinance in front of us.

0:48

It's ordinance 174 2026.

0:51

An ordinance authorizing the mayor to execute an amendment to the design build contract with the AKA team Inc.

0:59

for the Kane Park Restrooms Renovation Project and declaring the necessity that this legislation become immediately effective as an emergency measure.

1:14

Yes, thank you.

1:14

I think that Director Gonzalez will begin.

1:17

And we also have our finance and law directors here who've worked on this project and can add to it.

1:23

I just wanted to note that there is a second piece of legislation this evening, ordinance number 175-2026.

1:30

Happy to talk about that whenever you would like.

1:33

Okay, very good.

1:35

That's just the companion piece, the appropriation side of it.

1:39

All right.

1:39

Thank you.

1:42

Would you like to speak?

1:45

Sure.

1:46

Can everybody hear me?

1:47

Yes.

1:48

Very, very good.

1:50

Well, City Council, thank you for having me this evening.

1:52

I apologize I couldn't be in person.

1:55

Um, but I have my also my uh city council uh diligence that I have to do on my end tonight over here in Brook Park.

2:02

Um, but thank you for allowing me to to join via Teams.

2:05

We're very excited about this project that's that's getting moved forward here.

2:10

Um with with all of the the updates that have happened at Came Park.

2:16

Um, you know, this is just another great addition that the city can be proud of.

2:20

Um, you know, we we've spent a lot of money in the in in actual the King Park Performers Um Center by updating the the performers building and the admin buildings.

2:30

Um we spent, you know, quite a bit of money on updating the sound system that exists there, um, and moving outside of that park.

2:38

You know, we've also you know spent quite a bit of money on renovating the tennis courts that are there, um, obviously the the solstice the solstice steps that are that are there, um, the ADA switchback ramps.

2:50

Um so we we've done a lot to to and and soon to come the uh the skate park that's gonna be coming here very soon as well, too.

2:59

Um so we've done a lot to enhance that park.

3:01

And and and what this does is just this just uh is another step of us enhancing that park, specifically for two different reasons.

3:09

Obviously, though the those bathrooms are very old and ancient.

3:13

Um, if you've stepped foot into them, you you would I think you could agree that they just need a complete facelift.

3:20

Um so they're gonna do two things is number one, um they're they're they're going to we're gonna make them look beautiful.

3:26

Um we're gonna make them look nice, updated, modern, adding new fixtures, different things like that.

3:32

Um so it's something that the that the residents can be proud of, like I said.

3:37

And number two, which is the most important piece, is that um we're we're updating these bathrooms to make them ADA compliant.

3:45

Um not sure if many of you know or maybe you do know, um, but over all these years, and and the and the law director, uh director Hannah can speak to this.

3:54

Over all these years, you know, we've gotten several lawsuits, whether it be the you know, the the the ones actually in the performers center or the tennis court bathrooms.

Discussion Breakdown — Share of Meeting
Public Works█████████████████████████████████████████████62%
Fiscal Sustainability█████████████████23%
Procedural███████9%
Disability Rights████6%
Summary of Proceedings

Special City Council Meeting – September 15, 2026

This special meeting of the Cleveland Heights City Council was called to consider two ordinances related to the Kane Park Restrooms Renovation Project. The council unanimously approved both pieces of legislation, authorizing a contract amendment and an appropriation adjustment funded entirely by reallocated ARPA dollars. Discussion focused on project scope, ADA compliance, cost estimates, and frustrations over last-minute document delivery.

Consent Calendar

  • No consent calendar items were presented.

Public Comments & Testimony

  • No public comments were made. Councilwoman Stone briefly noted that public comment is typically allowed at regular meetings but not at special meetings, though she expressed willingness to permit it if requested; no public testimony was given.

Discussion Items

  • Ordinance 174-2026 – Contract Amendment for Kane Park Restrooms Renovation: Director Gonzalez (via Teams) presented the project, highlighting that the restrooms are “very old and ancient” and in need of a complete facelift. He emphasized that the primary goal is ADA compliance, noting that the city has faced lawsuits and payouts for non-compliant bathrooms in the past. The scope includes replacing toilets (12 new toilets, 13 urinals, 15 sinks), adding four exterior ADA-compliant drinking fountains, replacing three dozen light fixtures, installing new hollow metal doors, stainless steel partitions, epoxy floors, painting, and masonry refinishing. The total maximum contract amount is $1,011,054, fully covered by ARPA funds.
  • ARPA Funding Reallocation: Councilwoman Cohen questioned the reallocation of ARPA dollars from other programs (e.g., the exterior home repair program) that were closed due to full expenditure. Finance Director Brodzinski explained that savings from completed ARPA projects (which came in under budget) provided the surplus, and that this project was prioritized because it is easier to execute and avoids using general fund dollars. Councilman Cobb requested a future itemization of all ARPA spending at Kane Park and other parks.
  • Project Design and Cost: Councilwoman Stone asked whether council had ever seen the actual designs. Director Gonzalez noted that the initial cost estimate was $250,000 based on available ARPA funds, but the actual design-build contract was awarded for $475,000 in 2024. Over the past 19 months, the city worked with the design-builder to finalize scope and decided to go beyond bare ADA compliance to include quality finishes. Plumbing costs were higher than expected due to demand, but were renegotiated down by about 7.5% ($75,000). Vice President Larson asked about plumbing infrastructure improvements; Law Director Hannah confirmed the pipes were aging and the project will enhance them.
  • Ordinance 175-2026 – Appropriation Amendment: This companion legislation adjusts appropriations to fund the project. Vice President Larson expressed frustration that the legislation was not received until 11:15 AM on the day of the meeting, but she voted yes to meet the ARPA spending deadline of December 31, 2026. Council President Kuda echoed frustration about repeated last-minute document delivery.

Key Outcomes

  • Vote on Ordinance 174-2026: Passed unanimously (6-0). Roll call: Vice President Larson (aye), Councilwoman Stone (aye), Councilwoman Cohen (aye), Councilman Cobb (aye), Councilman DeWitt Foy (yes), Council President Kuda (aye). Councilman Posh was absent on vacation.
  • Vote on Ordinance 175-2026: Passed unanimously by voice vote (all ayes).
  • Next Steps: The project must be completed by December 21, 2026, and funds paid out by December 31, 2026, to meet the federal ARPA deadline. The council reiterated the importance of avoiding any return of funds to the federal government.

Meeting Transcript

Okay, I'd like to call the special Cleveland Heights City Council meeting to order. It is Tuesday September 16th. 15th. 15th, right? 15th. Thank you. It's 532. I'll call the roll. Councilman DeWitt Foy. Here. Council President Kuda is here. Councilman Cobb. Here. Councilwoman Cohen. Here. Councilwoman Stone. Vice President Larson. Here. Very good. And Councilman Posh is on vacation. All right. So we have one ordinance in front of us. It's ordinance 174 2026. An ordinance authorizing the mayor to execute an amendment to the design build contract with the AKA team Inc. for the Kane Park Restrooms Renovation Project and declaring the necessity that this legislation become immediately effective as an emergency measure. Yes, thank you. I think that Director Gonzalez will begin. And we also have our finance and law directors here who've worked on this project and can add to it. I just wanted to note that there is a second piece of legislation this evening, ordinance number 175-2026. Happy to talk about that whenever you would like. Okay, very good. That's just the companion piece, the appropriation side of it. All right. Thank you. Would you like to speak? Sure. Can everybody hear me? Yes. Very, very good. Well, City Council, thank you for having me this evening. I apologize I couldn't be in person. Um, but I have my also my uh city council uh diligence that I have to do on my end tonight over here in Brook Park. Um, but thank you for allowing me to to join via Teams. We're very excited about this project that's that's getting moved forward here. Um with with all of the the updates that have happened at Came Park. Um, you know, this is just another great addition that the city can be proud of. Um, you know, we we've spent a lot of money in the in in actual the King Park Performers Um Center by updating the the performers building and the admin buildings. Um we spent, you know, quite a bit of money on updating the sound system that exists there, um, and moving outside of that park. You know, we've also you know spent quite a bit of money on renovating the tennis courts that are there, um, obviously the the solstice the solstice steps that are that are there, um, the ADA switchback ramps. Um so we we've done a lot to to and and soon to come the uh the skate park that's gonna be coming here very soon as well, too.