Lakewood Committee of the Whole Meeting – September 23, 2026: First Energy Infrastructure and Accountability

Council Meetings — Wednesday, September 23, 2026
BodyLakewood, Ohio
SessionCouncil Meetings
DateWednesday, September 23, 2026
StatusFILED
Video Record
0:00 / 2:08:53

Original source
Transcript — VerbatimClick a timed line to jump · ⧉ to share it

Speaker numbers apply only to this recording.

Unassigned speaker

0:02

All

Speaker 1

0:02

right, we will call to order the uh September 28th meeting of Committee of the Whole.

0:08

I will first move to approve the minutes of the July 27th meeting without the necessity of a reading.

Speaker 2

0:14

Second.

Speaker 1

0:15

Motion's been made and seconded.

0:16

Any discussion?

0:18

Hearing none, all those in favor?

0:20

Aye.

0:21

And that motion passes.

0:22

Okay, so tonight we have two items docketed, but they're both kind of about the same thing.

0:29

So I'm going to attempt to summarize that a little bit.

0:34

So I'll just begin by welcoming Mayor George, Council members, members of the administration, First Energy representatives, and our neighbors.

Unassigned speaker

0:44

We

Speaker 1

0:44

here in Lakewood are all entirely too familiar with First Energy's ongoing failures to provide the Lakewood community with reliable electricity.

0:54

Beyond experiencing these outages ourselves, we have heard from countless residents who have endured extreme hardship, losing food, throwing out critical medicine, and in some cases facing hospitalization and life-threatening conditions.

1:09

These perpetual electrical failures are entirely unacceptable.

1:13

They drain our city's resources as we work to support a community suffering from this wealthy corporation's blatant neglect.

1:21

Our response must be multifaceted.

1:24

It requires continued legal pressure through the Public Utilities Commission of Ohio, PUCO or PUCO, as you'll hear mentioned probably a few times tonight, an expansion of local resilient and sustainable solutions, and advocacy for statewide policies to reduce strain on our outdated system.

1:43

The purpose of tonight's hearing is to review First Energy's plans to improve infrastructure reliability and communication, specifically regarding the corrective action plans required by the Public Utilities Commission of Ohio.

1:59

Both the 2025 and 2026 investigations resulted in the PUCO issuing notices of probable noncompliance, a PNC, that concluded that most of the outages were caused by equipment or line failure, and both highlighted First Energy's failure to invest in infrastructure and maintain and implement a comprehension comprehensive communication plan.

2:24

To help us understand how we got to tonight's hearing, it is worth reviewing the timeline.

2:29

In June of 2025, after a series of severe outages, Mayor George and Cleveland City Council members representing the affected areas petitioned the PUCO to investigate.

2:41

In July, the mayor, Cleveland Councilmember Casey, State Rep Raider, and I met with the First Energy representatives here with us tonight or their predecessors, and were assured that the temporary transformers in place and various repairs would be sufficient to handle Lakewood's energy needs.

2:58

Later that month, the PUCO issued a letter of probable noncompliance that told a different story and ordered First Energy to replace two transformers at the substation in the Birdtown area, improve communications, address other equipment issues, and we'll review those tonight.

3:17

In August, First Energy held a town hall at Lakewood Civic Center in August of 2025, holding up smart meters and tree trimming as solutions to the problem and promising to do better while simultaneously filing with the PUCO to be allowed to reduce reliability standards.

3:35

In June of 2026, the City of Lakewood successfully intervened, and the PUCO denied First Energy's attempt to lower its reliability standards, heavily citing the massive volume of complaints filed by Lakewood residents.

3:51

So thank you for

Unassigned speaker

3:52

that.

Speaker 1

3:52

Summer 2026.

3:54

Interestingly, the day after the ruling denying their request to lower reliability standards, First Energy issued a press release announcing the delivery of two transformers

Unassigned speaker

4:04

to

Speaker 1

4:04

a Lakewood substation, leaving out of the press release that they were ordered to do so by the PUCO following Lakewood's complaint.

4:12

Less than a week after issuing that press release, equipment failures at the Lauderdale substation caused thousands of Lakewood residents to suffer loss of crucial electricity during dangerously hot weather, in many cases for multiple days leading up to the 4th of July.

4:29

During this period, First Energy refused to put out a press release or social media posts, educating residents about what was happening.

4:36

They also cut off communication with city council members who were working hard to keep residents informed.

Unassigned speaker

4:43

We heard from many residents that the limited communications that they did receive from First Energy were inaccurate, informing them of rolling periods of electrical restoration that never came, or insultingly encouraging them to reduce electrical usage to relieve strain on a system that they could not use.

Speaker 1

5:01

On August 7th, 2026, after investigating more complaints from Lakewood, the PUCO issued a second letter of noncompliance.

5:10

While the final orders from that PNC have not been issued, tonight's hearing will go through improvements that the POCO identified as needed and First Energy's plans to address

Unassigned speaker

5:21

them.

Speaker 1

5:22

In short, both the 2025 and 2026 investigations concluded the same thing.

5:29

Outages are caused by equipment failure.

5:31

First Energy has not adequately invested in infrastructure, and communication between First Energy and those served must be improved.

5:39

Tonight's hearing is to investigate how those improvements will happen.

5:43

Before we begin, a few notes about tonight's structure and rules for decorum.

5:47

This is an official City Council Committee of the Whole meeting.

5:51

As the chair, questions and public comment will run through

Unassigned speaker

5:54

me.

Speaker 1

5:55

While I know that all of us who live in Lakewood and have dealt with the hardships caused by these electoral outages are frustrated, I would ask those in attendance to please maintain decorum.

6:07

We have a lot to get through tonight.

6:09

And while I sincerely understand the desire to uh respond to comments, um,

Unassigned speaker

6:16

you

Speaker 1

6:16

know, booing, clapping, talking out of turn will take time away from productive dialogue and the opportunity for our neighbors to speak.

6:25

Because I anticipate that many neighbors will want to speak, the public comment timer will be set to two minutes uh per person this evening.

6:33

When you come up, please address the chair, which is me, state your name and address, and avoid personalities.

6:38

Don't worry, I'll remind you of this when we get there.

6:41

The format tonight will be a brief presentation by the law department, after which council members will have each have a few minutes to ask questions, and then a brief presentation by First Energy, after which council members will each have a few minutes to ask questions, and of course, members of the administration.

6:56

To ensure time for public comment, I'll ask council members to keep remarks and questions as concise as possible.

7:04

Tonight we are joined from members of the administration by Mayor George, Law Director Ernie Vargo, Chief of Staff John Story, and Assistant Law Director Jeff Crossman.

7:14

From First Energy, we are joined by Sally Thomas, VP of Distribution Engineering, Satfire O'Doule, VP of Operations Transmission, Joseph Ashburn, Director of Distribution Engineering, Daniel Nup, Manager of Reliability Engineering, David Turner, Director of Customer Accounts and Local Engagements, and Charles Seco, local engagement specialist.

Discussion Breakdown — Share of Meeting
Energy Infrastructure█████████████████████████████████████████████58%
Public Utilities Commission of Ohio█████████████████22%
Public Safety████████10%
Public Engagement█████6%
Procedural██2%
Legal Procedure█1%
Economic Development█1%
Summary of Proceedings

Lakewood Committee of the Whole Meeting – September 23, 2026: First Energy Infrastructure and Accountability

This Committee of the Whole meeting, held September 23, 2026, focused on First Energy's ongoing failures to provide reliable electricity to Lakewood, recent PUCO corrective actions, the city's legal intervention in a rate case, and First Energy's plans for infrastructure improvements. Council heard from the administration, law department, First Energy representatives, and public commenters.

Consent Calendar

  • Approval of Minutes: The minutes of the July 27, 2026 Committee of the Whole meeting were approved unanimously without discussion.

Public Comments & Testimony

  • Linda Barley (Lakewood resident): Described experience with a municipally owned utility in Colorado Springs, emphasizing that citizen-owned utilities can be more efficient and accountable. Urged Lakewood to consider similar models.
  • Lauren Small (CEO, Lakewood Chamber of Commerce): Stated that reliable electricity is essential for businesses and that the Chamber supports the city's aggressive legal strategy. Expressed concern about rate increases without service improvements.
  • Ashley Drakenberg (Newman Avenue resident): Criticized First Energy for cutting corners and charging premium rates while failing to maintain infrastructure. Questioned the value of smart meters and demanded the $3 million PUCO forfeiture be returned to Lakewood ratepayers, not the state.
  • Alison Urbanic (St. Charles Avenue resident, representing Barton communities): Represented older adults in affordable housing. Called attention to vulnerable populations lacking backup power and criticized First Energy's critical care program as inadequate. Asked for prioritization of people over profits.
  • Don Noddage (Morrison Avenue resident): Described a personal medical emergency and financial loss due to the July 4th outage. Demanded concrete action, not baby steps, including temporary rate reductions and proactive assessment.
  • Teresa Sweeney (Lakewood resident, mother of ventilator-dependent son): Delivered an emotional account of life-threatening situations during outages. Stated her son requires reliable power for life support equipment and criticized the lack of a whole-house generator. Called on First Energy's leadership to understand the human impact.

Discussion Items

  • President Kepple's Opening Remarks: Reviewed a timeline of PUCO investigations (2025 and 2026) and First Energy's failures, including equipment failures, communication breakdowns, and a press release misleadingly announcing transformer delivery. Emphasized need for multi-faceted response: legal pressure, local resilience, and state-level advocacy.
  • Mayor George: Thanked residents and the law department. Noted the city filed an addendum to the PUCO complaint demanding an interim emergency capacity plan and filed to intervene in First Energy's rate increase case. Stated that long-term capital improvements must be paired with immediate measures.
  • Law Director Ernie Vargo: Detailed PUCO-ordered corrective actions, including transformer replacements at Athens substation, pole equipment inspections (19 deficiencies found, 15 repaired), smart meter deployment, and improved ETR communications. Highlighted that the 2025 PNC led to a requirement for monthly outage reporting, which revealed structural issues. Described the ongoing 2026 PNC focusing on capacity and aging underground cables (some nearly 100 years old). Noted First Energy's $19 million commitment through 2027, but cautioned that $7 million is for smart meters (which do not improve reliability). Stressed that long-term upgrades (7–9 years) are needed, and interim solutions like backup generators and peak demand rebates must be explored. Mentioned the city's demand that the $3 million PUCO forfeiture be returned to Lakewood ratepayers.
  • First Energy Presentation (Sally Thomas, VP Distribution Engineering): Apologized for outages and acknowledged unmet expectations. Presented a plan including: 2 new transformers at Lakewood substation (first installed June 2026, second on track by end of 2026); 93% smart meter deployment; $6.5 million additional investment for circuit inspections (360+ deficiencies found), transformer banks for capacity, and replacement of pole-top transformers. Announced a long-term Lakewood improvement plan to be filed with PUCO by end of 2026, developed with independent engineering firm De Novo. Committed to improving communication with more accurate restoration time estimates.
  • Council Questions: Council members pressed for specifics on the long-term plan, the timeline for ETR improvements, the aging 4 kV system, and the lack of proactive maintenance. Councilmember Bullock suggested a voluntary economic assistance program for impacted residents; First Energy engineers said that was outside their scope. Councilmember Strebig criticized the critical care program as “let them eat cake.” Councilmember Baker raised the possibility of municipal appropriation of infrastructure as a “nuclear button.” First Energy representatives acknowledged past neglect but committed to future investments.

Key Outcomes

  • No formal votes were taken on agenda items, but council expressed unified support for the administration's legal strategy.
  • The city's motion to intervene in First Energy's rate case (PUCO Case No. 26‑0347‑EL‑AIR) is pending before an administrative law judge; council received updates.
  • First Energy committed to filing a comprehensive long-term reliability improvement plan with PUCO by December 31, 2026.
  • The law department will continue to monitor First Energy's compliance with all PUCO corrective actions and the $3 million forfeiture demand.
  • Council directed First Energy to provide exact completion dates for all outstanding corrective actions and to improve communication transparency.
  • Public comment underscored the severe impacts on vulnerable residents and businesses, with many calling for accountability and interim backup power solutions.

Meeting Transcript

All right, we will call to order the uh September 28th meeting of Committee of the Whole. I will first move to approve the minutes of the July 27th meeting without the necessity of a reading. Second. Motion's been made and seconded. Any discussion? Hearing none, all those in favor? Aye. And that motion passes. Okay, so tonight we have two items docketed, but they're both kind of about the same thing. So I'm going to attempt to summarize that a little bit. So I'll just begin by welcoming Mayor George, Council members, members of the administration, First Energy representatives, and our neighbors. We here in Lakewood are all entirely too familiar with First Energy's ongoing failures to provide the Lakewood community with reliable electricity. Beyond experiencing these outages ourselves, we have heard from countless residents who have endured extreme hardship, losing food, throwing out critical medicine, and in some cases facing hospitalization and life-threatening conditions. These perpetual electrical failures are entirely unacceptable. They drain our city's resources as we work to support a community suffering from this wealthy corporation's blatant neglect. Our response must be multifaceted. It requires continued legal pressure through the Public Utilities Commission of Ohio, PUCO or PUCO, as you'll hear mentioned probably a few times tonight, an expansion of local resilient and sustainable solutions, and advocacy for statewide policies to reduce strain on our outdated system. The purpose of tonight's hearing is to review First Energy's plans to improve infrastructure reliability and communication, specifically regarding the corrective action plans required by the Public Utilities Commission of Ohio. Both the 2025 and 2026 investigations resulted in the PUCO issuing notices of probable noncompliance, a PNC, that concluded that most of the outages were caused by equipment or line failure, and both highlighted First Energy's failure to invest in infrastructure and maintain and implement a comprehension comprehensive communication plan. To help us understand how we got to tonight's hearing, it is worth reviewing the timeline. In June of 2025, after a series of severe outages, Mayor George and Cleveland City Council members representing the affected areas petitioned the PUCO to investigate. In July, the mayor, Cleveland Councilmember Casey, State Rep Raider, and I met with the First Energy representatives here with us tonight or their predecessors, and were assured that the temporary transformers in place and various repairs would be sufficient to handle Lakewood's energy needs. Later that month, the PUCO issued a letter of probable noncompliance that told a different story and ordered First Energy to replace two transformers at the substation in the Birdtown area, improve communications, address other equipment issues, and we'll review those tonight. In August, First Energy held a town hall at Lakewood Civic Center in August of 2025, holding up smart meters and tree trimming as solutions to the problem and promising to do better while simultaneously filing with the PUCO to be allowed to reduce reliability standards. In June of 2026, the City of Lakewood successfully intervened, and the PUCO denied First Energy's attempt to lower its reliability standards, heavily citing the massive volume of complaints filed by Lakewood residents. So thank you for that. Summer 2026. Interestingly, the day after the ruling denying their request to lower reliability standards, First Energy issued a press release announcing the delivery of two transformers to a Lakewood substation, leaving out of the press release that they were ordered to do so by the PUCO following Lakewood's complaint. Less than a week after issuing that press release, equipment failures at the Lauderdale substation caused thousands of Lakewood residents to suffer loss of crucial electricity during dangerously hot weather, in many cases for multiple days leading up to the 4th of July. During this period, First Energy refused to put out a press release or social media posts, educating residents about what was happening. They also cut off communication with city council members who were working hard to keep residents informed. We heard from many residents that the limited communications that they did receive from First Energy were inaccurate, informing them of rolling periods of electrical restoration that never came, or insultingly encouraging them to reduce electrical usage to relieve strain on a system that they could not use. On August 7th, 2026, after investigating more complaints from Lakewood, the PUCO issued a second letter of noncompliance. While the final orders from that PNC have not been issued, tonight's hearing will go through improvements that the POCO identified as needed and First Energy's plans to address them. In short, both the 2025 and 2026 investigations concluded the same thing. Outages are caused by equipment failure. First Energy has not adequately invested in infrastructure, and communication between First Energy and those served must be improved. Tonight's hearing is to investigate how those improvements will happen. Before we begin, a few notes about tonight's structure and rules for decorum. This is an official City Council Committee of the Whole meeting. As the chair, questions and public comment will run through me. While I know that all of us who live in Lakewood and have dealt with the hardships caused by these electoral outages are frustrated, I would ask those in attendance to please maintain decorum. We have a lot to get through tonight.