Mandan City Commission Meeting - June 2, 2026: Construction Updates, Special Use Permits, and Street District Creation

City CommissionTuesday, June 2, 2026
BodyMandan, North Dakota
SessionCity Commission
DateTuesday, June 2, 2026
StatusFILED
Video Record
0:00 / 48:55

Transcript — Verbatim
0:10

Today is June 2nd, 2026.

0:13

It is 5:30 p.m.

0:15

and we are in the Bosch Frelik meeting room at Mandan City Hall.

0:18

Mr.

0:19

Neubauer, could you please take the roll call?

0:21

Commissioners Schoberg.

0:23

Heinson.

0:24

Here, Ron.

0:25

Here.

0:25

Roar.

0:26

Here.

0:26

Mayor Frelick.

0:27

Here.

0:28

And at this time we will have Megan Kloninger, who is the summer intern in the engineering department.

0:36

Lead us in the Pledge of Allegiance.

0:39

Please remove all headgear.

0:43

I pledge allegiance to the five of the United States of America.

0:48

And to the Republicans.

0:51

One undergo individual midlifer to justice for all.

1:00

Thank you, Megan.

1:03

We will start out with announcements, construction project updates.

1:09

Mayor and Commissioners, good evening here.

1:11

Let me pull up my slides.

1:13

Same group of projects that I had from last time.

1:16

We'll start off with Memorial Highway, as usual.

1:21

Reminder, once again, this is split into two phases.

1:24

The uh west half is being constructed by Northern Improvement, and the east half, which is the one that's further along, is being constructed by Reedy Construction.

1:33

Some of the happenings on the corridor right now.

1:36

There's a there's been a traffic traffic shift for median and turn lane paving.

1:42

Um I do have a picture of that right there.

1:44

You can kind of see how it shifts over uh for the work to be completed in the middle there.

1:50

That traffic shift will be moving along the corridor as they uh get further and further along to do that median paving.

1:58

Um 43rd has been reopened since our last meeting, and then on June 4th, we're expecting um the northern portion of 40th Avenue Southeast to be closed in order to resolve some utility conflicts.

2:10

Um this project is still on schedule to be complete at the beginning beginning of July, ahead of July 4th.

2:16

And I don't have any pictures.

2:17

Uh I do have to have a closer view of the um traffic shift if people are interested in looking at that a little bit better.

2:25

Um I don't have any pictures of the phase two work right now, but they are still at that main street intersection working on con concrete, and um there will be uh more traffic changes as they switch from subphase to sub phase uh maintaining traffic throughout the intersection.

2:42

And then um they will start utility work along third street or some storm sewer work, uh, but we're kind of waiting on some more information before that that starts.

2:52

Um any questions on Memorial Highway?

2:54

No.

2:55

Okay.

2:55

First street reconstruction.

2:57

Last week uh there were they were working on uh water main in phase two, which is shown in blue over in the picture here.

3:02

This week they're working on the storm sewer on first in red, and they are working on sanitary sewer in the blue area.

3:10

And then upcoming that we're gonna have roadway preparation in curb and gutter curb and gutter and roadway paving in phase one, getting everything closed back up, as well as storm sewer installation on phase two.

3:22

So the way that this project is set up is that the contractor can have two phases open at a single time.

3:28

So if before they open up phase three, they'll have to close up phase one.

3:32

Before they open up phase four, they'll have to close up phase two, and you know, so on so forth.

3:38

Um project looking looking forward at this project.

3:41

We are expecting them around the 4th of July to be uh to have phase one closed up to be possibly closing up phase two, have phase three opened up, and then depending on where phase two is at, have phase four on the brink of being opened up.

3:59

So for the fourth of July, we feel pretty confident that phase five will be absolutely open.

4:04

And I know that there has maybe been some comments around uh seeing if phase four uh could be opened at that, stay open at that time, and we'll just we'll try and cross that bridge when we get to it.

4:15

But there's a good possibility, I think, at this point.

4:19

Um once again, project website for this to get more information on it.

4:23

And the uh the contractor has been really good about putting newsletters out weekly for this project, and it's got a lot of good information in there.

4:32

Collins Avenue Reservoir, the big update here is just site grading restoration.

4:37

Uh they are currently working on painting activities of the pump house.

4:42

They're going to move over to the uh dome and the walls for uh painting.

4:47

They're gonna move to concrete installation, irrigation installation, some light pole reinstallation, and it's really just site cleanup from here on out.

4:55

Is the area gonna be fenced, Jerick?

Discussion Breakdown — Share of Meeting
Land Use Planning█████████████████████████25%
Procedural█████████████████████21%
Engineering And Infrastructure██████████████14%
Arts And Culture█████████9%
Water And Wastewater Management████████8%
Public Safety██████6%
Public Engagement█████5%
Community Engagement████4%
Youth Programs████4%
Summary of Proceedings

Mandan City Commission Meeting - June 2, 2026

The Mandan City Commission met on June 2, 2026, at 5:30 p.m. in the Bosch Frelik meeting room at Mandan City Hall. The meeting covered construction project updates, a presentation on the upcoming Buggies and Blues event, community cleanup month results, and several new business items including special use permits and approvals for infrastructure projects.

Consent Calendar

  • Approved the agenda with a motion by Commissioner Brown and a second by Commissioner Schoberg (unanimous roll call).
  • Approved the minutes of the May 19, 2026, Board of City Commission meeting (unanimous roll call).
  • Approved the consent agenda as published (unanimous roll call).

Public Comments & Testimony

  • No public comment cards were submitted.

Announcements & Presentations

  • Construction Project Updates (Jerick, Engineering):
    • Memorial Highway: Phase 1 (west half, Northern Improvement) and Phase 2 (east half, Reedy Construction) ongoing. Traffic shift for median and turn lane paving; 43rd Avenue reopened; 40th Avenue Southeast closure planned June 4th for utility conflicts. Project on schedule for early July completion.
    • First Street Reconstruction: Phase 2 water main work, storm sewer, and sanitary sewer installation. Phased approach aims to have Phase 5 open by July 4th; Phase 4 may also remain open.
    • Collins Avenue Reservoir: Site grading restoration, painting, and cleanup ongoing. Fence to be reinstalled.
    • 8th Avenue Northwest/27th Street: Approximately 60% complete on 60 identified locations. A second public input meeting is scheduled for June 25th, 2026, 6-7:30 p.m. at Mandan High School.
    • Water and Sewer District 65 (near Lewis and Clark Elementary): Milling completed; overlay, sanitary sewer lining, and restoration planned.
    • SID 241 (near Red Trail Elementary): Concrete crews working eastward; roadway patching ahead of milling and overlay.
  • Buggies and Blues Event (Tristan, Mandan Progress Organization):
    • 33rd annual event, June 12-14, 2026. Expected 35,000 attendees.
    • Friday (June 12) kickoff at 4 p.m. with Randy James Band and Shirts and Skin; Saturday (June 13) block party from 6:30-11 p.m. with bands including Dream Boats and Pork Tornadoes (Iowa-based, 9 million YouTube views).
    • New collaboration: Hot Rods and Hamburgers at Dakota Customs on Friday (5-8 p.m.).
    • Sunday (June 14): Classic car show (11 a.m.-4 p.m.), plus Planes and Pancakes at Mandan Regional Airport (8 a.m.-noon, free will donation).
    • Fireworks show (Prairie Pyro Musical) on July 3rd at 10:30 p.m., located north of Mandan Middle School, seating for at least 17,000, free.
  • Community Cleanup Month (Kerry):
    • Over 140 volunteers cleaned 17 routes in Mandan. Door prizes donated by 18 local businesses (listed).
  • New Employee Introduction (Jerick):
    • Megan Kloninger, summer intern in Engineering, introduced. She recently graduated in civil engineering and will pursue a master's degree in environmental engineering.
  • Congratulations:
    • Mayor recognized the Mandan Girls Soccer team for an undefeated WDA regular season and second-place state finish. Coach Aaron Maclee was Coach of the Year; Sarah Helderop scored over 100 goals, a state record.

Discussion Items

  • Special Use Permit – Propane Storage (2264 Sunny Road South):
    • Proposed for two 30,000 gallon propane tanks in an existing truck yard on a 21-acre site zoned C-B (commercial). Located in the Extended Territorial Area (ETA). No comments from adjacent property owners; Planning and Zoning Commission recommended unanimous approval on May 27, 2026.
    • Motion: Commissioner Schoberg moved to approve; second by Commissioner Heinshawn. Approved unanimously.
  • Special Use Permit – Event Venue (210 Fifth Avenue NW):
    • Former church to be used for weddings and events. Located in Downtown Fringe district, largely residential area. Parking includes on-street and off-street stalls; applicant provides parking maps. Alcohol will be served (beer/wine license), requiring private security per Chief Ziegler. 99 adjacent property owners notified; several opposed at Planning and Zoning due to parking, noise, and smoking concerns. Planning and Zoning recommended approval (all but one commissioner in favor).
    • Motion: Commissioner Schoberg moved to approve; second by Commissioner Heinshawn. Approved unanimously.
  • Master Lift Station Interim Improvement Project (Project 2026-20):
    • Replaces aging dual 60-inch asbestos cement pipes with a single 20-inch PVC pipe. Includes pump and electrical upgrades. Engineer Apex Engineering completed plans; bids to be advertised, opened later in June. Army Corps of Engineers permit pending; award expected in November 2026 with construction in 2027. Rationale: existing pipes are brittle and prone to failure (e.g., January 2025 failure in -20°F weather).
    • Motion: Commissioner Braun moved to approve plans/specs and authorize advertisement for bids; second by Commissioner Schoberg. Approved unanimously.
  • Task Order with AE2S – Raw Water Intake Study:
    • Addresses sandbar migration issues at the raw water intake. Study includes data gathering, river modeling, and recommendations for modifications. Cost: $225,000, split 50/50 with Marathon; funded through existing SRF loan for the raw water intake project.
    • Motion: Commissioner Braun moved to approve Task Order No. 17; second by Commissioner Heinshawn. Approved unanimously.
  • Ordinance 1486 – Alarm Systems (Second Consideration):
    • Cleanup ordinance; only change was adding effective date of January 1, 2026. No public comments.
    • Motion: Commissioner Heinshawn moved to approve; second by Commissioner Rohr. Approved unanimously.
  • Ordinance 1487 – Traffic Penalties (First Consideration):
    • Restores doubling of fines for most traffic violations except speeding, after an unintended removal due to a state law change.
    • Motion: Commissioner Braun moved to approve first consideration; second by Commissioner Schoberg. Approved unanimously.
  • Street Improvement District 244 – 8th Avenue/27th Street Phase 2 (Project 2026-15):
    • Reconstruction of 8th Avenue NW from 24th Street to 27th Street, and 27th Street from 8th Avenue NW to 1806, plus patching and chip sealing in adjacent areas. Total project cost estimate $6.7 million: $4 million from federal urban roads program, $200,000 from federal transportation alternatives grant, $435,000 from city utility funds, remainder from a 2% low-interest loan backed by special assessments. Non-adjacent lot assessment approximately $2,500. Project dependent on timely use of grants; if not obligated, funds may be redistributed. Engineering report and feasibility report approved.
    • Motion: Commissioner Heinshawn moved to approve all four resolutions (creating district, engineer's report, feasibility report, resolution of necessity); second by Commissioner Rohr. Approved unanimously.

Key Outcomes

  • Four unanimous approvals of special use permits, project plans, and task orders.
  • Two ordinances approved (one final, one first reading).
  • Street Improvement District 244 officially created, with a public input meeting scheduled June 25th and a protest period to follow.
  • Commissioner Rohr's last meeting will be June 16, 2026; future meetings set for July 7 and July 21, 2026.
  • The meeting adjourned with a reminder to vote in the upcoming June 9th city fire department election and June 10th rural fire protection district election.

Meeting Transcript

Today is June 2nd, 2026. It is 5:30 p.m. and we are in the Bosch Frelik meeting room at Mandan City Hall. Mr. Neubauer, could you please take the roll call? Commissioners Schoberg. Heinson. Here, Ron. Here. Roar. Here. Mayor Frelick. Here. And at this time we will have Megan Kloninger, who is the summer intern in the engineering department. Lead us in the Pledge of Allegiance. Please remove all headgear. I pledge allegiance to the five of the United States of America. And to the Republicans. One undergo individual midlifer to justice for all. Thank you, Megan. We will start out with announcements, construction project updates. Mayor and Commissioners, good evening here. Let me pull up my slides. Same group of projects that I had from last time. We'll start off with Memorial Highway, as usual. Reminder, once again, this is split into two phases. The uh west half is being constructed by Northern Improvement, and the east half, which is the one that's further along, is being constructed by Reedy Construction. Some of the happenings on the corridor right now. There's a there's been a traffic traffic shift for median and turn lane paving. Um I do have a picture of that right there. You can kind of see how it shifts over uh for the work to be completed in the middle there. That traffic shift will be moving along the corridor as they uh get further and further along to do that median paving. Um 43rd has been reopened since our last meeting, and then on June 4th, we're expecting um the northern portion of 40th Avenue Southeast to be closed in order to resolve some utility conflicts. Um this project is still on schedule to be complete at the beginning beginning of July, ahead of July 4th. And I don't have any pictures. Uh I do have to have a closer view of the um traffic shift if people are interested in looking at that a little bit better. Um I don't have any pictures of the phase two work right now, but they are still at that main street intersection working on con concrete, and um there will be uh more traffic changes as they switch from subphase to sub phase uh maintaining traffic throughout the intersection. And then um they will start utility work along third street or some storm sewer work, uh, but we're kind of waiting on some more information before that that starts. Um any questions on Memorial Highway? No. Okay. First street reconstruction. Last week uh there were they were working on uh water main in phase two, which is shown in blue over in the picture here. This week they're working on the storm sewer on first in red, and they are working on sanitary sewer in the blue area. And then upcoming that we're gonna have roadway preparation in curb and gutter curb and gutter and roadway paving in phase one, getting everything closed back up, as well as storm sewer installation on phase two. So the way that this project is set up is that the contractor can have two phases open at a single time. So if before they open up phase three, they'll have to close up phase one. Before they open up phase four, they'll have to close up phase two, and you know, so on so forth. Um project looking looking forward at this project. We are expecting them around the 4th of July to be uh to have phase one closed up to be possibly closing up phase two, have phase three opened up, and then depending on where phase two is at, have phase four on the brink of being opened up.