The Milwaukee City Council held a work session on August 19, 2025, to receive updates and discuss several key city projects. Presentations covered the Stormwater System Plan update, completion of the Public Safety Building seismic retrofit and Johnson Creek Campus solar array, and a detailed discussion of challenges facing the Kellogg Dam removal project, including a critical sewer line relocation, conservation easements, and coordination with the Coho development. Councilors provided staff with direction on priorities and requested further analysis.
Stormwater System Plan Update
- Peter Pasarelli (Public Works) and Scott Bern (consultant) presented the update on the Stormwater System Plan. The project is behind schedule due to data incompatibility issues with the hydraulic model, which required rebuilding and field verification of elevations. The last plan was from 2014. The update will address new regulatory requirements (MS4 permit, TMDLs, UIC dry well rules), climate vulnerability (using climate models to 2080), growth impacts (minimal increase in impervious area), and operations/maintenance standards. Area of concern include the industrial park, Dave Green wetlands, Apple Plum Hemlock (a known flooding area), and the Island Station neighborhood near the railroad. The city is also reviewing development standards, considering adopting Clackamas County's stormwater manual or creating a custom one to reduce administrative burden. The plan is expected to be finalized in spring 2026.
Public Safety Building Seismic and Johnson Creek Solar Projects
- Mandy (project manager) reported completion of two projects: the Public Safety Building seismic retrofit (completed November 2024, on time and under budget, funded by a $1.2M Business Oregon grant) and the Johnson Creek Solar Campus (completed February 2024, with a 164.8 kW system providing 85-90% of building load, also under budget). The solar project was funded by a $375,000 Department of Administrative Services grant. Councilors praised the work and inquired about potential battery storage for resilience, which staff indicated is being explored for a future phase.
Kellogg Dam Removal Project – Sewer Line Relocation, Conservation Easements, and Coho Coordination
- Joseph Relio (Assistant City Manager) and Jim Barley (Public Works Director) led a discussion on three critical issues for the Kellogg Dam removal project.
- Sewer Line Relocation: A gravity sewer line on the project site (serving Lake Village Apartments and other areas) must be relocated to allow full floodplain restoration. Three options exist, with the preferred being a pump station to pump sewage up to Lake Road. Estimated cost is $3.5–5 million for construction, plus ongoing operations and maintenance (estimated at ~0.5 FTE and 160 hours/year for two maintenance staff). The sewer line is not currently in the CIP. Councilors Massey and others expressed concern about the impact on wastewater rates and the city's affordability goals, especially given other significant projects (e.g., PFAS treatment). Councilor Massey noted the worst-case risk that if the dam removal project loses funding, the sewer work would be a stranded cost. Staff will work with rate consultants to provide a detailed rate impact analysis and explore funding options (e.g., Clean Water Revolving Loan Fund with potential $2M forgiveness, state and federal appropriations). Council did not give a definitive yes/no but directed staff to proceed with gathering information and to prioritize ratepayer impact.
- Conservation Easements: The project will lower water levels after dam removal, potentially affecting ~20 private properties along the creek. The city may need conservation easements from all property owners to satisfy federal and ODOT funding requirements. If voluntary agreements cannot be reached, the city might need to consider eminent domain, which grants do not cover. Staff are working with Metro to begin negotiations. Councilors noted that many property owners may simply choose to fence their property lines, but the legal necessity of easements is still being clarified. No formal decision made; staff will continue engaging property owners and return with more details.
- Coordination with Coho Development: The Coho housing development project is on a similar timeline and may conflict with Kellogg dam removal design (e.g., a retaining wall at Coho impacts the restoration plan). Staff have been representing both projects as equally important but seek policy direction. Councilor suggested waiting until October 7, 2025, for more information on Coho's status before making trade-off decisions. Council concurred to maintain a parallel approach for now.
Key Outcomes
- Stormwater Plan: No decisions; staff will continue model runs and return with a draft plan in spring 2026.
- PSB Seismic and Solar: Projects completed successfully; council expressed appreciation.
- Kellogg Dam Removal – Sewer Line: Council directed staff to provide a detailed analysis of rate impacts, funding options (including revolving loans and appropriations), and operations & maintenance costs before committing to the sewer relocation. Staff to report back at upcoming CIP milestones (September 9 and November budget committee).
- Kellogg Dam Removal – Conservation Easements: Staff to begin property owner outreach with Metro; no eminent domain decision made.
- Kellogg/Coho Coordination: Council advised to continue gathering information and wait for the October 7 update on Coho before adjusting priorities.
- No formal votes were taken; council provided verbal guidance.
Meeting Transcript
Okay, we are on the air. Welcome to our August 19 work session. Counselor Seven Jordan is not with us tonight, and Counselor Cosrobani is on his way, but still five or so minutes out. But we're gonna go ahead and get started with a presentation on our starwater system plan. Thanks. Thanks, Bear Betty, and Counselors. I'm on Peter Pasarelli with me tonight is Scott Bern, our sort of lead consultant on our uh stormwater system plan. Uh just before Scott's gonna give a presentation of where we are in the plan and what we'll what we're looking at and where we're headed. Uh this plan, uh we're actually a little bit behind schedule uh in terms of getting getting the work done. And I think I guess similar to uh with the water and the wastewater system plans. One of the things that we found when we've gone through uh the update and the plan and actually modeling the systems is we've we found issues with some of the data that we have, you know, you know in our GIS. And trying to get the model to do the things that we want to do, and models in a paid in the software we know using different software. Often there's new data requirements that we need to have. So, you know, we've spent probably most of the year trying to get the model uh and the data to work uh fee and to make sure that we were getting good results on that. And when I say the data, I'm making sure that uh, you know, that our elevations that we have in our source systems are based off of uh not based off of fully surveyed data. It's based off of you know, as builds and and what else do we use, Scott? Well I don't know what the elevations of those systems were. Um I think we're in a good place now. We've got the model working. Uh it's it's providing uh some results that we think are consistent with what we see in the community uh and it's identified perhaps some other places that are that are problematic as well. Uh so that means I'll turn it over to Scott. There we go. I'm not sure I understand what the problem was. Uh incomplete data. So was the data missing or was it incompatible with what we're trying to do with a little a little bit above. Uh it was incompatible with what we're trying to do. And in some cases, I think we expanded the scope of the model too. So uh when we expanded that scope to maybe smaller pipe diameters, uh, we didn't necessarily have that component set of data that we needed to do to make the model. Yeah, I mean the I'd say the city has really good data in really nice shades that has a lot of stuff. We find a lot. We did code logged um supermodel and model things. It's like lots of great data, unfortunately not you're not running the model setups. It's lots of like depths or um space and the mammals. You have to turn that into elevations to how smoothly because we're a storm range. Um a few inches or uh three can make a big difference for how the water moves through that. So the problem with that is you um elevation surveyed in um small errors can magnify as you cover the call system, so that's some of the things that we ran into. Um we also on our end, like we made a decision early on to use um the existing model, which is an old model. A lot of good reasons to do that, but what we realize is that when you try to make an old an old model do new things, uh it breaks and it breaks pretty bad. So we had to kind of work back and rebuild it and get it to work the way it should have. So it's a job. I mean, the advantage of uh modern, you know, last time it was updated was 2014 in 10 years, competing powers on you know, these models can do a lot more stuff, and we're tempted to do more with them and so look at uh more of the system, but uh that requires more data to have meaningful outcomes. And so the process it feels like when we do these master plans, we're kind of always just taking it one step further and getting better and doing more information to better science. So you go out and you survey, you measure these we intercrease run field verify uh and in certain locations where we needed to get that feedback. You know, when I was sitting back in my in my previous job in in Illinois, uh we inherited uh lots of infrastructure from the Air Force and compatibility issues along with the issues of uh the compatibility that we had or accuracy issues that we had with our internal systems. Um one of the ways to get around that was to go out and get it all surveyed. And we we spent money to do that, but that was a lot of money. Uh we got some money you know from the airports at the time we could do that. But you know, we spent in terms of going out to surveying storm and sanitary sewer uh sewers to get you know very accurate elevations of all of the all of the structures we spent close to a million dollars just working on that. So we and we do this on the wastework plan too, is we can prioritize that data gathering, right? Like we can do some quick looks that'll tell us where there's potential problems, and then hone in on those of the areas to spend um the more money.