The Milwaukee City Council held a work session on July 7, 2026, to receive a quarterly update on the Capital Improvement Plan (CIP) from City Engineer Jennifer Garbly. The session covered progress and upcoming milestones for numerous transportation, sewer, water, and paving projects, along with discussions on funding, coordination, and community impact. No formal votes were taken; the session served as a briefing and discussion ahead of future council actions.
Seven council work session. We have only uh one item on the agenda because we do follow it with an executive session. Um so I will turn it over to our city engineer Jennifer Garbly for a capital improvement plan quarterly update. All right. I'm gonna stand up because we've got a lot of slides and some good things to look at. Um if you have questions, type up because we'll be moving on after we move from that slide. So welcome to take questions and have discussion. So let's first start with King Road Improvements. I hope you've seen some of the uh lovely um improvements that have started. Yeah, we are done with all the utility work at this time. Uh so that's exciting. We've updated water and storm water, and now we're working on our curves, and we paved the first um side path from Lenwood to about halfways um around 52nd, and on Thursday and Friday, we'll be paving the other half of the all the way 243rd. So that is super exciting. And then about mid-July, they're gonna um move over to the south side, and we're gonna make our way up. Do you have to close the road as you do the side side? I live right there. They don't close the road. Oh, we're not closing the road. It's gonna get narrow, but no, we're not closing the road. We won't have a third lane, right? The third line is not gonna be available until we actually come back and pave. So the only thing I can't um we are working right now to come up with a paving plan for the actual roadway because this gets a three-inch overlay on it. Yeah, um, of course. And in order to uh actually pave that, we're gonna definitely need to uh probably have some closures or uh down the one lane. So we're still working at those details. That is gonna happen in September, maybe early October. I know we did horse on late. Is this the second time we've done horse? Or okay, yeah. This is our second project reports. So we're looking at finishing up um October 2026 this fall on King Bart. Awesome. Any other questions for King Road? Great. Um I've seen some great um traffic control going on. Um they've really been on top of it, so uh I know that um PD has been really supportive. Um and also um controlling and making sure people are actually slowing down for 25 miles per hour in terms of that. So they're a good reminder. So does you say okay? One question I'm remembering. I know it's not roadway that we own, but the portion where King has with Linwood. Is Clackens County gonna design a bike box or something? It's really difficult right now to go make a left-hand turn from the Linwood multi-use path on the King Road multi-use path. I do not know. Okay. Is that something that we should reach out and ask? Um yeah, I can reach out to Ken to see if he has any possibilities. You want to go from Linwood to King Road. If you're going Linwood King Road, um northbound Linwood to King Road. Yeah.