Moline Committee-of-the-Whole and City Council Meeting - October 22, 2025
Moline Committee-of-the-Whole and City Council Meeting - October 22, 2025
Note: The agenda for this meeting was dated October 21, 2025, but the recorded date is October 22, 2025 per instruction. This summary uses the provided date.
The Moline City Council and Committee-of-the-Whole met on October 22, 2025, to discuss and act on a range of items, including a community solar project, change orders for a major wastewater facility, a sidewalk variance, and multiple ordinances. The meeting included a public comment from a resident, a presentation on the Shine on Moline solar project, and approval of resolutions and ordinances.
Consent Calendar
- Board Appointments: Reappointments of Jeff Dismer, Daniel Otten, and Lucie VanHecke to the Public Art Commission for 2-year terms expiring September 30, 2027, were approved.
- Consent Agenda Items 17.1-18.4: Approved unanimously via omnibus vote. These included:
- Ordinance adding all-way stop intersection at Forty-Third Street and Fifth Avenue.
- Ordinance enacting thirty-minute parking restrictions at 1518 15th Street.
- Resolution authorizing purchase of a Mini-Pitch System for Riverside Park from Musco Lighting for $111,700.
- Resolution extending Thomas A. Skorepa as Zoning Hearing Officer for three years.
- Licensing agreements with Harolds Chicken & Sports Bar LLC and New Style Barbershop Inc. for overhanging signs.
Public Comments & Testimony
- Scott Sheddick (via emailed comment read by the clerk) requested a variance for sidewalk installation at his property, 3418 14th Street. He argued that the street lacks curbs, gutters, and existing sidewalks, making a sidewalk impractical and unsafe. He noted 13 years of service to Moline Little League and his investment in the most neglected property on the block. His request was for a temporary modification to delay installation.
Discussion Items
- Shine on Moline Community Solar Project (Presentation): Shawn Ajazi of Progressive Business Solutions presented the proposed community solar farm. The city would lease 25 acres of the FOIA property to Community Power Group at $2,000 per acre annually with a 2% escalator, generating $50,000/year ($1,214,868 over 20 years; $3,020,000 over 40 years). The project would be 5 megawatts, with no upfront cost to the city. Residents could subscribe for 10-15% savings on utility bills. The project includes a pollinator habitat and game-friendly fencing. Risks include federal incentive deadlines (construction must start by July 4, 2026, and complete by December 31, 2027) and Mid-American interconnection. Council members asked about subscription mechanics, lease terms, and tax obligations. City Administrator Bob Vitas endorsed the recommendation.
- Resolution 8.2 / 20.1 – South Slope Wastewater Reclamation Facility Change Orders: The resolution authorized the Director of Utilities, with concurrence of the Finance Director and City Administrator, to approve change orders up to the budgeted contingency of $3,415,860, with ratification by the City Council afterward. A debate ensued over oversight. Councilmember Schmidt requested a timeline for council notification. After discussion, an amendment was added: "All change orders above $100,000 will come to the City Council for ratification within 30 days of necessary signatures." The amendment was approved, and the amended resolution passed 7-0.
- Resolution 8.3 / 20.2 – Washington Square Apartments Right of First Refusal: The city authorized staff to notify DHC, LLC that it will not exercise its right of first refusal to purchase the Washington Square Apartments (316 17th Street), allowing Renew Moline to proceed with its purchase. Approved 7-0.
- Ordinance 8.4 – Moline Dispatch Apartments TIF Agreement: An ordinance authorizing a redevelopment and economic incentive agreement with Moline Dispatch Apartments, LLC for TIF 15 – 5th Avenue Redevelopment Project Area. The project includes 63 residential units (studios, one- and two-bedrooms) and parking. Councilmembers praised the design and the return of housing to downtown. Approved.
- Strategic Plan Dashboard FY25 Q3 Report (Informational): City Administrator Bob Vitas reported 23 goals on track, 19 completed, 3 on hold, and 2 behind schedule. Enhanced quarterly reporting will begin in 2026. Council noted the importance of transparent communication.
Key Outcomes
- Change Order No. 1 for Project #1488 (2025 Sealcoat Ditch Restoration) with Stichter Construction, Inc. approved for $11,030.78.
- South Slope WWRF Change Order Resolution approved with amendment requiring council ratification within 30 days for change orders over $100,000, up to $3,415,860.
- Right of First Refusal Waiver for Washington Square Apartments approved, allowing Renew Moline to proceed.
- Moline Dispatch Apartments TIF Agreement ordinance approved.
- Sidewalk Variance for 3418 14th Street granted (7-0), allowing a temporary modification to delay installation.
- First Reading Ordinances (21.1-21.7): All advanced to second reading. Key items:
- Tax Levy Ordinance: Amount adjusted from $17,685,290 to $17,346,149 after the October 18 budget work session; final reading set for November 18, 2025.
- Special Service Area #5 and #6 tax levies.
- Ordinance requesting county clerk not to extend taxes for certain bond series.
- Ordinance amending tobacco product regulations.
- Ordinance enacting new division on private security guards.
- Ordinance authorizing TIF 13 redevelopment agreement with Illinois Domus Two, LLC.
- Miscellaneous Business: Announcements about a Rebuild Illinois press conference, listening post on Monday, and comprehensive plan kickoff.
Meeting Transcript
Good evening, everyone. I'll call our meetings in order here in Council Chambers at 6 p.m. Roll call, please. Present. Mastias. Rosak. Present. Timion. Present. Bench, President McNeil. Present. Castro. Schmidt. Present. We don't have any remote electronic attendance. So we move to public comment. Is there any for us? Okay, I do believe we have an emailed public comment that the clerk will read. Council members, I appreciate your attention to agenda item 20.3 and would like to offer additional context regarding the sidewalk requirement for my property on 14th Street Mole. This section of 14th Street is unique. There are no existing sidewalks in front of any homes, nor is the street constructed to support them. The absence of curbs, gutters, or a defined edge means a sidewalk has no natural starting or ending point. The street is finished with a sail coat crowned in the center and tapering to gravel at the edges, which blends directly into the front yards. Installing a sidewalk here would introduce significant risks and complications. Snow removal relies on the gravel shoulders and portions of the yards to clear enough space for vehicles. A sidewalk would be exposed to damage from plows, requiring drivers to remember its location and navigate around abrupt concrete ends that do not align with the street's natural grade. This threatens the sidewalk's integrity and creates a safety hazard for city equipment and personnel. Importantly, there is no precedent for sidewalks in this area. Two weeks ago, a neighbor two houses south installed a new driveway without any sidewalk requirement. My request is not for a variance in a neighborhood where sidewalks are standard, but for consideration in a location where they have never existed. On a personal note, I am a lifelong member of the Mulline community, committed to its growth and improvement. For 13 years, I have served a critical role for one of Moline's most successful youth sports programs, Mulline Little Lake. By choosing to invest in and rebuild the most neglected property on the stretch of 14th Street, I am enhancing my home and contributing to the neighborhood's overall value and the city's tax base. Thank for you. Thank you for your thoughtful consideration, Scott Sheddick. Thank you very much. And with no other uh public comment, we move to board appointments. Excuse me. Uh these are reappointments of Jeff Dismer, Daniel Atten, and Lucy Venheck to the public art commission for two year terms to expire September 30th, 2027. Um questions. Hearing none, we move to our presentation. Shine on Moline Community Solar Project. Good evening, everybody. Uh we're pleased to have Shauna Jazzi uh with us. He's the vice president of Progressive Business Solutions. Uh he has sense of experience in solar energy development and is here to present an overview of our proposed community solar farm project. Sean has worked on numerous renewable energy initiatives focusing on sustainable community centered solutions that maximize environmental and economic benefits. Today they will walk us through the project's scope, potential impacts, and opportunities for the city and its residents. Please welcome Sean and Jeff. Good evening.
openpublica.com