Joint Workshop on Easton's Beach Resilience Planning – February 4, 2026

Meeting PortalWednesday, February 4, 2026
BodyNewport, Rhode Island
SessionMeeting Portal
DateWednesday, February 4, 2026
StatusFILED
Video Record
0:00 / 1:53:33

Transcript — Verbatim
0:00

And the uh Newport Beach Commission.

0:03

Um, we thank everyone for coming tonight.

0:05

Uh so we from the city council, we have uh Stephanie Smythe.

0:10

Oh, give me applause.

0:12

Yeah, right, right.

0:13

Exactly.

0:14

Exactly.

0:14

To the end.

0:15

Uh Gina Politano, uh, Lynn Segley, uh, myself, and we'll wait on.

0:21

I know uh Sai can't make it tonight because under the weather.

0:25

And hopefully we uh Dave and Ellen can make it.

0:28

Uh then I'll turn it off to you, um Mark.

0:31

Good evening, Mayor.

0:32

Um, my name is Mark Fitzgerald.

0:34

I'm the chairman of the Newport Beach Commission.

0:36

To my left is Allie Oakley, our vice chair.

0:39

To my right is Susan Marks, our newest member as of January.

0:43

And at the end there is Elizabeth Ponte.

0:46

Um we have a couple of members, one that is on his way and may come in at about 6.15.

0:50

The other mayor, the other members, we have one illness and one possibility that may also come in late.

0:55

They're also a little bit worried about uh getting here by and finding a parking spot at this time of day with everyone, the rest of us here.

1:02

Sure.

1:03

Um, so what we're gonna do tonight, um in a moment, I'll turn it over to um our director of resiliency and sustainability, uh, Teresa Crean.

1:11

Um, and she'll introduce uh the members of our um well the everyone that's doing the the concepts and the uh engineers and architectures and all those fun positions that are way over my pay grade.

1:25

But um for anyone here from the public, we're gonna uh go through the presentation and then after the presentation are our done and after the the council and beach commission go through the questions, then we'll open it up to any public comment after that.

1:39

Okay.

1:40

Uh so without any further ado, I'll introduce uh Director Creen.

1:45

There it is.

1:46

So you see uh delayed applause for the council and the beach commission.

1:51

Uh Teresa Crean, Director of Resilience and Sustainability.

1:54

Thank you so much for everybody's attendance tonight um for this joint workshop with the City Council and Beach Commission to talk about the status of where we are with the East Ends Beach planning for a resilient future project, which started over a year ago.

2:09

Um even longer than that.

2:11

It goes back several years where these facilities were first deliberated by the city, and this recent effort has taken a look at the structures, um, especially what we the reality that we're facing after the storms that took place in December of 2023 and and January of 2024.

2:29

And our um very talented uh consultant team has put together a great suite of uh products for us to move the conversation forward to determine how we the city plans to spend the 11 million dollars that was positioned in the general obligation bond that passed in 2024 and make some decisions on what the future of the beach will look like.

2:55

The project has been really robust with public engagement.

2:59

The um there were there was a walk shop, and I don't want to steal too much of the thunder with the review of what where we where we were.

3:05

Um, but we had um a walkshop in June.

3:08

Uh there were concept drawings and an eight-foot model with uh movable pieces that the public was able to engage with, and that series of workshops and on-site um charredding that the consultant team um engaged in led to some concept alternatives that were released for public review and survey.

3:28

Um we did a lot of outreach to get survey responses for that.

3:32

So I think the public engagement part has been really strong.

3:35

And with the leadership of the beach commission and the members of the Easton's Beach Resilience Committee, we've been giving the beach commission regular updates and we've had a good diverse set of um community members weigh in on different aspects of beach use over the course of this project.

3:52

So tonight we have our consultant team here to walk you through about a half an hour presentation of where we are with the concept review and the modeling that took place after the concepts were generated back in June.

4:04

And without further ado, I will turn the floor um over to our consultant team led by Beth uh at Fuss and O'Neill.

4:11

Thank you.

4:14

Thank you, Teresa.

4:15

And thank you all for having us here tonight.

4:18

We're very, very excited to be able to show you the results of the work that we've put in so far.

4:25

So if we could advance to the next slide.

4:28

I have the clicker over here if you want to take it.

4:29

Thanks.

4:30

Or don't trust myself with those things.

4:36

I thought it was my garage door opener.

4:39

Cars are beeping now, everything's going crazy.

4:43

Um like um Teresa said, or or Director Crean said, uh we have been at this for a while.

4:51

Uh I know a number of you have heard us talk uh at length on some of these concepts.

5:00

What we're hoping to do tonight is give you a very pared down overview of exactly where we are with the concepts.

5:05

Before we jump into that, just wanted to revisit the problem statement.

5:09

So when we started this project, um, it was a follow-on to another study that looked at the facilities more specifically.

5:18

What was decided in that at the outcome of that study was that the beach itself was vulnerable.

5:25

You've seen it sustain damage from multiple very low level storms over the past couple of years.

Discussion Breakdown — Share of Meeting
Environmental Protection████████████████████████████████████36%
Engineering And Infrastructure██████████████████████████████████34%
Parks and Recreation███████████████████19%
Public Engagement████4%
Procedural██2%
Historic Preservation██2%
Budget Equity Analysis1%
Water And Wastewater Management1%
Transportation Safety1%
Summary of Proceedings

Joint Workshop on Easton's Beach Resilience Planning – February 4, 2026

This joint workshop of the Newport City Council and Beach Commission was held to review the status of the Easton's Beach resilience project, which began over a year ago. The project aims to address beach vulnerability following storms in December 2023 and January 2024, and to determine how to spend the $11 million general obligation bond approved in 2024. Consultants from Fuss & O'Neill, Woods Hole Group, and DBVW Architects presented three dune nourishment concepts, a building conditions assessment, and a potential funding timeline.

Public Comments & Testimony

  • Mike Ryan (59 Hunter Avenue) expressed support for prioritizing recreation and family-oriented amenities at the beach, including a possible carousel relocation, splash pad, and snack bar. He defended the private bathhouses and argued that parking lot and road flooding are not major concerns, but protecting the drinking water supply is critical. He urged splitting the project into phases to address deteriorating facilities sooner.
  • Emily Conklin (7 Gwyn Court), Vice Chair of the Energy and Environment Commission and a marine biologist, expressed strong support for nature-based solutions and emphasized that a resilient beach is necessary for recreation. She agreed with Commissioner Allie Oakley that parking should not be the primary focus and that adding hard structures would be a mistake.
  • Lola Herrera, an oceanographer, supported the second (partial dune) and third (full dune) options, arguing that recreation must be balanced with resilience. She cautioned against wasting money on buildings that will be destroyed by future storms and recommended permeable parking solutions to reduce flooding.
  • Michael Wilson (5 Annadale, Newport) advocated for studying offshore wave attenuation (e.g., concrete jacks) to reduce wave energy, and for raising Memorial Boulevard with state cooperation. He argued that without addressing the root cause of erosion, sand nourishment alone will be insufficient.

Presentation on Dune Nourishment Concepts

  • Brittany Hoffnagel (Woods Hole Group) presented the data collection and modeling approach. Field investigations in fall 2024 informed existing conditions modeling in spring 2025. Three concepts were developed:
    • Phased Dune Concept: 100-foot beach berm with a 40-foot dune; maintains all existing infrastructure. Estimated cost $6.3–$6.5 million; service life ~2.5 years before nourishment needed. Provides protection against a 2-year storm but not against larger or sequential storms.
    • Partial Dune Concept: Maintains 500 parking spaces (out of ~850). Wider dune on west side, narrower on east to preserve parking. Estimated cost $9–$10.2 million; service life ~6 years. Protects against 2- and 10-year storms, but not larger.
    • Full Dune Concept: Reduces parking to ~300 spaces; consistent 80-foot dune along the entire beach. Estimated cost $9.9–$11.7 million; service life ~6–8 years. Protects against 2- and 10-year storms and sequential storms; still vulnerable to 20-year+ storms.
  • Sea level rise scenario (1.5 feet by 2060) shows that even the 2-year storm would overwhelm the phased concept; only partial and full dunes offer some protection.
  • Beth (Fuss & O'Neill) noted that the phased approach is risk‑based and could be wiped out by a single storm, while the partial and full dunes provide more robust, longer‑lasting resilience. The $11 million bond could serve as matching funds for a federal grant (e.g., NIFWIF).

Presentation on Building Assessments and Amenity Recommendations

  • Martha Warenfelds (DBVW Architects) presented findings from a 200‑page conditions assessment of the bathhouses, restrooms, picnic pavilion, and rotunda. Key issues: concrete deck not properly pitched, steel connections rusted, rotunda basement floods regularly, and buildings are not resilient to storms. Survey results (229 responses) indicated that private bathhouses and private event spaces scored lowest in importance; public restrooms and lifeguard facilities were top priorities.
  • Recommendations: demolish existing bathhouses and concrete platform (cost ~$800,000), build new elevated restroom and lifeguard pavilions (cost estimate TBD), consider temporary trailers for food/retail, and either renovate the rotunda (cost $3.2 million for like‑for‑like rebuild), convert it to an open‑air folly, or remove it. The rotunda is not historically designated.

Discussion on Trade-offs and Next Steps

  • Beach Commission members and City Council discussed the balance between parking, resilience, and recreation. Commissioner Allie Oakley noted that the parking lot does not fill every summer day and that losing some spaces is acceptable for saving the beach. Chair Mark Fitzgerald stressed the need for an economic impact study to understand the beach's value to the city; Salve Regina University has been proposed to conduct such a study.
  • Mayor and Councilor Gina Politano raised concerns about construction duration (estimated 1–1.5 years) and the impact on parking revenue and event parking. Commissioner Nick (last name not given) noted that the phased concept is considered ineffective and urged focusing on partial or full options.
  • The team clarified that no hard structures (seawalls, breakwaters) are permitted; nature‑based sand solutions are the only viable option. Parking garages were deemed too expensive and not cost‑effective.
  • The $11 million bond has $10 million remaining after initial expenditures for design and permitting. The NIFWIF grant requires permits and construction documents to be ready by the time funding arrives (estimated May 2027 if awarded in December 2026). A letter of interest is due by April/May 2026, with a full proposal due by July 2026. Waiting a year would delay construction further and risk bond fund expiration.

Key Outcomes

  • No formal votes were taken; this was a workshop to inform decision‑making.
  • The Beach Commission indicated they will provide a formal recommendation at a future meeting, likely favoring either the partial or full dune concept, with a preference for the medium (partial) option due to its balance of parking and protection.
  • The City Council acknowledged the timeline pressure and the need to decide soon to meet grant deadlines.
  • Further steps include:
    • Engaging Salve Regina University for an economic impact study of the beach.
    • Coordinating with Rhode Island DOT on Memorial Boulevard resilience (the road is a top state priority).
    • Developing a maintenance and nourishment funding plan, as done in neighboring Narragansett.
    • Continuing to explore sediment sources and permitting with the Army Corps and CRMC.

Meeting Transcript

And the uh Newport Beach Commission. Um, we thank everyone for coming tonight. Uh so we from the city council, we have uh Stephanie Smythe. Oh, give me applause. Yeah, right, right. Exactly. Exactly. To the end. Uh Gina Politano, uh, Lynn Segley, uh, myself, and we'll wait on. I know uh Sai can't make it tonight because under the weather. And hopefully we uh Dave and Ellen can make it. Uh then I'll turn it off to you, um Mark. Good evening, Mayor. Um, my name is Mark Fitzgerald. I'm the chairman of the Newport Beach Commission. To my left is Allie Oakley, our vice chair. To my right is Susan Marks, our newest member as of January. And at the end there is Elizabeth Ponte. Um we have a couple of members, one that is on his way and may come in at about 6.15. The other mayor, the other members, we have one illness and one possibility that may also come in late. They're also a little bit worried about uh getting here by and finding a parking spot at this time of day with everyone, the rest of us here. Sure. Um, so what we're gonna do tonight, um in a moment, I'll turn it over to um our director of resiliency and sustainability, uh, Teresa Crean. Um, and she'll introduce uh the members of our um well the everyone that's doing the the concepts and the uh engineers and architectures and all those fun positions that are way over my pay grade. But um for anyone here from the public, we're gonna uh go through the presentation and then after the presentation are our done and after the the council and beach commission go through the questions, then we'll open it up to any public comment after that. Okay. Uh so without any further ado, I'll introduce uh Director Creen. There it is. So you see uh delayed applause for the council and the beach commission. Uh Teresa Crean, Director of Resilience and Sustainability. Thank you so much for everybody's attendance tonight um for this joint workshop with the City Council and Beach Commission to talk about the status of where we are with the East Ends Beach planning for a resilient future project, which started over a year ago. Um even longer than that. It goes back several years where these facilities were first deliberated by the city, and this recent effort has taken a look at the structures, um, especially what we the reality that we're facing after the storms that took place in December of 2023 and and January of 2024. And our um very talented uh consultant team has put together a great suite of uh products for us to move the conversation forward to determine how we the city plans to spend the 11 million dollars that was positioned in the general obligation bond that passed in 2024 and make some decisions on what the future of the beach will look like. The project has been really robust with public engagement. The um there were there was a walk shop, and I don't want to steal too much of the thunder with the review of what where we where we were. Um, but we had um a walkshop in June. Uh there were concept drawings and an eight-foot model with uh movable pieces that the public was able to engage with, and that series of workshops and on-site um charredding that the consultant team um engaged in led to some concept alternatives that were released for public review and survey. Um we did a lot of outreach to get survey responses for that. So I think the public engagement part has been really strong. And with the leadership of the beach commission and the members of the Easton's Beach Resilience Committee, we've been giving the beach commission regular updates and we've had a good diverse set of um community members weigh in on different aspects of beach use over the course of this project. So tonight we have our consultant team here to walk you through about a half an hour presentation of where we are with the concept review and the modeling that took place after the concepts were generated back in June. And without further ado, I will turn the floor um over to our consultant team led by Beth uh at Fuss and O'Neill. Thank you. Thank you, Teresa. And thank you all for having us here tonight. We're very, very excited to be able to show you the results of the work that we've put in so far. So if we could advance to the next slide. I have the clicker over here if you want to take it. Thanks.