San Diego Active Transportation and Infrastructure Committee Meeting - September 14, 2022
STREAMING COPY IN PREPARATION — RECORDING AVAILABLE FROM THE ORIGINAL SOURCE
San Diego Active Transportation and Infrastructure Committee Meeting - September 14, 2022
The Active Transportation and Infrastructure Committee of the San Diego City Council met on September 14, 2022, at 2:00 p.m. (10:00 UTC). The meeting was chaired by Councilmember Joe LaCava, with Council President Pro Tem Monica Montgomery Steppe and Councilmember Jennifer Campbell present; Councilmember Von Wilpert was absent. All votes were unanimous (3-0) across consent and discussion items. The meeting was held in a hybrid format due to the state of emergency under AB 361, allowing teleconference and in-person participation.
Consent Calendar
- Item 1: Acceptance of an in-lieu fee of $150,000 from Airway Logistics Owner LLC to satisfy a condition for project 665589.
- Item 2: Contribution agreement with Youth Tennis San Diego and Ed Brown Senior Center to implement a California Natural Resource Agency grant.
- Item 3: Construction contract extension with Newest Construction Inc. for the La Jolla Country Club Reservoir and Pump Station, and a sole-source amendment with Harris and Associates.
- Item 4: First amendment to agreements with Doken Engineering, Parsons Transportation Group, RIC Engineering, and Nasland Engineering.
Public comment: One speaker (Joyce Yaka) supported item 2, praising the youth-senior center partnership. No items were removed. The consent agenda passed 3-0.
Public Comments & Testimony
- Non-agenda public comment: Michael Schmidt (Morney's Vaughn district) requested road repairs on Carmel Mountain and Black Mountain Road. Joyce Yaka (District 3) praised the new bikeways on 4th and 5th Avenue, calling them "sexy streets."
- On specific items: No public testimony was offered on items 5, 7, 8, or 9. Gina Jacobs of San Diego State University spoke in support of item 6 (Fenton Parkway Bridge MOU).
Discussion Items
- Item 5 (Ocean Beach Pier Replacement): Staff (James Nagelvoort, Elizabeth Schroef Nichols) presented a third amendment to the sole-source agreement with Moffat & Nickel for up to $2.4 million (implied by the contract increase) to support full replacement of the 55-year-old pier, which suffered damage in 2019 and 2021. An $8.4 million state grant with a July 2024 expenditure deadline funds the planning. The amendment covers task force support, CEQA/NEPA, and bridging documents for design-build. Councilmember Campbell moved approval, citing the pier's deteriorated condition; passed 3-0.
- Item 6 (Fenton Parkway Bridge MOU with SDSU): Staff (Abby Palosate, Heidi Vonblum) introduced an MOU to formalize the city's $10.8 million cap for the bridge, with total estimated cost at $30 million. SDSU will lead design and CEQA; the bridge would connect Friars Road across the San Diego River. The IBA noted the city's cap is fixed at $10.8 million, with SDSU responsible for overruns. Motion by Montgomery Steppe, seconded by Campbell; passed 3-0.
- Item 7 (NTC Lab Remodel and Solar Project): Staff (Elif Cetin, Edgar Lozano) proposed a $2.4 million, nine-year contract with Silman Wright Architects for design and construction support of the Environmental Monitoring and Technical Services lab at the former Naval Training Center. The $36 million project includes structural retrofits, a new ocean operations building, and solar carports to achieve zero net energy. Funding comes from Metro Sewer CIP funds. Motion by Campbell, seconded by Montgomery Steppe; passed 3-0.
- Item 8 (CMP Repairs and Santa Clara Pump Station Emergency): Interim Stormwater Director Bethany Bizek requested authorization for city force work (exceeding $100,000) on two corrugated metal pipe (CMP) repair projects in Districts 4 and 8, and a $3.7 million budget transfer from green infrastructure to flood resilience for emergency repairs at the Santa Clara Pump Station (District 2). The pump station had a 2010 flood causing electrical hazards; total emergency cost is $5 million. The IBA noted a $1.8 billion stormwater funding gap and that emergency repairs totaled $63 million from FY2019-21. Motion by Montgomery Steppe, seconded by Campbell; passed 3-0.
- Item 9 (Denry Ranch Neighborhood Park Reimbursement Amendment): Staff (Gaetano Martetti) requested approval of a first amendment to increase the reimbursement agreement from $15.1 million to $22 million for a 9-acre park in Otay Mesa, funded by the Otay Mesa Facilities Benefit Assessment (FBA). Bids came in higher in 2019 and 2020. The IBA highlighted the trend of rising construction costs (13.4% inflation in 2021 in California). Motion by Campbell, seconded by Montgomery Steppe; passed 3-0.
Key Outcomes
- All nine agenda items were approved unanimously (3-0).
- No items were removed from the consent calendar.
- The committee received updates from the Mayor's Office (Randy Wilde) on the "sexy streets" pavement program, EV charging RFP, and shared mobility device deployment.
- The IBA provided comments on CIP streamlining, cost overruns, and stormwater emergency repair trends.
- The next regularly scheduled meeting is October 12, 2022, at 2:00 p.m.
Meeting Transcript
Until further notice, committee meetings will be conducted pursuant to the provisions of California Government Code Section 54953E, added by Assembly Bill 361, which allows the city to use teleconferencing and to provide the public an opportunity to address the city council via call-in option or an internet-based service option during a proclaimed state of emergency. While the public is allowed to attend the meetings in person, we encourage you to maintain six feet of social distance as well as follow California mask guidelines where masks are strongly recommended. In addition to being able to attend in person, this meeting is being televised and live streamed on the city's website, and the community liaison will continue to make arrangements for the public to comment using the Zoom webinar platform. Additionally, members of the public who wish to provide testimony via call-in or an internet-based service option must enter the virtual speaking queue within five minutes after the conclusion of in-person public testimony or before the virtual speaking queue is exhausted, whichever occurs first. This will allow for better meeting management between the two platforms and ensure the committee is able to manage and conduct city business. We appreciate the public's cooperation. I will now call the active transportation and infrastructure committee meeting of September 14th, 2022 to order. Let me call the roll. Council President Pro Tam Montgomery Step. Here. Councilmember Campbell. And as I noted for the record, Councilmember Von Wilpert is not joining us this afternoon. So we have three members and we uh have a quorum. Also attending the meeting is uh the IBA representative, Erin Noel, City Attorney Representative Dana Fairchild, Mayoral Representative Randy Wilde, and the fourth person who will keep me on the Strait and Arrow, Committee Consultant Justin Garver. If you are in person, please complete a speaker slip located at the entrance of chambers and place it in the box indicated at the speaker's lectern at the front of the room. Please do so in a timely manner to ensure proper meeting management. Members of the public can join the webinar by computer, tablet, or smartphone by accessing the link which is listed online in the preamble language of the agenda on the city's webpage. To join the Zoom webinar by telephone, please dial 1669-254-5252. And when prompted, input webinar ID 160-556-7518 pound. This information is also available on the agenda and will appear on the screen during the public comment period for each agenda item. Members of the public who wish to provide testimony via call-in or an internet-based service option must enter the virtual virtual speaking queue within five minutes after the conclusion of in-person public testimony or before the virtual speaking queue is exhausted, whichever occurs first. As I said, we have a quorum present. We will now take up the approval of the committee actions of July 20th, 2022. Justin, please proceed with public comment. Thank you. The public comment period for this item is now open. If you're in person, please be sure to have your speaker slips submitted and come to the front reserve seats. Members of the public who wish to provide testimony via call-in or internet-based service option must enter the virtual speaking queue within five minutes after the conclusion of in-person public testimony or prior to the virtual speaking queue being exhausted, whichever is first. If you've already joined the Zoom webinar online or by phone, you can raise your hand if you wish to speak. And you can do so by selecting the raise your hand button or input star nine if by phone. To call in, the phone number will be 1669-2545252. And the webinar ID is 160-556-7518 pound. I will announce when it's to your turn to speak, and you will need to unmute yourself by either selecting the unmute button or pressing star six. We did not receive any slips in chambers for the minutes. And we have no hands raised there, so that will conclude public testimony on the minutes for July. Great. Thank you, Justin. We will now vote on the approval of the committee actions of July 20th, 2022. Do I have a motion to approve? And so that's uh Council President Pro Tam Montgomery Step and then seconded by Councilmember Campbell. Uh we'll take committee member questions and comments and have each committee member register their vote. I think we'll just do this verbally. Uh please mute yourself once you have completed your comments. Councilmember Montgomery Step. Yes. And Councilmember Campbell. Yes. And that should have been Council President Pro Tem. My apologies. And I vote yes as well.