Syracuse Planning Commission Meeting – February 2, 2026: Multiple Project Approvals and BESS Moratorium Workshop
Syracuse Planning Commission Meeting – February 2, 2026
The Syracuse Planning Commission convened on February 2, 2026, to approve minutes, act on several development applications, and conduct a workshop on a proposed moratorium for battery energy storage systems (BESS). The meeting resulted in approvals for a special use permit, the Parkside Commons project, the West Genesee redevelopment, and the South Krauss apartment project, along with a discussion on the BESS moratorium.
Consent Calendar
- Minutes Approval: The commission unanimously approved the minutes from the January 12, 2026 meeting. The motion carried with all in favor.
Public Comments & Testimony
- SP-25-26 (401 Pond Street): Councilor Martinabe spoke in favor of the application but raised concerns about ongoing vehicle parking issues, including unlicensed vehicles and vehicles blocking the sidewalk. She requested clarification on where vehicles will be parked after the project is completed. The applicant responded that the parking issues are caused by an adjacent property owner, not his own lot, and that he plans to install curbing and signage to prohibit parking on the grass and sidewalk. No other public speakers appeared for or against this application. For all other agenda items, no public speakers came forward.
Discussion Items
- Old Business – Withdrawal of BESS Applications: The commission noted that three companion applications for a battery energy storage system at East Brighton Ave (resubdivision, special use permit, and major site plan review) were withdrawn by the applicant. No further action was taken.
- SP-25-26 – All-American Market (401 Pond Street): The applicant, Jesus Ibrahim of TMB Properties, presented revised site plans addressing DPW comments on ADA access, bike parking, sidewalk, and parking area. The commission acknowledged compliance with the SEPTED report. Discussion focused on parking enforcement and neighbor disputes. The special use permit was approved with seven conditions.
- Parkside Commons Project (193 units, Westmoreland Ave & East Fayette St): The applicant (Ed Martin, Passero Associates; Connor Kenny, developer) presented six companion applications (master plan review, zoning map amendment, two resubdivisions, two major site plan reviews). Key features: 143 units in Parcel A (5-story, now compliant after adding a strip of land), 50 units in Parcel B. Parking: 82 interior, no exterior lot. The developer noted relocation of existing residents from the eastern portion of the campus into new construction, with the western portion (200 units) to be substantially rehabbed. Safety measures include 24-hour security and an office for Syracuse Police. All applications were approved individually with conditions.
- 1207 West Genesee Redevelopment Project: Ben Harrell (CHA Consulting) proposed a 6,900 sq ft retail/office building on 0.93 acres, with demolition of two existing buildings. The project includes 55 parking spaces, landscaping, and bicycle parking. Discussion included a county planning board recommendation for additional screening at the rear; the applicant agreed to consider adding trees. The resubdivision and major site plan review were approved.
- 201 South Krauss Apartment Project (88 studio apartments): Brian Bouchard (CHA Consulting) presented a five-story building with preservation of the historic Ignatius Feisinger House (1010 East Washington) as an amenity space. The house will be renovated with an ADA lift enclosure approved by the Syracuse Landmark Preservation Board. The project includes 12% affordable units (30-year affordability period). The resubdivision and major site plan review were approved with conditions, including outstanding taxes noted.
- Workshop on Battery Energy Storage Systems (BESS) Moratorium: Staff outlined the proposed six-month moratorium to allow the city to study BESS safety, fire prevention, decommissioning funding, and zoning updates. The commission clarified this was an information session only; no recommendation to council will be made. Discussion included the 80-kilowatt threshold (based on DeWitt's model), interactions with the fire code, and upcoming educational symposia. No public comments were offered.
Key Outcomes
- Minutes: Approved unanimously.
- SP-25-26 (All-American Market): Approved (motion carried with conditions: hours of operation, no neon signage, no cooked food, photographic evidence of site improvements within 90 days, no tobacco sales, DPW conditions including 5-ft sidewalk and turf grass with parking prohibition).
- Parkside Commons – Master Plan Review (MASPR-25-27): Approved with two conditions (obtain all city approvals, continue working with departments).
- Parkside Commons – Zoning Map Amendment (Z-29-18): Approved as a recommendation to the Common Council (after correction of vote procedure) with two conditions.
- Parkside Commons – Resubdivision (R-25-72): Approved with condition to file map within 62 days of council approval of Z-29-18.
- Parkside Commons – Major Site Plan Review (MASPR-25-25): Approved with five conditions (council approval of zoning amendment, affordable units compliant with city restrictions, certification by DNB).
- Parkside Commons – Resubdivision (R-25-73): Approved with condition to file map within 62 days of approval.
- Parkside Commons – Major Site Plan Review (MASPR-25-26): Approved with four conditions (affordable unit compliance, certification by DNB, 30-year affordability, necessary land use approvals before commercial use).
- 1207 West Genesee – Resubdivision (R-25-61): Approved with condition to file map within 62 days.
- 1207 West Genesee – Major Site Plan Review (MASPR-25-30): Approved with four conditions (curbing/landscaping to prevent sidewalk parking, snow storage on site, updated floor plans for tenants, coordination with county WEP).
- 201 South Krauss – Resubdivision (R-25-64): Approved with condition to file map within 62 days (note: outstanding taxes must be paid before map signing).
- 201 South Krauss – Major Site Plan Review (MASPR-25-31): Approved with ten conditions (including 6 covered bike spaces, 12% affordable units, compliance with city income/rent restrictions, certification by DNB, 30-year affordability, coordination with I-81 project, county water capacity insurance, ADA lift enclosure details per Landmark Preservation Board).
- BESS Moratorium Workshop: Informational only; no vote. The proposed moratorium will be submitted to the Common Council for consideration within the next few weeks.
Meeting Transcript
Welcome to this meeting of the Syracuse Planning Commission. We will begin our uh formal agenda in just a moment. Before we do that, however, we will take action on the minutes of our previous meeting held last month on January twelfth. Minutes have been distributed to the commission members in advance, and it'd be appropriate this time for a motion for action on those minutes. Move approval of the minutes from the January meeting. Second. Thank you. Both discussion on that motion. If not, all in favor, please indicate by saying aye. Aye. Aye. Those opposed, please say nay. Any abstentions. Minutes are approved. And we can move into our public hearings. Before we do that, just a word of um by way of procedure for those who might be unfamiliar with our process. As each application is announced by a member of the staff, we would ask that the applicant or their representative come to the podium in the center front of the room, provide your name and address for the record, and then uh a brief description of the project involved. Following questions from the commission members, if there are any, we will provide an opportunity for members of the public to speak in favor of the application. And then likewise an opportunity for those members of the public who wish to speak in opposition uh to the application where comments are offered in opposition, the applicant will be invited to return to the podium to address the comments made in opposition. And we ask that all speakers for or against um keep their comments to about three minutes apiece. With that, we are ready to begin. I think there is an update on the agenda from what was published uh several days ago, if I'm not mistaken. Say that again, I'm sorry. I think there's a recent update on the agenda. Yeah, sorry. Um yes, the first item under old business for the East Brighton Ave battery energy storage system. Uh those three companion applications, the resub, the special use permit, and the major site plan review have all been withdrawn by the applicant. So if you were here for those items, uh they will not be in our our agenda this evening. If they should return uh at some future meeting, um similar notice will go out in advance of this meeting. So with those withdrawn, we move to our first item, which is an item of old business. Yes, uh special use permit sp-25-26 at 401 Pond Street in Steuben. This is in the MX2 zone district. Welcome back. Good evening. My name is Jesus Ibrahim, own property at TMB properties. Live at 399 Village Boulevard North in Bonesville. 13207. I'm here for uh the special use permit for uh the all-american market. So what what I can try to uh maybe explain to the the board is uh we've received uh revised and updated site plan uh from the applicant to address all the subtle review comments, but also the DPW review uh comments related to ADA access, bike parking, uh the sidewalk on Steuben, and uh also the parking area in front of the store facing pond. Anything else you want to add to that? Um I've been going I've I've been doing everything you guys been asking me to do. I followed everything. Uh the only thing that's been holding me back was DPW. Um I've been getting a hold of contractors, but they can't do nothing right now because of the winter. Um willing to go go ahead with the project. It's just a matter of when they can get ready to go start it. Um I submitted this back probably November, December, October. I've just been waiting, and I finally got the okay for the meeting today. Go ahead. Yeah, I I guess I'd like I began by expressing my appreciation.