Joint Schools Construction Board Meeting - April 23, 2026

Public MeetingsThursday, April 23, 2026
BodySyracuse, New York
SessionPublic Meetings
DateThursday, April 23, 2026
StatusFILED
Video Record

STREAMING COPY IN PREPARATION — RECORDING AVAILABLE FROM THE ORIGINAL SOURCE

Transcript — Verbatim
0:05

Good morning, huh?

0:47

Yeah.

2:19

Just got it.

2:34

Small guys.

5:44

We have the March 26 2026 uh meeting minutes.

5:52

I asked for a motion.

5:54

So move.

5:55

Second.

5:57

All in favor?

5:59

Any opposed?

6:00

So move.

6:01

Report of the secretary.

6:03

Yes.

6:04

Good morning, Mayor and Board members.

6:07

Morning.

6:08

I'm pleased to report we're moving forward with the construction management contract.

6:12

We have to uh finalize some aspects of it, so we anticipate that for the next board meeting for board approval.

6:20

And uh a JACB staff and program manager met with our outside council for the PLA yesterday, and we're working on our internal strategy uh to make sure that we propose the language that we feel is is best for the most part.

6:39

We're comfortable with uh phase two PLA, but as with anything and looking back, uh we may see some advantages to proposing some adjustments.

6:50

Okay, and uh that we will have to get our language together and then present it to the trade.

6:56

So we we feel comfortable that we're on schedule with that.

6:59

Those uh proposed changes at what uh uh point during that cadence will you uh uh advise us as far as the uh changes you're anticipating?

7:10

We can uh circulate a draft.

7:12

Okay.

7:13

Uh you know, for the most part, I think a lot of them will be more technical.

7:18

Um there may be one in particular about diversity that would be of interest.

7:25

Okay.

7:26

So we'll we'll make sure we get that out to the board.

7:28

Thank you.

7:29

Thank you, sir.

7:31

Do I need a motion for your report?

7:33

Uh no, thank you.

7:34

That uh I ask you that every meeting, but always good to check.

7:38

Yes.

7:38

That completes my report.

7:40

Thank you, sir.

7:41

Thank you.

7:41

Uh report from the program manager.

7:44

Before the point of manager start, this is a question to you.

7:48

Because we were delayed, are we still anticipated to be on time?

7:54

Yes.

7:55

Yes.

7:56

Right.

7:56

And on time meaning like third quarter twenty-seven to start construction.

8:02

So that when we have the swing schools, we empty them.

8:05

We have the construction start following that.

8:11

So that you know, if there's kids aren't in the building, we would be starting construction.

8:16

Does that make sense?

8:17

Yeah, and that's what we mean by on time as okay.

8:20

Starting that because I'm looking at the six weeks later than anticipated.

8:25

Right.

8:26

So we got some time to make up.

8:29

Right.

8:29

And working towards that, but again, it's still early on in the design process.

8:34

So working towards keeping that goal of starting construction in the third quarter of 27.

8:40

Okay.

8:46

Um, particularly the 81 project.

8:48

Is there any synergy with any of the locations we're looking at to start with with what's going on with the DOT and what they're working on?

8:57

As far as like scheduling and time conflicts and in and road usage and all that.

9:05

I don't currently we'll foresee that being an issue, but we'll take a look at it.

9:10

Okay.

9:19

Um, we could facilitate a conversation between you all and them.

9:23

Okay.

9:27

Um design meetings are progressing.

9:31

Meeting with um uh principals, building staff, um, key stakeholders to solicit input on design concepts.

9:43

Um currently at Seymour, some of the key design concepts are building envelope improvements, which includes like windows, roofs, exterior doors, uh secure single point entry, reconfiguration of some interior classrooms to help with programming and support spaces.

10:02

Also looking at site logistics to improve arrival dismissal congestion.

10:09

Pretty much the same type of scopes we're looking at at Webster as well.

10:14

Um Webster, potentially maybe an addition or two to help with that reconfiguration and usage of the building footprint.

10:25

Has there been any community input that is affecting any of these scopes?

10:30

Um it's being incorporated.

10:32

Okay, and we do plan on um meeting with public again in probably um July once we're done with the CD phase or sorry, SD phase, which is schematic designs, and seek some of their input on the designs.

10:51

Uh at Nottingham, a couple of spaces we're looking at is the GW wing look at converting that into a CTE program space, uh kitchen cafeteria renovations, um exterior envelope improvements is needed, um selecterior and renovations for like the auditorium pool.

11:11

Um those areas would not probably be total renovations but improvements, and then again some site logistics.

11:20

Is GW the wing headed towards the pool?

11:22

Yes, yes, yeah, beyond the pool.

11:25

Right.

11:26

Okay.

11:26

I'm so excited.

11:29

It has not been touched since I was a student there.

11:32

So it's gonna look great.

11:36

Um and then uh moving forward at the end of SD, we would submit to uh state ed for review for compliance with the um special legislation and probably the end of July for that.

11:52

Okay, uh as Joe mentioned, uh CM's firm has been selected for three buildings.

11:58

Uh letter of intent was issued, uh working on their insurance and diversification plans, get those in and approved and anticipate having um their approval brought to you next month, and then continue to meet with SED on a monthly basis.

12:17

Um nothing major to report there, but those conversations are good.

12:21

And then um as Joe mentioned, the PLE internal meetings have started.

12:28

Any other questions or uh when do you hope to finalize this plan with the PLA to what's the target?

12:41

You know, based on past experience, it it took several months.

12:46

Okay, so it it really depends on the initial response we get from the trades how how kind of open they are to okay changes, etc.

12:56

But I I think in the PM can confirm we're really our need is to have it in place for construction bids.

13:05

Correct.

13:06

And that would be next spring.

13:08

Yeah, next second quarter of 27 would be would we want to have it in place by before?

13:15

That makes sense.

13:16

Fortunately, we have some time to work work around that.

13:19

And just touching on the PLA, how far are we with the language?

13:23

Are we a ways away?

13:25

We we have you know, I think we're comfortable with 90 percent of the language from PLA phase two, but we we've had we are in the process of identifying some areas that we think could be changed for our benefit.

13:43

So we're gonna work in the next several weeks to put that document together, uh, which I'll share with the board, and then we'll approach the the trades and see if we can get their agreement.

13:55

Is the negotiation with the building trades or individual unions?

14:00

Uh fortunately it's with the the coalition of building trades, so they they have an attorney, um the same law firm and attorney that worked on previous PLAs, and uh so it's it's kind of a preset process fortunately.

14:20

Any other questions?

14:24

Thank you.

14:26

All righty, we have uh two resolutions, resolution resolution 10 2026, authorizing monthly payments to all JSCB contractors, including the PM, and a cost not to exceed 106,538 dollars and sixty-one cents.

14:48

Yes, this would be our monthly payment resolution with the thank you.

14:53

All in favor?

14:54

Oh did we get a second?

14:55

I'm sorry, yeah, we did.

14:57

Thank you.

14:57

Super gives Derek.

15:00

No, it was okay.

15:01

Who was the second?

15:02

I said so move.

15:02

So move.

15:03

You said so move.

15:04

I said second.

15:04

You said sorry, I didn't.

15:05

I heard two.

15:07

Thank you.

15:08

Got to be all right.

15:10

Don't be so quick.

15:12

I gotta write it down.

15:14

Thank you.

15:14

Um the the second one, if I can just preview it is um what unusual just because we don't do it that often.

15:22

But like the city, uh, from time to time, the joint schools construction board will look to refund and reissue prior bonds because with the change in the interest rate environment, uh refunding the bonds and reissuing them will uh save a substantial amount of interest, uh, which benefits the school district directly.

15:46

So we we we have our finance team here today, uh fiscal advisors, if you want them to speak to that.

15:55

We would thank you.

15:59

Brendan Ryan, on behalf of fiscal advisors and uh the city.

16:03

Um so the current outstanding 2018 A and 2018 B serial bonds um have about 3.92 uh 39 and 23 million outstanding each, so a total of about 63 uh in the current interest rate environment.

16:24

We um recommended that the school district refund these so redeem and reissue the debt.

16:31

Uh the poor amount of 63 million would be the maximum amount outstanding.

16:36

The duration of the bonds would still go out the same year, which is roughly 10 years, uh, with an approximate savings of over 500,000 dollars a year.

16:45

Um that is as of uh with the current interest rate.

16:52

We were in um in beginning of March, we were realizing about a nine percent savings into April with a lot of the fluctuations in the market, we reduced to about seven and a half percent savings.

17:06

Um the industry standard to move forward the refunding is anywhere from two and a half to three percent savings on the outstanding debt.

17:14

So we believe it is a great advantage for the school district to take advantage of this.

17:20

Any questions?

17:24

Thank you.

17:24

Sure.

17:25

Thank you.

17:26

Okay.

17:26

So the JSCB goes first.

17:29

It's kind of a multi-agency effort because of all the connections.

17:33

Um ultimately it's the Syracuse Industrial Development Agency that that issues our bonds, but the JSCB, the school district, and the common council all have to approve because of our joint interest in the project.

17:46

And we're first in line.

17:48

We are okay.

17:49

So I'll entertain a motion.

17:52

So move.

17:53

Second.

17:54

So move, probably second.

17:56

All in favor?

17:58

Motion moves.

18:00

Any other questions, items?

18:03

That completes our agenda unless there's follow up questions or concerns.

18:08

Enjoy this last.

18:11

Uh entered in a motion to adjourn.

18:13

So moved.

18:14

Second, second Derek second.

18:17

Derek second.

18:19

We are adjourned.

18:19

We're adjourned.

Discussion Breakdown — Share of Meeting
Engineering And Infrastructure██████████████████████████████████████38%
Procedural███████████████████████████████████35%
Procurement█████████████13%
Fiscal Sustainability██████████10%
Community Engagement████4%
Summary of Proceedings

Joint Schools Construction Board Meeting - April 23, 2026

The Joint Schools Construction Board met on April 23, 2026 to discuss updates on school construction projects, project labor agreements, and approve resolutions related to contractor payments and bond refunding.

Consent Calendar

  • Approval of March 26, 2026 meeting minutes was moved, seconded, and approved unanimously.
  • Resolution 10-2026 authorizing monthly payments to JSCB contractors not to exceed $106,538.61 was approved unanimously.

Discussion Items

  • Secretary's Report: The secretary reported progress on the construction management contract, which will be presented for board approval next meeting. A meeting was held with outside counsel regarding the Project Labor Agreement (PLA) for phase two. Staff is comfortable with 90% of the language but will propose adjustments, particularly regarding diversity. A draft will be circulated to the board.
  • Program Manager's Report: The program manager confirmed the project remains on schedule for construction start in Q3 2027, despite a six-week delay. Design meetings are progressing for Seymour, Webster, and Nottingham schools. At Seymour, key scopes include building envelope improvements, secure single-point entry, and site logistics. At Webster, potential additions are being considered. At Nottingham, the GW wing may be converted for CTE programs, along with kitchen/cafeteria renovations, envelope improvements, and auditorium/pool upgrades. Community input is being incorporated, with a public meeting planned for July 2026. Schematic design submissions to SED are expected by end of July. The CM firm has been selected for three buildings, with letter of intent issued. PLA internal meetings have started, with a target to have the PLA in place by Q2 2027 for construction bids.
  • Bond Refunding Resolution: Brendan Ryan from fiscal advisors presented a proposal to refund and reissue outstanding 2018A and 2018B serial bonds (total ~$63 million) to take advantage of lower interest rates, saving approximately $500,000 per year. The savings rate is about 7.5% currently, well above the industry threshold of 2.5-3%. The refunding requires approval from JSCB, school district, and common council. Questions were answered.

Key Outcomes

  • Minutes Approved: Previous meeting minutes approved unanimously.
  • Monthly Payments Approved: Resolution 10-2026 passed unanimously.
  • Bond Refunding Approved: Resolution to authorize refunding of 2018 bonds was moved, seconded, and approved unanimously.
  • Next Steps: Secretary will circulate draft PLA changes; program manager will continue design and public engagement; bond refunding will proceed through multi-agency approvals.

The meeting adjourned.

Meeting Transcript

Good morning, huh? Yeah. Just got it. Small guys. We have the March 26 2026 uh meeting minutes. I asked for a motion. So move. Second. All in favor? Any opposed? So move. Report of the secretary. Yes. Good morning, Mayor and Board members. Morning. I'm pleased to report we're moving forward with the construction management contract. We have to uh finalize some aspects of it, so we anticipate that for the next board meeting for board approval. And uh a JACB staff and program manager met with our outside council for the PLA yesterday, and we're working on our internal strategy uh to make sure that we propose the language that we feel is is best for the most part. We're comfortable with uh phase two PLA, but as with anything and looking back, uh we may see some advantages to proposing some adjustments. Okay, and uh that we will have to get our language together and then present it to the trade. So we we feel comfortable that we're on schedule with that. Those uh proposed changes at what uh uh point during that cadence will you uh uh advise us as far as the uh changes you're anticipating? We can uh circulate a draft. Okay. Uh you know, for the most part, I think a lot of them will be more technical. Um there may be one in particular about diversity that would be of interest. Okay. So we'll we'll make sure we get that out to the board. Thank you. Thank you, sir. Do I need a motion for your report? Uh no, thank you. That uh I ask you that every meeting, but always good to check. Yes. That completes my report. Thank you, sir. Thank you. Uh report from the program manager. Before the point of manager start, this is a question to you. Because we were delayed, are we still anticipated to be on time? Yes. Yes. Right. And on time meaning like third quarter twenty-seven to start construction. So that when we have the swing schools, we empty them. We have the construction start following that. So that you know, if there's kids aren't in the building, we would be starting construction. Does that make sense? Yeah, and that's what we mean by on time as okay. Starting that because I'm looking at the six weeks later than anticipated.