The Syracuse Common Council held a meeting with the New York State Department of Transportation (NYSDOT) to receive an update on the I-81 Viaduct project. Officials presented progress on nine contracts in two phases, detailed community concerns, and discussed the upcoming largest contract in NYSDOT history. Councilors and members of the public raised issues regarding construction impacts, dust, noise, truck routes, small business disruptions, and landscape design.
I'm Call Sir Nave. I'm joined by Counselors Holland Hudson. Patrona Jones Rouser. Rashida Caldwell. So we have asked Scott Butler and those of the Route 81690 project to speak today to give us an update on the project. We're also going to be uh asking questions from my colleagues from the common council. And we've asked those here to offer their comments as well. So I want to welcome everyone here. And if you want to introduce yourselves, and we can get started. Thank you. Okay. I'll kick us off. My name is Betsy Parmley. I'm the regional director with New York State Department of Transportation. I'm Mike Ryan. I'm the deputy director for the 81 project with New York State DOT. Scott Butler, I'm a special assistant with the I81 project and for the region. Yeah, thank you. All right. So we just have a you know an update on where we are with this project. Um so um we'll go quickly through these first few slides. Counselors, you um have the package in front of you, it matches what's on the screen. Um we always like to start with this slide, just it's an overall view of all of the work that's part of the 81 Viaduct project, two phases, nine contracts. So um we are making really significant uh progress on this project. So just real quick, let's see if this works. Uh up in the northern interchange ID 141, that work is more or less complete. It's operational. Um we just have a few uh miscellaneous things to take care of up there, but otherwise that work is complete. That work is all complete, more or less. There's a little you know, buttoning up to do, but it's all operational. Um we have those new roundabouts along Brighton Ave. We have the new interchange at East Glenab. Um, but that work is is complete. So then moving right along. Um this is also a view of that new interchange in contract two down in the valley serving um East Glen Ave. So now uh people can actually get on and off I-81 going north and south. Um that didn't exist before. Um, and what we're hearing from people actually is it saves them from going through eight traffic signals actually by using uh this new interchange and this new um on and off ramp. So that's complete and operational. So then again, real quick, moving along to what we have going on in the north side. So what we're looking at here is um that first bridge you see is Bear Street. Um I-81 is running underneath it, then we have North Clinton. So what we have completed so far is Bear Street is open, and Spencer Street is open, and we're in the process of rebuilding Court Street. We also installed new on and off ramps serving ID one southbound to North Clinton. So eventually, as part of this whole project, there will be a full interchange to get northbound and southbound all in this area, all in the bare area. So we did kind of the southbound side, so that's really progressing. Um shared use paths, sidewalks, um, street trees, decorative lighting had all have all been installed in that. That is projected to be completed um for the most part at the end of this year with some buttoning up in the spring of 2027. So um a lot of work happening. So then that takes us to the contracts that are, I guess, much deeper in construction, if you will, and I'm gonna hand it off to Scott Butler to talk about.